Determination 389582

Delay in approving subdivision plan after FSP lost original documents

FirmFinancial Firm (Unknown - Credit)
Decided2016-04-22
ProductCredit · Home loan
OutcomeFor the complainant in part
Amount awarded$165
Non-financial loss$1,000
Amount claimed—
SourceAFCA PDF

Summary

The applicant's representative lodged original subdivision plans with the FSP in July 2014, which the FSP lost, and approval took until December 2014. AFCA found unreasonable delay and ordered an interest refund of $8,614.76, a $165 fee refund and $1,000 non-financial loss compensation, but refused interest accruing after December 2014.

Industry practice allowed four to five weeks for approval, the FSP's loss of documents and later inaction caused the delay, and the applicant failed to mitigate by not registering the subdivision after December 2014.

Issues

Subjects and remedies

third party authoritydebt waiver or reductionpay interestpay non financial lossrefund fees or charges

Related

All Financial Firm (Unknown - Credit) determinations · Find similar determinations

Text of the determination

Determination Case No: 389582 Determination Page 1 of 10 Case number: 389582 23 March 2016 1 Overview 1.1 Dispute The Applicant has the following loan and credit facilities with the Financial Services Provider (FSP): Account Loan Amount Security Outstanding balance (as at 5 June 2015) Home loan 1 $112,000 B property $125,816.92 Home loan 2 $440,000 B property $459,910.63 Personal loan $80,000 Unsecured $108,847.87 Credit card $16,000 Unsecured $17,861.86 The B property (Property) consists of two adjoining townhouses. However, there is only one title for the Property. The Applicant previously lodged dispute 338098 with the Financial Ombudsman Service (FOS) which was resolved during a conciliation conference. The terms of the resolution agreement (Agreement) relevantly provided that:  the Applicant had until 31 December 2014 to provide the FSP with an unconditional contract of sale for the Property,  the sale proceeds would be used to repay the Applicant’s outstanding debt to the FSP, and  if the Applicant failed to provide the FSP with an unconditional contract of sale by 31 December 2014, he would surrender the Property to the FSP by 31 January 2015. The Applicant commenced the process of subdividing the Property and, in July 2014, provided the FSP with the relevant original Plan of Subdivision documents for its approval. The FSP provided its formal consent to the Plan of Subdivision in December 2014. The dispute concerns whether the FSP:  delayed its approval of the subdivision plans submitted by the Applicant, and  caused the Applicant loss for which he should be compensated. Case No: 389582 Determination Page 2 of 10 1.2 Issues and key findings Did the FSP delay its approval of the subdivision plans submitted by the Applicant? The available information establishes that the FSP unreasonably delayed approving the Applicant’s Plan of Subdivision with regard to the Property. Is the Applicant entitled to any compensation? The Applicant is entitled to the following compensation:  $8,614.76 representing interest charged to Loan 1 and Loan 2 for the period 1 September to 16 December 2014 (being comprised of the following components; $1,876.69 to Loan 1 and $6,738.07 to Loan 2),  $165 to reimburse him for additional fees incurred as a result of commissioning a second set of original subdivision documents, and  $1,000 as compensation for his non-financial loss. 1.3 Determination This Determination is in favour of the Applicant. I understand that the Applicant is currently unable to make any repa yments to the Loans. The only viable option for the debt to be repaid is for the Property to be sold. If the Applicant accepts this Determination within 30 days of its date, within a further 14 days of that acceptance, the FSP must:  reduce Loan 1 by $2,459.19 and  reduce Loan 2 by $7,320.57 – (to take into account the interest charged these loan accounts for the period 1 September to 16 December 2014 ($1,876.69 to Loan 1 and $6,738.07 to Loan 2) and the fee refund ($165) and non-financial loss compensation ($1,000) due to the Applicant under this Determination (with that $1,165 sum to be split evenly when credited to the two loans)). The Applicant remains liable to pay the FSP the outstanding balances owing on each of the two loans. Within 30 days of the date of this Determination, the Applicant must provide a statement of his current financial position and a repayment proposal to the FSP and work with the FSP to agree upon a mutually acceptable repayment arrangement for the amounts outstanding. If the parties are unable to work out a repayment arrangement in relation to the arrears under both loans within 14 days of the date that the Applicant provides repayment proposal to the FSP, the FSP is entitled to continue with the enforcement action in relation to the loans. Case No: 389582 Determination Page 3 of 10 2 Reasons for Determination 2.1 Did the FSP delay its approval of the subdivision plans submitted by the Applicant? The FSP lost the original Plan of Subdivision submitted in July 2014 A complete timeline of events is set out in section 3.2 of this Determination. The information shows that the Applicant submitted the original Plan of Subdivision to an FSP branch on 28 July 2014. This is supported by the fact that the original Plan of Subdivision was “ receipted ” by an FSP staff member. On 25 August 2014, the Applicant’s representative followed up the status of the FSP’s approval. In response, on 27 August 2014, the