Text of the determination
Determination
Case No: 391334 Determination Page 1 of 19
Case number: 391334 1 8 September 2015
1 Overview
1.1 Dispute
The Applicant holds a Home and Contents policy and a Landlords Residential
Property policy with the Financial Services Provider (FSP). On 2 June 2014 the
Applicant lodged a claim for damage to his property which he says was caused by a
leaking pipe on the adjoining neighbour‟s property.
The FSP has partly indemnified the Applicant for damage to his bamboo flooring but
has denied the balance of his claim on the basis the Applicant has not demonstrated
the damage was caused by an event covered by the policy.
The Case Manager provided the parties with a Recommendation on the issues in
dispute. The Recommendation was mainly in favour of the FSP.
The FSP accepted the Recommendation but it was not accepted by the Applicant. In
the circumstances, the dispute has been referred to me for Determination.
1.2 Issues and key findings
Is the FSP liable for the claimed damage?
The expert evidence establishes that while the leaking downpipe caused damage to
the bamboo flooring another cause of the damage was poor subfloor ventilation
which cause is excluded from cover. It is fair in all the circumstances that there be an
apportionment of 20% for this cause of the damage. The FSP is only to indemnify the
Applicant for 80% of this part of the claim which it has done.
The expert evidence establishes that, on the balance of probabilities, the damage to
the brickwork was caused by subsidence which occurred over a period of time.
Damage caused in this manner is not covered under the policy.
The expert evidence also establishes tha t on the balance of probabilities the present
damage to the pavement was caused by shrinkage. Damage caused in this manner
is not covered under the policy.
However, the expert evidence establishes that on the balance of probabilities the
damage to the pavement repaired by the Applicant in 2011/12 was caused by the
leaking pipe. Although it is not fair in all the circumstances for the FSP to rely on a
policy term that the insured is not to repair damage without its consent, in view of the
policy terms regarding settlement of a claim, it is fair in all the circumstances that the
FSP pay only half the claim to repair the pavement being $3,750.
Case No: 391334 Determination Page 2 of 19
1.3 Determination
This Determination is substantially in favour of the FSP.
The FSP is not obliged to pay anything further to the Applicant for the damage to the
flooring or the brickwork.
If the Applicant accepts this Determination, within seven days of acceptance, the
FSP is to pay to the Applicant:
$3,750 for the 2011/12 damage to the concrete
statutory interest on $3,750 from the date the Applicant paid the concreter.
Case No: 391334 Determination Page 3 of 19
2 Reasons for Determination
I have decided this case on its merits, having regard to the relevant law, good
industry practice, codes of practice and previous FOS decisions. I have taken into
account all the material submitted by the parties, both before and after the
Recommendation. I am satisfied that the documentation I have relied on has been
provided to both parties.
New material provided after Recommendation
After the Recommendation was rejected, the Applicant made further submissions
and provided more material which is referred to below in Supporting Information. The
FSP provided a summary from its expert and made further submissions in rebuttal
referred to herein. Both parties essentially reiterated their positions.
2.1 Is the FSP liable for the damage claimed?
Leaking downpipe has caused damage to bamboo flooring
The Applicant claims his neighbour‟s leaking downpipe has damaged the insured
property. Specifically, that the leaking downpipe caused cracking of the pavement,
damage to brickwork, and damage to bamboo flooring.
In order to succeed the Applicants must establish on the balance of probabilities that
an insured event caused the damage.
The Applicant purchased the property in 2007 and rented it to his sister who lived
there for several years. During her tenancy, she noted mould issues from around
2009. Also during her tenancy, the Applicant carried out renovations to the property
including better subfloor ventilation. When the Applicant occupied the house in late
2011, he also noticed mould.
The Applicant did not know the cause of the mould. The opinion of the FSP‟s expert
was that there were pre-existing and long term building issues relating to subfloor
ventilation and general moisture conditions which were made worse by the ingress of
the stormwater from the leaking pipe. He apportioned damage 20% to pre-existing
issues and 80% to the leaking pipe.
The leaking downpipe was discovered 8 March 2014 and rectified 3 May 2014. The
FSP‟s engineers consider ed it is very likely that the pipe have been leaking from 26
June 2008.
In or about February 2013, the floating flooring was installed and it began to lift. It
was rectified by the original contractor but began to lift again. The second contractor,
DW, identified the leaking pipe in March 2014 and rectified the damage again.
A claim was made under the home insurance policy. The policy was incepted 15
November 2011 and continued until 15 November 2014 save for the policy year
commencing 15 November 2012.
The policy provides accidental damage cover which is defined as damage caused by
an unintentional act, or an unforeseen and uncontrollable incident. The damage
Case No: 391334 Determination Page 4 of 19
caused by the leaking pipe was accidental damage as defined. Therefore I am
satisfied the Applicant has established a prima facie claim for the damage to the
floating floor.
Expert material establishes poor ventilation also caused damage to flooring
The onus now shifts to the FSP to prove on the balance of probabilities that an
exclusion applies if it seeks to deny or limit its liability for loss.
The FSP‟s engineer inspected the property on 25 June 2014. He confirmed the
floating floor damage. He took moisture readings which he said indicated a high
entrapment moisture within the timber floor indicati ve of a high level of subfloor
moisture consistent with the short-term exposure from the leaking pipe. He also
visually inspected the subfloor. There was no surface water (which was not surprising
in view of the fact the leaking pipe had been repaired some several weeks earlier).
