Quality of mould remediation and building repairs disputed, cash settlement amount and claim conduct challenged
Text of the determination
Determination
Case No: 399300 Determination Page 1 of 10
Case number: 399300 15 December 2015
1 Overview
1.1 Dispute
The Applicant lodged a claim under her home insurance policy with the Financial
Services Provider (FSP) for damage to her property following a storm in January
2013.
The FSP accepted the claim and arranged for its contractors to commence repairs.
However, after the parties were unable to agree on the conduct of the repairs, the
FSP cash settled the Applicant for the cost of the outstanding repairs.
The Applicant is dissatisfied with the quality of the repairs carried out by the FSP’s
contractors and the cash settlement provided. In particular, she says the FSP did not
adequately remediate mould at the property before commencing the building repairs.
The Applicant also seeks compensation for stress and inconvenience caused by the
manner in which the FSP has handled her claim and the actions of the FSP’s
contractors during the claim process.
1.2 Issues and key findings
Has the FSP settled the Applicant’s claim fairly and reasonably ?
While the cash settlement is generally fair and reasonable, the available information
establishes that it should be increased by $4,000 to take account of additional items
of damage which were not provided for in the settlement amount.
Is the Applicant entitled to compensation?
The Applicant is not entitled to compensation. The available information is not
sufficient to establish misconduct on the part of the FSP and its contractors. The FSP
managed the claim reasonably overall.
1.3 Determination
This Determination is substantially in favour of the FSP.
The FSP is required to pay the Applicant an additional $4,000 in full and final
settlement of her claim, plus interest on this amount at the rate calculated in
accordance with section 57 of the Insurance Contracts Act 1984 (Cth) from 12 May
2015 until the payment date.
Case No: 399300 Determination Page 2 of 10
2 Reasons for Determination
2.1 Has the FSP settled the Applicant’s claim fairly and reasonably ?
Policy provides cover for storm damage subject to exclusions
The Applicant is required to show that, on the balance of probabilities, she has
suffered a loss caused by a risk insured against under the policy. This is known as a
prima facie claim.
If the Applicant is able to establish a prima facie claim, then the onus shifts to the
FSP to show that, on the balance of probabilities, it is entitled to rely on an exclusion
under the policy or is otherwise entitled to deny the claim.
The Applicant’s policy provides cover for damage to her home caused by storm,
subject to the conditions and exclusions set out in the policy.
The FSP accepts that the Applicant’s property was affected by a storm in January
2013. The available information confirms that the Applicant had previously lodged
claims for storm damage to the property, going back as far as 2008.
In these circumstances, the Panel is satisfied that the Applicant has established a
prima facie claim under the policy.
Accordingly, the FSP bears the onus of establishing that, on the balance of
probabilities, it is entitled to rely on a policy exclusion or is otherwise entitled to deny
(or reduce its liability for) the Applicant’s claim.
FSP arranged mould remediation works at the property
The FSP accepted the Applicant’s claim for damage to her home caused by the
storm in January 2013 and arranged for an assessor to inspect the damage.
During the assessment, it was identified that repairs to the flashing around one of the
windows at the property (which had been carried out by the FSP’s contractors
following the storm in 2008) were inadequate and needed to be rectified.
The assessor identified additional damage to the front and rear doors, an upstairs
window frame and the front external wall at the property, caused by the storm in
January 2013.
The repairs required as a result of this additional damage were not finalised until
March 2014. This delay was caused by various factors, including the need to rectify
the previous works, a dispute over the nature of the repairs to the front door and the
Applicant’s request to have the claim suspended following the death of her m other.
In August 2014, the Applicant notified the FSP that a painter working at her property
had identified additional water damage. The FSP’s assessor (SD) attended the
property on 15 September 2014 and confirmed there was a gap in the skirting of the
internal wall under the window and slight stains to the carpet in two rooms, which SD
considered would respond to cleaning.
Case No: 399300 Determination Page 3 of 10
Following receipt of SD ’s report, the FSP appointed a restoration specialist (NR) and
a builder (AB) to prepare a scope of works for the necessary repairs.
The restoration specialist (NR) advised that there was mould damage to the floors
and carpets in the lounge, main bedroom and stairs, which were not capable of being
restored. Accordingly, NR recommended that the carpets be removed, the affected
areas treated and replacement carpet installed. NR also confirmed that the curtains
in the upstairs bedroom required replacement due to mould damage.
