Determination 392511

Cash settlement of building and contents fire claim, temporary accommodation and claim service

FirmFinancial Firm (Unknown - Insurer)
Decided2016-05-31
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded$274,897
Non-financial loss$3,000
Amount claimed—
SourceAFCA PDF

Summary

The applicants' home was damaged by fire and the agreed building settlement collapsed; they also complained about contents handling, temporary accommodation and communication. AFCA ordered the agreed building settlement, further contents and temporary accommodation payments, interest, and non-financial loss compensation.

The insurer's poor handling, delays and failure to secure the property caused additional loss, so the agreed settlement and further compensation were payable under the policy.

Issues

Subjects and remedies

home or building damagepay claimpay compensationpay interestpay non financial loss

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 392511 Determination Page 1 of 8 Case number: 392511 13 May 2016 1 Overview 1.1 Dispute The applicants made a claim under their building and contents insurance held with the financial services provider (FSP) following a fire at their property. The FSP accepted the claim, but the applicants remain dissatisfied with:  the cash settlement for the building and contents  the provision made for temporary accommodation costs  the standard of service they have received from the FSP. 1.2 Issues and key findings Is the FSP’s settlement offer fair and reasonable? The previously agreed settlement of $240,000 was fair and reasonable to repair the building. The FSP is liable in respect of the total sum insured for contents, plus an additional $15,000 which is an estimate of the damage caused by the FSP, as opposed to the fire. Are additional temporary accommodation costs payable? The a pplicants are entitled to an additional month’s temporary accommodation which should have been sufficient for the two parties to negotiate and implement the building settlement they had agreed. Are the applicants entitled to additional compensation? The FSP’s handling of the contents claim was poor, as well as the breakdown in communications regarding the building settlement. The applicants should be compensated for this. Further, it led to the applicants’ need to engage lawyers and the applicants should also be compensated for this. 1.3 Determination This determination is in favour of the applicants. The FSP must pay the applicants: Case No: 392511 Determination Page 2 of 8  $240,000 in respect of the building claim, in accordance with the terms and conditions of the policy. Interest is payable on this amount in accordance with the Insurance Contracts Act from 15 May 2015 until the date payment is made.  A further $31,897 in respect of the contents claim, in accordance with the terms and conditions of the policy. Interest is payable on this amount at the rates prescribed by the Insurance Contracts Act from 1 January 2015 until the date payment is made.  A further $3,000 in respect of the temporary accommodation, in accordance with the terms and conditions of the policy. Interest is payable at the rates prescribed by the Insurance Contracts Act from 15 May 2015 until the date payment is made.  $3,000 for non financial loss. No interest is payable.  Upon receipt from the applicants of evidence of payment of the legal adviser’s fees applicable to this dispute, the FSP is required to pay the applicants up to $3,000 for such fees. No interest is payable. Case No: 392511 Determination Page 3 of 8 2 Reasons for determination 2.1 Is the FSP’s settlement offer fair and reasonable? The applicant had cover for both building and contents The applicants’ policy provided building cover of $380,268 and contents cover of $174,934. It had a cap for collections of $2,500. The parties have obtained a number of quotes to rebuild the property The parties have obtained the following quotes: Builder On behalf of Quote MM 25.01. 15 Applicants $246,796.00. EH 15.2.15 Applicants $254,028.50. AJ (undat ed) FSP $ 193,463.16 r evis ed to $220,182.58 CP FSP $211,254.41 JL 17.12. 14 FSP $ 212,729.89. The parties entered into settlement negotiations The FSP originally based settlement on C P’s quote, and then JL’s quote, in an attempt to resolve the dispute. After further review, the FSP offered $226,366 which included an additional $3,000 for council fees and allowed for a 5% additional variance. The applicants proposed a settlement figure of $240,000 which the FSP agreed to. However, the FSP says it required a payout figure from the financier which was not provided. The applicants say that its financier required details of the settlement sum before it would release the payout figure and that the FSP refused to provide such details on the basis of possible breach of privacy. This is supported by the available documentation. As a consequence, the settlement fell over. The applicants have provided quotes for the rebuild that are between $20,430 and $27,622 higher than the FSP’s current offer of $226,366. EH’s quote included items additional to the scope of works and related to the staircase, kitchen and wall linings and flooring to wet