He also noted of a number of ventilation measures undertaken by the Applicant who
had installed new vents.
The FSP‟s engineer was of the opinion the soil under the house was medium
reactive clay and would subside and move over an e xtended period of time after rain.
The engineer reinspected the property 19 August 2014. Although the stormwater
outlet was now functioning and therefore not impacting the Applicant‟s home, the
moisture content had in fact increased which the engineer attributed to recent rain.
He concluded the subfloor of the house continues to have a relatively high
entrapment of moisture within the timber floating floor which he attributed to poor
subfloor ventilation. He wrote:
“In my opinion, the drainage vents placed by the Insured are not effectively proving
natural airflow and cross-ventilation throughout the subfloor area given their location
and placement height.
The reason why these installed vents are not providing effective cross-ventilation
allowance is that they are installed at an incorrect height due to the construction of the
footpath which consequentially corresponds to the mid-level of the floor joists which are
running parallel with the dwarf wall alignment.
In my opinion, the floor vents will need to be replaced by the insured prior to any
remedial works to the flooring is undertaken.
This will require the Insured to install mechanical ventilation system to ensure continual
flow of air and the construction of internal flow passages through the intermediate
dwarf walls.
A month earlier, on 19 July 2014 the FSP‟s property services expert O inspected the
site and noted the soil under the house was wet. O made similar comments to the
engineer about the subfloor ventilation and wrote:
“There is a cement slab with a brick imprint surrounding the house which has breather
vents for the void area underneath the house however these are at the same level as
the paved slab therefore this will continue to cause problems every time it rains or the
area is washed down as the water will once again enter the void under the house.
Soil under the house which is wet.
High moisture content in the affected areas.
Ongoing problem and the insured will need to address how drying of t he underneath of
the property can be managed” .
Case No: 391334 Determination Page 5 of 19
A few months later on 11 November 2014 another engineer (MP) inspected the
property for the FSP. He noted that the underfloor ventilation had recently been
improved by the Applicant. Because of this and because the leaking pipe and been
repaired, he expected underfloor issues would abate once the soil was completely
dry. He was also of the opinion that the damage to the floor was not caused solely by
the leaking pipe. He also considered that:
“…poor underfloor ventilation may have also influence the underfloor humidity.”
After the Recommendation, the Applicants provided some further material. However,
the email from the engineer is not persuasive on this point. The concreter makes no
comment about the flooring. The plumber confirms that the water pooling under the
front of the Applicant‟s property can cause problems to the floor.
FSP’s offer to contribute 80% of the cost of the flooring is fair
The FSP does not deny the leaking pipe caused damage. None of the material
provided by the Applicant after the Recommendation addresses the issues relevant
to the FSP‟s reliance on policy exclusions.
I have considered the terms of the relevant policy. The FSP is not obliged to cover
any loss or damage as a result of or caused by structural defects or faulty
workmanship or design. I am satisfied the FSP has established on the balance of
probabilities that the cause of some of the damage to the flooring is as a result of
poor or inadequate ventilation which is a structural de fect.
In all the circumstances, having carefully considered all the material provided, I am
satisfied that an apportionment of 20% to this cause of the damage is fair in all the
circumstances.
The FSP has offered to pay 80% of the cost of rectifying the bamboo floors. I am
satisfied the FSP is not obliged to pay no more than 80% of the cost of rectifying the
bamboo floors.
Expert evidence and the circumstances surrounding the loss demonstrate that
the leaking pipe did not cause damage to brickwork
The Applicant also claims $6,000 being the cost to re point the brickwork. He says
when he bought the house in 2007 there was no cracking in the brickwork and he
began to notice the cracking a few years later.
The Applicant claims the leaking pipe caused this damage also.
The material indicates that this repair work was done in October 2011.
At that time, the Applicant rented the house to his sister. The property was insured
with the FSP but under a landlord policy.
The FSP‟s engineer advised that it is very likely the pipe had been leaking since June
2008. The FSP denied the claim relying on policy exclusion that it is not liable to pay
loss or damage caused by settling, shrinkage or any movement of earth.
When the FSP‟s engineer (M) inspected the property on 25 June 2014, he observed
the brickwork to be in excellent condition. He was of the opinion that any brick
Case No: 391334 Determination Page 6 of 19
movement was a pre-existing issue relating to long-term, general building and ground
movement and was unrelated to the leaking pipe.
The FSP appointed a second engineer (MP) who inspected the property on 4
November 2014. He also observed no cracking. He says a downward movement will
only occur if the soils become drier. He also says that if water from the leaking pipe
affected the underfloor soils it would have resulted in an upward heaving movement
which was not the case.
The Applicant provided some material after the Recommendation. The plumber and
the concreter‟s letters do not take this part of the dispute further. The engineer
provided only an email. Essentially he considered that as the brickwork was
damaged in one location only, this pointed to exposure to the leaking water rather
than to erosion which would have a more generalised effect on the entire building.