After arranging temporary accommodation for the Applicant, the FSP authorised its
mould specialist (MCS) to undertake remediation works in mid-November 2014.
During the course of these works, further mould was identified behind the walls in the
downstairs bedroom, lounge room and upstairs bedroom, which required additional
remediation measures.
After mould tests carried out in December 2014 showed that there were still high
levels of fungal hyphae in th e upstairs area of the property, the FSP’s mycologist
advised that the continuing mould issues were due to cross-contamination from the
external environment.
On the advice of the mycologist, MCS re-treated the ceilings, walls and floors of the
property with air scrubbers operating and containment walls in place. Subsequent
tests carried out in late January 2015 (after further treatment of the lounge room
window wall) indicated there was no further mould at the property
On several occasions during the course of the mould remediation works, t he
Applicant raised concerns that the works were not adequate to effectively eradicate
all of the mould at the property. The Applicant subsequently advised that she had
suffered a respiratory infection due to inhaling mould at the property on 5 February
2015, after the remediation works had been completed.
In order to confirm the property was free of mould and the building repairs could
commence, the FSP arranged for another mould specialist (EO) to carry out further
testing at the property on 1 April 2015. EO also undertook final cleaning and
sanitising of the affected areas.
The results of the air and surface tests carried out at the property on 1 April 2015
revealed normal or lower than normal levels of mould inside the property (against
standard benchmarks, as well as rela tive to the external environment). Accordingly,
the FSP instructed its builder (AA) to commence the building repairs.
Applicant considers mould remediation works were ineffective
The Applicant says the mould remediation works carried out by the FSP were
inadequate to remove all of the mould at the property. She believes the property is
still contaminated with mould which poses a serious threat to her health, given her
extensive history of respiratory illness.
Among other things, the Applicant says the measu res used by the FSP’s contractors
were ineffective to remove mould and the FSP failed to treat the main downstairs
bedroom at the property.
Case No: 399300 Determination Page 4 of 10
She wants further mould remediation works carried out throughout the property and
the entire eastern and western walls (as well as carpets and flooring) removed and
replaced.
The FSP believes its contractors have effectively treated all mould-affected areas of
the property. The FSP’s contractors have advised that not all rooms required the
same level of treatment as they had not been subject to water entry to the same
extent.
During the course of this dispute, the Applicant provided photographs of timber
boards showing mould growth which she says she removed from a window sill at the
property in June 2015. The Applicant considers the presence of mould on these
boards establishes that the FSP’s mould remediation works were ineffective.
However, the FSP has queried whether the timber boards identified by the Applicant
were in fact removed from the interior of the house. The FSP’s contractors have
advised that the house has an ongoing susceptibility to mould due to its location in a
shaded environment surrounded by trees. The presence of external mould on the
roofs and garages of properties in the area is clearly evident in photographs taken by
the FSP’s contractors.
Available information does not establish further mould remediation is required
As outlined above, separate air and surface tests ca rried out by MCS in December
2014/January 2015 and EO in April 2015 (and analysed by independent laboratories)
confirmed that mould spores at the property were within acceptable levels.
The FSP has provided a report from EO which confirms that tests carried out in April
2015 included air samples taken from two sites on each level of the property and
surface samples taken from four sites on each level (including both downstairs
bedrooms).
EO’s report states that, when he attended the property on 1 April 201 5, the walls in
the three main areas of concern had been partially stripped (as a result of MCS’s
earlier works). Photographs provided together with the report show swab tests being
carried out in the wall cavities.
EO confirmed that each of the wall cavities were dry and showed no signs of visible
mould. He subsequently arranged for the walls in each area to be stripped to a height
of 1.2 metres and found no further mould.
The Applicant has raised concerns about the fact that EO’s testing was carried out
after the wall cavities had been sprayed with a further mould treatment liq uid.
However, the swabs relied upon for the purpose of EO’s report were taken on 1 April
2015, while the further mould treatment was not carried out until 13 April 2015.
The Applicant has provided a significant volume of material from Australian and
international organisations outlining recommended measures for mould remediation.
She has also identified a number of specific concerns with the remediation and
testing methodology employed by the FSP’s contractors.
