Text of the determination
Determination
Case No: 389582 Determination Page 1 of 10
Case number: 389582 23 March 2016
1 Overview
1.1 Dispute
The Applicant has the following loan and credit facilities with the Financial Services
Provider (FSP):
Account Loan Amount Security Outstanding balance (as
at 5 June 2015)
Home loan 1 $112,000 B property $125,816.92
Home loan 2 $440,000 B property $459,910.63
Personal loan $80,000 Unsecured $108,847.87
Credit card $16,000 Unsecured $17,861.86
The B property (Property) consists of two adjoining townhouses. However, there is
only one title for the Property.
The Applicant previously lodged dispute 338098 with the Financial Ombudsman
Service (FOS) which was resolved during a conciliation conference. The terms of the
resolution agreement (Agreement) relevantly provided that:
the Applicant had until 31 December 2014 to provide the FSP with an
unconditional contract of sale for the Property,
the sale proceeds would be used to repay the Applicant’s outstanding debt to
the FSP, and
if the Applicant failed to provide the FSP with an unconditional contract of sale
by 31 December 2014, he would surrender the Property to the FSP by 31
January 2015.
The Applicant commenced the process of subdividing the Property and, in July 2014,
provided the FSP with the relevant original Plan of Subdivision documents for its
approval. The FSP provided its formal consent to the Plan of Subdivision in
December 2014.
The dispute concerns whether the FSP:
delayed its approval of the subdivision plans submitted by the Applicant, and
caused the Applicant loss for which he should be compensated.
Case No: 389582 Determination Page 2 of 10
1.2 Issues and key findings
Did the FSP delay its approval of the subdivision plans submitted by the
Applicant?
The available information establishes that the FSP unreasonably delayed approving
the Applicant’s Plan of Subdivision with regard to the Property.
Is the Applicant entitled to any compensation?
The Applicant is entitled to the following compensation:
$8,614.76 representing interest charged to Loan 1 and Loan 2 for the period 1
September to 16 December 2014 (being comprised of the following
components; $1,876.69 to Loan 1 and $6,738.07 to Loan 2),
$165 to reimburse him for additional fees incurred as a result of commissioning
a second set of original subdivision documents, and
$1,000 as compensation for his non-financial loss.
1.3 Determination
This Determination is in favour of the Applicant.
I understand that the Applicant is currently unable to make any repa yments to the
Loans. The only viable option for the debt to be repaid is for the Property to be sold.
If the Applicant accepts this Determination within 30 days of its date, within a further
14 days of that acceptance, the FSP must:
reduce Loan 1 by $2,459.19 and
reduce Loan 2 by $7,320.57 –
(to take into account the interest charged these loan accounts for the period 1
September to 16 December 2014 ($1,876.69 to Loan 1 and $6,738.07 to Loan 2) and
the fee refund ($165) and non-financial loss compensation ($1,000) due to the
Applicant under this Determination (with that $1,165 sum to be split evenly when
credited to the two loans)).
The Applicant remains liable to pay the FSP the outstanding balances owing on each
of the two loans. Within 30 days of the date of this Determination, the Applicant must
provide a statement of his current financial position and a repayment proposal to the
FSP and work with the FSP to agree upon a mutually acceptable repayment
arrangement for the amounts outstanding.
If the parties are unable to work out a repayment arrangement in relation to the
arrears under both loans within 14 days of the date that the Applicant provides
repayment proposal to the FSP, the FSP is entitled to continue with the enforcement
action in relation to the loans.
Case No: 389582 Determination Page 3 of 10
2 Reasons for Determination
2.1 Did the FSP delay its approval of the subdivision plans submitted by
the Applicant?
The FSP lost the original Plan of Subdivision submitted in July 2014
A complete timeline of events is set out in section 3.2 of this Determination.
The information shows that the Applicant submitted the original Plan of Subdivision to
an FSP branch on 28 July 2014. This is supported by the fact that the original Plan of
Subdivision was “ receipted ” by an FSP staff member.
On 25 August 2014, the Applicant’s representative followed up the status of the
FSP’s approval. In response, on 27 August 2014, the FSP confirmed it had had no
record of receiving original documentation, nor did it have any system notes to
support that the documents had been referred to the relevant FSP department for
approval. This is despite the notation appearing on the copy Plan of Subdivision
documents provided by the Applicant to FOS.
In response to the FSP’s loss of the documents, the Applicant obta ined a further
original Plan of Subdivision. On 12 September 2014, there was an email exchange
between the Applicant’s representative and an FSP staff member, Mr L, in which the
representative confirmed that he was in the possession of the second set of p lans
and was seeking to fast track the process by meeting Mr L in branch. It appears that
the second set of original Plan of Subdivision documents were submitted to the same
FSP branch on 19 September 2014.
