Determination 398236
Extent of cash settlement for water-damaged floorboards
Summary
The Applicants disputed the home insurer's offer to cash settle only the damaged part of water-damaged floorboards after matching flooring could not be found. AFCA ordered the FSP to replace the floorboards in the kitchen, dining and living areas, plus interest, but not the hallway.
Where undamaged flooring cannot be matched, the buildings cover limits repair or replacement to the affected room, so the open-plan kitchen, dining and living floorboards must be replaced.
Issues
- Claim amount dispute primary · upheld
“The FSP is required to pay for the cost to replace the floorboards in the kitchen, dining and living area as well as interest.”
- Product terms interpretation secondary · upheld
“The policy is not clear as to what this means in context of flooring.”
Subjects and remedies
home or building damagepay claimpay interestrepair or rectify
Text of the determination
Determination
General Insurance - Domestic Insurance - Home Building - FSP Decision - Denial of
claim-Exclusion/ condition
Case number : 398236 25 September 2015
1 Overview
1.1 Dispute
The Applicants lodged a claim with their home insurer, the Financial Services
Provider (FSP), for water damage to the flooring and cabinets in the kitchen.
The FSP has accepted the claim. However, a dispute has arisen regarding the
floorboards as the FSP is only prepared to cash settle the Applicants for the
damaged portion.
The Applicants are disputing this noting the cash amount would not enable them
to repair the damaged area. Instead, they believe all of the flooring requires
replacement.
1.2 Issues and key findings
What is the extent of the FSP’s liability ?
The extent of the FSP‟s liability is to replace the floorboards in the kitchen , dining
and living areas because of the following:
the current floorboards cannot be matched
any repair process will require a break in the floor and the likely installation of
a metal strip
the policy requires the FSP to replace the floorboards in the rooms affected
1.3 Determination
This Determination is substantively in favour of the Applicants.
The FSP is required to pay for the cost to replace the floorboards in the kitchen,
dining and living area as well as interest in accordance with section 2.1 of this
Determination.
In the event any additional damage occurs if a break in the flooring is followed
through with, the FSP is liable to repair same.
Case No: 398236 Determination Page 2 of 5
2 Reasons for Determination
2.1 What is the extent of the FSP’s liability ?
FSP based its cash settlement on JL’s quote
The following facts are relevant to this dispute and do not appear to be disputed:
approximately 8 square metres of flooring was affected by water
the undamaged flooring in the Applicants‟ home cannot be matched
the FSP‟s cash settlement is based on a quotation provided by its builder, JL,
dated 25 November 2013
Given these facts, the FSP has relied on the following provision to substantiate its
position:
“If we choose to repair your building, we will:
make reasonable attempts to match the materials used when your buildings were built
or last renovated
only repair or rebuild that part of your buildings which has been damaged
not pay to repair or replace undamaged materials or sections of your building in order to
create a uniform effect throughout your home
Where we are unable to match materials, we will use or pay for materials which we believe
to be of a similar kind or quality.”
The damaged floor is part of the “Building”
The Applicants dispute this aspect of the policy as they maintain the floorboards
should be classed as Contents.
I note “Building” has been specifically defined to include the following:
“fixed wall, ceiling or floor coverings other than carpets”
However, “loose floor coverings” or “any item which is not fixed to the buildings”
have been specifically included as categories that do not fall within the term
“Building”.
The flooring has been described as floating floorboards. However, it is clear that
they would not be described as “loose floor coverings” as they are fixed securely
to the floor of the home.
Given this, I am satisfied they should be considered as part of the “Buildings”.
Therefore, the above policy provision is relevant to this dispute.
It is not clear if new floorboards cannot lock in to the existing ones
The main argument presented by the Applicants is their belief that any floorboards
used to repair the damaged area will not physically fit (lock in) to the existing
floorboards.
I no te the Applicants‟ position is predominantly based on an email trail between JL
and a flooring specialist (DG) where the following was stated:
Email from DG to JL dated 26 February 2014
“No luck this is an old profile.
I have some 14mm being machined down (from identical stock to existing) – tests will be
done on locking mechanism, should all be ok we can schedule repairs for next week.”
Case No: 398236 Determination Page 3 of 5
Email from JL to Applicant dated 28 February 2014
“I have been in cont act with Steve several times and we are looking at (with your approval,
of course) total floor replacement as we do not feel that the machined 14mm boards will be
an acceptable material to use on the damaged area.”
Having reviewed this, I cannot be satisfied that JL‟s email stated with any
sufficient clarity that the reason the machined boards were not suitable was due
to the locking mechanism.
If this was the case, I would have anticipated that JL‟s email would have stated
that in clearer terms.
The repair process will require the installation of a metal strip
Despite this, I note the FSP‟s settlement is based on JL‟s quotation dated 25
November 2013. This quotation included all of the proposed works necessary.
With respect to the flooring, the works included the following description:
“Remove and replac e 8m2 of water affected bamboo floating floor to match existing as near
as possible. (Flooring specialist to report back to supervisor on availability of flooring
profile).”