FSP confirmed it had had no record of receiving original documentation, nor did it have any system notes to support that the documents had been referred to the relevant FSP department for approval. This is despite the notation appearing on the copy Plan of Subdivision documents provided by the Applicant to FOS. In response to the FSP’s loss of the documents, the Applicant obta ined a further original Plan of Subdivision. On 12 September 2014, there was an email exchange between the Applicant’s representative and an FSP staff member, Mr L, in which the representative confirmed that he was in the possession of the second set of p lans and was seeking to fast track the process by meeting Mr L in branch. It appears that the second set of original Plan of Subdivision documents were submitted to the same FSP branch on 19 September 2014. It therefore took the Applicant from 27 August 2014 until 19 September 2014 (i.e. three weeks) to submit the second set of documents to the FSP. The FSP’s approval of the subdivision should have taken four to five weeks The FSP’s policy on “Consents Affecting Security” does not stipulate a timeframe fo r the time taken to approve a plan of subdivision. FOS has sought advice from our Banking Specialist (the specialist) about acceptable timeframes relevant to an FSP’s approval of a plan of subdivision (from an industry practice perspective). The specialist has extensive industry experience in the banking and financial services industry, and regularly provides advice about what constitutes good industry practice. The specialist is of the opinion that an acceptable timeframe can vary between four to five weeks given the nature and extent of the plan of subdivision. In applying this timeframe to the length of time taken by the FSP, it is readily apparent that the FSP unreasonably delayed in providing its approval due to the loss of the original documentation and further instances of FSP inaction which ultimately delayed its approval of the Plan of Subdivision until December 2014. Case No: 389582 Determination Page 4 of 10 The FSP’s Legal Department endorsed the Plan of Subdivision in October 2014 On 3 October 2014, the FSP’s internal lega l department received a request seeking approval of the Plan of Subdivision with respect to the Property. On 13 October 2014, the FSP’s legal department advised Mr L that the FSP’s security position was not compromised by the subdivision of the Property and endorsed the Plans with its consent stamp. The FSP ordered the Property valuation one month after its legal department approved the subdivision On 13 November 2014, the FSP commissioned a property valuation for the Property. This was one month after t he FSP’s legal department had advised that it had no objection to the planned subdivision of the Property. There is no information which explains why it took the FSP one month to seek a valuation. Shortly before commissioning the Property valuation, the FSP received certain property particulars from the Applicant’s representative (on 12 November 2014). However, the FSP ought to have obtained this information from the Applicant earlier because:  the FSP’s legal department approved the subdivision on 13 Octob er 2014  on 3 November 2014, the Applicant’s representative sent an email to Mr L, confirming the address of the firm of surveyors to which the FSP was to send the endorsed documentation,  the FSP responded on 11 November 2014 (over a week later) advising that it had not yet ordered the property valuations for the Property but made a request that the Applicant’s representative complete property particulars relating to the Property, and  the Applicant’s representative responded one day later (on 12 November 201 4) with the requested information. Ultimately, the one month between the FSP’s legal department confirming that the subdivision would not impact its security position and ordering the Property Valuation is unreasonable and contributed to the FSP’s ultimat e delay in approving the subdivision. The Applicant’s response to the FSP’s requests were timely The FSP says that on 25 August 2014, the Applicant was advised that the FSP could not locate the original Plan of Subdivision documents. It then says it took the Applicant another month before a second set of original plans was submitted by the Applicant in branch. The available information shows that between 25 to 27 August 2014, the Applicant’s representative and Mr L were corresponding with each other to ascertain whether the original Plans submitted in July 2014 had, in fact, been lost. This is not unreasonable in the circumstances given the additional time and expense that would be incurred if a further original set of documentation was required. The FSP confirmed this to the Applicant’s representative on 27 August 2014 which resulted in the Applicant commissioning a further set of original plans from the firm of surveyors it had previously engaged. Case No: 389582 Determination Page 5 of 10 The surveyor firm sent the second set of Plans to the Applicant under cover letter dated 11 September 2014. This is further supported by an email from the Applicant’s representative to Mr L on 12 September 2014 in which he stated that he was in possession of the new set of Plans and seeking to arrange a date at the relevant branch (ie. 16 September 2014) in order to meet and fast track the process of the FSP’s approval. The second set of original Plan of Subdivision documents was eventually delivered to the relevant FSP branch on 19 September 2014. Given that the Applicant had to approach