Home / Financial Firm (Unknown - Insurer) / Determination 390501
Determination 390501
Quality of replacement concrete slab after flood claim
Summary
The applicants disputed the quality of a replacement concrete slab installed after a flood claim and sought its replacement. AFCA found the FSP is not obliged to provide further slab cover but ordered it to scope and cash settle the other workmanship complaints.
The insured must prove on the balance of probabilities that poor workmanship caused the claimed damage, and the expert evidence did not establish that.
Issues
- Repairs or contractors primary · not upheld“The material does not establish on the balance of probabilities that the claimed damage is caused by the installation of the replacement slab or its levels.”
- Poor claim handling secondary · not upheld“Not satisfied on the material provided that the complaints about claims management are made out, though the reports should have been provided to the Service.”
Subjects and remedies
home or building damagenatural disasterpay claim
Related
All Financial Firm (Unknown - Insurer) determinations · Find similar determinations
Text of the determination
Determination
Case No: 390501 Determination Page 1 of 16
Case number: 390501 16 September 2015
1 Overview
1.1 Dispute
The Applicants lodged a claim on their home building insurance policy with the
Financial Services Provider (FSP). The claim related to stormwater/flood damage
on their property from 2 February 2012.
The FSP considered and ultimately accepted the claim. In part, this involved a
consideration of whether the concrete slab at the home had been damaged. Once
accepted, the FSP agreed to replace the slab.
It is the Applicants‟ view that the replacement slab is of inferior quality and that it
needs to be replaced. They contend it has caused movement in the home and
further damage. The FSP disagrees and the parties seek a decision on the issue.
The Case Manager provided the parties with a Recommendation on the issues in
dispute. The Recommendation was in favour of the FSP.
The FSP accepted the Recommendation but it was not accepted by the
Applicants. In the circumstances, the dispute has been referred to me for
Determination.
1.2 Issues and key findings
Has the claim been appropriately settled?
Although the replacement slab may not have been installed in accordance with
the engineer‟s specifications, the material provided does not establish on the
balance of probabilities that the claimed damage is caused by the installation of
the replacement slab or by the levels of the slab. Rather, the available evidence
establishes the replacement slab was installed in accordance with normally
accepted building practices and that the levels are adequate.
1.3 Determination
This Determination is in favour of the FSP.
It is not obliged to provide any further cover to the Applicants in relation to the
concrete slab.
Insufficient material is provided in relation to other workmanship complaints such
as painting plastering etc. and if it has not already done so, the FSP is to attend
the property, prepare a scope of works and cash settle the Applicants for these
other complaints.
Case No: 390501 Determination Page 2 of 16
2 Reasons for Decision
I have decided this case on its merits, having regard to the relevant law, good
industry practice, codes of practice and previous FOS decisions. I have taken into
account all the material submitted by the parties, both before and after the
Recommendation. I am satisfied that the documentation I have relied on has been
provided to both parties.
Applicants provided new material after the Recommendation
After the Recommendation was rejected, the Applicants made further
submissions and provided new material. Where relevant, the submissions and
material are referred to in this Determination and are set out in Section 3 in
Supporting Information.
The FSP has not provided any new information or responded to the Applicants‟
new material and submissions.
2.1 Has the claim been appropriately settled?
Applicants’ home damaged by floodwater
In February 2012, the Applicants‟ home was flooded, as a result of which the
home and concrete slab were damaged.
The FSP‟s assessor (TJ) inspected the home 13 February 2012. He
recommended a structural engineer be appointed to prepare a scope of works to
rectify the concrete slab.
WJ provided scope of works to rectify slab
The engineer WJ was engaged by the FSP to inspect the home. WJ inspected the
property once and then on the second occasion on 12 June 2012. Neither party
has provided a report from WJ about the first inspection. WJ wrote a report after
the second inspection. He recommended:
the slab and path under the house is to be removed and replaced with a new
slab are shown on the slab plan dated 14 June 2012
a 800mm reinforced raft slab is to be used
the slab is to be poured on to a minimum of 150mm clean road base filling
and waterproof membrane of minimum thickness 0.2mm
after removal of the topsoil, the slab area is to be proof rolled and any
defective areas are to be excavated and replaced with suitable road base
material and compacted
slabs are to be monolithic slabs with stainless steel mesh protection
various Australian Standards were cited
concrete specifications included very specific information including:
“all filling below slabs is to be contacted in layers not exceeding 150mm
thickness, to 97% SSD at approximately 2% below optimum moisture content, ..”