It therefore took the Applicant from 27 August 2014 until 19 September 2014 (i.e.
three weeks) to submit the second set of documents to the FSP.
The FSP’s approval of the subdivision should have taken four to five weeks
The FSP’s policy on “Consents Affecting Security” does not stipulate a timeframe fo r
the time taken to approve a plan of subdivision. FOS has sought advice from our
Banking Specialist (the specialist) about acceptable timeframes relevant to an FSP’s
approval of a plan of subdivision (from an industry practice perspective). The
specialist has extensive industry experience in the banking and financial services
industry, and regularly provides advice about what constitutes good industry practice.
The specialist is of the opinion that an acceptable timeframe can vary between four
to five weeks given the nature and extent of the plan of subdivision. In applying this
timeframe to the length of time taken by the FSP, it is readily apparent that the FSP
unreasonably delayed in providing its approval due to the loss of the original
documentation and further instances of FSP inaction which ultimately delayed its
approval of the Plan of Subdivision until December 2014.
Case No: 389582 Determination Page 4 of 10
The FSP’s Legal Department endorsed the Plan of Subdivision in October 2014
On 3 October 2014, the FSP’s internal lega l department received a request seeking
approval of the Plan of Subdivision with respect to the Property. On 13 October 2014,
the FSP’s legal department advised Mr L that the FSP’s security position was not
compromised by the subdivision of the Property and endorsed the Plans with its
consent stamp.
The FSP ordered the Property valuation one month after its legal department
approved the subdivision
On 13 November 2014, the FSP commissioned a property valuation for the Property.
This was one month after t he FSP’s legal department had advised that it had no
objection to the planned subdivision of the Property. There is no information which
explains why it took the FSP one month to seek a valuation.
Shortly before commissioning the Property valuation, the FSP received certain
property particulars from the Applicant’s representative (on 12 November 2014).
However, the FSP ought to have obtained this information from the Applicant earlier
because:
the FSP’s legal department approved the subdivision on 13 Octob er 2014
on 3 November 2014, the Applicant’s representative sent an email to Mr L,
confirming the address of the firm of surveyors to which the FSP was to send
the endorsed documentation,
the FSP responded on 11 November 2014 (over a week later) advising that it
had not yet ordered the property valuations for the Property but made a request
that the Applicant’s representative complete property particulars relating to the
Property, and
the Applicant’s representative responded one day later (on 12 November 201 4)
with the requested information.
Ultimately, the one month between the FSP’s legal department confirming that the
subdivision would not impact its security position and ordering the Property Valuation
is unreasonable and contributed to the FSP’s ultimat e delay in approving the
subdivision.
The Applicant’s response to the FSP’s requests were timely
The FSP says that on 25 August 2014, the Applicant was advised that the FSP could
not locate the original Plan of Subdivision documents. It then says it took the
Applicant another month before a second set of original plans was submitted by the
Applicant in branch.
The available information shows that between 25 to 27 August 2014, the Applicant’s
representative and Mr L were corresponding with each other to ascertain whether the
original Plans submitted in July 2014 had, in fact, been lost. This is not unreasonable
in the circumstances given the additional time and expense that would be incurred if
a further original set of documentation was required. The FSP confirmed this to the
Applicant’s representative on 27 August 2014 which resulted in the Applicant
commissioning a further set of original plans from the firm of surveyors it had
previously engaged.
Case No: 389582 Determination Page 5 of 10
The surveyor firm sent the second set of Plans to the Applicant under cover letter
dated 11 September 2014. This is further supported by an email from the Applicant’s
representative to Mr L on 12 September 2014 in which he stated that he was in
possession of the new set of Plans and seeking to arrange a date at the relevant
branch (ie. 16 September 2014) in order to meet and fast track the process of the
FSP’s approval. The second set of original Plan of Subdivision documents was
eventually delivered to the relevant FSP branch on 19 September 2014.
Given that the Applicant had to approach the surveyor firm and for a second set of
Plans, it is reasonable that it took the Applicant one month to resubmit the second set
of documents to the FSP. This entailed (amongst other things) the surveyor firm
requesting and compiling original property, plan and title documentation (at a cost)
and then resubmitting the original Plan of Subdivision to Council for its endorsement.
Once the original Plan was endorsed it was then sent to the surveyor firm who
forwarded it on to the Applicant for the purpose of providing it to the FSP. It is not
apparent that the Applicant caused any delay in securing a second set of original
Plans.