Having considered all the material, I am not satisfied the leaking pipe caused the
cracking damage to the brickwork as if the leaking pipe was the cause of the
damage, then as the pipe continued to leak after the brickwork was repointed in 2011
and until May 2014 when the leaking pipe was repaired, I would expect cracking
damage to the brickwork to become evident again after it was repointed. This is not
the case. The expert evidence is the brickwork is presently in good condition.
In all the circumstances, I am not satisfied the Applicant has established the cracking
to the brickwork was caused by accidental damage or by an insured event under the
landlord policy.
Probable cracking to the pavement in 2011/12 was caused by leaking pipe
Finally, the Applicant claims the cost of repairs for cracking damage to the pavement.
On or about 12 July 2012, he paid the concreter $7,500 to replace the pavement.
The material establishes that in or around 2008/2009, the property was renovated
which included a new concrete pavement.
When the engineer M inspected the pavement on 25 June 2014 he considered it was
in excellent condition. He considered this claimed damage was pre-existing or related
to general building movement/settlement and not the leaking pipe.
When the FSP‟s second engineer MP inspected th e property on 4 November 2014,
he noted cracking in the perimeter pavement but considered it was consistent with
concrete shrinkage because the concrete dehydrated after being cast. He also
observed that the cracking was widespread and present in areas remote from the
leaking pipe. He concluded this cracking in the pavement was not caused by the
leaking pipe.
The Applicant‟s engineer does not assist the Applicant if the Applicant‟s claim was
about the present cracking in the concrete as the Applicant‟s eng ineer is of the
opinion that the leaking pipe would cause cracks in a specific location which is not
the case.
The plumber takes this aspect of the dispute no further.
Case No: 391334 Determination Page 7 of 19
Probable current cracking to the pavement not caused by leaking pipe
However, the state of the concrete presently is not relevant as the material
establishes the Applicant‟s claim is not about the present state of the concrete. If the
claim was about the present state of the concrete, I am not satisfied the material
establishes that an insured event has caused damage to the concrete as it presents
now.
However, the material establishes it is the Applicant‟s claim that he had to pay to re -
lay the concrete (after initial renovations) because it was not safe to leave it as itwas
as the cracking damage was at the point of entry to the property. He says that at that
time (presumably around 2011/212) he was unaware of the leaking pipe.
After the Recommendation, the Applicant provided a letter from the concreter who
did work at the insured prop erty “due to severe cracking in the concrete walkway.”
The letter does not say when the concreter did that work but as the invoice is
rendered by the concreter in July 2012, I presume the work was done at or near that
date.
The concreter also says that water created a major sinkhole which caused the
concrete to lift and crack. He describes the walkway as a major trip hazard. In the
letter of 16 July 2015 he said that:
“With our experience, we believe that the cracking was caused by the pipe work which
runs underneath the concrete…”
There is no evidence that the pipe work ran under the concrete but the material does
establish that the leaking downpipe was proximate to the entry to the property. If the
Applicant‟s engineer‟s opinion is to be accepted then the 2011/2012 damage is in a
specific location and is likely to be caused by the leaking pipe.
After the Recommendation, the FSP says that the concreter offers retrospective
speculation. The FSP makes the point that a major sinkhole had never been
mentioned before and that there is localised damage and severe damage whereas
the cracking was widespread. However, a careful analysis of the material, indicates
that it is the present damage to the concrete which is widespread and the 2011/12
damage which was localised.
Further, the FSP‟s engineer advised the FSP‟s assessor it was very likely that the
pipe had been leaking from June 2008 impacting this area.
The Applicant concedes he laid the second slab of concrete without the FSP‟s
consent as he was not aware at that time that he could successfully claim under his
insurance policy. He said that he acted in good faith by mitigating any liability
exposure that may have arisen due to the damaged slab.
Fair that the FSP pay 50% of the 2012 cost to repair the pavement
The FSP says that it is prejudiced in that it is now unable to remove the top slab to
see if the damage to the bottom slab has been caused by a claimable event. The
FSP also says that it is prejudiced as the Applicant was aware of damage yet he did
not lodge a claim with the FSP until 2014.
Case No: 391334 Determination Page 8 of 19
However, for many years, the Applicant was aware of mould damage only. I accept
that when the concrete path was re-laid in 2011/12, he was aware there was damage
to the concrete path but was unaware of the cause of the damage or that there was a
possible insurance claim for the damage.
The FSP concedes that the pipe was leaking from 2008. The Applicant and his
concreter describe lifting and cracking of the concrete path near the entrance to the
house which is proximate to the neighbour‟s leaking pipe. Although the FSP
describes the concreter‟s evidence as retrospective, nonetheless, the concreter does
describe severe cracking which he says was caused by the leaking pipe. In view of
his occupation, I am satisfied he has expertise to make that statement.
Having considered all the material carefully, I am satisfied that the 2011/12 damage
to the concrete path was caused by the leaking pipe.
Much of the FSP‟s evidence from its experts is not relevant as it addresses the sta te
of the concrete now and not at the time of the work done by the Applicant‟s
concreter.
I accept that the FSP is not able to verify the account given by the concreter and the
Applicant of the state of the concrete in 2011/2012 but, in the face of the positive
assertions by the Applicant and his concreter, I consider the FSP could make a
claims decision.
