Text of the determination
Determination
Case No: 392670 Determination Page 1 of 10
Case number : 392670 2 September 2015
1 Overview
1.1 Dispute
The Applicant claimed under her home building insurance policy with the Financial
Services Provider (FSP) for cracking and movement damage to her home, which she
believed had been caused by water leaking from a cracked stormwater pipe and/or
stormwater run-off during a hail storm on 6 March 2010.
The FSP accepted that some of the claimed damage was due to the leaking pipe and
offered to cash settle the Applicant for $6,718, based on the estimated cost of
repairs. However, the FSP denied liability for the bulk of the damage, on the basis
that it had not been caused by the storm or the leaking pipe, but by factors which are
excluded under the policy.
The Applicant seeks cover for the repair of all of the damage to her home at an
estimated cost of $70,000, together with compensation for stress and inconvenience
due to the manner in which the FSP handled her claim. She is also dissatisfied with
the approach taken by the FSP following the temporary cancellation of her policy in
June/July 2014.
1.2 Issues and key findings
Is the FSP liable for the disputed damage to the property?
The available information establishes that the bulk of the disputed damage was
caused by differential foundation movement due to variations in the soil moisture
content over time, as a result of ongoing drainage issues at the property. The FSP is
not liable for damage caused in this manner.
How should the claim be settled?
The cash settlement amount should be increased by 20% to ensure that the
Applicants are able to carry out the repair of the damage for which the FSP has
accepted liability. The Applicants are not entitled to compensation.
1.3 Determination
This Determination is substantially in favour of the FSP.
The FSP is to pay the Applicant the amount of $8,061.60 (less any applicable
excess) in full and final settlement of their claim.
Case No: 392670 Determination Page 2 of 10
2 Reasons for Determination
2.1 Is the FSP liable for the disputed damage to t he property?
Policy provides cover for damage caused by storm and leaking pipe
The Applicants’ policy provides cover for damage caused by the events listed in the
policy, including the insured events of “Storm” and “Water – leaking or escaping”.
The cover for damage caused by storm extends to damage resulting from a sudden,
excessive run-off of water as a direct result of a storm in the local area. The cover for
damage caused by escaping water includes water leaking from pipes, house gutters
and drainpipes.
The Applicants had also elected to take out the optional cover for accidental damage
available under the policy (which provides cover for damage caused unintentionally).
However, the policy is subject to general exclusions for damage caused by faulty
design or workmanship, wear and tear and/or deterioration. Further, the cover for
accidental damage is subject to a specific exclusion for damage caused by the
settling, shrinkage or expansion of buildings, or foundations.
Dispute concerns extent of damage caused by insured events
The FSP accepts that the Applicants’ property was affected by a hail storm in March
2010, which resulted in stormwater flowing down the driveway and flooding the
garage and basement area on the southern side of the house, to a depth of
approximately half a metre.
A subsequent investigation by the Applicants’ plumber identified a cracked
stormwater pipe at the front of the garage.
The Applicants have identified a number of separate items of damage to the
property, which they consider were caused by the effects of the stormwater run-off
and the damaged pipe. These items include:
cracking to the internal plaster walls and ceilings;
cracking to the external render of the house;
misalignment of tiles in the bathroom;
lifting and cracking of tiles on the northern balcony; and
gaps and distortions to various parts of the house, including edge misalignment
over the front entrance area.
The Applicants say that, in addition to cosmetic repairs to the existing damage, the
property requires underpinning in order to prevent further movement damage. They
estimate the total cost of the repairs to be around $70,000, based on quotations
provided by their contractors.
The FSP accepted liability for repairing some of the cosmetic damage to the house,
on the basis that the water leaking from the damaged pipe may have caused or
contributed to this damage.
Case No: 392670 Determination Page 3 of 10
However, the FSP says the remainder of the claimed damage was not caused by the
stormwater run-off or the leaking pipe. Based on reports provided by its engineer
(JM), the FSP says the property is susceptible to ongoing cracking and movement
damage due to the manner in which it was constructed and, in particular, the lack of
appropriate drainage. The FSP also says that some of the damage identified by the
Applicants has been caused by other factors, such as faulty design and
workmanship.
Accordingly, the FSP says it is entitled to deny the Applicants’ claim for the disputed
damage, on the basis that this damage was not caused by the insured events (storm
and leaking pipe) which occurred in March 2010, but by factors which are excluded
under the policy.
Parties have provided conflicting engineers’ reports
In addition to the reports provided by the FSP’s engineer (JM), the Applicants have
provided reports from three engineers (AG, RC and ME) who they engaged at
various stages during the course of the claim.
Each engineer has reached his own conclusions as to the cause of the disputed
damage to the Applicants’ property, supported by varying levels of analysis.
