Determination 390501

Quality of replacement concrete slab after flood claim

FirmFinancial Firm (Unknown - Insurer)
Decided2015-09-16
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicants disputed the quality of a replacement concrete slab installed after a flood claim and sought its replacement. AFCA found the FSP is not obliged to provide further slab cover but ordered it to scope and cash settle the other workmanship complaints.

The insured must prove on the balance of probabilities that poor workmanship caused the claimed damage, and the expert evidence did not establish that.

Issues

Subjects and remedies

home or building damagenatural disasterpay claim

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 390501 Determination Page 1 of 16 Case number: 390501 16 September 2015 1 Overview 1.1 Dispute The Applicants lodged a claim on their home building insurance policy with the Financial Services Provider (FSP). The claim related to stormwater/flood damage on their property from 2 February 2012. The FSP considered and ultimately accepted the claim. In part, this involved a consideration of whether the concrete slab at the home had been damaged. Once accepted, the FSP agreed to replace the slab. It is the Applicants‟ view that the replacement slab is of inferior quality and that it needs to be replaced. They contend it has caused movement in the home and further damage. The FSP disagrees and the parties seek a decision on the issue. The Case Manager provided the parties with a Recommendation on the issues in dispute. The Recommendation was in favour of the FSP. The FSP accepted the Recommendation but it was not accepted by the Applicants. In the circumstances, the dispute has been referred to me for Determination. 1.2 Issues and key findings Has the claim been appropriately settled? Although the replacement slab may not have been installed in accordance with the engineer‟s specifications, the material provided does not establish on the balance of probabilities that the claimed damage is caused by the installation of the replacement slab or by the levels of the slab. Rather, the available evidence establishes the replacement slab was installed in accordance with normally accepted building practices and that the levels are adequate. 1.3 Determination This Determination is in favour of the FSP. It is not obliged to provide any further cover to the Applicants in relation to the concrete slab. Insufficient material is provided in relation to other workmanship complaints such as painting plastering etc. and if it has not already done so, the FSP is to attend the property, prepare a scope of works and cash settle the Applicants for these other complaints. Case No: 390501 Determination Page 2 of 16 2 Reasons for Decision I have decided this case on its merits, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions. I have taken into account all the material submitted by the parties, both before and after the Recommendation. I am satisfied that the documentation I have relied on has been provided to both parties. Applicants provided new material after the Recommendation After the Recommendation was rejected, the Applicants made further submissions and provided new material. Where relevant, the submissions and material are referred to in this Determination and are set out in Section 3 in Supporting Information. The FSP has not provided any new information or responded to the Applicants‟ new material and submissions. 2.1 Has the claim been appropriately settled? Applicants’ home damaged by floodwater In February 2012, the Applicants‟ home was flooded, as a result of which the home and concrete slab were damaged. The FSP‟s assessor (TJ) inspected the home 13 February 2012. He recommended a structural engineer be appointed to prepare a scope of works to rectify the concrete slab. WJ provided scope of works to rectify slab The engineer WJ was engaged by the FSP to inspect the home. WJ inspected the property once and then on the second occasion on 12 June 2012. Neither party has provided a report from WJ about the first inspection. WJ wrote a report after the second inspection. He recommended:  the slab and path under the house is to be removed and replaced with a new slab are shown on the slab plan dated 14 June 2012  a 800mm reinforced raft slab is to be used  the slab is to be poured on to a minimum of 150mm clean road base filling and waterproof membrane of minimum thickness 0.2mm  after removal of the topsoil, the slab area is to be proof rolled and any defective areas are to be excavated and replaced with suitable road base material and compacted  slabs are to be monolithic slabs with stainless steel mesh protection  various Australian Standards were cited  concrete specifications included very specific information including: “all filling below slabs is to be contacted in layers not exceeding 150mm thickness, to 97% SSD at approximately 2% below optimum moisture content, ..” Case No: 390501 Determination Page 3 of 16 and “… recommend that the non -reactive filling material, be ridge gravel, or road base gravel rather than pure river gravel or pure coarse sand, so that water cannot penetrate the compacted fill material, at a later date.” The two drawings dated 14 June 2012 that accompanied