Determination 398219

Garage rebuild with non-motorised roller doors; claim settlement scope and delay

FirmFinancial Firm (Unknown - Insurer)
Decided2015-09-25
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicant's home insurer rebuilt his garage with non-motorised roller doors he had agreed to, and he complained about the doors and the time taken. AFCA found the insurer complied with the policy and need not motorise the doors or pay compensation, but must cash settle the pigeon run and shelving.

Having replaced the damaged structure as the applicant agreed, the insurer was not required under the policy to fund motorised doors.

Issues

Subjects and remedies

elderly or capacityhome or building damagepay claim

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 398219 Determination Page 1 of 8 Case number : 398219 2 5 September 2015 1 Overview 1.1 Dispute The Applicant lodged a claim under his home insurance policy with the Financial Services Provider (FSP) after his garage was damaged by a falling tree branch. The FSP accepted the claim and arranged for the garage to be demolished and rebuilt. The Applicant is unhappy that the replacement garage has manual lift roller doors rather than hinged doors like the original garage. He wants the FSP to install a motor, as he has difficulty operating the roller doors due to age and illness. The Applicant is also dissatisfied with the manner in which the FSP has handled his claim . 1.2 Issues and key findings Has the FSP complied with its obligations to the Applicant? The FSP complied with its obligations under the policy by replacing the damaged garage with a new garage constructed in accordance with specifications agreed to by the Applicant. The Applicant’s existing garage did not have motorised doors and therefore the FSP was not required to include motorised doors in the design of the replacement. The Applicant has not established that the FSP’s contractors agreed to provide a mechanism to motorise the garage doors. Is the Applicant entitled to compensation? The FSP managed the Applicant’s claim reasonably overall. The time taken to complete the rebuilding of the garage was not unreasonable, having regard to the nature and extent of the works required. 1.3 Determination This Determination is in favour of the FSP. The FSP has discharged its obligations and is not required to take any further action, other than cash settling the Applicant for the pigeon run and internal shelving as previously offered and on the basis set out in section 2.1 below (to the extent it has not done so already). Case No: 398219 Determination Page 2 of 8 2 Reasons for Determination 2.1 Has the FSP discharged its obligations to the Applicant? FSP replaced damaged garage with modern structure Under the terms of the Applicant’s policy, the FSP was entitled to settle the Applicant’s claim by :  subject to the Applicant’s agreement, arranging for the FSP’s preferred contractors to repair or rebuild the damaged garage; or  paying the Applicant the reasonable cost of repairing or rebuilding the damaged garage. The FSP initially considered cash settling the Applicant for the cost of repairing the damage to his garage caused by the fallen tree. A cash settlement was considered approp riate based on advice from the FSP’s builder that, due to the age and condition of the existing structure, he would not be able to guarantee the repairs. The FSP subsequently concluded that the repairs were not feasible and instead offered to demolish the damaged garage and replace it with a new garage to be built on a freshly poured concrete slab. The Applicant agreed to this approach. Where an insurer elects to rebuild a damaged section of the insured property, the insurer is required to replace the damaged section on a like for like basis (subject to any modifications required to comply with applicable building requirements). In certain situations, an insurer may agree to incorporate additional improvements or upgrades during the rebuilding process. However, the insurer is not obliged to do so and may require the insured to fund the increased costs associated with any such improvements or upgrades. The FSP’s technical specialist (BS) described the Applicant’s existing shed and garage as very old and eclectic in nature, consistent with the estimated age of his home (over 70 years old). BS considered that, while the Applicant’s garage was still functional, it was nearing the end of its useful life. Photographs of the existing structure suggest BS’s description was accurate. A photograph of the replacement garage following completion of construction shows a substantial, modern structure with a steel frame and Colourbond cladding . The FSP’s claim records indicate that the replacement garage was constr ucted at a cost of approximately $50,000. Based on the available information, I am satisfied that the approach taken by the FSP to settling the Applicant’s claim by rebuilding his garage was appropriate in the circumstances. Applicant agreed to inclusion of non-motorised roller doors The Applicant’s existing garage had two hinged , barn-type doors which opened into the bluestone laneway at the rear of the property. However, the replacement garage Case No: 398219 Determination Page 3 of 8 constructed by the FSP’s builder included double and si ngle roller doors. It appears this change was necessary to comply with council requirements. The Applicant says the roller doors are too heavy for him and his wife to open and therefore the FSP should provide a motorised mechanism to operate the roller doors. The FSP’s claim notes include a file note by its technical specialist (BS) confirming that he met with the Applicant on 12 March 2015 to discuss the proposed replacement of the garage. BS’s file