Case No: 390501 Determination Page 3 of 16
and
“… recommend that the non -reactive filling material, be ridge gravel, or road base
gravel rather than pure river gravel or pure coarse sand, so that water cannot
penetrate the compacted fill material, at a later date.”
The two drawings dated 14 June 2012 that accompanied the letter described the
typical raft slab sections and included the annotation that there be:
“150mm consolidated roadbased filling”.
From the material provided, there appears to be no material change provided in
the letter from WJ dated 10 September 2012.
Insufficient proof that failure to comply with scope of works caused damage
It is not clear from the information provided when the work was carried out, but at
some time after completion, a site inspection took place with the Applicants, the
assessor, the builder (RG) and the concrete contractor (T).
The assessor not ed a number of the Applicants‟ complaints with the repair work
including that the floor tiles in the lounge have opened up since installation of the
slab. The assessor‟s notes indicate the Applicants claimed this occurred because
the contractor used crusher dust under the new slab which did not compact
sufficiently and allowed water to affect the subsoil.
The assessor was of the view that the cause of damage was typical ground
movement from the highly reactive soil found in the area. Nonetheless, the
assessor arranged for an engineer to inspect the slab.
The FSP‟s policy provides a lifetime guarantee. This means that when an insured
home is repaired or rebuilt by one of the FSP‟s repairers or builders, the FSP will
guarantee the workmanship of repairs that were authorised by it for the lifetime of
the home and will fix any defect caused by poor workmanship.
The Applicants claim a number of problems because of poor workmanship. The
Applicants claim the slab should be replaced as it was damaged and will cause
further movement damage to the home. They assert the slab was not constructed
according to the engineer‟s design, the water runs in the wrong direction resulting
in pooling in the garage, storage and laundry rooms, the slab is not the
appropriate thickness and the slab is smooth causing slipping injuries.
The Applicants have the onus to establish on the balance of probabilities the poor
workmanship of the FSP‟s contractors have caused the claimed damage.
Aside from its assessors‟ opinion about the cause of damage, the FSP provided
material from a building consultant (EF) and a consulting engineer (RC).
EF supports the Applicants after his inspection of the property for the FSP on 18
December 2013. EF reported he considers the movement of the vinyl floor tiles in
the kitchen lounge area appears to be a direct consequences of foundation
movement caused by flooding inundation. EF said that as the slab had been laid
on highly reactive soil, without expansion joints, it was likely to crack. EF does not
appear to have a copy of the material from WJ who designed the slab in that
Case No: 390501 Determination Page 4 of 16
manner. Therefore, EF suggested a structural engineer‟s opinion was required on
the movement control aspects of the slab.
A new assessor (GH) had taken over conduct of the matter for the FSP and
engaged a consulting engineer RC who provided a report on 20 October 2014.
RC referred to drawings, structural details, scope of works and specifications
prepared by WJ. RC appears to have looked at photographs of the old slabs and
considers the new slab system represented a substantial improvement. Having
performed various tests which are described in the report in detail, he concludes
that there is no evidence to suggest unacceptable movement and he says the
slab is within the appropriate building standards.
RC also said it is not normal practice to excavate and place roadbase material
under buildings and not necessary to do this to comply with the relevant
Australian Standards. He concludes that the use of “crusher dust” under house
slabs is a common and acceptable building practice.
Further, he says the level survey indicates that the slab system drains marginally
and that there was no evidence in the level survey to suggest the slab had
heaved at the outside so as to retain water. The level survey attached to his
report shows the floor slab is within 26mm of being level which RC says is well
within the allowance considered reasonable in Australian Standards.
GH was asked by the FSP to comment and in a recent email said he preferred the
view of RC to EF as RC was a professional engineer experienced with concrete
slabs.
After the Recommendation, the Applicants provided two reports from WJ who re-
inspected the slab on 16 April 2014. WJ addressed these two reports to the FSP
dated 1 and 21 July 2014. It is not clear from the material provided why this
information had not been provided by the FSP to its experts or to the Service in
consideration of this dispute. It is particularly concerning in view of the
submissions made by the Applicants that pertinent material was not provided.
In any event, WJ reinspected the site in April 2014. WJ does not appear to have
measured levels, but refers to “levels supplied by others”. He notes the fall on the
slab to the centre of the garage to be approximately 9mm. It is assumed this
information was obtained from the FSP‟s assessor, TJ.