areas. The applicants state both their quotes included structural Case No: 392511 Determination Page 4 of 8 dama ge that the FSP’s builders had failed to identify or had declined to include in its scope of works (however precisely what these works were are not readily identifiable). The FSP has provided no anaylsis to FOS on the quotes obtained by the applicants to explain the discrepancies from its own quotes. JL’s quote noted that the quote for the staircase allowed for the existi ng stairs to be replaced, but not for bringing it up to current building standards, as required by the policy. Further, JL’s quote predate s the FSP’s advice of 31 December 2014 that the scope of works was yet to be updated to take into account additional damage caused in the preceding 11 weeks when the property had not been properly waterproofed. The applicants also state that their quotes did not include the additional works subsequently identified by the FSP, although I note both quotes post date when such works should have been known. On the information before me, I consider it fair in all the circumstances to revert to the agreed settlement of $240,000. This is because I largely accept the quote from JL which is comprehensive, was based on the scope of works, but for which provision has then been made for some additiona l items, including damage caused to the building by the FSP’s failure t o properly secure the property. For the reasons set out below regarding temporary accommodation, interest is payable at the rates prescribed by the Insurance Contracts Act from 15 May 2015 to the date payment is made. I have also reviewed the product disclosure statement in terms of the third party financier. The policy states the FSP will only pay the credit provider (rather than the applicant) if the financier has given any help asked for. In this dispute there appears to have been a significant communication breakdown between the parties and the financier. This should be rectified on settlement of this determination. If no agreement can be reached, the FSP is to pay all the building component of the claim to the applicants in accordance with the policy. Contents loss exceeded the sum insured The applicants ’ contents were insured for a maximum of $174,934. The FSP has already made the following payments to the applicants in respect of contents:  $5,000 (emergency funds for lost contents).  $115,564.07 (contents) + $397.70 for the dryer.  $37,075.54 restoration of contents As such, the applicants have already received $158,037 payment in respect of contents. This leaves a balance of $16,897 payable in the event the applicants can establish they have suffered further loss. The applicants provided an inventory which listed all items yet to be paid out. The FSP provided handwritten notations on this which demonstrated that at least a further $20,000 was outstanding to the applicants (and this was prior to costing additional Case No: 392511 Determination Page 5 of 8 items in the hallway, bathroom, dining, lounge, laundry, toilet, junk room and pergola). Accordingly, I am satisfied that the applicants should be paid their total sum insured under the contents policy. The applicants are to be compensated for further contents loss due to the FSP The applicants have disputed the restoration bill, noting that many of the items restored, should not have been. The FSP has acknowledged in an email to the applicants that whilst the FSP appreciated the applicants would have preferred not to have these items restored, there was little that now could be done. The difficulty with this is that the $37,000 is taken from the total contents, which becomes an issue when the applicants have reached their insured sum, as the y have here. There is a further issue given some contents were damaged as a result of the FSP’s failure to waterproof the building in a timely manner (it was some two months and even then the tarp was not secure and the windows and doors were not boarded up). The FSP also failed to remove some contents as required, but advised the applicants the contents had been removed. While the FSP states there was only a small hole in roof, having been exposed to the elements would undoubtedly have caused some further damage. The FSP considers the dispute should have settled in December 2014, at which time it says damages were all accounted for, and that further damage continued after this time was due to the failure to repair the property. However, as at December 2014, the FSP was yet to update its scope of works to include the damage caused in the previous 11 weeks (which it acknowledged had occurred). Further, there was still significant questions over who had what contents where, which remained unresolved until 18 November 2015, over one year after the fire. At this time, the FSP advised that it retained 14 pallets of restorable items and 4 pallets of non restorable items. Without either the updated statement of works or the opportunity to review these contents, it is difficult to see how the claim could have been settled by the applicants. Accordingly, the additional damage cannot be said to be the fault of the applicants. It would not be fair in these circumstances for additional