The Applicants’ engineers have (for varying reasons) concluded that the disputed
damage was caused by stormwater run-off and/or the effects of the leaking pipe.
The views of the Applicants’ engineers directly conflict with the findings of the FSP’s
engineer (JM), who found that the damage had occurred over an extended period of
time due to ongoing issues associated with the design and construction of t he
property, including inadequate drainage.
Having carefully reviewed the reports provided (including the photographs contained
therein), the Panel considers that the explanation provided by the FSP’s engineer
(JM) is most consistent with the observed fac ts. The basis for the Panel’s conclusion
is set out below.
Property experienced ongoing movement issues due to poor drainage
In his initial report dated 14 September 2010, JM noted that the Applicants’ property
had been excavated into a substantial hill, t hereby creating a “virtual drainage sump”,
which required appropriate provision for surface and sub-surface drainage.
JM observed that virtually no proper drainage provisions had been made around the
high sides of the property to divert rainwater run-off around the house to lower
ground.
Accordingly, JM concluded that, even in moderate rainfall conditions, the large
concrete driveway at the property would collect and direct rainwater runoff down the
slope and straight into the garage, basement and storage area which had been built
into the hill on the southern side of the property.
JM considered that the 100 millimetre stormwater pipe from the gated trench at the
front of the garage was incapable of diverting rainwater runoff rapidly enough to
avoid the garage being flooded during periods of heavy rainfall.
Case No: 392670 Determination Page 4 of 10
JM did not believe that the crack in the stormwater pipe identified following the storm
in March 2010 would have contributed to the flooding of the garage, because the
pipe was only cracked (and not blocked), and therefore most of the water from the
gated trench would still have flowed down the pipe.
The photographs taken by JM clearly show the steep slope of the Applicants’
property, the design of the driveway, the gated trench at the front of the garage and
the cracked stormwater pipe. The Panel considers these photographs support JM’s
observations in relation to the inadequacy of the drainage provisions.
JM concluded that the failure to provide adequate drainage at the property had led to
rainwater runoff and seepage from higher ground flowing into the foundation soils at
various times over the life of the house. The resulting wetting and drying of the soil
caused differential foundation movement, leading to the cracking and movement
damage observed.
JM also identified water damage to the rear basement wall - that is, the opposite side
from where the cracked pipe was located. He considered this damage had been
caused by ongoing rainwater run-off and seepage from higher ground and the lack of
an effective waterproof membrane on the buried wall. This is consistent with the
property being subject to ongoing drainage issues.
JM’s conclusions are supported by the Applicants’ advice that the basement also
flooded in February 2011.
The Applicants say that, on this occasion, rainwater run-off entered the basement
through cracks caused by the previous flooding event. However, given the nature
and extent of the cracking damage shown in the photographs, the Panel considers
this unlikely.
In contrast to the views exp ressed by JM, the Applicants’ engineers (AG, RC and
ME) identified the events in March 2010 as the sole and underlying cause of all of the
damage.
AG considered the rainwater run-off and leaking pipe may have flowed into the
foundation soils, affecting the bearing capacity of the soil and resulting in settlement
of the foundations. However, AG’s conclusions are not consistent with the level
surveys carried out by RC, which showed heave (rather than settlement) in the
immediate vicinity of the garage.
The findings of the remaining engineers (RC and ME) are consistent with JM’s
findings, to the extent that they concluded that the disputed damage had been
caused by differential movement resulting from changes in the moisture content of
the foundation soils.
However, RC and ME attributed all of the damage to the effects of the single storm
event in March 2010, with the cracked pipe potentially contributing to the influx of
moisture into the soil.
Although they were provided with a copy of JM’s reports, neither ME nor RC
specifically addressed the ongoing drainage issues at the property identified by JM
(even after RC had participated in a joint site visit with JM during which he reaffirmed
his views on this issue).
Case No: 392670 Determination Page 5 of 10
Nor did any of the Applicants’ engineers prov ide any analysis of drainage conditions
at the site. The Panel considers this somewhat surprising, particularly given both AG
and ME expressly recommended extensive underpinning works.
The Panel acknowledges that the hailstorm in March 2010 was a very severe
weather event. However, the Panel does not consider the nature and extent of the
disputed damage is consistent with it having been caused solely by this event, given
the age of the property, the manner in which it was designed and built and the
drainage issues identified by JM.
The cracking and movement damage to the property was not localised to the area in
which the flooding occurred but was apparent in various locations throughout the
house (including on the northern side, which was unaffected by the flooding of the
basement in March 2010). The Applicants and their engineers have confirmed that
further damage is continuing to occur.
These features of the damage are consistent with the property being subject to
differential foundation movement over time as a result of ongoing drainage issues.
