Home / Financial Firm (Unknown - Insurer) / Determination 399398

Determination 399398

Cash settlement amounts for 2014 and 2015 storm damage

FirmFinancial Firm (Unknown - Insurer)
Decided2015-10-22
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed$200,000
SourceAFCA PDF

Summary

The Applicant disputed cash settlements for two storms to his home and sought $200,000 plus compensation for stress. AFCA found the amounts paid and offered sufficient for the covered storm damage, excluded the overflow damage under a design-fault exclusion, and found misconduct not established.

Where the insurer cash settles it must pay the cost of repairing covered storm damage, and the policy excludes damage whose proximate cause was a known design fault that was not fixed.

Issues

Subjects and remedies

home or building damagenatural disasterno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 399398 Determination Page 1 of 11 Case number: 399398 22 October 2015 1 Overview 1.1 Dispute The Applicant lodged a claim under his home insurance policy with the Financial Services Provider (FSP) for damage to his home following a storm in October 2014. The FSP accepted the claim and sought to arrange for the repair of the property. However, due to its builders' inability to guarantee the necessary repairs, the FSP offered to cash settle the Applicant for the estimated cost of the repairs. The Applicant disputed the amount of the cash settlement. In the interim, the property sustained additional damage from a second storm in April 2015, which the Applicant attributes to the initial repairs carried out by the FSP’s contrac tors. He seeks a total cash settlement of $200,000 for all of the damage to his property, together with compensation for stress and inconvenience due to the FSP’s handling of his claim 1.2 Issues and key findings Is the cash settlement paid by the FSP for the 2014 storm fair and reasonable? The cash settlement amount of $24,410.25 (less excess) paid by the FSP is sufficient to repair all of the damage caused by the storm in October 2014. Accordingly, the cash settlement is fair and reasonable and the FSP is not required to pay any additional amounts in respect of this damage. Is the FSP’s cash settlement offer for the 2015 storm fair and reasonable? The cash settlement amount of $20,715 offered by the FSP (together with the $1,400 previously paid) is sufficient to repair all of the damage caused by the storm in April 2015. The FSP is not liable for the damage resulting from the overflow of water through the front awning, as this damage was caused by a design fault of which the Applicant had previously been made aware. Accordingly, the cash settlement offered by the FSP is fair and reasonable. The FSP is not required to pay any additional amounts in respect of the further damage to the Applicant’s property which occurred in April 2015. Is the Applicant entitled to compensation? The Applicant is not entitled to compensation. The available information is not sufficient to establish misconduct on the part of the FSP and its contractors. The FSP managed the claim reasonably overall and is not solely responsible for the delays experienced during the claim process. Case No: 399398 Determination Page 2 of 11 1.3 Determination This Determination is in favour of the FSP. The Applicant is not entitled to any further amounts (in addition to those amounts already paid and/or offered by the FSP). Case No: 399398 Determination Page 3 of 11 2 Reasons for Determination 2.1 Is the cash settlement paid by the FSP for the 2014 storm fair and reasonable? Policy provides cover for storm damage subject to exclusions The Applicant is required to show that, on the balance of probabilities, he has suffered a loss caused by a risk insured against under the policy. This is known as a prima facie claim. If the Applicant is able to establish a prima facie claim, then the onus shifts to the FSP to show that, on the balance of probabilities, it is entitled to rely on an exclusion under the policy or is otherwise entitled to deny the claim. The Applicant’s policy provides cover for damage to his home caused by storm, subject to the conditions and exclusions set out in the policy. The FSP accepts that the Applicant’s property was affected b y storms in October 2014. In these circumstances, the Panel is satisfied that the Applicant has established a prima facie claim under the policy. Accordingly, the FSP bears the onus of establishing that, on the balance of probabilities, it is entitled to rely on a policy exclusion or is otherwise entitled to deny the Applicant’s claim. Dispute concerns extent of storm damage and cost of repairs The FSP accepted the Applicant’s claim for damage to his home caused by the storm in October 2014 and arranged for its contractors to prepare a scope of works and provide a quotation for the necessary repairs. However, a dispute arose between the parties as to the extent of the storm-related damage and the estimated cost of repairs. The first builder (LS) appointed by the FSP prepared a scope of