I note there is a policy condition which says that an insured is not to repair or replace
any damaged items without the FSP‟s consent. However, I do not consider that it is
fair in all the circumstances of this dispute for the FSP to rely on that policy term as
the Applicant was not aware at the time of the loss of the cause of the damage or the
fact that he may make a claim upon insurance. Furthermore, I consider section 54 of
the Insurance Contracts Act 1984 would apply so that the FSP may not refuse to pay
the claim in the circumstances for this reason.
However, having considered all the policy terms, and particularly how the FSP settles
a claim, I do not consider it that it is fair in all the circumstances that the FSP pay the
Applicant the whole of the claim being $7,500.
The policy makes it clear that the FSP is only to repair or pay for the cost of repairs to
that part of the building that actually sustained loss or damage. Further, the FSP can
try to match material used to repair the building with the original materials or nearest
equivalent.
The Applicant claims the cost of concreting the entire pathway. The concreter says
that he was unable to match the pattern of the existing concrete, as that pattern had
discontinued and that he had no choice but to colour the whole area.
The entire pathway was not damaged. The FSP has been denied the opportunity to
settle the claim in accordance with policy conditions by trying to match material.
In all circumstances I consider it is fair that the FSP pay the Applicant $3,750 being
50% of the claim to repair the concrete pavement.
Case No: 391334 Determination Page 9 of 19
3 Supporting information
3.1 FOS Approach
It is an accepted principle of general insurance law that an insured bears the onus to
establish on the balance of probabilities that they have suffered a loss caused by an
event to which the policy responds. This is known as a prima facie claim. Once so
established, the onus shifts to the insurer to prove on the balance of probabilities that
an exclusion applies if it seeks to deny or limit its liability for the loss.
3.2 Policy Schedules
26/9/08 – 15/11/11 Landlords Residential Insurance.
15/11/11- 15/11/12 Home Insurance.
15/11/13 -15/11/14 Home Insurance.
3.3 Relevant Policy extracts from Landlord policy
“Accidental damage cover
We will cover your buildings or contents for any accident al loss or damage.
There are also a number of incidents we will cover under specific conditions - these are listed
on the following pages.
Landslide of subsidence
We will cover your buildings or contents for loss or damage as a result of a landslide or
subsidence.
We will only do this if the loss occurs within 72 hours of:
Liquid escaping from a fixed pipe, or an object attached to a pipe, fixed gutter, or a drain.
Water or liquid damage
We will cover your buildings… For loss or damage caused by water or liquid…
Your re sponsibilities when you are making a claim
When you are making a claim you must meet a number of responsibilities.
You must:
- Not repair or replace any damaged buildings or contents without our consent.
Exclusions to your cover
We will not cover any loss or damage as a result of, or caused by:
- settling, shrinkage or movement of any earth
- erosion, rust, corrosion, gradual deterioration, depreciation, wear and tear
- a defect in an item, structural defects, or faulty workmanship or design
- landslide or subsidence, unless:
We agree to cover the incident as described under “landslide or subsidence”
How we settle a buildings claim
“ How we settle a buildings claim
1. We will decide how we will settle your claim
If your buildings suffer loss or damage, we will decide whether to:
repair
rebuild, or
Case No: 391334 Determination Page 10 of 19
pay you the cost to repair or rebuild that part of your buildings that suffered loss or
damage.
If we do, we will:
…
only repair, rebuild or pay you for the part or parts of the building that actually
sustained loss or damage, including damaged portions of fixed coverings to walls,
floors and ceilings only in the room, hall or passage where the damage occurred
try to match any material used to repair your buildings with the original materials or
nearest equivalent available to the original mat erials.”
3.4 Relevant Policy extracts from Home policy
Accidental damage cover
We will cover your buildings or contents for any accident al loss or damage.
There are also a number of incidents we will cover under specific conditions – these are listed on the following
pages.
….
Landslide or subsidence
We will cover your buildings or contents for loss or damage as a result of a landslide or subsidence.
We will only do this if the loss or damage occurs within
72 hours of:
• an earthquake or explosion
• a storm or flood, including rainwater or wind, or
• liquid escaping from a fixed pipe , or an object attached to a pipe, fixed gutter, fi xed tank or a drain.
….
Water or liquid damage
We will cover your buildings or contents for loss or damage caused by water or liquid.
….
We will not cover your buildings or contents for loss or damage caused by:
• landslide or subsidence, unless:
–– we agree to cover the incident as described under
„Landslide or subsidence‟.
• ……
Exclusions
We will not cover any loss or damage as a result of, or caused by:
• settling, shrinkage or any movement of earth
• erosion, rust, corrosion, gradual deterioration, depreciation, wear or tear
a defect in an item, structural defects, or faulty workmanship or design
General exclusions
We will not cover any loss or damage, or liability as a result of, or arising from:
• any incident that does not occur within your period of insurance
You need to make your claim as soon as possible.
An y delays may:
• reduce the amount that we pay, or
• prevent us from paying a claim.
Glossary
accidental loss or damage
damage to, loss or destruction of the buildings that make up your home, or your contents and valuable
items, when it is caused by an unintentional act, or an unforeseen and uncontrollable incident.