note states that the Applicant agreed to the construction of a Colourbond garage with double and single roller doors with “no power”. In addition to his contemporaneous file note, BS has provided a statutory declaration in which confirms that he discussed the inclusion of non-motorised roller doors with the Applicant at the meeting on 12 March 2015. The Applicant signed a scope of works for the construction of the new garage on 29 April 2015, which stated that the garage was to be installed in accordance with the engineer’s recommendations. The FSP’s technical specialist (BS) has confirmed that he showed the plans for the garage to the Applicant and his niece’ s husband (a qualified builder who assisted the Applicant during the claim process). While the scope of works includes a line item for disconnec ting the power to the existing garage, I am satisfied that this item was included in error. The statutory declaration provided by BS confirms that electricity was not connected to the original garage and the Applicant has not provided any information to re fute this. Based on the available information, I am satisfied that the design of the replacement garage (as agreed to by the Applicant) included non-motorised roller doors. The Applicant had sufficient time between the initial discussion on 12 March 2015 and his subsequent acceptance of the scope of works on 29 April 2015 to raise any concerns about the design of the garage. However, he did not do so. While the Applicant was elderly and in ill health, he was ably assisted by his niece and her husband who were actively involved in the claim process. On this basis, I am satisfied that, once the Applicant signed the scope of works on 29 April 2015, the FSP was entitled to proceed with the construction of the garage in accordance with the agreed specifications. FSP is not required to provide motorised mechanism for roller doors The available information indicates that the Applicant did not raise concerns about the design of the garage doors until June 2015, more than a month after he had accepted the scope of works. The claim records reflect that the FSP made enquiries with its builder to confirm whether any arrangements could be made to address the Applicant’s concerns. T he FSP’s builder confirmed that the design of the doors could not be changed as this would require changes to the structure as a whole, and council approval had already been obtained based on the existing plans. Case No: 398219 Determination Page 4 of 8 The builder advised that it would be possible to motorise the roller doors at a cost of approximately $400 to $800. However, the FSP declined to cover this as part of the claim and told the Applicant that the necessary modifications would need to be completed at his own cost. As outlined above, the Applicant’s existing garage did not have motorised doors (or any power connection) and the Applicant had agreed to the construction of a new garage with non-motorised roller doors. In these circumstances, the FSP was not required to pay for a motorised mechanism to operate the roller doors in order to satisfy its obligations to the Applicant under the policy. The FSP’s contractors also discussed with the Applicant the possibility of installing solar panels to the garage, to provide an alternative source of power for the roller doors. However, the FSP says that any such arrangements would be at the Applicant’s cost. The Applicant says that the FSP’s contractors agreed to motorise the roller door (whether by solar power or otherwise) as part of the settlement of his claim. However, I do not consider the available information is sufficient to establish this. Further, even if advice to this effect was provided, there is no information to suggest that the Applicant acted to his detriment in reliance on such advice. In these circumstances, the FSP is not required to motorise the roller doors. FSP has agreed to cash settle Applicant for cost of pigeon run and shelving The construction of the replacement garage necessitated the removal of internal shelving and a homemade pigeon run. The FSP has agreed to cash settle the Applicant for the cost of replacing the pigeon run and the internal shelving, subject to him proposing a reasonable basis for settlement. The Applicant says he never received any written documentation concerning this aspect of the settlement. However, he has not disputed the approach proposed by the FSP. In the circumstances, I am satisfied that the FSP’s proposed approach is reasonable, Accordingly, the FSP should cash settle the Applicant for the cost of replacing the pigeon run and the internal shelving (to the extent it has not do ne so already), subject to the Applicant providing a reasonable estimate. If the Applicant does not provide a reasonable estimate within 30 days of accepting this Determination, the FSP is to assess the Applicant’s loss based on the information available, and cash settle him on that basis. Case No: 398219 Determination Page 5 of 8 2.2 Is the Applicant entitled to compensation? FSP did not unreasonably delay claim settlement The Applicant is dissatisfied with the time taken to complete the rebuilding of his garage. He says it is unreasonable that it took almost six months to replace “a tin shed”. Having carefully reviewed the claim history, I am satisfied that the time taken to rebuild the Applicant’s garage was reasonable in the circumstances. The appropriate timeframe for completing the rebuilding of the garage needs to be considered in the context of the nature and extent of the works required. In this regard, the available information indicates that:  the replacement garage was a significantly more substantial structure than the “tin shed” describ ed by the Applicant;  the construction of