works and provided a quotation of $9,638 for the necessary repairs. However, after the Applicant raised concern s about LS’s scope of works, the FSP appointed an internal assessor who amended the scope of works to include certain additional items of damage identified by the Applicant. Based on the amended scope of works, the FSP obtained quotations for the repairs from two other builders (D and J), who quoted $7,127 and $10,386 respectively. However, both builders advised that they were unable to guarantee the repairs due to defects in the construction of some of the damaged areas of the property. Accordingly, the FSP offered to cash settle the Applicant for $10,386 (less the policy excess). The Applicant disputed the amount of the cash settlement and obtained a quotation from his own repairer (SC) for $37,500, following which the FSP agreed to increase the cash settlement to $24,410 (less the policy excess). This amount was paid to the Applicant in May 2015. Case No: 399398 Determination Page 4 of 11 In determining the amount of the cash settlement, the FSP took into account the estimates provided by SC for repairing certain items of damage for which the FSP had accepted liability. However, the FSP considered that SC’s quotation included items of damage which had not been caused by the storm and therefore over-estimated the cost of the necessary repairs. The Applicant remains dissatisfied with the amo unt of the cash settlement offered. He says the cash settlement should be based on the quotation provided by SC, which he considers represents the cost of repairing all of the damage to the property caused by the storm in October 2014. Claim should be cash settled At various stages during the course of this dispute, the Applicant has sought to have the FSP undertake the necessary repairs, which would enable him to obtain the benefit of the lifetime repair guarantee provided under the policy. However, having carefully reviewed the claim history, the Panel considers it is more appropriate for the claim to be cash settled. Despite lengthy and repeated discussions over an extended period of time, the parties have been unable to agree on the extent of the storm-related damage. It is clear from the call recordings of these discussions that the relationship between the parties has irretrievably broken down. Further, on a number of occasions, the Applicant has expressed doubt about whether the FSP’s contractors hav e the skills and experience required to carry out the necessary repairs. In these circumstances, the Panel considers that a cash settlement is the only feasible way to resolve the dispute. Under the terms of the policy, where it elects to cash settle a c laim, the FSP is required to pay the Applicant the amount it would have cost the FSP to undertake the necessary repairs. Cash settlement is fair and reasonable As noted above, the FSP cash settled the Applicant for a number of individual items of damage based on the quotation provided by his repairer (SC). The only aspects of SC’s quote which the FSP did not accept were as follows:  the FSP did not accept SC’s quote of $8,210 for the pressure cleaning and partial replacement of the tiles in the rear pool area and the re-grouting, rebedding and partial replacement of the driveway tiles. Instead, the FSP allowed an amount of $1,868.50 for the pressure cleaning and limited replacement of the driveway tiles, based on the scope of works and quotation prepared by its contractors;  the FSP adopted the quote of $2,480.50 provided by its electrician for the replacement of the damaged awning, pool and driveway lights, in preference to the quote of $7,700 provided by SC; and Case No: 399398 Determination Page 5 of 11  the FSP determined the cost of repairing the damage to the timber slats of the pool screening based on the quote of $1,361.25 provided by its carpenter, rather than the quote of $2,700 provided by SC. Having carefully reviewed the available information (including the reports prepared by the various contractors), the Panel considers the approach taken by the FSP to determining the cash settlement amount was fair and reasonable. The Panel notes that, while the Applicant has obtained quotations from SC and B (in respect of the tiles only), both contractors appear to have prepared their quotations based solely on their assessment of the repairs required at the property. Neither contractor has provided any opinion as to the cause of the various items of damage or confirmed that they were linked to the storm in October 2014. In contrast, the FSP has provided several reports from its contractors which conclude that the disputed items of damage were not caused by the storm (or any other event which is insured against under the policy). In relation to each of the items outlined above (in respect of which the FSP adjusted SC’s quote), the Panel notes as follows:  the Panel is not satisfied that the loss of grout from between the tiles and the staining damage to the tiles is consistent with having been caused by the storm in October 2014. The FSP’s