3.5 Expert and other evidence
Record Key points
Claim Form Claim on home policy re loss/damage occurred 8 March 2014
Case No: 391334 Determination Page 11 of 19
4 May 2014 Discovered by DW (when rectifying floorboards)
Water damage from next - door neighbor downpipe (9 V St) causing
water going under the house making moisture, mould in the house
(health haz ard)
Caus ed floorboards to bow
Claimed damage $30,530
FSP’s Engineer
(M)
Report
30 June 2014
Inspected and photographed property 25 June 2014
2007 property purchased
2007 - 2010 rented to Applicant‟s sister
2008/2009 renovat ed by insured with addition of rear extension,
painting, flooring, concrete footpath, new sewer pipes, subfloor
vents, repointing external face brickwork
2009 Applicant replaced all sewer pipes wit h plastic as he was
constructing new concrete paths over old concrete pipes
Since 2009 damp and mould noted by sister, but didn‟t know the
cause.
2010 Applicants took occupation, and noted moisture and mould
and distortion of floorboards
From September 2013, ongoing issues
Applicant investigates and discovers in April 2014 that the house
next door had a leaking storm water pipe which was leaking storm
water into the subfloor of the ins ured property
16 April 2014 Council inspection identifies defective guttering and
storm water pipe work and neighbour ordered to repair
3 May 2014 neighbour rectified defective guttering/storm water pipe
Claim in relation to subsided flooring, cracking brickwork, and mould
issues as noted from 2009 attributable to the now identified
defective guttering and storm water pipe from the neighbour
“ Observations – In ternal
Floating Flooring
7. I noted the areas of floating floor board damage in the hallway,
bedroom 1 and bedroom 2 which consisted of minor cupping.
…
9. In my opinion, [the moisture readings of 12% - 14%] indicate
relatively high entrapment of moisture within the timber floating floor
indicate of a high level of subfloor moisture consistent with short -
term exposure consistent with the alleged leaking pipe from
[neighbouring property].
Bedroom 1
10. I noted the north eastern corner of the floor subside d
considerably and was not level and [Applicant] indicated that the
built - in wardrobe doors did not close effectively.
11. I did not identify any visible settlement cracking within the walls
or cornices which would correspond to footing settlement in line with
the floor framing.
12. In my opinion, the floor framing and subsidenc e has been an
ongoing and pre - existing issue with floating flooring installed over
the existing sloped substrate.
…
Observations – External
Brickwork and Concret e Footpath
15. I did not observe or identify any damage or cracking to the
external brickwork or concrete footpaths attributable as a result of
the leaking pipe.
Case No: 391334 Determination Page 12 of 19
16. In my opinion, the brickwork and footpaths were viewed to be in
excellent condition.
17. I noted and qu estioned [Applicant] the brickwork and foot paths
were in excellent condition and that alleged damage appears to be
rectified through conducted re pointing and concrete works.
18. [Applicant] replied that he undertook these works without
knowledge that pos sible recourse could be made through insurance
and has now provided [FSP] with receipted costs.
19. In my opinion, any brick movement and associated subsidence
within the dwelling have been ongoing and pre - existing issues
relative to age and construction unrelated to the leaking pipe.
Subfloor
20. The subfloor was visually inspected from a small access point
from the southern side of the dwelling only.
…
23. I note that [Applicant] has undertaken a number of ventilation
measures in installing new vents through external and internal dwarf
walls to facilitate effective sub floor ventilation.
24. Foundation material can be classified as medium reactive
clay/ silt (M Class) …
25. Such M Class foundation material is susceptible to
footing/foundation reactivity relative to general site and weather
conditions.
26. An increase in moisture content and saturation of M Class
foundation materials subsequent to general rainfall will trigger
reactivity leading to subsidence and movement over an extended
period of time.
27. In saying this, no surface water was noted about the footings or
subfloor area at the time of my inspection.
…
29. Such footing construction is extr emely susceptible to differential
settlement which is likely the attributing factor in observed floor
levelling issues.
Conclusion
…
Proximate Cause & Effect
…
Description of
Damage
Plausible Causation of
Damage Including
Apportionment (%)
Estimated Timing
of Damage
Propagation
General
excessive mould
and moisture
issues
throughout the
dwelling.
Pre - existing and long - term
building issues relating to
subfloor ventilation and
general moisture
conditions of the dwelling
which appears to have
been exacerbated by the
ingress of stormwater
water from leaking pipe
from [neighbouring
property].
In my opinion, damage can
be apportioned as follows:
Pre - existing and long - term
building and ground
movement issues – 20%.
Ingress of stormwater
water from the leaking pipe
of [neighbouring property]
Issues have been
ongoing prior to 28
February 2012;
however appear to
have initiated from
15 September
2013 as a
contributing factor
and exacerbating
damage on from
the leaking pipe as
identified in April
2014.
Case No: 391334 Determination Page 13 of 19
– 80%
Floating floor
has cupped and
warped in
locations –
Hallway,
Bedroom 1 &
Bedroom 2.
Pre - existing and long - term
building issues relating to
subfloor ventilation and
general moisture
conditions of the dwelling
which appears to have
been exacerbated by the
ingress of stormwater from
the leaking pipe of
[neighbouring property].
In my opinion, damage can
be apportioned as follows:
Pre - existing and long - term
building issues – 20%.
Ingress of stormwater
water from the leaking pi pe
of [neighbouring property]
– 80%
Issues have been
ongoing prior to 28
February 2012;
however appear to
have initiated from
15 September
2013 as a
contributing factor
exacerbating factor
exacerbating
damage on from
the leaking pipe as
identified in April
2014.