the garage involved building works at a cost of over $50,000, including the construction of new foundations and the pouring of a concrete slab;  the location of the garage adjacent to the rear bluestone laneway required modifications to the design of the garage to provide adequate vehicle access;  the works required planning approval, which necessitated the engagement of an a draftsman to prepare plans and the appointment of a private building inspector;  the characteristics of the soil at the site required the involvement of an engineer to ensure the appropriate design of the concrete slab for the garage; and  the FSP also engaged a surveyor to confirm that the replacement garage would not extend beyond the legal boundar y of the Applicant’s property. The Applicant has suggested that not all of the steps taken by the FSP (for example, the engagement of a surveyor) were necessary. However, in circumstances where the FSP was responsible for significant building works at th e Applicant’s property, it was incumbent on the FSP to make sure that these works were carried out in compliance with all applicable requirements. Given the features of the site and the extent of the proposed works, I am satisfied that the actions taken by the FSP in carrying out were appropriate in the circumstances. While the engagement of several specialist contractors may have increased the time taken to complete the works, their involvement also ensured that the works were completed to an adequate standard. The FSP’s claim notes reflect that the Applicant was advised when the works were agreed in March 2015 that it may be up to two months before the works commenced (while plans were completed and approval obtained). The works ultimately commenced in early June. Accordingly, while there may have been some avoidable delays during the course of the works, these delays were not significant in the context of the overall timeframe. Case No: 398219 Determination Page 6 of 8 Given his personal circumstances, it is understandable that the Applicant and his family sought to have the claim resolved as soon as possible. However, the rebuilding of the garage necessarily involved a somewhat lengthy process, most aspects of which could not be easily expedited. FSP has managed claim reasonably overall Based on the available information, I am satisfied that the FSP handled the Applicant’s claim reasonably overall. While there may have been occasions where the FSP’s consultants failed to promptly respond to the Applicant’s enquiries, I am satisfied that the F SP generally sought to keep the Applicant reasonably informed as to the progress of the claim. It is clear that there were some communication issues between the Applicant’s representatives and the FSP’s consultants. However, I am not satisfied that the Applicant has established any behaviour on the part of the FSP or its consultants such as would justify the award of compensation. Case No: 398219 Determination Page 7 of 8 3 Supporting information 3.1 FOS approach to this dispute As advised to the parties, FOS has considered it appropriate to expedite this dispute in accordance with the Operational Guidelines to the FOS Terms of Reference, due to the nature of the dispute. Accordingly, this dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination. There has been a full exchange of all material information relied on for the purposes of this Determination and each party has had the opportunity to address any issues raised by the other. All of the material provided by the parties has been reviewed and considered for the purposes of this Determination. This dispute has been decided on its merits, having regard to the relevant law, good industry practice, codes of practice and previous Financial Ombudsman Service (FOS) decisions. While the parties have raised numerous issues in their submissions, for the purposes of this Determination, commentary has been restricted to those issues considered directly relevant to the outcome only. The Applicant has been assisted by his niece and her husband during the course of this dispute. For the purposes of this Determination, submissions made by the Applicant’s niece have been treated as if they were made by the Applicant himself. Further, in the interests of brevity and simplicity, any actions taken or statements made by the Applicant’s niece or her husband during the claim process have been treated as if such actions were taken or such statements were made by the Applicant himself. 3.2 Renewal premium The Applicant sought a refund of his renewal premium for the policy period following the collapse of the tree which gave rise to his claim. The FSP agreed to credit him with a loyalty discount of $41 as a good will gesture, but refused to refund his premium. The FSP was entitled to charge the Applicant a premium for the renewal of his insurance policy for the new policy period. To the extent that the Applicant disputes the amount charged, this issue is outside FOS’s jurisdiction, in accordance with paragraph 5.1(b) of the FOS Terms of Reference. The FSP’s decision to credit the Applicant with a loyalty discount was a good will gesture. Actions of this type are not subject to review by FOS. 3.3 Terms of policy Subject Terms Case No: 398219 Determination Page 8 of 8 Subject Terms Settlement of building claims If we agree to cover your claim under Buildings Insurance, then we will:  pay you the cost to repair or rebuild the part of your home that was damaged (whic hever is lower) … We will choose to settle your claim for loss or damage to your home … in one of the following ways …  If you agree, we can arrange for our preferred repairs, suppliers or builders to repair or rebuild your home .

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.