Had the disputed damage been solely attributable to the events of March 2010, it
could be expected to have been relatively localised. Further, given the nature of the
foundation soils, any damage resulting from these events alone could reasonably be
expected to have stabilised by the time of the most recent inspection (by ME) in
October 2014.
Disputed damage was caused by excluded factors
As outlined above, the Applicants’ claim relates to a number of separate item s of
cracking and movement damage observed at various locations throughout the
property.
For the reasons outlined above, the Panel considers that the bulk of the disputed
damage was caused by differential foundation movement due to variations in the soil
moisture content over time, as a result of ongoing drainage issues at the property.
Accordingly, the FSP is not liable for this damage as it was not caused by the storm
and leaking pipe in March 2010, but by gradual deterioration over an extended period
of time. Damage caused in this manner is excluded under the policy.
2.2 Are the Applicants ent itled to any additional amounts?
FSP accepted liability for cosmetic damage caused by leaking pipe
As outlined above, the FSP accepted liability for some of the cosmetic damage to the
building, on the basis that this damage may have been caused by the leaking pipe.
The FSP offered to cash settle the Applicants for $6,718 (less any applicable excess)
for this damage, based on a quote provided by its builder for the repair of damage
identified by JM in a scope of works prepared during the joint site inspectio n in March
2011.
Case No: 392670 Determination Page 6 of 10
The FSP’s claim records reflect that it initially estimated the cost of repairing the
damage associated with the leaking pipe at approximately $3,800. This amount was
later increased to $6,000 and then to $6,718, after the damage continued to worsen
(although, as outlined above, the Panel is not convinced this was necessarily due to
the ongoing effects of the leaking pipe).
Cash settlement amount should be increased by 20%
The Applicants say the amount offered by the FSP is not sufficient to enable them to
undertake the necessary repairs. They have provided copies of quotations from their
repairers for cosmetic repairs at a cost of approximately $30,000 and underpinning
works at a cost of approximately $40,000.
In his reports, the FSP’s engineer (JM) disputed the findings of the Applicants’
engineers that underpinning of the property was required. He considered the damage
to be largely cosmetic and noted that the level surveys carried out by RC in January
2011 showed only minimal movement of the floors at the property, indicating that
underpinning was not required.
For the reasons outlined above, the Panel does not accept that the bulk of the
cracking and movement damage to the property was caused by the insured events in
March 2010. To the extent that underpinning is required due to ongoing differential
foundation movement, the FSP is not liable for these costs.
One of the engineers engaged by the Applicants (RC) estimated the cost of cosmetic
repairs to the property at approximately $30,000. The FSP obtained an estimate from
its builder for $26,934 based on RC’s scope of works.
However, the scope of works prepared by RC included provision for the replacement
of the tiles and the waterproofing of the balcony (at an estimated cost of $12,000)
and the full repainting of the house (at an estimated cost of $10,000).
Based on the reports of the various contractors and the photographic evidence
provided, the Panel is not satisfied that the damage to the balcony tiles was caused
by the insured events in March 2010.
The FSP’s engineer (JM) considered that the balcony tiles had moved and cracked
due to a failure to install movement joints along the length of the tiling when the tiles
were laid on the roof of the lower level to create the balco ny. JM also noted the tiles
were drummy due to the adhesive having been poorly applied.
While the Applicants’ engineer (RC) attributed the damage to the tiles to movement
following the storm in March 2010, he did not expressly address the issues identified
by JM (even after the site meeting one year later).
In these circumstances, and having regard to the Panel’s conclusions regarding the
ongoing movement issues at the property, the Panel does not consider the FSP
should be liable for the cost of replacing the balcony tiles and installing a waterproof
membrane.
While RC’s estimate provides for a full repainting of the property, the photographic
evidence suggests that this is not required. The scope of works prepared by JM in
Case No: 392670 Determination Page 7 of 10
March 2011 provides for replastering and painting in the areas where cracking
damage was observed.
Based on the available information, the Panel is satisfied that the scope of works
prepared by JM in March 2011 reflects a fair and reasonable basis for settling the
Applicants’ claim.
The Panel notes that JM’s scope of works is stated to be prepared on “a maximum
benefit of the doubt basis” and includes repairs to some items of damage which JM
considered was unlikely to have been caused by the leaking pipe (such as cracking
damage to the walls on the northern side of the property).
However, the Panel notes that the FSP has provided limited information to support its
estimate of the cost of the repairs. In these circumstances, and given the time which
has passed, the Panel considers it appropriate that the cash settlement amount be
increased by 20%, to a total of $8,061.60 (less any applicable excess).
Given the increase in the cash settlement (and the fact that the Applicants have
previously been offered and rejected the original amount), the Panel does not
consider the FSP should be required to pay interest on the settlement amount.