contractors have advised that a one -off storm event would not be sufficient to result in the loss of grout or cause the staining identified, assuming the tiles had been correctly laid. Nevertheless, the FSP has included provision for the pressure cleaning of the tiles;  the cash settlement amount for electrical works provided for the replacement of four eave lights, two pool lights and twelve driveway lights (although the FSP’s electrician subsequently advised that water damage to some of these lights was due to the lights being inappropriate for outside installation) . The Applicant’s quote was based on the replacement of all of the external lights – however, under the terms of the policy, the FSP is not required to pay for the cost of replacing undamaged lights to maintain a uniform appearance; and  the allowance made by the FSP for the repair of the privacy screen included the amount quoted by its carpenter for the repair of the side gate as well, despite the FSP also allowing for the full cost of replacing the gate (which the Applicant had disposed of in the interim). Further, the Panel notes that the cash settlement paid by the FSP included the amount of $12,350 (as quoted by SC) for the full replacement of the kitchen benchtop, splashback, joinery and sink. An allowance for these repairs was made in order to address a stain which the Applicant said was caused when a watermelon fell onto the benchtop during the storm. The cash settlement included the full cost of replaci ng the bench (and related items), despite the FSP’s stone mason advising that it would be reasonable to attempt cleaning of the benchtop as a first step. For the reasons outlined above, the Panel considers that the cash settlement of $24,410.25 (less excess) paid by the FSP was sufficient to repair the damage caused by the storm in October 2014. Case No: 399398 Determination Page 6 of 11 2.2 Is the FSP’s settlement offer for the 2015 storm fair and reasonable? Dispute concerns extent of further damage and cost of repairs The Applicant’s home suffere d additional damage during a second storm on or around 21 April 2015. The Applicant says some of this damage was due to the FSP’s contractors having placed a tarpaulin over the front awning, as part of make safe repairs carried out after the first storm i n October 2014. The Applicant considers the manner in which the tarpaulin was installed damaged the roof tiles and awning and led to the overflow of rainwater, damaging areas including the external entry wall, the front door and the ceiling in one of the bedrooms. The Applicant says the overflowing water also damaged the electrical system throughout the house, as well as various electrical fittings and fixtures. The Applicant says the storm also caused damage to the granny flat and various external areas of the house, including the side fence and gate, the steps leading to the pool area and the pavers around the pool. The FSP accepted liability for the Applicant’s claim arising out of the second storm and sought to assess the extent of the additional, storm-related damage. The FSP’s assessor carried out an initial assessment of the damage in late April 2015. However, the assessor was unable to carry out a close inspection of the internal damage and was unable to access the roof due to poor weather conditio ns. The Applicant was initially reluctant to agree to a further assessment, as he was dissatisfied with the time taken to resolve his claim. However, after the Applicant lodged his dispute with FOS, he agreed to a further, more detailed assessment, which was undertaken in July 2015. Based on this assessment, the FSP offered to cash settle the Applicant for $20,715 for the additional damage to his property resulting from the storm in April 2015. This was in addition to the amount of $1,400 previously paid for damage to the bedroom ceiling ($700) and the costs of cleaning the blocked gutters at the front of the property ($700). The Applicant says the amount offered by the FSP is not sufficient to repair the additional damage to his property caused by the storm in April 2015 and the actions of the FSP’s contractors. He has provided a quote from his own repairer (D) for $83,415 (plus GST) for the necessary repairs, together with a quote from his tiler (B) for the replacement of all of the paving to the external areas. FSP is not liable for damage caused by overflowing water Having carefully reviewed the available information, the Panel considers the FSP is not liable for damage to the front part of the property caused by the overflow of water during the storm in April 2015. The quotation provided by the Applicant’s builder (D) states that the awning over the entry door was damaged by the plastic tarpaulin placed on it by the FSP’s Case No: 399398 Determination Page 7 of 11 contractors. The Applicant also says the tarpaulin blocked the drains and trapped rainwater during the storm, causing water to flood the interior of the property. In conjunction with the detailed assessment of the property carried out in July 2015, the FSP