Settlement in
flooring within
the north
eastern corner
of the front
Bedroom 1.
Pre - existing issue relating
to long - term and general
building and ground
movement of the dwelling
unrelated specifically to the
leaking pipe of
[neighbouring property] .
In my opinion, damage can
be apportioned as follows:
Pre - existing issue relating
to long - term and general
building and ground
movement – 100%
Ingress of stormwater
water from the leaking pipe
of [neighbouring property]
– 0%
Issues have been
ongoing p rior to 28
February 2012.
Cracking of
external
brickwork about
the north
eastern corner
and archway at
front door entry
(northern wall).
Pre - existing issue relating
to long - term and general
building and ground
movement of the dwelling
unrelated specifica lly to the
leaking pipe of
[neighbouring property].
In my opinion, damage can
be apportioned as follows:
Pre - existing issue relating
to long - term and general
building and ground
movement – 100%
Ingress of stormwater
water from the leaking pipe
of [neigh bouring property]
– 0%
Issues have been
ongoing prior to 28
February 2012.
Repair
procedures
discussed but no
scope of works
produced.
FSP’s Property
Services Expert
(O)
Report
12 August 2014
Inspected site 19 July 2014
Water from neighbour flowed under house some time ago
“The Insured showed us a section of the bamboo floating floor in the
main bedroom that has dropped. We were advised that the Insured
had to request the installers re - attend after installation as part of the
floor was lifti ng. We cannot confirm if this damage is related to the
moisture or if it is an installation problem therefore we would
recommend a builder attend and inspect the flooring and structure
under the house to determine the cause.
Case No: 391334 Determination Page 14 of 19
…
Exterior of property:
There is a cement slab with a brick imprint surrounding the hous e
which has breather vents for the void area underneat h the house
however these are at the same level as the paved slab therefore
this will continue to cause problems every time it rains or the are a is
washed down as the wat er will once again enter the void under the
house.
…. Soil under the house which is wet.
….. High moisture content in the affected areas
…… Ongoing problem and the insured will need to address how
drying of the underneat h of the property can be managed”
FSP’s External
Assessor (C)
Report
25 July 2014
Attended and photographed property 22 July 2014
Photographs are annotated “floating flooring swollen” and “bedroom 1
bedside table mouldy ” It is noted the downpipe was rectified and the
bricks repointed.
Water damage claim – began to investigat e issues 15 September 2013.
Claim relates to wat er damage occurring over a long period of time due
to storm water runoff flowing beneath the home in conjunction wit h the
escape of water fro m a fixed pipe from an adjacent property.
Prior to 2010, Applicant and tenant (his sister ) first identified
occurrence of mould in clothing stored in wardrobe of bedroom 3 and
bedroom 1
Cracking identified eastern corner of front exterior wall which appe ared
to have sunk. Front archway brickwork had also cracked.
Side concret e path had cracked.
Applicant carried out repairs to these items.
21 October 2011 repointed all brickwork to front and sides
12 July 2012 contract with AC re - c oncrete path in the amo unt of $7500
Floating flooring began to lift approximately 1 year after installation
(refer installation invoice from S dated 26 April 2013 for $6300).
Applicant initially believed this to be an issue with installation and
arranged attendance by original contractor to reinstall.
Flooring began to lift after reinstallation and alternative contractor DW)
appointed and 8 March 2014 identified flooring lifting and cupping due
to water ingress from below (primarily in bedroom 2).
Applicant claimed swollen bam boo floating floor in hallway, front living
room and bedrooms 1 - 3. Resultant damage repair quote from S dat ed
28 April 2014 $5800 including GST
Applicant subsequently discovered that during severe weather, storm
water runoff was backflowing out of the down pipe at the front eastern
corner of the neighbouring property and flowing towards the insured
property.
FSP appointed structural engineers and panel restorers to inspect/carry
out work on the property.
Applicant has stated moisture and mould issues were present whilst his
sister was a tenant at the property prior to 2010 and continued when
the Applicant moved into the property.
The leaking storm water pipe and defective guttering at the adjacent
property was identified in April 2014 and stormwat er line r ectified in May
2014.
Applicant states since rectification of storm water pipe the moisture in
his home was greatly reduced.
The Applicant has also carried out additional works to assist with air
flow beneath the home by removing several bricks from unde rfloor walls
and by replacing the access door with one with larger holes.
The Applicant has also purchas ed a fan which he intends to install with
ducting beneath the home to assist with ventilation.
Case No: 391334 Determination Page 15 of 19
All water damage occasioned after 15 September 2013 cou ld be
considered under the policy.
Mould damage prior to that date should be excluded due to long - term
pre - existing moisture conditions advised by the Engineer
Claims include: cracked external brickwork, cracked conc rete footpath,
repair swollen bamboo floating flooring, distortion in the flooring and
built - in wardrobes in front bedrooms 1 and 2, installation of 4 vents to
ventilate underfloor space; various contents items.