Case No: 399300 Determination Page 5 of 10
However, it does not appear that any of the organisations who have advised the
Applicant in relation to mould remediation (or on whose documentation she relies)
have inspected the Applicant’s home or carried out mould tests at the property.
During the course of the dispute, the Applicant engaged he r own mould specialist
(HP) to carry out further mould testing. After testing twelve separate areas of the
property in October 2015, HP advised that the mould levels were not overly high and
did not constitute a threat to health.
While the Applicant has ch allenged HP’s findings, she has not provided any
independent information which establishes that they are incorrect.
The Panel acknowledges that, given her serious and ongoing health issues, the
Applicant is understandably concerned to ensure that her property is free of mould.
The Panel also appreciates that, based on her own research, the Applicant believes
the FSP’s contractors should have adopted alternative mould remediation measures.
However, the Applicant has not provided any reports from appropriately qualified
specialists who have inspected her property which confirm that the measures
adopted by the FSP’s contractors have not been effective to ensure the property is
free of mould.
On this basis, and in the absence of any scientific tests which confirm the ongoing
presence of mould at the property (despite such tests being undertaken on several
occasions), the Panel is not satisfied that the FSP should be required to carry out any
further mould remediation works.
Available information does not establish methods used were harmful
The Applicant is also concerned that the mould remediation measures used by the
FSP’s mould specialist (EO ) have severely exacerbated her pre -existing health
issues.
EO’s report indicates that he used an organically-derived compound to treat the
exposed wall cavities on 13 April 2015. The Applicant says she has confirmed that
the compound used contained clove oil and cinnamon oil, which she considers have
damaged her health and have left the internal wall cavities coated in a flammable
substance.
The Applicant has provided various fact sheets providing risk and safety information
about products which contain similar ingredients to those she believes were used by
EO (although it is unclear whether any of the fact sheets relate to products containing
identical ingredients in the same concentration as the compound used by EO). She
says she has been advised by the Asthma Foundation that cinnamon oil is
contraindicated for people (such as herself) with respiratory illnesses.
The information provided by the Applicant indicates that products of this type
(particularly when used in high concentrations) may cause respiratory irritation,
dizziness and fainting. However, the Panel is not satisfied the material provided
establishes the use of such products to sanitise wall cavities presents any long term
danger to health, such that the FSP should be required to remediate the relevant
areas of the Applicant’s home.
Case No: 399300 Determination Page 6 of 10
The mould specialist (HP) engaged by the Applicant in October 2015 queried
whether the use of organic compounds was effective to combat the spread of mould.
However, HP confirmed that such compounds would not have any adverse effect on
the structural stability of the treated timber and did not suggest that their use was
hazardous to health.
HP suggested that the Applicant’s ongoing medical issues are more likely to have
been exacerbated by the presence of Volatile Organic Compounds (VOCs) that are
released from timber resins, carpet and paint at room temperature. However, there is
nothing to suggest that the release of VOCs at the Applicant’s property is in any way
connected with the works undertaken by the FSP’s contractors.
The Applicant has provided extensive medical documentation and reports from her
treating doctors which confirm that she has suffered from severe asthma and
recurrent respiratory infections since 2008, complicated by an intolerance to multiple
antibiotics. During the course of the claim, the Applicant has been hospitalised on
several occasions.
The Panel has carefully reviewed the medical information provided by the Applicant
and is comfortable that it clearly outlines her health issues. On this basis, the Panel
considers it unnecessary to seek further information from the App licant’s doctors,
noting that to do so would be inconsistent with the usual procedures adopted by
FOS.
In the Panel’s view , none of the medical reports provided by the Applicant clearly
establish a link between her continued health issues during the claim period and the
works carried by the FSP’s contractors.
The Applicant’s medical reports confirm that, in order to best maintain her respiratory
health, she requires her home to be kept at a constant temperature and free of
potential allergens.
For the reasons outlined above, the Panel is not satisfied that the available
information establishes that the works carried out by the FSP’s contractors have left
the property adversely affected by mould or organic compounds.
The Applicant has also expressed concerns about the presence of plaster dust
throughout her home after the FSP’s contractors commenced building works.
Given the nature and extent of the works required, the Panel is not satisfied that it
was practical for the FSP’s contractors to carry out the wo rks in a manner which did
not generate any plaster dust in the Applicant’s home.