When TJ inspected the site with the builder and the concrete contractor, he noted
the concrete was checked with a laser measure. He noted the highest point was
in the carport which was 9mm higher sloping to edge of slab which he said would
assist in water draining away.
WJ concluded that the slab had either been poured with incorrect levels or
insufficient compaction to the fill beneath the slab. WJ had concerns about the fill
as no certification was issued (and if it was, he had not seen it). The parties have
not provided any certification. The Applicants mention in their submissions they
have requested approvals from the FSP but they were not provided.
However, when advised by the Applicants that the fill material used beneath the
new slab was crusher dust and not the roadbase material specified by WJ, WJ
Case No: 390501 Determination Page 5 of 16
said it was quite possible (my emphasis) that the fill could be responsible for any
subsidence in the new slab.
WJ said:
“Crusher dus t has the disadvantage of not being able to be compacted to a
satisfactory degree and is not waterproof, it allows water to infiltrate through under
the slab, which can cause the highly reactive soil to move”
WJ contrasted this to compacted roadbase (which he had specified as fill) which
he says creates a waterproof barrier which is extremely important when the soil is
extremely reactive (like the soil on the site).
WJ concluded that if compaction had not been done to a sufficient level, this
would allow the slab to settle. WJ comments about the old concrete footing and its
effect on settlement of the slab but there is insufficient information provided by
either party to comment on this speculation about the cause of subsidence.
Finally, although WJ makes some suggestions in his report of 1 July 2014 about
how to rectify the problem, the three remedies appear to only address the issue of
water ponding on the slab and not the fundamental complaint of subsidence in the
new slab.
The Applicants have not provided any expert material because of financial
constraints. I have considered carefully all the expert material provided. I am not
satisfied that the Applicants have established on the balance of probabilities that
the poor workmanship of the FSP‟s contractors caused the damage claimed by
movement. Although EF is supportive of the Applicants, his opinion is
misconceived as the slab was designed as a monolithic slab.
Although I accept the FSP‟s contractors did not construct the concrete slab in
accordance with t he specifications of WJ, WJ‟s opinion is insufficiently persuasive
about the consequence of the use of crusher dust as fill material. He says it is
“quite possible” that the fill could be responsible for subsidence in the new slab
but the standard of proof required is that it is “probable” not merely “quite
possible”.
This ambivalence by WJ coupled with the comprehensive report from RC results
in the material provided (when considered in totality) being insufficiently
supportive of the Applicants‟ claims.
Despite the Applicants‟ criticism of RC, the report demonstrates he has
undertaken the requisite work to support his opinion that the workmanship was
completed in accordance with normally accepted building practices.
Material establishes levels adequate and not the cause of claimed damage
As for the issue of water pooling under the house, both TJ and RC took
measurements or undertook level surveys and concluded that water would fall to
the edge of the slab which would assist in water draining away.
I have carefully considered the floor level survey dated 3 October 2014 and am
satisfied the slab system drains to the edges of the slab.
Case No: 390501 Determination Page 6 of 16
EF says there appears to be minimal positive fall anywhere on the slab to the
perimeter of the slab, but he did not take meas urements or undertake a level
survey.
WJ did not take levels either. He says he relies on levels supplied by others. But
WJ seems to be under the misapprehension that the fall on the slab is to the
centre of the slab whereas the level survey arranged by RC and the laser survey
conducted by TJ show the fall is to the edge of the slab. TJ‟s notes says:
“The concrete was checked with a laser measure and found the highest point was
in the carport which was 9mm higher sloping to edge of slab which would assist in
water draining away.”
I have considered the photographs provided and accept there is evidence of
water pooling but I also note the area is open to the elements.
Having considered all the material provided, I am not persuaded on the balance of
probabilities that poor workmanship caused the water pooling issue.
Other complaints about the slab not established
The Applicants complain the slab in many places is not to the thickness required,
but no independent expert evidence establishes this contention.
The Applicants also complain the concrete is smooth rather than “a rough broom
finish” but there is no documentation to support this contention either.
Finally, the Applicants complain that the house is now 40mm lower than
previously and they cannot put a car into the carport. The only comment made
about this complaint was by WJ who said that he was:
“unsure if this was ever possible.”
Insufficient material to comment on other complaints
The Applicants made a number of other complaints about the FSP‟s
workmanship. They say no one has come to the house since to see what work
needs completing but rather the concrete issue was to be dealt with first and then
the other complaints would be addressed.