the letter described the typical raft slab sections and included the annotation that there be: “150mm consolidated roadbased filling”. From the material provided, there appears to be no material change provided in the letter from WJ dated 10 September 2012. Insufficient proof that failure to comply with scope of works caused damage It is not clear from the information provided when the work was carried out, but at some time after completion, a site inspection took place with the Applicants, the assessor, the builder (RG) and the concrete contractor (T). The assessor not ed a number of the Applicants‟ complaints with the repair work including that the floor tiles in the lounge have opened up since installation of the slab. The assessor‟s notes indicate the Applicants claimed this occurred because the contractor used crusher dust under the new slab which did not compact sufficiently and allowed water to affect the subsoil. The assessor was of the view that the cause of damage was typical ground movement from the highly reactive soil found in the area. Nonetheless, the assessor arranged for an engineer to inspect the slab. The FSP‟s policy provides a lifetime guarantee. This means that when an insured home is repaired or rebuilt by one of the FSP‟s repairers or builders, the FSP will guarantee the workmanship of repairs that were authorised by it for the lifetime of the home and will fix any defect caused by poor workmanship. The Applicants claim a number of problems because of poor workmanship. The Applicants claim the slab should be replaced as it was damaged and will cause further movement damage to the home. They assert the slab was not constructed according to the engineer‟s design, the water runs in the wrong direction resulting in pooling in the garage, storage and laundry rooms, the slab is not the appropriate thickness and the slab is smooth causing slipping injuries. The Applicants have the onus to establish on the balance of probabilities the poor workmanship of the FSP‟s contractors have caused the claimed damage. Aside from its assessors‟ opinion about the cause of damage, the FSP provided material from a building consultant (EF) and a consulting engineer (RC). EF supports the Applicants after his inspection of the property for the FSP on 18 December 2013. EF reported he considers the movement of the vinyl floor tiles in the kitchen lounge area appears to be a direct consequences of foundation movement caused by flooding inundation. EF said that as the slab had been laid on highly reactive soil, without expansion joints, it was likely to crack. EF does not appear to have a copy of the material from WJ who designed the slab in that Case No: 390501 Determination Page 4 of 16 manner. Therefore, EF suggested a structural engineer‟s opinion was required on the movement control aspects of the slab. A new assessor (GH) had taken over conduct of the matter for the FSP and engaged a consulting engineer RC who provided a report on 20 October 2014. RC referred to drawings, structural details, scope of works and specifications prepared by WJ. RC appears to have looked at photographs of the old slabs and considers the new slab system represented a substantial improvement. Having performed various tests which are described in the report in detail, he concludes that there is no evidence to suggest unacceptable movement and he says the slab is within the appropriate building standards. RC also said it is not normal practice to excavate and place roadbase material under buildings and not necessary to do this to comply with the relevant Australian Standards. He concludes that the use of “crusher dust” under house slabs is a common and acceptable building practice. Further, he says the level survey indicates that the slab system drains marginally and that there was no evidence in the level survey to suggest the slab had heaved at the outside so as to retain water. The level survey attached to his report shows the floor slab is within 26mm of being level which RC says is well within the allowance considered reasonable in Australian Standards. GH was asked by the FSP to comment and in a recent email said he preferred the view of RC to EF as RC was a professional engineer experienced with concrete slabs. After the Recommendation, the Applicants provided two reports from WJ who re- inspected the slab on 16 April 2014. WJ addressed these two reports to the FSP dated 1 and 21 July 2014. It is not clear from the material provided why this information had not been provided by the FSP to its experts or to the Service in consideration of this dispute. It is particularly concerning in view of the submissions made by the Applicants that pertinent material was not provided. In any event, WJ reinspected the site in April 2014. WJ does not appear to have measured levels, but refers to “levels supplied by others”. He notes the fall on the slab to the centre of the garage to be approximately 9mm. It is assumed this information was obtained from the FSP‟s assessor, TJ. When TJ inspected the site with the builder and the concrete contractor, he noted the concrete was checked with a laser measure. He noted the highest point was in the carport which was 9mm higher sloping to edge of slab which he said would assist in