the surveyor firm and for a second set of Plans, it is reasonable that it took the Applicant one month to resubmit the second set of documents to the FSP. This entailed (amongst other things) the surveyor firm requesting and compiling original property, plan and title documentation (at a cost) and then resubmitting the original Plan of Subdivision to Council for its endorsement. Once the original Plan was endorsed it was then sent to the surveyor firm who forwarded it on to the Applicant for the purpose of providing it to the FSP. It is not apparent that the Applicant caused any delay in securing a second set of original Plans. The Applicant also responded to the FSP’s 11 November 2014 request for information in a timely manner. I n this instance, The Applicant’s representative responded one day later (on 12 November 2014) with the requested information. The available information shows that the Applicant’s response to any requests from the FSP was timely and that he did not cause any delay. The FSP’s delay can be attributed to a period greater than two months The FSP has conceded that the approval process “took longer than expected” but limits its concession to a two month period. The available information does not support the FSP’s position given that the original Plan of Subdivision was submitted to its branch on 28 July 2014 with ultimate approval conveyed to the Applicant’s representative on 8 December 2014 (i.e. almost four and a half months later). Further, the original endorsed Plan of Subdivision documentation was posted to the surveyor firm and receipted by them on 16 December 2014. As noted above, the specialist considers an acceptable timeframe can vary between four to five weeks for an FSP to provide its consent and appro val for a Plan of Subdivision. Therefore, had the FSP not lost the original documents the Applicant provided on 28 July 2014, it is likely that it would have approved the sub-division five weeks later on 1 September 2014. The FSP did not notify the Applicant that it had approved the plan of subdivision until 16 December 2014, three and a half months later. Although the FSP accepted responsibility for a level of delay attributed to two months, it is apparent that the FSP delayed the provision of its approval for a period of three and a half months. Case No: 389582 Determination Page 6 of 10 2.2 Is the Applicant entitled to any compensation? The Applicant is entitled to an interest refund The Applicant seeks compensation as a result of the FSP’s conduct in delaying its approval of the Plan of Subdivision and says that he has incurred additional interest on the loans and has missed out on three potential purchasers of the town houses. The Applicant has provided three emails from real estate agents confirming that there were interested parties in the properties. Had the FSP approved the sub-division in a timely manner, it is arguable that the Applicant would have sold the Property and repaid his outstanding debts to the FSP entirely. However, given the FSP’s delay, additional interest has accrued against the loans. In the circumstances, it is appropriate that interest for Loan 1 and Loan 2 for the period of the delay to be refunded. In the circumstances, the FSP should refund the interest that accrued to Loan 1 and Loan 2 for the period 1 September 2014 (being the date that the approval ought to have been provided) until 16 December 2014. This amount is $8,614.76 and should be refunded as follows:  $1,876.69 to Loan 1, and  $6,738.07 to Loan 2 with - the balances of both loans recalculated accordingly. The Applicant has failed to mitigate his loss Although the FSP did unreasonably delay providing its approval for the sub -division, since 16 December 2014, the Applicant has not taken steps to complete the process by registering the final sub-division with the relevant state based land title authority. Indeed, as of the date of this Determination, the plans of sub-division have still not been registered. When assessing loss, FOS will have regard to an applicant’s duty to minimise (or mitigate) any loss they may suffer as a result of a financial services provider’s error. An Applicant who incurs loss as a result of a breach of an obligation or duty b y a financial services provider has a duty to take reasonable steps to minimise that loss. As a result, an Applicant cannot claim compensation for any loss they could have reasonably avoided. Given that the Applicant has still not taken steps to finalise the plan of sub-division, he has failed to take adequate steps to minimise his loss. In doing so, the Applicant has broken the chain of causation from the FSP’s error. It is therefore not appropriate for the FSP to pay any further compensation (such as interest) that has accrued against Loan 1 and Loan 2 since December 2014 as these amounts have been accrued as a result of the Applicant’s action and not the FSP’s. The Applicant paid for a further original Plan of Subdivision As a result of the FSP losing the initial original Plan of Subdivision documents lodged with its branch on 28 July 2014, the Applicant had to recommission a second set of original Plans through the firm of surveyors he had previously engaged for the first Case No: 389582 Determination Page 7 of 10 set of original plans. As a result, new original documentation had to be requested and resubmitted to the local Council for its certification. The Applicant was charged an additional $165 for which he is entitled to be reimbursed. The Applicant is entitled to compensation for non-financial loss FOS has the