Determination 395915

Fire claim rectification cash settlement and delay

FirmFinancial Firm (Unknown - Insurer)
Decided2016-06-03
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$21,219
Non-financial loss$1,500
Amount claimed$23,834
SourceAFCA PDF

Summary

The applicants disputed the insurer's fire claim rectification, including painting quality and remaining defects, and sought further costs and compensation. AFCA ordered a cash settlement of $20,668.50 for repainting and remaining repairs, reimbursement of the MP report, and $1,500 for non-financial loss, but rejected the claim for a lost necklace.

Given the breakdown in trust with the insurer's contractors, a cash settlement was appropriate, and the insurer's delay and inadequate repairs justified non-financial loss compensation.

Issues

Subjects and remedies

home or building damagepay claimpay compensationpay non financial loss

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 395915 Determination Page 1 of 9 Case number: 395915 26 May 2016 1 Overview 1.1 Dispute The applicants lodged a claim under their home insurance policy with the financial services provider (FSP) after their home was damaged by a fire in November 2013. The FSP accepted the claim and made arrangements to repair the property. After the initial repairs proved inadequate, the FSP arranged for its builder to undertake rectification works. The FSP has acknowledged that the building still requires further repairs and has offered to cash settle the applicants for the cost of these works. However, the parties have been unable to agree on an appropriate cash settlement amount. The applicants are also dissatisfied with the manner in which the FSP has handled their claim and seek compensation for various financial and non-financial losses suffered as a result. 1.2 Issues and key findings How should the building claim be settled? The FSP is required to pay the applicants a total of $20,668.50 to reflect the reasonable costs of repainting the property and completing the remaining repairs. Are the applicants entitled to any additional amounts? The applicants are entitled to reimbursement of costs incurred in obtaining reports identifying the outstanding issues with the rectification repairs. They are also entitled to compensation for non- financial loss as a result of the FSP’s handling of their claim. The FSP is not liable for the loss of the female applicant’s necklace as there is insufficient inform ation to establish the necklace was stolen by the FSP’s contractor. 1.3 Determination This determination is partly in favour of the applicants. The FSP is to pay the applicants the amount of $20,668.50 in full and final settlement of their claim, plus an additional $1,500 as compensation for non-financial loss. If it Case No: 395915 Determination Page 2 of 9 has not already done so, the FSP is to reimburse the applicants for the cost of MP’s report ($550). The FSP is not required to pay interest on these amounts. Case No: 395915 Determination Page 3 of 9 2 Reasons for determination 2.1 How should the building claim be settled? Dispute concerns extent of FSP’s liability for further rectification repairs As outlined above, the FSP accepted the applicants ’ claim for damage to their home caused by an electrical fire in November 2013. The fire destroyed the garage at the property and also caused damage to other rooms, when smoke from the roof space entered the rooms in the main part of the house. The FSP arranged for repairs to the home to be carried out by its builder (JL). The FSP also engaged a rest oration specialist (C) to clean the applicants’ damaged contents items. After the applicants expressed concern about the standard of works carried out by the builder (JL), the FSP engaged a building consultant (S) to undertake an audit of the repairs. In June 2014, S prepared a report identifying various aspects of the repairs which he considered to be defective, together with a scope of works outlining the further steps required to address these issues. The FSP arranged for JL to undertake the rectification repairs in accordance with the scope of works provided by S. In October 2014, S re-inspected the property and advised that in his opinion the repairs had been completed to acceptable industry standards. In December 2014, the FSP engaged an electrical contractor (AJ) to inspect the electrical wiring at the property, after the applicants ’ electrician expressed concerns about the quality of the work performed by the FSP’s contractors. AJ attended the property and reinsulated wiring that appeared to have bee n inappropriately stripped. After carrying out this work, AJ confirmed that the electrical wiring at the property was safe. However, the applicants remain concerned that the rectification works carried out by the FSP’s contractors do not comply with industry standards and are inadequate to restore the property to its condition prior to the fire. In particular, the applicants have expressed concern about the quality of the painting completed by the FSP’s contractors , as well as defects in various other aspects of the repairs. Among other things, the applicants say that the FSP’s contractors failed to replac e a downpipe in the garage area which has resulted in the gutters overflowing during periods of heavy rain, causing water damage to their ceilings and various contents items. During the course of this dispute, the applicants obtained their own inspection reports which identified various defects in the building repairs. Case No: 395915 Determination Page 4 of 9 Following receipt of the applicants’ reports, the FSP accepted that further rectificati on works are required. However, the FSP disputes the extent of these works, as well as the estimated cost of undertaking them. Outstanding repairs should be cash settled Given the background to this dispute, it is appropriate that the FSP cash settle the applicants for the cost of completing the outstanding repairs. It is clear that the relationship between the parties has irretrievably broken