appointed a roofing specialist (MJ) to identify whether there was any damage to the roof tiles and front awning and determine what had caused the overflow of water. In his report dated 21 July 2015, MJ confirmed there was no damage to the tiled roof at the property. He concluded that the overflow of water was due to the design of the box gutter at the front of the roof, which did not have any overflow points and therefore was susceptible to overfilling and flooding the front of the house during periods of heavy rain. As a roofing specialist, the Panel considers MJ is appropriately qua lified to determine the cause of the water damage to the front of the property. The Panel considers MJ’s report provides a logical and rational explanation of the cause of the damage, which is consistent with the observed facts. MJ’s findings are also cons istent with the views expressed by the builder (LS) who was initially appointed by the FSP to assess the damage to the Applicant’s property following the storm in October 2014. LS concluded that the water damage at the front of the property had been caused by insufficient provision for drainage from the flat metal awning over the entry area. The Panel notes this damage occurred before the tarpaulin was installed by the FSP’s contractors as part of the make safe repairs. The Applicant’s builder (D) has not p rovided any information which rebuts the findings of MJ and LS that the box gutters at the front of the property were inadequate to allow for the effective drainage of water from the roof during periods of heavy rainfall. Based on the available information, the Panel considers that, on the balance of probabilities, the water damage to the front part of the property was caused by the design of the front awning and box gutters, rather than by the manner in which the tarpaulin was installed by the FSP’s contra ctors. As outlined above, the Applicant’s policy provides cover for damage caused by storm However, the policy excludes cover where the proximate cause of the damage (that is, the dominant, operating or effective cause) was a design fault which the Applicant knew about (or could reasonably have known about) and failed to fix before the damage occurred. The Panel is satisfied the FSP’s contractors told the Applicant about the design issue with the front awning relatively early in the assessment process for his first claim. The FSP advised the Applicant the problem with the awning was a maintenance issue for which he was responsible. However, the Applicant did not address the issues with the box gutter and the tarpaulin remained in place almost six months after the first storm. Accordingly, under the terms of the policy, the FSP is not liable for the water damage caused by the box gutters overflowing during the second storm in April 2015. Case No: 399398 Determination Page 8 of 11 Cash settlement is fair and reasonable The cash settlement of $20,715 offered by the FSP reflects a quotation provided by its builder (SH), based on the assessment of the storm- related damage by the FSP’s assessor (AT) completed during the second, more detailed inspection in July 2015. The Panel has carefully reviewed AT’s reinspection report, together with the numerous photographs included therein. In AT’s report, he identifies each of the items of damage claimed by the Applicant and provides his findings as to the cause of damage for each individual item. The Panel consid ers that AT’s report represents a detailed and comprehensive analysis of the cause of damage for each of the items clamed, which is supported by the photographic evidence attached. Based on AT’s findings, the FSP accepted liability for the following item s:  repair of water damage to the plaster in the granny flat;  repair of storm damage to the eaves lining on the side wall of the property;  impact damage to the aluminium door of the granny flat;  painting of water damaged internal areas; and  repair of two water damaged chandeliers. Some of the additional items of damage claimed by the Applicant are outside the scope of cover because they relate to items (such as plants and garden beds) which are not considered to be part of the insured building for the purposes of the policy or are treated as contents items. The Applicant elected not to take out contents cover under the policy. Based on the available information, the Panel is satisfied the FSP is not liable for the remaining items of damage claimed by the Applicant. In relation to some of the higher value items claimed by the Applicant, the Panel notes the following:  for the reasons outlined above, the FSP is not liable for items of damage caused by the overflow of water from the box gutters at the front of the property (including claimed damage to the front door, external stone wall and intercom);  the staining damage to the external pavers was caused by decking oil leeching from the surrounding timber structures, over an extended period of time. The Pane l notes that the report provided by the Applicant’s tiler (B) does not express a view about the cause