water draining away. WJ concluded that the slab had either been poured with incorrect levels or insufficient compaction to the fill beneath the slab. WJ had concerns about the fill as no certification was issued (and if it was, he had not seen it). The parties have not provided any certification. The Applicants mention in their submissions they have requested approvals from the FSP but they were not provided. However, when advised by the Applicants that the fill material used beneath the new slab was crusher dust and not the roadbase material specified by WJ, WJ Case No: 390501 Determination Page 5 of 16 said it was quite possible (my emphasis) that the fill could be responsible for any subsidence in the new slab. WJ said: “Crusher dus t has the disadvantage of not being able to be compacted to a satisfactory degree and is not waterproof, it allows water to infiltrate through under the slab, which can cause the highly reactive soil to move” WJ contrasted this to compacted roadbase (which he had specified as fill) which he says creates a waterproof barrier which is extremely important when the soil is extremely reactive (like the soil on the site). WJ concluded that if compaction had not been done to a sufficient level, this would allow the slab to settle. WJ comments about the old concrete footing and its effect on settlement of the slab but there is insufficient information provided by either party to comment on this speculation about the cause of subsidence. Finally, although WJ makes some suggestions in his report of 1 July 2014 about how to rectify the problem, the three remedies appear to only address the issue of water ponding on the slab and not the fundamental complaint of subsidence in the new slab. The Applicants have not provided any expert material because of financial constraints. I have considered carefully all the expert material provided. I am not satisfied that the Applicants have established on the balance of probabilities that the poor workmanship of the FSP‟s contractors caused the damage claimed by movement. Although EF is supportive of the Applicants, his opinion is misconceived as the slab was designed as a monolithic slab. Although I accept the FSP‟s contractors did not construct the concrete slab in accordance with t he specifications of WJ, WJ‟s opinion is insufficiently persuasive about the consequence of the use of crusher dust as fill material. He says it is “quite possible” that the fill could be responsible for subsidence in the new slab but the standard of proof required is that it is “probable” not merely “quite possible”. This ambivalence by WJ coupled with the comprehensive report from RC results in the material provided (when considered in totality) being insufficiently supportive of the Applicants‟ claims. Despite the Applicants‟ criticism of RC, the report demonstrates he has undertaken the requisite work to support his opinion that the workmanship was completed in accordance with normally accepted building practices. Material establishes levels adequate and not the cause of claimed damage As for the issue of water pooling under the house, both TJ and RC took measurements or undertook level surveys and concluded that water would fall to the edge of the slab which would assist in water draining away. I have carefully considered the floor level survey dated 3 October 2014 and am satisfied the slab system drains to the edges of the slab. Case No: 390501 Determination Page 6 of 16 EF says there appears to be minimal positive fall anywhere on the slab to the perimeter of the slab, but he did not take meas urements or undertake a level survey. WJ did not take levels either. He says he relies on levels supplied by others. But WJ seems to be under the misapprehension that the fall on the slab is to the centre of the slab whereas the level survey arranged by RC and the laser survey conducted by TJ show the fall is to the edge of the slab. TJ‟s notes says: “The concrete was checked with a laser measure and found the highest point was in the carport which was 9mm higher sloping to edge of slab which would assist in water draining away.” I have considered the photographs provided and accept there is evidence of water pooling but I also note the area is open to the elements. Having considered all the material provided, I am not persuaded on the balance of probabilities that poor workmanship caused the water pooling issue. Other complaints about the slab not established The Applicants complain the slab in many places is not to the thickness required, but no independent expert evidence establishes this contention. The Applicants also complain the concrete is smooth rather than “a rough broom finish” but there is no documentation to support this contention either. Finally, the Applicants complain that the house is now 40mm lower than previously and they cannot put a car into the carport. The only comment made about this complaint was by WJ who said that he was: “unsure if this was ever possible.” Insufficient material to comment on other complaints The Applicants made a number of other complaints about the FSP‟s workmanship. They say no one has come to the house since to see what work needs completing but rather the concrete issue was to be dealt with first and then the