FSP’s External
Assessor (C)
Report
25 July 2014
Insured should have lodged claiming 2010 when they were aware of
mould issue and a water issue
Noted engineers advised is very likely the pipe had been leaking
between 26 June 2008 and 30 September 2011
Recommended payment of 80% of the quote to fix the fl oor being
$4,640 including GST
Recommended payment of mould damage to bedside tables in
bedroom 1, bedroom 1 queen mattress and bedroom 3 mattress
FSP’s Engineer
(M)
Report
22 August 2014
M re attended property 19 August 2014
despite rainfall, the neighb ours stormwater outlet was functioning, so
concluded the stormwater issues eliminated and repaired
floating floor damage remains damaged and unchanged as does
moisture content
inspected the subfloor and found no significant water pooling but
consider subfl oor ventilation poor
“Proximate Cause & Effect
…
I confirm the moisture readings wit hin the external flooring areas of
damage cont ained in hallway, bedroom 1 & bedroom 2 have slightly
changed from my previous attendance in 25 June 215 by
approximately 3%.
In my opinion, the slight increase … can be attributed to a natural
spike in moisture contained within the atmospheric consistent with
three (3) continual days of rainfall causing an escalated MC within
timber products.
In my opinion, the slight obser ved variance … indicat es the subfloor of
the dwelling continues to have relatively high entrapment of moisture
within the timber floating floor.
… the entrapment of moisture is related to poor pre - existing subfloor
ventilation which is unable to effective ly regulate the moisture
conditions affecting the timber flooring.
Notwithstanding the above, the event being the pipe leakage from the
neighbouring property has caused an increase of water/moisture within
the subfloor whic h has contributed to the floorin g damage.
As previously reported, pre - existing and long - t erm building issues
relating to subfloor ventilation and general moisture conditions of the
dwelling have been exac erbated by the ingress of stormwater from the
leaking pipe of [neighbouring propert y].
Still apportioned damage 20/ 80%
…
In my opinion, the drainage vents placed by the Insured are not
effectively proving natural airflow and cross - ventilation throughout the
subfloor area given their location and placement height.
The reason why these i nstalled vents are not providing effective cross -
ventilation allowance is that they are installed at an inc orrect height
due to the construction of the footpath which consequentially
corresponds to the mid - level of the floor joists which are running
parall el with the dwarf wall alignment.
Case No: 391334 Determination Page 16 of 19
In my opinion, the floor vents will need to be replaced by the insured
prior to any remedial works to the flooring is undertaken.
This will require the Insured to install mechanical ventilation system to
ensure continual flow of air and the construction of int ernal flow
passages through the int ermediate dwarf walls.
I do not agree with the [O] statement that wat er during rainfall periods
will enter through the subject vents into the subfloor and cause
significant issue w ithin moisture and dampness.
I note during my visit of the dwelling which rainfall had been continually
fall for three (3) days, the subfloor area was noticeably dry without
significant pooling of water or wetness contrary to [O]‟s suggested
outcome.
…
I confirm my previously reported proximate cause remains unchanged
…” (sic)
FSP’s Engineer
(M)
Email
1 September 2014
“Our consultant has provided the following comments.
As indicated in both previously issued reports, damage outside of the
apportioned 20% of internal floating timber flooring wit hin the dwelling
is not considered to be attributable or relat ed to the claimed leaking
pipe.
On this basis, the claimed concret e works is not related to the leaking
storm water pipe and is considered works in li ne with general
upgrade/betterment on behalf of the Insured.”
FSP’s External
Assessor (C)
Report
9 September 2014
For buildings claim - Payment recommended in the amount of
$4,640.00 inclusive of GST being 80% of the quotation for replacement
floorin g
For contents claim - Payment recommended of $2,800.00 inclusive of
GST for:
- bedside tables bedroom 1
- queen mattress bedroom 1
- mattress bedroom 3
FSP’s Engineer
(M)
Email
21 October 2014
“I have reviewed the furnished quotations and confirm that in my opinion
and as articulated in previous reports that any claimed damage outside of
the internal flooring are not related to the leaking stormwater pipe event
and are considered pre - existing or relat ed to general building
movement/settlement outside of t he claimed event.”
FSP’s Engineer
(MP)
Report
11 November 2014
Appointed to det ermine cause of floor movement
Visited and photographed the site 4 November 2014 and discussed a
timeline of events
“ SITE OBSERVATIONS
We observed no discernible cracking within the repointed exterior
brickwork or with in the dwelling itself.
Cracking of concern in the perimet er pavement was aligned across the
pavement and therefore parallel to cont rol joints at various centres.
This cra cking appeared consistent with pavement shrinkage and
suggested no significant longitudinal movement.
The bamboo flooring appears to have been installed with a suitable
gap between its edges and the skirting boards. The bamboos flooring
boards have appear ed “springy” in some areas of the master bedroom
however we observed no gaps bet ween the floor joists, bearers and/or
the masonry stumps below the original flooring.
We observed no underfloor moisture or mould on the underside of the
flooring beneath the m aster bedroom. This flooring was supported on
two intermediate masonry piers which appeared in good condition as
did all underfloor timber framing. Underfloor ventilation had recently
been improved by the insured.
Case No: 391334 Determination Page 17 of 19
A floor level survey indicated a 40mm dif ferential… The lowest
recorded level was within the master bedroom is easternmost corner
…...
(Did not carry out soil testing) in our opinion, the foundation soils in the
vicinity of this site are likely to include reactive clay….