The cash settlement amount paid to the Applicant in May 2015 (after she indicated
she was unwilling to allow the FSP’s contractors to complete the repairs) included an
allowance for the property to be cleaned of plaster dust and other debris.
On several occasions during the claim process, the Applicant advised that her home
was a “registered medical unit/hospital home” being a sterile environment free of
mould, dust and other harmful elements.
The FSP sought to clarify with the Applicant what she meant by the reference to
“registration” and whether there were any specific legislative or other requirements
Case No: 399300 Determination Page 7 of 10
that applied to her home. In response, the Applicant advised that her home was
maintained at a constant temperature, had the windows and doors taped and the air
conditioning units regularly cleaned.
The FSP’s air conditioning technician has confirmed that he attended the property in
April 2015 to remove and clean the filters and covers of the indoor and outdoor air
conditioning units and confirmed they had no faults and were operating efficiently. As
noted above, the cash settlement made further provision for cleaning, to the extent
required as a result of the plaster dust generated during the building repairs.
Having carefully considered the measures adopted by the FSP, the Panel is satisfied
that it took reasonable steps to ensure the Applicant’s home would be reinstated to
its pre-existing condition following the repairs.
Cash settlement should be increased by $4,000
As outlined above, after the Applicant indicated she was unwilling to allow the FSP’s
contractors to complete the building repairs, the FSP cash settled her for the quoted
cost of the outstanding building repairs (and the cost of replacement carpet to be
paid as part of the contents claim).
The FSP also cash settled the Applicant for the costs of temporary accommodation
for the estimated time required to complete the building repairs and reimbursed her
for meal expenses incurred while she was living in temporary accommodation
(despite such expenses falling outside the terms of the policy).
The Panel is satisfied that settlement of the claim by way of a cash payment was
appropriate in the circumstances. It is clear that, by this time, the relationship
between the parties had significantly deteriorated and the Applicant had lost
confidence in the ability of the FSP and its contractors to complete the repairs to an
appropriate standard.
The Applicant says the amount of the cash settlement was insufficient to complete
the necessary repairs. However, under the terms of the policy, the FSP was entitled
to cash settle the Applicant for the amount quoted by the FSP’s builder to complete
the necessary building repairs, given it was the Applicant who elected not to have the
FSP’s contractors complete the repairs (which would have ensured she was not left
out of pocket).
Having regard to the nature of the damage and the extent of the outstanding repairs,
the Panel is satisfied that the cash settlement paid by the FSP was appropriate,
subject to the following comments.
The FSPs roof plumber (BW), who inspected the property on 5 February 2015,
identified damage to the floorboards in the main bedroom. While BW considered this
damage was pre- existing dry rot, the FSP’s claims consultant queried whether this
was in fact the case, given the extended history of the claim.
Having regard to the nature and location of this damage (as shown in the
photographs contained in BW’s rep ort), the Panel considers that it is quite possible
this damage was caused by the storm in January 2013 (or an earlier event for which
the FSP was liable). As outlined above, the FSP has acknowledged that the repairs
Case No: 399300 Determination Page 8 of 10
to the roof carried out following the 2008 storm claim were inadequate, which
resulted in ongoing water entry.
The Panel notes that the Applicant has advised that carpet has since been laid over
the damaged floorboards, in accordance with the settlement of the current claim.
Accordingly, this may need to be removed to address the damaged floorboards.
The FSP’s claim records suggest that the FSP’s contractors removed curtains in a
bedroom at the property which the restoration company (NR) had advised were not
restorable. However, it is not clear that the cash settlement paid by the FSP included
an allowance for the replacement of the curtains.
Given the above, the Panel considers it is fair in all the circumstances that the cash
settlement paid by the FSP be increased by an additional $4,000.
2.2 Is the Applicant entitled to compensation?
FOS may award compensation for financial and non-financial losses
Under the Terms of Reference, FOS may award compensation (capped at $3,300)
for consequential financial loss suffered by an applicant in connection with their
claim.
In addition, FOS may award compensation (capped at $3,000) for non-financial loss
where an applicant has suffered an unusual degree or extent of physical
inconvenience, time taken to resolve the situation or interference with their
expectation of enjoyment or peace of mind.