other complaints would be addressed. The Lifetime Guarantee under the policy means that the FSP will fix any defect caused by poor workmanship. In the alternative, the FSP can cash settle the Applicants for these other complaints. The FSP says that as the Applicants did not want the builder back, the FSP offered a cash settlement for the remainder of the r epairs. TJ‟s inspection report indicates the Applicants were cash settled for the painting and that once the engineer‟s report was received the builder would attend for minor rectifications. As well as TJ, both EF and RG have commented on these other complaints. In submissions, the Applicants said the FSP wanted to pay out approximately $3,500. However, insufficient information is provided by the parties about these other complaints and about a cash settlement to form part of this Determination. Case No: 390501 Determination Page 7 of 16 If it has not already done so, the FSP is to attend the property, prepare a scope of works and cash settle the Applicants for these other complaints. The Service encourages the parties to this dispute to resolve any issues that might arise during that process. However, the parties can return to the Service if they are unable to resolve any issues arriving from the scope of works for the other complaints and/or the costing of that work. WJ’s reports should have been provided to the Service Finally the Applicants also make a number of complaints about the conduct of the FSP in the management of his claim. They complain that they did not receive the levels from RC but they are attached to RC‟s report. They also complain that the FSP did not provide all reports. However, although they were not provided to the Service, they were provided to the Applicants who were able to produce them after the Recommendation. I agree the reports were material and should have been provided to the Service by the FSP. However, I am not otherwise satisfied on the material provided that the complaints about claims management are made out. Case No: 390501 Determination Page 8 of 16 3 Supporting information 3.1 FOS approach to this dispute It is an accepted principle of general insurance law that an insured bears the onus to establish on the balance of probabilities that they have suffered a loss caused by an event to which the policy responds. This is known as a prima facie claim. Once so established, the onus shifts to the insurer to prove on the balance of probabilities that an exclusion applies if it seeks to deny or limit its liability for the loss. 3.2 Extract from policy Lifetime guarantee We provide a „lifetime guarantee‟ when your home is repaired or rebuilt by one of our preferred repairers or builders. This means: 1. we guarantee the workmanship of repairs that we authorised for the lifetime of your home 2. we will fix any defect caused by poor workmanship. We will decide on what needs to be done to fix any defect. When you’re not covered by this guarantee This guarantee does not apply to: 3. repairs you authorised yourself 4. loss, damage or failure of any electrical or mechanical appliance or machine 5. wear and tear that is consistent with normal gradual deterioration of your home . 3.3 Relevant expert reports Record Key points FSP’s claim lodgement details  2/2/12 storm event causing flooding and cracking .  12/11/13 file notation that all works are now completed . Builder’s report (RG) 13 February 2012  FSP‟s assessor TJ engaged repairer RG who attended site 13/2/12 .  Flood water t ravelled through the bottom level of the home up to about 600mm .  Downstairs area consists of garage, laundry and storage area. Walls are fibro and can be repainted .  Split system air conditioner damaged by water and requires replacement .  House has suffered from structural movement as a result of the water ingress. Upstairs level of home is now cracking .  Concrete slabs are cracking as well. Recommends Case No: 390501 Determination Page 9 of 16 appointment of structural engineer to advise of scope to rectify slabs. Consulting civil and structural engi neer’s report (WJ) 14 June 2012  Second inspection carried out 12 June 2012 .  Scope of works to repair flood damage and particulars included for the laying of the new ground floor concrete slab noting after removal of the topsoil, the slab area is to be pro of rolled, detailed concrete specification provided .  After ground floor slab poured, levelling work for first floor and upstairs internal cosmetics works detailed .  2 drawings provided of proposed new slab 14/6/12 . Consulting engineer’s second report (WJ) 10 September 2012  Appears to be an incomplete (page 2 and 4 only) but duplicate of earlier report as it refers to 2 nd inspection carried out 12 June 2012 and recommendations in relation to the removal and replacement of the ground floor slab and describes same issues with:  Main hallway has cracking in the gyprock (recommends repair and repainting of this area) .  Main bedroom has cracking in the ceiling and the cornices at wall corners. Wardrobe door sticking and needs to be checked after the floor is levelle d. Cracks require repair and room is to be repainted .  Bedroom 3 has cracking in the cornices and there is carpet damage where water from the bathroom has been leaking .  