down and the applicants no longer have any trust or confidence in the ability of the FSP’s contractors to carry out their appointed tasks. The applicants have confirmed that they would prefer a cash settlement, so they can engage their own contractors to complete the necessary works. The current dispute has arisen as a result of the repeated failure by the FSP’s contractors to complete the repairs to an adequate standard. In these circumstances, it is important to ensure that the applicants are not disadvantaged by being paid a cash settlement (rather than having the FSP undertake the further repairs). FSP is required to cash settle the applicants for the cost of repainting The applicants have provided a report from the master painters association in their State (MP) which identified quality issues with the paintwork carried out by the FSP’s contractors. MP confirmed that the quality issues had occurred as a result of excessive film build and/or the plaster not being allowed to fully cure between the application of the base and top coats. MP considered the issues were widespread and would require the property to be repainted. In addition to issues with the painting in the interior of the home, MP identified problems with the external painting of the soffit panel at the north-east corner of the garage and the timber trim above the dining room door. The applicants were required to obtain a report from MP after the FSP rejected the findings of an earlier report from the applicants’ builder (HI) which found that the paintwork was poorly done and did not comply with the relevant Australian standard. Both the reports prepared by MP and HI include close-up photographs which clearly indicate issues with the quality of the paintwork. The applicants have provided a quotation from their painter (BB) for $14,668.50 for the repainting of the property based on a detailed scope of works prepared by BB. BB’s quotation covers the repainting of the interior of the property, as well as a number of external areas (including the fascia, lattice panels and timber hardwood posts). Case No: 395915 Determination Page 5 of 9 The applicants have provided other quo tations for the repainting of their property. However, these quotations are either incomplete and/or do not contained a detailed scope of works equivalent to that prepared by BB. The FSP accepts the findings in MP’s report regarding the poor quality of the paintwork completed by its contractors. The FSP also acknowledges that the interior of the applicants’ house requires repainting . However, the FSP says it should not be liable for the entirety of BB’s quotation because some of the external elements (including the fascia and timber posts) were replaced (and therefore not repainted) during the original repairs. The FSP’s position appears inconsistent with the original scope of works for the repair of the fire damage prepared in November 2013. The original scope of works provided for the painting of a number of external elements including the new fascia, timber posts and lattice panels. In circumstances where the applicants have established that there are significant issues with the quality of the painting co mpleted by the FSP’s contractors, I consider it is reasonable to require the FSP to fund the cost of repainting both the interior and exterior of the property, in accordance with the scope of works set out in BB’s quotation. Accordingly, the FSP is required to cash settle the applicants for $14,668.50 for the cost of repainting. The FSP is not required to pay interest on this amount, as it does not appear that the applicants have incurred the repainting costs to date. FSP is required to pay an additional $6,000 for the remaining repairs The applicants have provided a report from their building inspector (HI) which identifies various defects in the repairs carried out by the FSP’s builder. HI’s report includes close-up photographs illustrating the issues identified. The applicants have also provided a quotation for $3,140 from their builder (LS) for the repairs required to rectify the bulk of the issues identified in HI’s report. LS noted that some of the remaining issues (being mismatching brickwork and a damp course defect in the lower section of a brick wall) were not capable of a practical solution. The FSP accepts that it is liable for a number of the defects identified in HI’s report. However, the FSP says it is not liable for other issues such as the damp course defect (on the basis that it did not repair the relevant section of the wall) or the broken bathroom tile (which it says was not related to the claim). The FSP notes it has previously paid the applicants an amount of $2 ,500 to enable them to render the non-matching brickwork in order to create a uniform appearance. In addition to the defects identified in HI’s report, the applicants have provided a report from their plumber (R) which states that there is a missing downpipe at the front right side of the house. The FSP has subsequently confirmed that its contractors failed to reinstall the downpipe when they completed the claim-related repairs to the garage. Case No: 395915 Determination Page 6 of 9 Based on the information provided, it appears the missing downpipe has caused the gutters to overflow during periods of heavy rain, resulting in water damage to the applicants’ dining room ceiling. This issue has not previously been addressed, despite the applicants notifying the FSP of the leak on several occasions during the claim process. The applicants’ plumber (R) has provided a quotation for $475 to reinstall the missing downpipe. However, this figure does not include the costs of re-connecting the downpipe to the underground stormwater system, which would necessarily involve digging up the surrounding concrete. The FSP’s assessor has confirmed the reconnection is necessary to avoid the rainwater run-off discharging onto the driveway. It is not entirely clear to what extent the quotations provided by the applicants include the costs of repairing the additional