Home / Financial Firm (Unknown - Insurer) / Determination 397145

Determination 397145

claim_amount_dispute

FirmFinancial Firm (Unknown - Insurer)
Decided2015-12-09
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicant disputed the $178,596.74 cash settlement for fire repairs and sought more, plus $11,900 temporary accommodation. AFCA found the FSP followed the prior determination's process, the consultant was independent, and the accommodation was already paid, and ordered nothing further.

Having complied with the prescribed process for a revised scope and independent quote, the FSP is not liable for more unless the applicant shows lack of independence or a manifestly insufficient amount.

Issues

Subjects and remedies

home or building damageno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 397145 Determination Page 1 of 6 Case number: 397145 8 December 2015 1 Overview 1.1 Dispute In November 2013, the Applicant lodged a claim under his home insurance policy with the Financial Services Provider (FSP) after his home suffered significant damage in a fire. The FSP accepted the Applicant’s claim and made arrangements to repair the property. However, the parties were unable to agree on the nature and extent of the repairs required and so the Applicant lodged a dispute with FOS. The Panel issued a FOS Determination (367706) in December 2014, which provided that the FSP was to cash settle the Applicant for the cost of the necessary repairs, based on a revised scope of works and quotation to be provided by suitably quali fied consultants. The Applicant is dissatisfied with the settlement amount of $178,596.74 offered by the FSP following this process. 1.2 Issues and key findings Is the FSP required to increase the settlement amount? The FSP is not required to increase the settlement amount because:  it has complied with the process for determining the settlement amount as set out in the previous FOS Determination; and  the Applicant has not established that the building consultant appointed by the FSP to prepare the scope of works has failed to act independently, or that the cost estimate is otherwise inadequate. 1.3 Determination This Determination is in favour of the FSP. The FSP is not required to increase the settlement amount. Case No: 397145 Determination Page 2 of 6 2 Reasons for Determination 2.1 Is the FSP required to increase the settlement amount? Previous Determination outlined process for determining settlement amount As outlined above, this matter was the subject of a previous FOS Determination in December 2014. In that Determination, the Panel concluded that the FSP had failed to adequately manage the process for finalising the scope of works for the repair of the fire damage to the Applicant’s home, and was responsible for the bulk of the delay in settling the claim. On this basis, the Panel determined that the FSP was liable for the cost of restoring the Applicant’s property to its condition prior to the fire. However, the Panel concluded that, given the considerable discrepancies between the various scopes of work and quotations provided during the claim process, it was not possible to determine with any certainty the nature and extent of the necessary repairs. Accordingly, the Panel determined that the FSP was required to:  appoint a suitably qualified independent consultant (who was acceptable to bot h parties and had not been involved in the claim to date) to undertake a detailed assessment of the property and prepare a revised scope of works for the necessary repairs; and  engage an appropriately qualified builder to provide a quotation based on the revised scope of works, and cash settle the Applicant for the quoted cost of the repairs. Applicant is dissatisfied with proposed settlement amount Following the issue of the previous Determination, the FSP appointed a building consultant (S) to inspect the property and prepare a revised scope of works. The Applicant agreed to the appointment of S, who had not previously been involved in the claim. A building consultant (GJ) employed by S inspected the Applicant’s property on 16 January 2015, following which he prepared a fire reinstatement inspection report and a scope of works for the repair of the property. An estimator (DS) employed by S provided a detailed cost estimate for the necessary repairs of $151,379.78, based on the scope of works prepared by G J. DS’s estimate included a margin of 15% as well as additional allowances of 6% for overheads (such as building insurance), 5% for the cost of a project manager and 3% for unforeseen risks. At the Applicant’s request, the FSP agreed to increase the settle ment amount by an additional 15%. The FSP also included an amount of $4,165 for temporary accommodation expenses for a period of seven weeks while the repairs were Case No: 397145 Determination Page 3 of 6 completed. These adjustments resulted in the FSP’s final settlement offer of $178,596.74. However, the Applicant is not willing to accept this amount in full and final settlement of his claim, as he considers it is not sufficient to allow him to restore his property to its condition prior to the fire. The Applicant considers that S has failed to act independently and has been unduly influenced by the FSP in preparing the revised scope of works and cost estimate. FSP has complied with process outlined in previous Determination The Panel is satisfied that, by appointing S to prepare the revised scope of works and cost estimate, the FSP has complied with the process outlined in the previous Determination. The Panel notes that the Applicant agreed to S being appointed to undertake this work. Accordingly, the Applicant will be bound by the outcome of this process, unless he is able to establish that S has failed to act independently or that the settlement offer is otherwise manifestly insufficient. Available information does not establish a lack of independence by S The Applicant says S has simply adopted the findings in reports provided by previous contractors engaged by the FSP which provided for certain items to be cleaned or repaired, rather than replaced. The Applicant considers the FSP has deliberately influenced S to adopt this approach, in order to reduce the cash settlement amount. However, having carefully reviewed the available information, the Panel does not consider it supports the Applicant’s position. The fire reinstatement inspection report prepared by GJ provides a detailed assessment of the fire and smoke-related damage to each area of the property, based on the visual inspection carried out in January 2015. GJ’s report explains the basis on which he has identified the appropriate method for the repair of each aspect of the damage, as reflected in the revised scope of works. On this basis, the Panel is satisfied that GJ applied an independent mind (as well as his own skill and expertise) in determining the repairs required to reinstate the Applicant’s property to its condition prior to the fire. The Panel notes that, as outlined in the previous Determination, one of the key issues regarding the scope of repairs required concerned the extent to which it was necessary to strip out the plasterboard wall and ceiling linings in the lower level of the property. The revised scope of works prepared by GJ provides for the removal and