The fact that the Applicant’s policy excludes cover for consequential losses does not
preclude the award of compensation where such losses have occurred as a result of
the way in which the FSP has handled her claim, rather than as a result of the
insured event itself.
However, FOS adopts a conservative approach to the award of compensation for
non-financial loss. FOS expects applicants to be moderately robust and bear the
usual stress and inconvenience associated with an insurance claim.
Applicant has not established misconduct by FSP or its contractors
The Applicant has raised a number of concerns about the manner in which the FSP
handled her claim. Among other things, the Applicant says the FSP’s contractors
trespassed on her property and stole items in order to conceal evidence of ongoing
mould issues.
The Applicant also says the FSP and its contractors spied on her while she was living
in temporary accommodation.
It is clear the relationship between the Applicant and the FSP has deteriorated
significantly over the course of this claim, leading to an atmosphere of mistrust and
suspicion between the parties.
Case No: 399300 Determination Page 9 of 10
However, the FSP and its contractors have emphatically denied behaving in the
manner claimed by the Applicant, and the Applicant has been unable to provide any
proof confirming they have done so.
The concerns identified by the Applicant raise issues of serious misconduct. The
Panel considers it inappropriate to make a finding on such matters without a
substantial weight of proof confirming the events alleged by the Applicant occurred in
the manner claimed.
In the absence of any such confirming proofs, the Panel is not satisfied that the
Applicant has established any misconduct on the part of the FSP or its contractors.
FSP managed claim reasonably in the circumstances
The Applicant is also dissatisfied with various actions taken and procedures adopted
by the FSP during the course of the claim. Among other matters, she says the FSP:
failed to put in place appropriate video-conferencing arrangements to ensure
that she could participate in a site meeting at her property on 1 April 2015, given
she was unable to attend in person due to health issues; and
instructed its builder to commence repairs at the property on 14 April 2015,
despite not having provided her with a copy of the mould test results.
However, having carefully reviewed the claim records, the Panel is satisfied the FSP
acted reasonably on each of these occasions.
The FSP arranged for the contractors who attended the property on 1 April 2015 to
speak with the Applicant over the telephone, in order to assist in identifying the key
areas of concern for the purposes of the mould tests.
The Panel does not consider it is reasonable to require an insurer to provide video-
conferencing facilities in order to facilitate an insured person’s attendance at a site
meeting, particularly where the primary purpose of the inspection is to enable the
FSP’s appointed experts to conduct further inspection and testing.
The Panel is satisfied that the FSP acted reasonably and in good faith when it
authorised its builder to commence repairs at the property on 14 April 1015.
The repairs had been delayed pending receipt of the results of the mould tests
carried out on 1 April 2015. These results (which confirmed the mould levels were
within acceptable parameters) were received by the FSP on Sunday, 12 April 2015,
although they were not communicated to the Applicant until 14 April 2015.
Accordingly, at the time it commenced repairs, the FSP did so on the basis that the
mould remediation works had been successful and with the intention of ensuring the
repairs were completed and the Applicant’s property restored to its pre -existing
condition as soon as possible. The FSP has apologised to the Applicant for any
miscommunication as to when the repairs would commence.
Applicant is not entitled to compensation
For the reasons outlined above, the Panel is satisfied that the FSP managed the
Applicant’s claim reasonably in the circumstances. Accordingly, the Applicant is not
entitled to compensation.
Case No: 399300 Determination Page 10 of 10
3 Supporting information
3.1 FOS approach to this dispute
This dispute has not been the subject of a FOS Recommendation. Due to the nature
of the dispute, it has been referred directly to a Panel for Determination, in line with
the Operational Guidelines to the FOS Terms of Reference. The Panel consists of an
Ombudsman and two representatives with consumer and insurance experience.
The Panel has decided this case on its merits, having regard to the relevant law,
good industry practice, codes of practice and previous Financial Ombudsman
Service (FOS) decisions.
There has been a full exchange of all material information relied on for the purposes
of this Determination and each party has had the opportunity to address any issues
raised by the other.
The Panel has reviewed and considered all of the material provided by the parties.
While the parties have raised numerous issues in their submissions, for the purposes
of this Determination, the Panel has restricted its commentary to those issues that it
considers directly relevant to the outcome only.