The Applicant also responded to the FSP’s 11 November 2014 request for
information in a timely manner. I n this instance, The Applicant’s representative
responded one day later (on 12 November 2014) with the requested information.
The available information shows that the Applicant’s response to any requests from
the FSP was timely and that he did not cause any delay.
The FSP’s delay can be attributed to a period greater than two months
The FSP has conceded that the approval process “took longer than expected” but
limits its concession to a two month period. The available information does not
support the FSP’s position given that the original Plan of Subdivision was submitted
to its branch on 28 July 2014 with ultimate approval conveyed to the Applicant’s
representative on 8 December 2014 (i.e. almost four and a half months later).
Further, the original endorsed Plan of Subdivision documentation was posted to the
surveyor firm and receipted by them on 16 December 2014.
As noted above, the specialist considers an acceptable timeframe can vary between
four to five weeks for an FSP to provide its consent and appro val for a Plan of
Subdivision. Therefore, had the FSP not lost the original documents the Applicant
provided on 28 July 2014, it is likely that it would have approved the sub-division five
weeks later on 1 September 2014. The FSP did not notify the Applicant that it had
approved the plan of subdivision until 16 December 2014, three and a half months
later.
Although the FSP accepted responsibility for a level of delay attributed to two
months, it is apparent that the FSP delayed the provision of its approval for a period
of three and a half months.
Case No: 389582 Determination Page 6 of 10
2.2 Is the Applicant entitled to any compensation?
The Applicant is entitled to an interest refund
The Applicant seeks compensation as a result of the FSP’s conduct in delaying its
approval of the Plan of Subdivision and says that he has incurred additional interest
on the loans and has missed out on three potential purchasers of the town houses.
The Applicant has provided three emails from real estate agents confirming that there
were interested parties in the properties.
Had the FSP approved the sub-division in a timely manner, it is arguable that the
Applicant would have sold the Property and repaid his outstanding debts to the FSP
entirely. However, given the FSP’s delay, additional interest has accrued against the
loans. In the circumstances, it is appropriate that interest for Loan 1 and Loan 2 for
the period of the delay to be refunded.
In the circumstances, the FSP should refund the interest that accrued to Loan 1 and
Loan 2 for the period 1 September 2014 (being the date that the approval ought to
have been provided) until 16 December 2014. This amount is $8,614.76 and should
be refunded as follows:
$1,876.69 to Loan 1, and
$6,738.07 to Loan 2 with -
the balances of both loans recalculated accordingly.
The Applicant has failed to mitigate his loss
Although the FSP did unreasonably delay providing its approval for the sub -division,
since 16 December 2014, the Applicant has not taken steps to complete the process
by registering the final sub-division with the relevant state based land title authority.
Indeed, as of the date of this Determination, the plans of sub-division have still not
been registered.
When assessing loss, FOS will have regard to an applicant’s duty to minimise (or
mitigate) any loss they may suffer as a result of a financial services provider’s error.
An Applicant who incurs loss as a result of a breach of an obligation or duty b y a
financial services provider has a duty to take reasonable steps to minimise that
loss. As a result, an Applicant cannot claim compensation for any loss they could
have reasonably avoided.
Given that the Applicant has still not taken steps to finalise the plan of sub-division,
he has failed to take adequate steps to minimise his loss. In doing so, the Applicant
has broken the chain of causation from the FSP’s error. It is therefore not appropriate
for the FSP to pay any further compensation (such as interest) that has accrued
against Loan 1 and Loan 2 since December 2014 as these amounts have been
accrued as a result of the Applicant’s action and not the FSP’s.
The Applicant paid for a further original Plan of Subdivision
As a result of the FSP losing the initial original Plan of Subdivision documents lodged
with its branch on 28 July 2014, the Applicant had to recommission a second set of
original Plans through the firm of surveyors he had previously engaged for the first
Case No: 389582 Determination Page 7 of 10
set of original plans. As a result, new original documentation had to be requested and
resubmitted to the local Council for its certification. The Applicant was charged an
additional $165 for which he is entitled to be reimbursed.
The Applicant is entitled to compensation for non-financial loss
FOS has the ability to award compensation for non-financial loss. Non-financial loss
claims include claims for undue stress or inconvenience caused by an error of the
financial services provider. The maximum amount that can be awarded by FOS in
non-financial loss compensation is $3,000 (for each claim in extreme circumstances).
Most awards of non-financial loss compensation are in the hundreds rather than the
thousands of dollars.