I note this quotation pre-dated the email exchanges between JL, TG and the
Applicants regarding the availability of flooring.
As evident in that email exchange and subsequent correspondence, JL ultimately
recommended that the Applicant have all the floorboards replaced. This was
because the machined 14mm boards would not be an acceptable material.
The FSP was specifically asked to address how JL could follow through with its
quotation given its advice to the Applicants in this regard.
The FSP responded in a submission dated 7 July 2015 that included a response
from JL. According to the FSP, suitable replacement floorboards could be found
and a „break‟ in the flooring between the kitchen and living area could be installed.
This „break‟ would likely include the installation of a metal strip.
Given the FSP‟s response and JL‟s previous recom mendation, I therefore accept
that any repair process would likely require a break in the flooring and the
installation of a metal strip.
Parties’ arguments about how the policy operates
The Applicants have disputed the application of a metal strip noting this would
change the character of the floorboards and introduce a material that is neither of
a kind and quality similar to the current makeup.
Further, this would be contrary to the principle of indemnity, which is to restore
them to the position they were in prior to the claim occurring.
The FSP has argued that as the Applicants are seeking to replace floorboards
that were not damaged, this does not engage the insuring provision.
Case No: 398236 Determination Page 4 of 5
Policy clearly limits FSP’s liability when existing materials cannot be
matched
I have carefully considered the parties‟ arguments as well as the policy.
There are numerous parts of the policy that clearly explains that the FSP will not
commit to repairing undamaged areas to create a uniform appearance.
Further, the policy clearly states that the FSP will commit to repairing only that
part of the building that is damaged.
Given the clear wording of the policy, I do not accept the Applicants‟ argument
that the principle of indemnity, or the introduction of a metal strip, requires the
FSP to replace all undamaged areas.
FSP’s liability limited to the room affected
In regards to the extent of repairs, I note the FSP‟s liability is limited to the “part of
the building” that has been damaged.
The policy is not clear as to what this means in context of flooring.
I note that under the contents cover, the FSP commits to repairing or replacing
the whole room where the damage occurred if it involves carpets or loose floor
coverings that cannot be matched.
It seems appropriate that a similar limitation would apply to floorboards that form
part of the building. This is because it is difficult to accept that the mutual intent of
the parties would be for the cover to be distinct if the damaged flooring was part of
a building as compared to a content.
Further, such an interpretation is consistent with the following provision set out in
the buildings cover:
“If your claim is for damage to fixed coverings on walls, floors and ceilings, we will only pay
for repair or replacement in the room, hall or passage where the damaged occurred. In open
plan homes we will pay only for the damaged parts of such coverings in the functional area
we think is affected. ”
Therefore, I consider the extent of the FSP‟s indemnity in circumstances when it
cannot match the current floorboards and is required to install a metal strip is to
replace the room affected.
FSP liable to replace kitchen, dining and living area
The Applicants recently provided a copy of the floor plan. They noted that the
floorboards are contained in the following areas:
hallway leading from the front door to the kitchen
kitchen, dining and living area
I note the policy does not define what a room is for the purposes of cover. In a
previous decision issued by FOS (case 367171), a room was described as being
an area separated from other spaces or passageways by interior walls. That is, it
can be described as any distinguishable space within a structure.
I consider such a description to be fair and appropriate in this case.
Case No: 398236 Determination Page 5 of 5
In that previous decision, I note a passageway was specifically excluded.
According to the floor plan for the Applicants‟ home, the hallway from the front
door to the kitchen and dining area would be analogous to a passageway and
therefore should not be considered the same room.
Accordingly, the FSP is not required to replace this floor area.
However in regards to the kitchen, dining and living room, these are all part of an
open area. There is no distinguishable spaces or passageways. Therefore, it is
my opinion that the floorboards in this area should all be replaced.
Parties to work co-operatively to assess the amount of flooring needed
The extent of the FSP‟s liability is not clear.
JL‟s quotation is not a suitable cash settlement basis as it is too limited in scope
regarding th e area affected. Similarly, the Applicants‟ quotes are too large as they
provide for the full replacement of all the floorboards.
Given this, the parties are asked to work co-operatively to assess a reasonable
amount that enables the replacement of the areas set out in this Determination.
In this regard, I consider JL‟s quote should form the basis of any cash settlement.
It should be expanded to include the amount of necessary flooring that
encompass the areas allowed in this decision.
In the event any further aspect of this claim is cash settled, the FSP is to pay
interest on any additional sum paid. Interest is payable from 5 March 2014, being
the date it first attempted to cash settle the claim, to the date payment is affected.
FSP liable for additional costs if break in flooring results in additional
damage
By way of clarity, if the Applicants do decide to repair only the affected area and
the installation of a break in the flooring results in additional damage, the FSP is
liable for same.
This is regardless of the fact the FSP has chosen to cash settle the claim.
This is because I do not accept it is fair in all the circumstances or consistent with
the duty of utmost good faith that the FSP base its settlement on such a repair
method yet:
refuse to do the repairs itself, and
allow the Applicants to bear the cost of further damage that such a process
can possibly generate.