Summary

The applicant repaid a fixed rate home loan early and paid $26,405.07 in economic costs, saying the FSP never disclosed them. AFCA found the costs were adequately disclosed in the loan terms and approval letter, so no compensation was ordered.

Disclosure met the industry standard and loan documentation applying in 2007, and the applicant did not establish misleading silence or reliance.

Issues

Subjects and remedies

no remedy

Related

All Financial Firm (Unknown - Credit) determinations · Find similar determinations

Text of the determination

Determination Credit - Consumer Credit - Home Loans - Disclosure - Misleading product/service information Case number : 389389 2 5 August 2015 1 Overview 1.1 Dispute In March 2007, the Financial Services Provider (FSP) granted the Applicant a n investment home loan for $380,000 (the loan). The loan was secured by a mortgage over a property in NSW (the Property). Interest on the loan was fixed for the first 10 years at the rate of 6.95% per annum. On 2 September 2013, prior to the expiry of the fixed rate period, the Property was sold and the loan repaid. At settlement the Applicant paid the FSP $26,405.07 in economic costs for breaking the fixed rate loan. The Applicant says the FSP did not explain that economic costs would be payable if the loan was repaid before the end of the fixed rate period. 1.2 Issues and key findings Was the FSP entitled to charge the Applicant economic costs? The terms and conditions of the loan agreement which govern the loan are set out in section 3.1 below. Under the terms and conditions, the FSP had the right to charge economic costs where the Applicant chose to repay his fixed rate loan before the end of the fixed rate period. Did the FSP fail to disclose economic costs or mislead the Applicant? The Applicant has not established that the FSP failed to disclose or misled him about economic costs. 1.3 Determination This Determination is in favour of the FSP. The FSP is not required to pay any compensation to the Applicant. Case No: 389389 Determination Page 2 of 8 2 Reasons for Determination 2.1 Was the FSP entitled to charge the Applicant economic costs? The terms and conditions allow the FSP to charge economic costs The loan facility agreement expressly incorporates the FSP’s Facility Agreement General Terms dated October 2006 (General Terms). The terms and conditions with respect to economic costs are set out in section 3.1 below. Clause 14 of the General Terms provides that economic costs are payable if the whole of the loan amount is repaid during the fixed rate term. There is a prominent “Warning” in the General Terms and that appears on page 10, being part of clause 16 under the heading “Economic costs” . The clause notes that economic costs can be high and increases the amount the borrower owes the FSP. Clause 16 also sets out the method of calculation of economic costs. Where the Applicant chose to end his loan before the fixed rate period expired on 19 April 2017, under the terms of the facility agreement, the FSP had the right to charge the Applicant economic costs. 2.2 Did the FSP fail to disclose economic costs or mislead the Applicant? The Applicant claims there was inadequate disclosure of economic costs and he was misled by the FSP ’s silence The Applicant claims there was inadequate disclosure and he was misled by the FSP ’s failure to make him aware of its right to charge economic costs if he repaid his fixed rate loan before the end of the fixed rate period. He says that if the FSP had made him aware of this term, he would not have entered the fixed rate loan and suffered a loss upon early termination. The Applicant says he:  had no previous experience with a fixed rate loan or economic costs  believed a fixed rate loan was the most economically viable loan option available to him at the time  received no written or verbal information about economic costs from the FSP at the time of entering the loan  did receive the loan approval letter dated 28 March 2007  acknowledges that prior to entering the loan the FSP’s staff member point ed out to him: o the amount of the loan o the amount of monthly repayments o the date the repayments would begin once he entered the loan however , the FSP’s staff member failed to provide information about economic costs. Case No: 389389 Determination Page 3 of 8 The FSP must disclose details of economic costs A financial services provider has obligations to exercise the care and skill of a diligent and prudent lender when providing credit. These obligations exist in law, statute and pursuant to the Code of Banking Practice (CBP) for those lenders that are signatories. The CBP applied to this loan and required the FSP to disclose full particulars of credit fees and charges payable under the contract. Good industry practice also requires a lender to disclose economic costs. The FSP ’s disclosure of economic costs met the industry standard The FSP says when it granted the loan in 2007:  its internal processes required a brochure about economic costs to be included in the loan pack for fixed rate loans  its brochure titled “Early repayment of fixed rate loans” and the loan facility agreement explain when economic costs are charged and how they are calculated  it provided the Applicant with its brochure called “ a guide to fees and c harges”  although, the Personal Banker who dealt with the Applicant’s loan has no specific recollection of his meeting with the Applicant, it was his usual practice to provide all customers who requested a fixed rate loan with the FSP’s brochure on economic costs and early repayment and to discuss the potential ramifications of economic costs. While there is no information to show the FSP specifically discussed economic costs with the Applicant before he entered the loan, this does not mean that the FSP did not disclose when its right to charge economic costs would arise. The FSP’s internal process required staff to provide customers entering a fixed rate loan with information regarding economic costs including the brochure on early repayment. Although, the FSP has produced the brochure titled “E arly repayment of fixed rate loans” , there are no documents to establish conclusively that the Applicant was given the brochure or that economic costs were discussed with him at the time he applied for the loan. However, the approval letter dated 28 March 2007 refers to economic costs, notes they are unascertainable and refers the customer to the General Terms and the FSP’s “a guide to fees and charges”. Page 35, clause 6 of the guide notes that “Economic costs may be payable when you prepay the whole of the loan amount which is under a fixed rate… Economic cost is the Bank’s reasonable estimate of its loss (if any) f rom the early