replacement of the ceiling and wall linings throughout the majority of the downstairs level. GJ advised that this was necessary to allow the removal of the smoke affected wall and ceiling insulation and access to the wall ties between the internal timber frames and the external brick walls. Case No: 397145 Determination Page 4 of 6 The Panel acknowledges that GJ’s scope of works provides for the cleaning, repair and/or reinstallation of certain items which the previous builder (M) had recommended be replaced. However, in each case, the Panel is satisfied that GJ has provided a logical and reasonable explanation for the approach adopted in his scope of works, which was based on his own visual inspection of the property. For example, GJ has confirmed that:  while the main ducting and outlets of the ducted air conditioning system suffered smoke damage and require replacement, the mechanical components were unaffected;  while two of the wall mounted condenser units forming part of the split system air conditioning units required replacing, the externally mounted compressors were unaffected;  the bulk of the kitchen cabinets did not require replacing as they exhibited light staining only which could be removed by clea ning. The cabinets did not require removal in order to allow access to the wall frames, as these could be accessed through adjacent rooms and external walls;  the bulk of the wiring had not been affected by smoke damage and was protected by being double insulated as well as by the insulation to the wall and ceiling frames;  the laundry had suffered minimal smoke damage as it was outside the main footprint of the building and therefore required repainting only; and  the downstairs tiles did not need to be replaced as the upstairs ties (which had been more severely affected by smoke from the fire) had responded well to cleaning. Accordingly, the Panel does not consider that the Applicant has established that S failed to act independently or was unduly influenced by the FSP in preparing the revised scope of works and cost estimate. Provision of forged cleaning report did not alter outcome As outlined in the original Determination, the Applicant’s trust in the FSP to properly manage his claim was adversely affected by an incident early in the claims process, when the FSP’s restoration sub - contractor forged the Applicant’s signature on a report confirming he was satisfied with the results of a test clean conducted at the property. The FSP has previously acknowledged the forgery occurred and has apologised to the Applicant for the actions of its sub-contractor. The FSP has also acknowledged that the cleaning report was included in the background materials provided to GJ when S was engaged to prepare the revised scope of works and cost estimate. In the Panel’s view, the provision of this document to GJ was extremely unfortunate and inappropriate, given the significant degree of distress it had already caused the Applicant. Case No: 397145 Determination Page 5 of 6 However, the Panel does not consider that the provision of the forged cleaning report altered GJ’s findings. As outlined above, GJ’s comments in his inspection report and scope of works indicate that he formed his views about the extent to which cleaning of various items would be effective based on his own inspection of the property, coupled with his skills and experience. GJ has also confirmed in writing that his report was not based on either the cleaning report or any earlier scopes of work prepared by the FSP’s previous contractors. FSP is not required to increase settlement amount For the reasons outlined above, the Panel does not consider the Applicant has established that the FSP failed to implement the process outlined in the previous Determination in order to determine the settlement amount. The Applicant has not provided any independent information to establish that the settlement amount is manifestly insufficient. The Panel notes that, as outlined above, the estimate includes significant allowances for overheads, project management costs and contingencies. Further, the FSP has already agreed to increase the estimate by an additional 15%. The Applicant says the settlement amount should be increased to reflect the final scope of works and quotation provided by the FSP’s original bu ilder (M) following protracted negotiations with the Applicant. However, as outlined in the previous Determination, the Panel was not satisfied that M’s final scope of works and quotation accurately reflected the repairs required to the property. It was for this reason that the Panel prescribed the process set out in the previous Determination to determine the appropriate settlement amount. Given the Panel is satisfied that the FSP has complied with this process, the Applicant is not entitled to any amount in addition to the amount of $178,596.74 offered by the FSP. Applicant is entitled to temporary accommodation costs for prior period The Applicant seeks an additional amount of $11,900 for temporary accommodation costs for the period from October 2014 to February 2015. However, the Applicant has not provided any additional information in relation to this aspect of his claim. The FSP has acknowledged that it agreed to pay the Applicant’s reasonable temporary accommodation costs for this period and has confirmed it paid the Applicant the amount of $7,050 in February 2015 (representing 12 weeks’ rent). On this basis, the FSP considers it has no further liability for temporary accommodation expenses during this period. The Panel accepts that the amount paid by the FSP satisfies its obligations to the Applicant for the relevant period. Accordingly, unless for some reason this payment has not been made, the FSP has no further obligations in this respect. Case No: 397145 Determination Page 6 of 6 3 Supporting information 3.1 FOS approach to this dispute This dispute has not been the subject of a FOS Recommendation. Due to the nature of the dispute, it has been referred directly to a Panel for Determination, in line with the Operational Guidelines to the FOS Terms of Reference. The Panel consists of an Ombudsman and two representatives with consumer and insurance experience. The Panel has decided this case on its merits, having regard to the relevant law, good industry practice, codes of practice and previous Financial Ombudsman Service (FOS) decisions. There has been a full exchange of all material information relied on for the purposes of this Determination and each party has had the opportunity to address any issues raised by the other. The Panel has reviewed and considered all of the material provided by the parties. While the parties have raised numerous issues in their submissions, for the purposes of this Determination, the Panel has restricted its commentary to those issues that it considers directly relevant to the outcome only. 3.2 Additional issues During the course of this dispute, the Applicant raised concerns about different signatures on two letters apparently signed by the FSP’s home claims manager (DH). However, a close inspection of one of these letters reveals notations indicating it appears to have been signed by another employee of the FSP on DH’s behalf, which would explain the apparent discrepancy.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.