DISCUSSION
…. observed no cracking within the perimeter masonry. Therefore this
perceived downward movement (of the floor) either predates the wall
repointing in 2011, or the middle of the floor has lifted.
…..
If the floors were indeed a relatively level when the building was
pur chased, and the master bedroom‟s corner became somewhat
lower, we would anticipate that this movement was most probably a
function of soil drying in that immediat e vicinity.
…..
SUMMARY
We do not believe the building‟s perimeter has settled since the
brick work was re - pointed in late 2011.
Despite the neighbouring stormwat er drainage deficiencies no
significant moisture has been observed under the dwelling.
If moisture did after the underfloor soils it would have resulted in an
upward heaving movement. Now that this deficiency has been
addressed and the insured has improved underfloor ventilation, we
would expect any stormwater overflow effects to abate, returning any
resultant floor curvature to its pre inundation level. ” (sic)
FSP’s Engineer
(MP)
Report
17 December 2014
“ MASONRY REPOINTING
As there is no evidence of recent movement within the masonry, and
therefore no resultant damage, the claim for repointing the masonry
should be ignored.
We reiterate earlier comments that the perimeter movement pre dates
the re - pointing in lat e 2011 and the downward movement experienced
is a function of reactive foundation soil drying and not related in any
way to moisture or any other insured event.
PERIMETER PAVEMENT
The cracking within the perimeter pavement is widespread and present
in areas remote from the neighbouring stormwater deficiencies. The
cracking is almost exclusively aligned across the pavement width.
This fine cracking is in our opinion a function of concrete shrinkage
resultant on the concrete de - hydrating after being cast. We do not
believe this damage is a function stormwater pipe discharge or
overflow.
FLOORING REPAI RS
In our earlier report…. we reported that we ex pected any underfloor
upward soil heaving as a result of neighbouring stormwate r
deficiencies would abate once the leak affected soils completely dry.
If the owner was unable to wait for this to occur, we would provide a
repair scope to drop the master bedroom‟s central flooring by 30mm.
…
Please note we do not recommend replacing t his floor as we are not
confident that it has complet ed moving. Future differential movement
between the buildings perimeter and the int ermediate piers should also
be anticipated depending on seasonal soil moisture changes outside
the building.
Case No: 391334 Determination Page 18 of 19
BAMBOO FL OORING
We do not concur that the bamboo flooring movement was solely the
results of the neighbour‟s stormwater deficiencies. While this down
pipe was clearly blocked and stormwater overflow was likely occurring
in that immediat e vicinity, the volume of ove rflow is unlikely to have
affected the entire underfloor area. General rainfall landing on
uncovered surfaces around the dwelling and poor underfloor
ventilation may have also influenced the underfloor humidity.
Factors other than reactive soil wetting ha ve also influenced the
dwelling during the period of ownership. As stated in our earlier report,
climatic soil drying during periods of low rainfall and the lack of a well
maintained neighbouring front yard has also contributed to historical
movement.
We consider the air vents installed by the owner an investment to help
with cross floor ventilation and therefore reduce the effects of humidity
build - up below floor level. However believe this would normally be
considered a building improvement, rather than being a necessary
requirement.” (sic)
Applicant’s
engineer
Email from GA to
Applicant
23 July 2015
“I can't meet the deadline in providing you with any report. I believe
you have a strong case against the insurance. If the brickwork and
concrete got damaged in one location rather than to the entire of
the house, it's more likely due to erosion caused by exposure to
leaked water.
The Insurance Company claiming that's its due to long term
subsidies, in my opinion it would have happened to the entire
building, not only one specific part of the wall. Also if the pad
footings got damaged due to the leaked pi pe and consequently
subsidies in the floor boards, there is evidence that water is going
under your wall as well and causing erosion, which will lead to
cracks in brickwork and concrete in a specific location(sic).”
Applicant’s letter
from concreter A
16 July 2015
“A took on the work … for (Applicant) due to severe cracking in the
concrete walkway which was due to leaking pipes from the next door
neighbor....
The water which was running from the neighbours property created a
major sinkhole which cause d the concrete to lift and crack. The
walkway became a major trip hazard.
We were unable to match the pattern of the existing concrete, as this
pattern has been discontinued. We had no choice but to colour the
whole area. With our experience, we believe that the cracking was
caused by the pipe work which runs underneath the concrete (sic).”
Applicant’s
Report from
plumber AP
24 August 2015
( Applicant) advised us to inspect the problem outside front of house as
there was a lot of water pooling under the front section of (Applicant‟s
house).
The inspection was completed and the following details were
observed: Pressure test was done on all pipework to check for any
leaks. All tests passed satisfactory wit h no loss of water pressure. The
main stormwater line (of neighbour) was found to be broken and all
the left hand side roof water was not going to the street, instead it was
pooling into (Applicant‟s house).
With my experience, the huge amount of water poo ling under the front
area of (Applicant‟s house) can be causing problems to the floor,
structure and footings of front area as the water is not being taken
away and this is also causing moisture to the above floorboards. Next
Case No: 391334 Determination Page 19 of 19
doors stormwater will need to be repaired to eliminate the huge
amount of water flowing to (Applicant‟s house).
Quote for repairs needed:
Take out broken pipework from (neighbour) and replace with new
connection
Test pipework and backfill any excavation needed.
Total cost of quotation including material is $950 including GST.