water damage caused by the overflowing gutter. While LS’s quote includes the repair of damage to the front eaves which occurred as a result of the leak gutter, none of the quotations provided appear to allow for any repairs (other than painting) which may be required to the dining room ceiling. In their submissions, the applicants say that some of their contents items (including blinds, rugs and furniture) have suffered water damage due to the overflowing gutter. However, the applicants have not provided details of the items affected and the extent of the damage is unclear from the photographs provided. The applicants have also raised concerns about various other issues, such as the failure of the FSP’s cont ractors to install door locks which could be opened with a single master key and to replace pet mesh on the laundry screen door. However, they have not provided quotations for the works required to rectify these issues. Having regard to the issues outlined above, I consider it likely that the quotations provided by LS and R underestimate the cost of the works required to address all of the damage arising from the fire and the initial repairs. In light of these issues, and in the interests of expediting the full and final resolution of the protracted dispute, I consider it fair in all the circumstances that the FSP be required to pay the applicants an amount of $6,000 for the remaining repairs (other than the repainting). The FSP is not required to pay interest on this amount, as it does not appear that the applicants have incurred the repair costs to date. 2.2 Are the applicants entitled to any additional amounts? FSP should reimburse applicants for costs of obtaining reports Under paragraph 9.4 of the FOS Terms of Reference, FOS may require a financial services provider to contribute to costs incurred by an applicant in the course of their dispute. Case No: 395915 Determination Page 7 of 9 As outlined above, the applicants obtained reports from their builder (HI) and master painter (MP) which ident ified defects in the repairs carried out by the FSP’s contractors. It was necessary for the applicants to obtain these reports, given the FSP had previously denied that there were any outstanding issues with the repairs (including the paintwork). The FSP has reimbursed the applicants for the cost of obtaining HI’s report ($270). However, it is unclear whether the FSP has also reimbursed the applicants for the cost of obtaining MP’s report ($550). To the extent that the FSP has not done so, it is required to reimburse the applicants for the cost of obtaining MP’s report. Applicants have not established theft by FSP’s contractor The applicants say that a contractor engaged by the FSP’s restoration company (C) stole a gold necklace with a jade pendant from their home, while undertaking contents restoration works on behalf of the FSP. It appears that the applicants notified the FSP of the theft in December 2014. However, the applicants do not appear to have made a police report and it is unclear exactly when the necklace went missing. The applicants have variously described the necklace as being 9 carat gold or 22 carat gold, and have estimated its value at approximately $5,000. However, the applicants have advised that, as the necklace was a gift from the fe male applicant’s mother in law, they are unable to provide any evidence of ownership or value (such as a purchase receipt, valuation or photographs). It appears that, despite having a value in excess of the policy limit for jewellery, the necklace was no t listed as a valuable contents item for the purpose of the applicants’ policy. In the circumstances, I am not satisfied that the applicants have established that the FSP should be liable for the loss of the necklace, given the lack of certainty about when the loss occurred and the absence of independent proof of ownership and value. Applicants are entitled to compensation for non-financial loss Under paragraph 9.3(b) of the Terms of Reference, FOS may award compensation (capped at $3,000) for non-financial loss where an applicant has suffered an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with their expectation of enjoyment or peace of mind. As outlined above, it has taken an excessive amount of time to resolve the applicants claim for damage caused by the fire in November 2013. It is now over two and a half years since the claim was lodged. I am satisfied that the applicants have suffered considerable stress and inconvenience as a result of the in itial inadequate repairs by the FSP’s builder, as Case No: 395915 Determination Page 8 of 9 well as the delay in the FSP acknowledging the extent of the issues which remained following the rectification repairs (even after the applicants had provided HI’s report) . In the circumstances, I consider that an award of compensation for non-financial loss in the maximum amount of $1,500 is appropriate. Case No: 395915 Determination Page 9 of 9 3 Supporting information 3.1 FOS approach to this dispute FOS has considered it appropriate to expedite this dispute in accordance with the Operational Guidelines to the FOS Terms of Reference, due to the nature of the dispute. Accordingly, this dispute has not been the subject of a FOS Recommendation and has proceeded directly to determination. There has been a full exchange of all material information relied on for the purposes of this determination and each party has had the opportunity to address any issues raised by the other. All of the material provided by the parties has been reviewed and considered for the purposes of this determination. This dispute has been decided on its merits, having regard to the relevant law, good industry practice, codes of practice and previous Financial Ombudsman Service (FOS) decisions. While the parties have raised numerous issues in their submissions, for the purposes of this determination, commentary has been restricted to those issues considered directly relevant to the outcome only.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.