The Lifetime Guarantee under the policy means that the FSP will fix any defect
caused by poor workmanship. In the alternative, the FSP can cash settle the
Applicants for these other complaints.
The FSP says that as the Applicants did not want the builder back, the FSP
offered a cash settlement for the remainder of the r epairs. TJ‟s inspection report
indicates the Applicants were cash settled for the painting and that once the
engineer‟s report was received the builder would attend for minor rectifications.
As well as TJ, both EF and RG have commented on these other complaints.
In submissions, the Applicants said the FSP wanted to pay out approximately
$3,500. However, insufficient information is provided by the parties about these
other complaints and about a cash settlement to form part of this Determination.
Case No: 390501 Determination Page 7 of 16
If it has not already done so, the FSP is to attend the property, prepare a scope of
works and cash settle the Applicants for these other complaints. The Service
encourages the parties to this dispute to resolve any issues that might arise
during that process. However, the parties can return to the Service if they are
unable to resolve any issues arriving from the scope of works for the other
complaints and/or the costing of that work.
WJ’s reports should have been provided to the Service
Finally the Applicants also make a number of complaints about the conduct of the
FSP in the management of his claim. They complain that they did not receive the
levels from RC but they are attached to RC‟s report. They also complain that the
FSP did not provide all reports. However, although they were not provided to the
Service, they were provided to the Applicants who were able to produce them
after the Recommendation. I agree the reports were material and should have
been provided to the Service by the FSP. However, I am not otherwise satisfied
on the material provided that the complaints about claims management are made
out.
Case No: 390501 Determination Page 8 of 16
3 Supporting information
3.1 FOS approach to this dispute
It is an accepted principle of general insurance law that an insured bears the onus
to establish on the balance of probabilities that they have suffered a loss caused
by an event to which the policy responds. This is known as a prima facie claim.
Once so established, the onus shifts to the insurer to prove on the balance of
probabilities that an exclusion applies if it seeks to deny or limit its liability for the
loss.
3.2 Extract from policy
Lifetime guarantee
We provide a „lifetime guarantee‟ when your home is repaired or rebuilt by one of
our preferred repairers or builders.
This means:
1. we guarantee the workmanship of repairs that we authorised for the lifetime of
your home
2. we will fix any defect caused by poor workmanship.
We will decide on what needs to be done to fix any defect.
When you’re not covered by this guarantee
This guarantee does not apply to:
3. repairs you authorised yourself
4. loss, damage or failure of any electrical or mechanical appliance or machine
5. wear and tear that is consistent with normal gradual deterioration of your
home .
3.3 Relevant expert reports
Record Key points
FSP’s claim lodgement
details
2/2/12 storm event causing flooding and cracking .
12/11/13 file notation that all works are now
completed .
Builder’s report (RG)
13 February 2012
FSP‟s assessor TJ engaged repairer RG who
attended site 13/2/12 .
Flood water t ravelled through the bottom level of the
home up to about 600mm .
Downstairs area consists of garage, laundry and
storage area. Walls are fibro and can be repainted .
Split system air conditioner damaged by water and
requires replacement .
House has suffered from structural movement as a
result of the water ingress. Upstairs level of home is
now cracking .
Concrete slabs are cracking as well. Recommends
Case No: 390501 Determination Page 9 of 16
appointment of structural engineer to advise of scope
to rectify slabs.
Consulting civil and
structural engi neer’s
report (WJ)
14 June 2012
Second inspection carried out 12 June 2012 .
Scope of works to repair flood damage and particulars
included for the laying of the new ground floor
concrete slab noting after removal of the topsoil, the
slab area is to be pro of rolled, detailed concrete
specification provided .
After ground floor slab poured, levelling work for first
floor and upstairs internal cosmetics works detailed .
2 drawings provided of proposed new slab 14/6/12 .
Consulting engineer’s
second report (WJ)
10 September 2012
Appears to be an incomplete (page 2 and 4 only) but
duplicate of earlier report as it refers to 2 nd inspection
carried out 12 June 2012 and recommendations in
relation to the removal and replacement of the ground
floor slab and describes same issues with:
Main hallway has cracking in the gyprock
(recommends repair and repainting of this area) .
Main bedroom has cracking in the ceiling and the
cornices at wall corners. Wardrobe door sticking and
needs to be checked after the floor is levelle d. Cracks
require repair and room is to be repainted .