Tiles have cracked in the bathroom and the shower. There is a broken step in the bathroo m which has allowed water to leak into bedroom 3 .  Concrete specification also listed .  One page of drawing re proposed new slab dated 10/9/12 . Assessor’s report (TJ) Undated  Photographs and site inspection by TJ, RG and concrete contractor T .  Notes Applicant was unhappy with several aspects of the repair work and not happy with the conduct/work of the FSP‟s nominated builder, RG. Complaints noted:  After the concrete slab was poured, contractor damaged the corner of the slab in front of the stairs .  T imber framing to wall sheets needs replacing .  Timber architrave had come away from the back door and this was caused by movement of the slab .  Air conditioner is discharging water directly onto the new slab and this water pools on the slab .  Builder to seal penetrations in wall sheets and bottom Case No: 390501 Determination Page 10 of 16 plates .  Downpipe on the left hand side of the home (above the veranda) has not been connected to the stormwater waste .  Vinyl floor tiles in the lounge have opened up since the installation of the slab and the tiles ha d been in place for six years. Applicant claims the slab is allowing water to seep under it and push up the flooring because contractor used crusher dust which did not compact sufficiently and allowed water to affect subsoil .  Crack is evident in the ceilin g cornice .  Every time it rains, water pools on the slab under the house and this never happened with the prior slab and water entering laundry and storage room from wind driven rain .  TJ writes builders have a picture of downstairs slab prior to removal with water pooling on the concrete; previous slab poured at different times with joins which would have allowed wind driven rain to run across and down the joins between the slabs .  TJ notes new concrete slab poured as one slab; existing house footings are original and not replaced.  Water marks on concrete slab into laundry indicate water has entered storage room via bottom plates which have not been sealed sufficiently and builder needs to seal bottom plates to stop wind driven rain .  Concrete was checked wi th a laser measure and found the highest point was in the carport which was 9mm higher sloping to edge of slab which would assist in water draining away .  Complaints re paint job and to be cash settled .  TJ said vinyl tiles complaint and cracks due to typical ground movement from highly reactive soil commonly found in the area (insured claimed no movement cracks prior to repairs) .  TJ arranging another engineer to inspect slab (house sits on adjustable fixings so they can be adjusted easily to allow for future movement) .  Concludes cannot finalize but engineer to inspect property and confirm cause of house moving and once report received, RG to attend for minor rectifications. Building Consultant’s report (EF) January 2014  Builder reported to TJ after an inspection 18/12/13 to ascertain if the repairs conducted were of a “tradesmanlike standard” and to identify areas for Case No: 390501 Determination Page 11 of 16 rectification if necessary .  Describes the insured property as a raised single story dwelling on steel piers with garage, laundry and stor age room underneath with the entire open area underneath the dwelling concreted .  EF notes some of the internal painting work was ill prepared and sub - standard .  Notes claim that cracked joints repaired in ceilings and walls have given way .  Some of the tilin g was sub - standard, with chipped, mismatched and poorly installed tiles .  Numerous additional repair - related issues were present .  Outside, the bottom batten which supports the bottom edge of the wall sheets around the perimeter of the building has been cut off to allow for the building to be re - piered and re - levelled. This area does not appear to have been adequately re - supported .  So me of the bearers are not level.  As for the concrete, the concrete slab has some “minor flexing and shinkage cracks in areas an d there are no construction joints, key joints or saw cut articulation joints cut in the slab anywhere” .  Bobcats used by the builder have damaged the front left hand corner of the slab. The area was not repaired, it was simply cut out .  Appears to be “minim al positive fall anywhere on the slab to the perimeter of the slab”. Water falling on the left - hand side of the garage runs underneath into the garage and wets items there; water falling on the rear right hand corner tracks underneath the laundry and colle cts there;  Movement of the vinyl floor tiles in the kitchen lounge area appears to be a “direct consequence of the foundation movement caused by flood inundation” .  As the slab has been laid on highly reactive soil and is without expansion/articulation joints, EF considers it is likely to crack. EF says it is standard practice to incorporate articulation joints to minimise the effect of highly reactive clay soils and EF recommends that an opinion is obtained from a structural engineer regarding the movem ent of the concrete slab and any opinions on what needs addressing .  