termination of a fixed rate loan or a prepayment”. The Applicant has confirmed he received the approval letter dated 28 March 2007. The Applicant also signed the Facility Agreement Details which included an acknowledgement on page 9 that he had read and received the General Terms, which outline how and when economic costs will be charged. If the Applicant was Case No: 389389 Determination Page 4 of 8 unsure of the ramifications of these provisions then he was free to obtain independent legal advice on those matters. At the time the loan was granted in March 2007, the increased disclosure requirements put in place following the introduction of the National Consumer Credit Code in 2011 did not apply. The FSP’s disclosure of how and when economic costs could be charged in the f acility agreement and in the FSP’s guide to fees and charges was in line with the FSP’s obligations and the industry standard which applied in March 2007. Accordingly, I am satisfied the early repayment economic cost was adequately disclosed by the FSP. It is unclear when the Applicant became aware of economic costs The Applicant says that he did not become aware of his obligation to pay economic costs until just before the settlement of the sale of the Property in September 2013. The FSP says in response to the Applicant’s request to pay out his loan, on 28 August 2013, and again on 2 September 2013, it sent a letter to the Applicant and his solicitor advising of the total payout figure at settlement which included an amount for economic costs. The Applicant has provided a copy of a contract of sale for the Property dated 2 August 2013. The document shows the Applicant had committed to sell the Property over 26 days before the letter advising him of the amount of economic cost was issued. The Applicant has not established that the FSP engaged in misleading conduct In order to establish a claim of misleading conduct, the Applicant has to establish that:  he accepted the FSP’s offer of a fixed rate loan where the FSP was silent on its right to charge economic costs in circumstances that amount to misleading conduct; and  he suffered loss as a result. In March 2007, the Applicant applied for and was granted a $380,000 fixed interest rate investment home loan. At the same time the Applicant applied for and was granted an $110,000 variable interest rate home loan. Both loans were secured by the Property. Therefore, the Applicant must have understood there were differences between how interest and fees were structured and charged between the loans. The Applicant chose to invest $380,000 on a fixed rate basis and $110,000 on a variable rate basis. Given my comments above on the disclosure of the economic costs, the FSP was not required to show it verbally discussed the issue with the Applicant. The Applicant does not say that he asked the FSP to explain early repayment in 2007. Such a question would have prompted the FSP to discuss the issue of economic costs. A failure by the FSP to respond to such a query would amount to a misrepresentation by silence. However this did not occur in this instance. Case No: 389389 Determination Page 5 of 8 The Applicant has not established the FSP was silent in circumstances where it was specifically obliged to discuss economic costs upon early repayment. Since the Applicant has not established the FSP’s conduct was misleading , I do not need to consider whether he relied upon it to enter the fixed rate loan. Case No: 389389 Determination Page 6 of 8 3 Supporting information 3.1 Relevant terms and conditions Terms and conditions of the facility agreement dated 28 March 2007 Economic costs payable whenever an economic costs event occurs. However, we will not charge economic costs for any partial early repayment up to and including the first $20, 000 per fixed rate period . See economic costs clause in the General Terms. Unascertainable Facility Agreement General Terms October 2006 (General Terms) Early repayment 14 Fixed interest rate Whenever a loan amount has a fixed interest rate, you may repay early the whole o f the loan amount during the fixed rate period. However, you may have to pay economic costs (see clause 16) and any other applicable fee. Economic costs events 16.1 …. if a loan amount has a fixed interest rate, you must pay economic costs whenever an economic costs event occurs. Where a loan amount has a fixed interest rate an economic costs event is taken to have occurred if, before the end of the fixed rate period: ……… (b) you repay early all or part of the amount of the balance owing on the account for that loan amount before the end of the fixed rate period ……… Case No: 389389 Determination Page 7 of 8 3.2 FOS approach Misleading or deceptive conduct If a person signs a document that they know contains contractual terms and which they understand will affect their legal relationship with a financial services provider, then the person is legally bound by those terms. It is irrelevant whether or not the person read the document before signing it. The only exception to this is if there are extenuating circumstances, for example if the person was misled into signing the document. Misleading conduct may occur where a financial services provider makes a statement which is likely to be misleading or deceptive or where a financial services provider has been silent about a particular matter, in circumstances where that silence was likely to be misleading or deceptive. If we find that the Applicant was misled, we assess how much worse off they are as a result of reasonably relying on the misleading conduct and changed their position to their detriment. When there are opposing views about what occurred in a dispute, FOS will decide what was more likely than not to have occurred based on the available documents, the recollections of the parties, and all relevant circumstances. FOS is not a court and we do not have the power to take or test evidence on oath and we give more weight to contemporaneous documentary information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. Case No: 389389 Determination Page 8 of 8 Break costs FOS accepts that a financial services provider will not know the amount of a future break (economic) cost as the amo unt will depend on the financial services provider’s cost of funds at the time, the time remaining on the contract and the amount of the contract to be repaid. This means that any disclosure obligation will be limited to the details contained in the loan documentation and the answer to any questions raised by the applicant. In 2007 this would not normally have included an obligation on the financial services provider to quote a future break cost or even to provide some type of estimate.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.