Bedroom 3 has cracking in the cornices and there is
carpet damage where water from the bathroom has
been leaking .
Tiles have cracked in the bathroom and the shower.
There is a broken step in the bathroo m which has
allowed water to leak into bedroom 3 .
Concrete specification also listed .
One page of drawing re proposed new slab dated
10/9/12 .
Assessor’s report (TJ)
Undated
Photographs and site inspection by TJ, RG and
concrete contractor T .
Notes Applicant was unhappy with several aspects of
the repair work and not happy with the conduct/work
of the FSP‟s nominated builder, RG. Complaints
noted:
After the concrete slab was poured, contractor
damaged the corner of the slab in front of the stairs .
T imber framing to wall sheets needs replacing .
Timber architrave had come away from the back door
and this was caused by movement of the slab .
Air conditioner is discharging water directly onto the
new slab and this water pools on the slab .
Builder to seal penetrations in wall sheets and bottom
Case No: 390501 Determination Page 10 of 16
plates .
Downpipe on the left hand side of the home (above
the veranda) has not been connected to the
stormwater waste .
Vinyl floor tiles in the lounge have opened up since
the installation of the slab and the tiles ha d been in
place for six years. Applicant claims the slab is
allowing water to seep under it and push up the
flooring because contractor used crusher dust which
did not compact sufficiently and allowed water to
affect subsoil .
Crack is evident in the ceilin g cornice .
Every time it rains, water pools on the slab under the
house and this never happened with the prior slab
and water entering laundry and storage room from
wind driven rain .
TJ writes builders have a picture of downstairs slab
prior to removal with water pooling on the concrete;
previous slab poured at different times with joins
which would have allowed wind driven rain to run
across and down the joins between the slabs .
TJ notes new concrete slab poured as one slab;
existing house footings are original and not replaced.
Water marks on concrete slab into laundry indicate
water has entered storage room via bottom plates
which have not been sealed sufficiently and builder
needs to seal bottom plates to stop wind driven rain .
Concrete was checked wi th a laser measure and
found the highest point was in the carport which was
9mm higher sloping to edge of slab which would
assist in water draining away .
Complaints re paint job and to be cash settled .
TJ said vinyl tiles complaint and cracks due to typical
ground movement from highly reactive soil commonly
found in the area (insured claimed no movement
cracks prior to repairs) .
TJ arranging another engineer to inspect slab (house
sits on adjustable fixings so they can be adjusted
easily to allow for future movement) .
Concludes cannot finalize but engineer to inspect
property and confirm cause of house moving and
once report received, RG to attend for minor
rectifications.
Building Consultant’s
report (EF)
January 2014
Builder reported to TJ after an inspection 18/12/13 to
ascertain if the repairs conducted were of a
“tradesmanlike standard” and to identify areas for
Case No: 390501 Determination Page 11 of 16
rectification if necessary .
Describes the insured property as a raised single
story dwelling on steel piers with garage, laundry and
stor age room underneath with the entire open area
underneath the dwelling concreted .
EF notes some of the internal painting work was ill
prepared and sub - standard .
Notes claim that cracked joints repaired in ceilings
and walls have given way .
Some of the tilin g was sub - standard, with chipped,
mismatched and poorly installed tiles .
Numerous additional repair - related issues were
present .
Outside, the bottom batten which supports the bottom
edge of the wall sheets around the perimeter of the
building has been cut off to allow for the building to be
re - piered and re - levelled. This area does not appear
to have been adequately re - supported .
So me of the bearers are not level.
As for the concrete, the concrete slab has some
“minor flexing and shinkage cracks in areas an d there
are no construction joints, key joints or saw cut
articulation joints cut in the slab anywhere” .
Bobcats used by the builder have damaged the front
left hand corner of the slab. The area was not
repaired, it was simply cut out .
Appears to be “minim al positive fall anywhere on the
slab to the perimeter of the slab”. Water falling on the
left - hand side of the garage runs underneath into the
garage and wets items there; water falling on the rear
right hand corner tracks underneath the laundry and
colle cts there;
Movement of the vinyl floor tiles in the kitchen lounge
area appears to be a “direct consequence of the
foundation movement caused by flood inundation” .
As the slab has been laid on highly reactive soil and is
without expansion/articulation joints, EF considers it is
likely to crack. EF says it is standard practice to
incorporate articulation joints to minimise the effect of
highly reactive clay soils and EF recommends that an
opinion is obtained from a structural engineer
regarding the movem ent of the concrete slab and any
opinions on what needs addressing .