ability to award compensation for non-financial loss. Non-financial loss claims include claims for undue stress or inconvenience caused by an error of the financial services provider. The maximum amount that can be awarded by FOS in non-financial loss compensation is $3,000 (for each claim in extreme circumstances). Most awards of non-financial loss compensation are in the hundreds rather than the thousands of dollars. I am satisfied that the Applicant suffered undue stress and inconvenience as a result of the FSP;  misplacing the original Plan of Subdivision submitted to the branch in July 2014 and  forcing the Applicant to provide a second original Plan of Subdivision which he ultimately did in September 2014. Taking into account this conduct and FSP’s delays and failure s, it is appropriate in the circumstances that the FSP compensate the Applicant for his non-financial loss by reducing his indebtedness by $1,000. Case No: 389582 Determination Page 8 of 10 3 Supporting information 3.1 How we assess disputes Assessment of disputes FOS is not a court of law. This means that FOS is not able to take evidence on oath. When presented with differing accounts of what occurred in a scenario, FOS will decide what is most likely to have occurred on the balance of probabilities, taking into account available contemporaneous documentation. If we find that the available information is not conclusive, we may find that a claim cannot be established. 3.2 Timeline of events Timeline of events from April 2014 to February 2015 The following timeline of events has been compiled from information and supporting documentation from the Applicant and FSP: Date Action 11 April 2014  Previous FOS dispute (338098) res olved by way of signed resolution agreement. The agreement provided the Applicant with (amongst o ther things) nine months to sell the security property (the subject of a subdivision and this dispute). 17 July 2014  The relevant municipal council endorses the Applicant’s Plan of Subdivision. 20 July 2014  The Applicant signs a sale agreement with a Real Estate agent to sell the properties. 28 July 2014  The Plan of Subdivision is submitted to an FSP branc h by the Applicant in person. An FSP bank officer (being an Assistant Manager) certifies the Strata Plan as a true copy of the original as sighted b y him with a furt her notation of “original received at branch # XX72. 25 August 2014 (at 2.55pm)  The Applicant’s representative emailed the FSP (Mr L) inquiring about the status of the FSP’s approval of the Plan of Subdivision. 25 August 2014 (at 4.41pm )  Mr L emails the Applicant’s representative with his contact details. 27 August 2014 (at 9.55am)  Mr L emails the Applicant’s representative advising that he received an email from the relevant FSP branch Case No: 389582 Determination Page 9 of 10 (XX72) with a copy of the Strata Plan. Mr L sought clarification whether an original or copy were provided in branch. 27 August 2014 (at 11.18am)  The Applicant’s representative confirms that the original documents were provided to the FSP branch on 28 July 2014. The represent ative also seeks confirmation whether the original documentation has been lost and, if so, to advis e as such so that the original surveyor can be contacted and a request made to provide a further original Plan of Subdivision at a cost of $165. 27 August 2014 (at 11.30am)  FSP staff me mber Mr L confirms that the original documentation was not receipted or system noted as being received by branch XX72. There are no system notes that support the original documentation being referred to him. 11 September 2014  Letter from firm engaged by A pplicant to draft Plan of Subdivision provides a further Original Strata Plan and two copies. 12 September 2014  Email from the Applicant’s representative to Mr L advising that another original Plan of Subdivision is in his possession and would like to att end the branch XX72 on 16 September 2014 to complete the issue. He queries whet her Mr L is available to complete the proc ess in branch on 16 September 2014. 12 September 2014  Email from Mr L to the Applicant’s representative advises he is unable to attend the relevant branch as it is in Queensland and he himself is based in Sydney. 19 September 2014  A further original plan and subdivision document is submitted to branch XX72 and acknowledged by the FSP. 1 October 2014  The FSP submits an internal request to its legal department seeking approval of the Plan of Subdivision with respect to the Property. 3 October 2014  Internal legal request is receipted by the Legal Department. 13 October 2014  FSP’s legal department’s internal memorandum states that it has reviewed the Plan of Subdivision, confirming no adverse impact as a result of the creation of Lots 1 and 2. Accordingly, it endorsed the Strata Plan with the FSP’s “Consent Stamp”. 3 November 2014  Email from Applicant’s representative to Mr L confirmin g the address of the firm of surveyors to which the FSP is to send the relevant documentation. 16 December 2014  The surveyor firm appointed to subdivide the Applicant’s property receives the FSP’s formal endors ement of the Case No: 389582 Determination Page 10 of 10 plan of subdivision. 16 December 2014  The Applicant’s representative emails the FSP seeking an additional nine months to sell the properties given the FSP’s delay in consenting to the subdivision and the inactive property market between December 2014 to February 2015. 5 February 2015  Applicant lodges new FOS dispute 389582. 6 February 2015  FSP issues a Notice of Default to the Applicant