EF also said the slab appears to have a minimal to no positive fall to the edge and any water falling on the slab next to the laundry or garage follows the level of the slab and flows in u nderneath wall frames and into Case No: 390501 Determination Page 12 of 16 the laundry and garage. If water ponded it would create a slip hazard and will rot out the bottom plates of the walls over time .  EF said the only option to rectify the problem of rotting out, would be to remove the walls, top the slab, reinstate the wall frames and refit the garage, laundry area but this would only solve ponding issues here and not throughout the remainder of the slab .  Monolithic slab may have to be topped or removed and replaced to ensure water does not pond in the garage and laundry and in general areas to minimise further moisture damage and slip hazards (however structural engineer‟s opinion required on the movement control aspects of the slab) .  Applicant is prepared to cut the opposite edge of the slab, so that it will match the damaged part caused by the bobcat. This would be an acceptable solution. Builder (RG) response to Building Consultant (EF) Undated  Photographs provided.  Plasterer went through house and patched all cracks and RG considers that crac king/movement has occurred due to foundation settlement .  Painter attended property 19/10/13 but Applicant not present. Some additional work was done but painter considers the doors at the property were “old and bowed due to maintenance” related issues .  Til es were from the same batch – one has chipped and can be replaced .  Spa bath is as it was as it was never taken out .  Pressure testing was done on the shower by a plumber and no leaks were present .  Downlights were not touched by RG .  No work was done in the k itchen and the problems here were pre - existing .  Noggins for the battens need to be at tended to and will be done by T.  Adjusted structural piers were put under the home only. This was in accordance with the engineer‟s plans. There are veranda bearers under the staircase which are not part of the structural floor plan .  There had only been a temporary downpipe present when work was done as the existing one had rusted off. The damage was not event related and the fact that downpipe is not being replaced by the Applicant explains why water is getting into the garage .  Concrete slab is a structural slab “designed to engineers specifications”. It cannot have construction Case No: 390501 Determination Page 13 of 16 joints. Photographs of the slab shows slab to be flat.  Bobcat operator is prepared to attend to the concrete damage .  Nails missing from the battens were not part of any work done by RG and were therefore pre - existing. Consulting civil and structural engineer’s report (WJ) 1 July 2014  Inspected new slab 16 April 2014 .  From levels supplied by others, believe the fall on the slab to the centre of the garage to be approximately 9mm resulting in water ponding in the centre of the slab and bottom plates to laundry walls rotting; not sure if ever possible for owner to drive utility under the house .  Slab eit her being poured with incorrect levels or insufficient compaction to the fill beneath the slab .  All slabs that are open to the weather should be poured with a slope to the external edges so when water blows in it runs back to the outside of the slab .  Conce rned that the fill has not been compacted to recommended standards as no certification has been issued .  If compaction not done to a sufficient level this would allow the slab to settle .  Recommended 3 solutions to rectify the problems .  Do not agree it is necessary or practical to remove the slab and relay it as one of the remedies suggested will stop water ponding on the slab. Consulting civil and structural engineer’s report (WJ) 21 July 2014  Engineer told by owner that fill material used beneath the new slab was crusher dust and not the road base material specified by WJ .  Crusher dust not able to compact to satisfactory degree and not waterproof which allows water to infiltrate under the slab causing highly reactive soil to move .  With the use of crusher dust as the fill material, it is quite possible that this fill is responsible for any subsidence in the new slab. FSP’s consulting engineer’s report (RC) 20 October 2014  Report prepared at request of assessor GH regarding the Applicants‟ concerns about gr ound preparation, structural performance of the slab, claim that water enters the subfloor space and does not drain out adequately, and that the bedding materials are unsuitable .  The Applicant‟s home is an “elevated timber framed structure supported on a s eries of steel posts which are connected to the new floating raft slab ”. Case No: 390501 Determination Page 14 of 16  Carport, laundry and storeroom constructed on slab .  RC understands that the original building was supported on isolated steel posts, with the floor slabs added later .  Following floodi ng of the site, various different slab sections became misaligned and replacement was necessary .  RC refers to the drawings, structural details, limited scope of works an d specifications prepared by WJ.  In order to prepare the report, RC measured, undertook a level survey, assessed building movements, interviewed the owners and undertook visual assessments .  