EF also said the slab appears to have a minimal to no
positive fall to the edge and any water falling on the
slab next to the laundry or garage follows the level of
the slab and flows in u nderneath wall frames and into
Case No: 390501 Determination Page 12 of 16
the laundry and garage. If water ponded it would
create a slip hazard and will rot out the bottom plates
of the walls over time .
EF said the only option to rectify the problem of rotting
out, would be to remove the walls, top the slab,
reinstate the wall frames and refit the garage, laundry
area but this would only solve ponding issues here
and not throughout the remainder of the slab .
Monolithic slab may have to be topped or removed
and replaced to ensure water does not pond in the
garage and laundry and in general areas to minimise
further moisture damage and slip hazards (however
structural engineer‟s opinion required on the
movement control aspects of the slab) .
Applicant is prepared to cut the opposite edge of the
slab, so that it will match the damaged part caused by
the bobcat. This would be an acceptable solution.
Builder (RG) response
to Building Consultant
(EF)
Undated
Photographs provided.
Plasterer went through house and patched all cracks
and RG considers that crac king/movement has
occurred due to foundation settlement .
Painter attended property 19/10/13 but Applicant not
present. Some additional work was done but painter
considers the doors at the property were “old and
bowed due to maintenance” related issues .
Til es were from the same batch – one has chipped
and can be replaced .
Spa bath is as it was as it was never taken out .
Pressure testing was done on the shower by a
plumber and no leaks were present .
Downlights were not touched by RG .
No work was done in the k itchen and the problems
here were pre - existing .
Noggins for the battens need to be at tended to and
will be done by T.
Adjusted structural piers were put under the home
only. This was in accordance with the engineer‟s
plans. There are veranda bearers under the staircase
which are not part of the structural floor plan .
There had only been a temporary downpipe present
when work was done as the existing one had rusted
off. The damage was not event related and the fact
that downpipe is not being replaced by the Applicant
explains why water is getting into the garage .
Concrete slab is a structural slab “designed to
engineers specifications”. It cannot have construction
Case No: 390501 Determination Page 13 of 16
joints. Photographs of the slab shows slab to be flat.
Bobcat operator is prepared to attend to the concrete
damage .
Nails missing from the battens were not part of any
work done by RG and were therefore pre - existing.
Consulting civil and
structural engineer’s
report (WJ)
1 July 2014
Inspected new slab 16 April 2014 .
From levels supplied by others, believe the fall on the
slab to the centre of the garage to be approximately
9mm resulting in water ponding in the centre of the
slab and bottom plates to laundry walls rotting; not
sure if ever possible for owner to drive utility under the
house .
Slab eit her being poured with incorrect levels or
insufficient compaction to the fill beneath the slab .
All slabs that are open to the weather should be
poured with a slope to the external edges so when
water blows in it runs back to the outside of the slab .
Conce rned that the fill has not been compacted to
recommended standards as no certification has been
issued .
If compaction not done to a sufficient level this would
allow the slab to settle .
Recommended 3 solutions to rectify the problems .
Do not agree it is necessary or practical to remove the
slab and relay it as one of the remedies suggested
will stop water ponding on the slab.
Consulting civil and
structural engineer’s
report (WJ)
21 July 2014
Engineer told by owner that fill material used beneath
the new slab was crusher dust and not the road base
material specified by WJ .
Crusher dust not able to compact to satisfactory
degree and not waterproof which allows water to
infiltrate under the slab causing highly reactive soil to
move .
With the use of crusher dust as the fill material, it is
quite possible that this fill is responsible for any
subsidence in the new slab.
FSP’s consulting
engineer’s report (RC)
20 October 2014
Report prepared at request of assessor GH regarding
the Applicants‟ concerns about gr ound preparation,
structural performance of the slab, claim that water
enters the subfloor space and does not drain out
adequately, and that the bedding materials are
unsuitable .
The Applicant‟s home is an “elevated timber framed
structure supported on a s eries of steel posts which
are connected to the new floating raft slab ”.
Case No: 390501 Determination Page 14 of 16
Carport, laundry and storeroom constructed on slab .
RC understands that the original building was
supported on isolated steel posts, with the floor slabs
added later .
Following floodi ng of the site, various different slab
sections became misaligned and replacement was
necessary .
RC refers to the drawings, structural details, limited
scope of works an d specifications prepared by WJ.