I am satisfied that the Applicant suffered undue stress and inconvenience as a result
of the FSP;
misplacing the original Plan of Subdivision submitted to the branch in July 2014
and
forcing the Applicant to provide a second original Plan of Subdivision which he
ultimately did in September 2014.
Taking into account this conduct and FSP’s delays and failure s, it is appropriate in
the circumstances that the FSP compensate the Applicant for his non-financial loss
by reducing his indebtedness by $1,000.
Case No: 389582 Determination Page 8 of 10
3 Supporting information
3.1 How we assess disputes
Assessment of disputes
FOS is not a court of law. This means that FOS is not able to take evidence on oath.
When presented with differing accounts of what occurred in a scenario, FOS will
decide what is most likely to have occurred on the balance of probabilities, taking into
account available contemporaneous documentation.
If we find that the available information is not conclusive, we may find that a claim
cannot be established.
3.2 Timeline of events
Timeline of events from April 2014 to February 2015
The following timeline of events has been compiled from information and supporting
documentation from the Applicant and FSP:
Date Action
11 April 2014 Previous FOS dispute (338098) res olved by way of signed
resolution agreement. The agreement provided the
Applicant with (amongst o ther things) nine months to sell
the security property (the subject of a subdivision and this
dispute).
17 July 2014 The relevant municipal council endorses the Applicant’s
Plan of Subdivision.
20 July 2014 The Applicant signs a sale agreement with a Real Estate
agent to sell the properties.
28 July 2014 The Plan of Subdivision is submitted to an FSP branc h by
the Applicant in person. An FSP bank officer (being an
Assistant Manager) certifies the Strata Plan as a true copy
of the original as sighted b y him with a furt her notation of
“original received at branch # XX72.
25 August 2014 (at 2.55pm) The Applicant’s representative emailed the FSP (Mr L)
inquiring about the status of the FSP’s approval of the
Plan of Subdivision.
25 August 2014 (at 4.41pm ) Mr L emails the Applicant’s representative with his contact
details.
27 August 2014 (at 9.55am) Mr L emails the Applicant’s representative advising that
he received an email from the relevant FSP branch
Case No: 389582 Determination Page 9 of 10
(XX72) with a copy of the Strata Plan. Mr L sought
clarification whether an original or copy were provided in
branch.
27 August 2014 (at 11.18am) The Applicant’s representative confirms that the original
documents were provided to the FSP branch on 28 July
2014. The represent ative also seeks confirmation whether
the original documentation has been lost and, if so, to
advis e as such so that the original surveyor can be
contacted and a request made to provide a further original
Plan of Subdivision at a cost of $165.
27 August 2014 (at 11.30am) FSP staff me mber Mr L confirms that the original
documentation was not receipted or system noted as
being received by branch XX72. There are no system
notes that support the original documentation being
referred to him.
11 September 2014 Letter from firm engaged by A pplicant to draft Plan of
Subdivision provides a further Original Strata Plan and
two copies.
12 September 2014 Email from the Applicant’s representative to Mr L advising
that another original Plan of Subdivision is in his
possession and would like to att end the branch XX72 on
16 September 2014 to complete the issue. He queries
whet her Mr L is available to complete the proc ess in
branch on 16 September 2014.
12 September 2014 Email from Mr L to the Applicant’s representative advises
he is unable to attend the relevant branch as it is in
Queensland and he himself is based in Sydney.
19 September 2014 A further original plan and subdivision document is
submitted to branch XX72 and acknowledged by the FSP.
1 October 2014 The FSP submits an internal request to its legal
department seeking approval of the Plan of Subdivision
with respect to the Property.
3 October 2014 Internal legal request is receipted by the Legal
Department.
13 October 2014 FSP’s legal department’s internal memorandum states
that it has reviewed the Plan of Subdivision, confirming no
adverse impact as a result of the creation of Lots 1 and 2.
Accordingly, it endorsed the Strata Plan with the FSP’s
“Consent Stamp”.
3 November 2014 Email from Applicant’s representative to Mr L confirmin g
the address of the firm of surveyors to which the FSP is to
send the relevant documentation.
16 December 2014 The surveyor firm appointed to subdivide the Applicant’s
property receives the FSP’s formal endors ement of the
Case No: 389582 Determination Page 10 of 10
plan of subdivision.
16 December 2014 The Applicant’s representative emails the FSP seeking an
additional nine months to sell the properties given the
FSP’s delay in consenting to the subdivision and the
inactive property market between December 2014 to
February 2015.
5 February 2015 Applicant lodges new FOS dispute 389582.
6 February 2015 FSP issues a Notice of Default to the Applicant