Applicants are not entitled to compensation for non-financial loss
Under paragraph 9.3(a) of the Terms of Reference, FOS may award an amount of
compensation (capped at $3,000) for non-financial loss where an applicant has
suffered an unusual degree or extent of physical inconvenience, time taken to
resolve the situation or interference with their expectation of enjoyment or peace of
mind.
However, FOS expects applicants to be moderately robust and bear the usual stress
and inconvenience associated with an insurance claim.
Having carefully reviewed the claim history, the Panel is satisfied that the FSP has
acted reasonably overall in the management of the App licants’ claim.
The FSP appointed appropriately qualified consultants to investigate the
circumstances of the claim and gave due consideration to the additional information
provided by the Applicants.
While the claim has taken an extended period of time to resolve, not all of the delays
are attributable to the actions of the FSP. There were several occasions during the
claim process when significant periods of time passed before the Applicants provided
further information to the FSP.
Accordingly, the Panel does not consider that the circumstances justify an award of
compensation for non-financial loss.
Applicants are not entitled to reimbursement of professional costs
Under paragraph 9.4 of the Terms of Reference, FOS may require a financial
services provider to reimburse an applicant for professional costs incurred in
connection with their claim.
Case No: 392670 Determination Page 8 of 10
The Applicants seek reimbursement for costs incurred in obtaining reports from their
engineers. However, having regard to its findings as set out above, the Panel is not
satisfied that the engineers’ reports obtained by the Applicants have assisted in the
resolution of this dispute.
Accordingly, the Panel does not consider that the FSP should be required to
reimburse the Applicants for their engineers’ fees.
FSP acted reasonably in reinstating policy
The FSP cancelled the Applicants’ policy in mid -2014 as a result of missed premium
payments, due to the Applicants not having updated their credit card details. The
FSP then advised the Applicants that the policy could not be reinstated because the
home was not waterproof as a result of the cracking and movement damage.
During the course of this dispute, the FSP agreed to reinstate the Applicants’ policy,
subject to payment of outstanding premiums for the relevant policy period. When the
Applicants advised that they were experiencing financial difficulties, the FSP allowed
them to defer payment until the end of the policy period (unless a claim was lodged in
the interim, in which case the outstanding premiums would be payable immediately).
The Panel considers the FSP acted reasonably by agreeing to reinstate the
Applicants’ policy, subject to payment of the outstanding premiums. The FSP
effectively agreed to provide cover during the relevant period, even though payment
had not yet been received.
Case No: 392670 Determination Page 9 of 10
3 Supporting information
3.1 FOS approach to this dispute
This dispute has not been the subject of a FOS Recommendation. Due to the nature
of the dispute, it has been referred directly to a Panel for Determination, in line with
the Operational Guidelines to the FOS Terms of Reference . The Panel consists of an
Ombudsman and two representatives with consumer and insurance experience.
The Panel has decided this case on its merits, having regard to the relevant law,
good industry practice, codes of practice and previous Financial Ombudsman
Service (FOS) decisions.
There has been a full exchange of all material information relied on for the purposes
of this Determination and each party has had the opportunity to address any issues
raised by the other.
The Panel has reviewed and considered all of the material provided by the parties.
While the parties have raised a number of issues in their submissions, for the
purposes of this Determination the Panel has restricted its commentary to those
issues which it considers directly relevant to the outcome only.
During the course of this dispute, the Applicants have been assisted by their solicitor.
For the purposes of this Determination, submissions made by the Applicants’ solicitor
have been treated as having been made by the Applicants themselves.
3.2 Terms of policy
Subject Terms
Insured event -
storm
If your home or contents suffer loss or damage caused by …
a violent wind, cyclone or tornado
thunderstorm or hail which may be accompanied by rain or snow, or
a sudden, excessi ve run - off of water as a direct result of a storm in
your local area
we will under buildings insurance
rebuild or repair that part of your home that was damaged.
Insured event –
leaking water
If your home or contents suffer loss or damage caused by water leaking
or escaping from
pipes
road gutters or curbing
house gutters or drainpipes …
we will under buildings insurance
rebuild or repair that part of your home that was damaged.
Accidental
damage
Accidental Damage is damage caused unintentionally and the cover is
in addition to the cover for the [insured events].
If you choose thi s option
Case No: 392670 Determination Page 10 of 10
Subject Terms
we will under buildings insurance
rebuild or repair that part of your home that was damaged
however … we will NOT cover damage caus ed by
the settling, shrinkage or ex pansion in buildings, foundations, walls or
pavements
General
exclusions
We will NOT cover … loss, damage, injury or death that occurs a s a
result of …
wear, tear, rust, corrosion, det erioratio n or erosion …
faulty design or workmanship
Things that may
put your claim at
risk
You may put your insurance claim or cover at risk if you do not meet
your obligations to us. We may refuse a claim … if you
do not maintain your home in good condition. This means your home must
be watertight, structurally sound, secure and well maintained