of this damage;  the damage to the timber boards (and glass) under the rear stairs was not caused by the storm in April 2015, but has occurred gradually over time; and  the FSP’s electrician (CE) confirmed that some of the electrical items claimed by the Applicant were tested and found to be working, while it was highly unlikely that the issues with the other items were due to the effects of stormwater. The Applicant has not provided a report from a qualified electrician refuting CE’s findings. The Panel notes the FSP’s proposed settlement offer of $20,715 (in addition to the amount of $1,400 already paid) includes an amount of $6,000 for the aluminium sliding door of the granny flat, despite the FSP’s assessor noting that the dent in the door was highly unlikely to have been caused by the storm. Case No: 399398 Determination Page 9 of 11 Further, it appears the settlement amount includes provision for the repair of some of the items damaged by the overflow of water through the front entry area (for which the FSP is not liable). On this basis, the Panel is satisfied that the cash settlement of $20,715 offered by the FSP is sufficient to repair the damage to the Applicant’s property caused by the storm in April 2015. 2.3 Is the Applicant entitled to compensation? Applicant has not established misconduct by FSP or its contractors The Applicant has raised a number of concerns about the manner in which the FSP handled his claim. Among other things, the Applic ant says the FSP’s contractors caused additional damage to his property and acted in a rude and unprofessional manner. It is clear the relationship between the Applicant and the FSP has deteriorated significantly over the course of this claim, leading to an atmosphere of mistrust and suspicion between the parties. However, the FSP’s contractors have emphatically denied behaving in the manner claimed by the Applicant and/or damaging his property and the Applicant has been unable to provide any independent information confirming they have done so. The concerns identified by the Applicant raise issues of serious misconduct. The Panel considers it inappropriate to make a finding on such matters without a substantial weight of evidence confirming the events alleged by the Applicant occurred in the manner claimed. In the absence of independent evidence confirming the matters alleged by the Applicant, the Panel is not satisfied that misconduct on the part of the FSP or its contractors has been established. FSP managed claim reasonably in the circumstances The Panel acknowledges it has taken a significant length of time to finalise the Applicant’s claims. However, having carefully reviewed the claim history, the Panel considers that the FSP is not responsible for all of these delays. The Panel accepts there was an initial delay in the FSP’s assessment of the Applicant’s claim following the storm in October 2014. However, this delay did not materially extend the overall claim period, as the claim was not released by the FSP’s investigations department until mid -December 2014. The further delays experienced during the claim process were, to some extent, due to the Applicant’s multiple requests that the contractors engaged by the FSP to manage the claim be replaced . The Applicant’s reluctance to allow the FSP to carry out a more detailed assessment in order to accurately assess its liability for the second claim also contributed to the time taken to resolve his dispute. Case No: 399398 Determination Page 10 of 11 The Applicant has also claimed for numerous separate items of damage, many of which the Panel has found were not caused by the storms in October 2014 and April 2015 or by the conduct of the FSP’s contractors. Applicant is not entitled to compensation For the reasons outlined above, the Panel is satisfied that the FSP managed the Applicant’s claim reasonably in the circumstances. Accordingly, the Applicant is not entitled to compensation. Case No: 399398 Determination Page 11 of 11 3 Supporting information 3.1 FOS approach to this dispute This dispute has not been the subject of a FOS Recommendation. Due to the nature of the dispute, it has been referred directly to a Panel for Determination, in line with the Operational Guidelines to the FOS Terms of Reference. This decision has been made by a Panel. The Panel consists of an Ombudsman and two representatives with consumer and insurance experience. The Panel has decided this case on its merits, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions. There has been a full exchange of all material information relied on for the purposes of this Determination and each party has had the opportunity to address any issues raised by the other. The Panel has reviewed and considered all of the material provided by the parties. While the parties have raised a number of issues in their submissions, for the purposes of this Determination, the Panel has restricted its commentary to those issues which it considers directly relevant to the outcome only.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.