Determination 399072

Storm damage to factory roof declined due to pre-existing roof defects and maintenance

FirmFinancial Firm (Unknown - Insurer)
Decided2016-05-23
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicant claimed further storm damage to a factory roof under a defined events policy, and the FSP had already paid part of the damage. AFCA found the roof had serious pre-existing defects, the applicant did not discharge his onus of proof, and no further indemnity was ordered.

The insured bears the onus of proving that storm rather than wear, tear or poor maintenance caused the damage, and unrefuted expert evidence showed prior defects.

Issues

Subjects and remedies

home or building damageno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 399072 Determination Page 1 of 4 Case number: 399072 23 May 2016 1 Overview 1.1 Dispute The applicant held a business insurance policy with the financial services provider (FSP), arranged through broker BJS. The cover was incepted on 15 September 2013. Building cover was provided for up to $569,250 under the policy, subject to an excess of $250. The applicant lodged a claim for storm damage to the roof of a factory which occurred on 31 July 2014. This led to an ingress of water into the building. Whilst the FSP’s policy extends to accidental damage cover, the FSP effectively contends the damage was due to a failure to keep the roof in an acceptable and waterproof state. It cited exclusions for wear, tear, gradual deterioration and maintenance-related issues. 1.2 Issues and key findings Is the FSP entitled to restrict its cover for the damage to the roof in the manner it has done? The roof of the building had serious pre-existing issues which allowed water to ingress during the storm. The FSP was entitled to deny liability for the claim. 1.3 Determination This determination is in favour of the FSP. Case No: 399072 Determination Page 2 of 4 2 Reasons for determination 2.1 Is the FSP entitled to restrict its cover for the damage to the roof in the manner it has done ? The applicant had a defined events policy The applicant had a policy which a defined events policy over a building he owned which covered storm damage to the building. He made a claim following a storm for damage to the building. The applicant has the onus of proof The applicant has the onus of proving that the damage to the building was caused by the storm. The roof of the building had serious pre-existing issues The FSP covered the cost of damage to the capping on the western wall and in the centre of the roof of the building, as well as the resultant damage inside the building. It otherwise denied cover for the balance of the claim. The FSP noted that a previous claim had been made by the applicant and declined in 2009/2010. Repairs were made to the roofing at the time by a repairer selected by the applicant. The FSP was not involved in this process of repair. The FSP obtained expert evidence in respect to the damage to the roof claimed. The FSP has pointed out in respect to this claim, that engineer SE considered the damaged roof was due to wear and tear and poor prior repairs. SE noted:  The ingress of water into the southwestern corner of the building was due to separation of the apron flashing from the rotation of the front western end tilt panel.  The ingress of water into the kitchen area was due to the separation of the capping due to storm activity.  He noted a ‘ number of maintenance issues ’ with the roof, including buckled roof sheets and a breakdown of the flexible sealing compound. Builder JP did the ‘make safe’ repairs to the roof. JP noted the maintenance issues with the roof and evidence of recent repair work. JP suggested the damage was: ‘… due to insufficient maintenance causing general wear and tear and incorrect installation. ’ Builder KC suggested there was differential movement between two tilt wall panels on the roof. This allowed water ingress. Unsuccessful attempts had been made to repair this damage in the past. Denting to roof sheets had caused pooling of water in some places (probably due to human traffic). There was no evidence of storm damage to the roof. Builder KP identified pre-existing: Case No: 399072 Determination Page 3 of 4 ‘… maintenance issues on the iron roof of the property have allowed water ingress to the kitchen, reception and showroom walls and ceilings, requiring rectification. ’ Plumber WE noted evidence of previous repairs to the flashings, roof sheets and bo x gutter and that he suspected ‘ this repair may have been unsuccessful, installation of capping along the front of building would fix this issue ’ . WE further noted that silicone had been used but had perished and was a likely point of water ingress. The available photographs of the roof (particularly the colour photographs from builders JP and KC) show a fairly dilapidated structure, which appears to have bee n subject to numerous previous repair attempts – this suggests the roof was an ongoing concern. The applicant has not discharged his onus of proof The applicant was invited to obtain/supply evidence to refute the contentions of the FSP’s experts but has fa iled to do so. After discussions with the Financial Ombudsman Service (FOS) staff, a specific email was sent to the applicant on 13 November 2015 to seek expert evidence about:  what damage was caused by the storm event, and  what damage could be attributed to prior poor repairs and/or maintenance issues. This evidence was not provided. As a consequence, without any contrary evidence, it is difficult to refute the existing evidence and find for the applicant. Conclusion Accordingly I find the roof of the building had serious pre-existing issues which allowed water to ingress during the storm. There is no persuasive evidence of storm created damage, beyond that already paid by the FSP. I find that the FSP is not liable to indemnify the applicant any further for the damage to the building. Case No: 399072 Determination Page 4 of 4 3 Supporting information 3.1 FOS process I have decided this dispute based on what I consider is fair in all the circumstances. I have had regard to the relevant law, good industry practice, codes of practice and previous decisions of the FOS. In making this determination I have considered the entire file, including all communications with the parties not specifically referred to in these reasons. I am satisfied that the documents I have relied on in making this decision have been exchanged between the parties. As a result, I am satisfied that the parties are aware of the issues to be considered and the submissions and evidence relevant to those issues. 3.2 Additional material The following additional material was considered:  applicant’ s quotations  FSP’s expert reports  reports from builders JP, KC and KP  report from plumber WE.