RC noted he was told by the owners that the original slab beneath the building comprised the section beneath the carport and other sections were added at various later dates to enlarge the extent of the original concrete; and that prior to the flooding, water did not pond beneath the building.  RC also noted the owners‟ assertions regarding preparation and materials used beneath this slab .  RC also noted WJ‟ s structural details and said there is no reference in the engineer‟s report which indicates that a soil test was undertaken and says it appears that the design of the new slab was prepared on the basis that it provided a substantial increase to the streng th a nd stiffness previously present.  RC also said it is reasonable to accept that the site is comprised of “highly or extremely highly reactive clay soils” capable of differential ground movement due to the changes in soil moisture conditions .  RC refers to a “photographic record” which shows the slabs which were removed were lightly reinforced with an approximate thickness of 100mm, not adequately dowelled and well below what would have been required to provide any reliable resistance to soil moisture induc ed movements.  Whereas, RC notes the new slab system represented a substantial improvement providing a reasonable degree of soil moisture related movement control. Whilst difficult to measure, RC estimated it was around 20 times stronger and stiffer .  A flo or level survey revealed that the slab is “within 26mm” of being level which represents good soil moisture related movement control .  Noting that drainage falls are factored into this, the deviation levels are more realistically less than 15mm. Case No: 390501 Determination Page 15 of 16 Both measure ments are comfortably within the appropriate building standards .  The slab def lection measurement is adequate.  The span - to - deflection ratio is less than one in 700. This again is comfortably within appropriate standards .  RC says the claim that the soil should been excavated and the site proof rolled is incorrect as there has been no movement to indicate any adverse effect and it is not normal practice to excavate and place roadbase material under buildings and not necessar y to comply with the construction requirements of the relevant Australian standards .  RC notes the ground surface beneath the house does not appear to have changed significantly from the time prior to construction and it was not necessary to import fill ma terials; the design specification relates to standard generic specification which does not necessarily apply to site specific situations; and is not required to follow normally accepted engineering practices .  The use of crusher dust under house slabs is a “common and acceptable building practice”. There was no evidence of any adverse effects with this practice .  The level survey indicates that the slab system drains marginally and there was no evidence the slab had heaved or that it retained water. The subfl oor space is “generally open” and some water will enter these spaces .  In summary, the slab system installed is a “substantial improvement” on the previous slabs and there was no evidence of unacceptable or excessive movement. Floor level survey attached t o RC’s report 15 October 2014  Floor surveyed 3 October 2014 .  Shows highest point in middle of slab proximate to laundry and storage area at 26mm sloping variously to 20, 16, or 14, and 10mm . FSP’s assessor opinion (GH) 14 May 2015  GH attended the site with male Applicant to try to resolve issues but Applicant remained adamant the concrete slab has not been built co rrectly and should be replaced.  Chief concern is the use of “crusher dust” which Applicant says should not have been used and was not properly compacted .  GH confirmed with engineer RC the concrete slab is within current building code tolerances and that the Case No: 390501 Determination Page 16 of 16 use of crusher dust is an acceptable practice.  EF are building consultants and not as well qualified as RC. RC is a professional eng ineer who deals with 700 – 800 concrete slabs per year. EF made some incorrect comments regarding the construction of the slab not being to standard such as no articulated joins in slab causing cracks .  GH prefers the view of RC who considers the slab to be within c urrent building code tolerances.  GH acknowledges water runs across the concrete slab but says that as it was poured in one piece it is far superior to the original slab as water cannot escape between the joins causing ground movemen t beneath.  GH s ays the original slab had several cracks running across it wi th which water could track down.  As the house is two story, with the bottom carport level open, it will always be subject to wind driven rain as it was before the new slab was built .  Whilst the A pplicant says the veranda at the top of the stairs was affected by the flood event (with the timber rotting due to movement), GH says the timber floor has deteriorated with age over time with exposure to the elements, and not from movement.  GH also provide d extracts from the report from EF with RG‟s comments annotated on it. Applicants’ Photographs  Show slab and water ingress in laundry and under the house .

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.