damage caused by the FSP (rather than the fire) to be deducted from the insured sum. No itemised costings have been provided in respect of the additional contents damage, which the applicants say relate to pool furniture, contents of the utility room, items in the kitchen cupboards and items in the roof space. Nor has any costing been provided in respect of what items were inappropriately restored. I consider it fair in all the circumstances to allow an additional $15,000 to take into account over payment by the FSP for restoring items that should not have been and for contents damaged after the fire as a result of the FSP’s actions (or inaction). The FSP must pay an additional $31,897 The applicants are therefore entitled to an additional $31,897 (less the contents excess if this has not already been paid). Interest is payable on this amount in accordance with the Insurance Contracts Act from 1 January 2015 to the date Case No: 392511 Determination Page 6 of 8 payment is made. This date has been chosen as reflecti ve of when the FSP believes that it should have been in a position to settle the dispute. 2.2 Are additional temporary accomodation costs payable? Further payment for temporary accommodation costs is necessary The FSP paid for temporary accommodation costs for the period 15 October 2014 to 29 May 2015. This was based on rental costs incurred at the date of the offer (10 March 2015) plus a 12 week repair (assumed the settlement was finalised that day). I have found the FSP’s buildin g offer of $240,000 to be reasonable. There is also no information before me to suggest that 12 weeks was inadequate for the repairs, and indeed this was accepted by the parties at the time. Had the parties co-operated it should have taken no longer than one month for the building settlement to be finalised and arrangements reached with the financier. Accordingly, I consider it fair in all the circumstances for the FSP to pay the applicants a further one month’s rent . This should have been sufficient time to finalise the building settlement agreement and resolve the issues regarding the third party financier. There is no dispute regarding the actual amount of rent, being $750 per week. The FSP must therefore pay the applicants an additional $3,000 for temporary accommodation costs. Interest is payable on this amount in accordance with the rates prescribed by the Insurance Contracts Act from 15 May 2015 to the date payment is made. This date is chosen given:  emails from the FSP show the $240,000 building settlement offer was open to the applicants as at 15 April 2015  15 May 2015 is one month after this date. 2.3 Are the applicants entitled to additional compensation? The applicants are entitled to non finanical loss Having read the chronology of this dispute, there can be no argument that the applicants received poor service from the FSP. This was acknowledged by the FSP in numerous correspondence to the applicants. Apart from issues relating to securing the property, the applicants were provided misinformation i n respect of their contents on numerous occasions, such that, for over a year, it was never clear where their belongings were or what belongs had been salvaged. This caused an unusual degree of interference with the applicant’s peace of mind, in circumstances where the applicants were already distressed given the roof of their house caught fire following a lightning strike, with their four children in the upstairs bedrooms. In addition, there were issues regarding the communication of asbestos in the property, which has led the applicants to believe they were exposed to asbestos for two days during which time the FSP’s contractors had been advised of the asbestos Case No: 392511 Determination Page 7 of 8 (and therefore did not return to the property) but the applicants’ continued to sort through their contents. The FSP itself noted a breach of the General Insurance Code of Practice in respect of its standard of service to the applicants. It is fair in all the circumstances for the FSP to pay the applicants $3,000 for non financial loss. The applicants may be entitled to legal fees When the agreed settlement could not be implemented, the applicants engaged a lawyer to represent them. While the adviser has not assisted in respect of the building claim, it is understandable that the applicants were no longer feeling capable of dealing with the FSP directly, especially in light of the contents claim. Upon receipt from the applicants of evidence of payment of the legal adviser’ s fees applicable to this dispute, the FSP is required to pay the applicants up to $3,000 for such fees. No interest is payable on these amounts. Case No: 392511 Determination Page 8 of 8 3 Supporting information 3.1 The FOS Approach I have decided this dispute based on what is fair in all the circumstances, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions. I have taken into account all the material submitted by the parties. I am satisfied that the documentation I have relied on has been provided to both parties and each party has had an opportunity to address the issues raised. This dispute was expedited to a determination. No recommendation was issued.