In order to prepare the report, RC measured,
undertook a level survey, assessed building
movements, interviewed the owners and undertook
visual assessments .
RC noted he was told by the owners that the original
slab beneath the building comprised the section
beneath the carport and other sections were added at
various later dates to enlarge the extent of the original
concrete; and that prior to the flooding, water did not
pond beneath the building.
RC also noted the owners‟ assertions regarding
preparation and materials used beneath this slab .
RC also noted WJ‟ s structural details and said there is
no reference in the engineer‟s report which indicates
that a soil test was undertaken and says it appears
that the design of the new slab was prepared on the
basis that it provided a substantial increase to the
streng th a nd stiffness previously present.
RC also said it is reasonable to accept that the site is
comprised of “highly or extremely highly reactive clay
soils” capable of differential ground movement due to
the changes in soil moisture conditions .
RC refers to a “photographic record” which shows the
slabs which were removed were lightly reinforced with
an approximate thickness of 100mm, not adequately
dowelled and well below what would have been
required to provide any reliable resistance to soil
moisture induc ed movements.
Whereas, RC notes the new slab system represented
a substantial improvement providing a reasonable
degree of soil moisture related movement control.
Whilst difficult to measure, RC estimated it was
around 20 times stronger and stiffer .
A flo or level survey revealed that the slab is “within
26mm” of being level which represents good soil
moisture related movement control .
Noting that drainage falls are factored into this, the
deviation levels are more realistically less than 15mm.
Case No: 390501 Determination Page 15 of 16
Both measure ments are comfortably within the
appropriate building standards .
The slab def lection measurement is adequate.
The span - to - deflection ratio is less than one in 700.
This again is comfortably within appropriate
standards .
RC says the claim that the soil should been
excavated and the site proof rolled is incorrect as
there has been no movement to indicate any adverse
effect and it is not normal practice to excavate and
place roadbase material under buildings and not
necessar y to comply with the construction
requirements of the relevant Australian standards .
RC notes the ground surface beneath the house does
not appear to have changed significantly from the
time prior to construction and it was not necessary to
import fill ma terials; the design specification relates to
standard generic specification which does not
necessarily apply to site specific situations; and is not
required to follow normally accepted engineering
practices .
The use of crusher dust under house slabs is a
“common and acceptable building practice”. There
was no evidence of any adverse effects with this
practice .
The level survey indicates that the slab system drains
marginally and there was no evidence the slab had
heaved or that it retained water. The subfl oor space is
“generally open” and some water will enter these
spaces .
In summary, the slab system installed is a “substantial
improvement” on the previous slabs and there was no
evidence of unacceptable or excessive movement.
Floor level survey
attached t o RC’s report
15 October 2014
Floor surveyed 3 October 2014 .
Shows highest point in middle of slab proximate to
laundry and storage area at 26mm sloping variously
to 20, 16, or 14, and 10mm .
FSP’s assessor
opinion (GH)
14 May 2015
GH attended the site with male Applicant to try to
resolve issues but Applicant remained adamant the
concrete slab has not been built co rrectly and should
be replaced.
Chief concern is the use of “crusher dust” which
Applicant says should not have been used and was
not properly compacted .
GH confirmed with engineer RC the concrete slab is
within current building code tolerances and that the
Case No: 390501 Determination Page 16 of 16
use of crusher dust is an acceptable practice.
EF are building consultants and not as well qualified
as RC. RC is a professional eng ineer who deals with
700 – 800 concrete slabs per year. EF made some
incorrect comments regarding the construction of the
slab not being to standard such as no articulated joins
in slab causing cracks .
GH prefers the view of RC who considers the slab to
be within c urrent building code tolerances.
GH acknowledges water runs across the concrete
slab but says that as it was poured in one piece it is
far superior to the original slab as water cannot
escape between the joins causing ground movemen t
beneath.
GH s ays the original slab had several cracks running
across it wi th which water could track down.
As the house is two story, with the bottom carport
level open, it will always be subject to wind driven rain
as it was before the new slab was built .
Whilst the A pplicant says the veranda at the top of the
stairs was affected by the flood event (with the timber
rotting due to movement), GH says the timber floor
has deteriorated with age over time with exposure to
the elements, and not from movement.
GH also provide d extracts from the report from EF
with RG‟s comments annotated on it.
Applicants’
Photographs
Show slab and water ingress in laundry and under the
house .
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.