Home / Financial Firm (Unknown - Insurer) / Determination 388933
Determination 388933
Denial of garage damage claim under strata policy
Summary
The Applicant claimed under a strata policy for damage to a garage after the FSP denied the claim. AFCA found the loss was caused by excluded ground movement, so the denial was valid and no delay compensation was payable.
Ground movement is specifically excluded under the policy, and loss of rent only applies where the building loss is covered.
Issues
- Claim denial primary · not upheld“The FSP was entitled to deny the claim as the policy excludes coverage for the loss suffered by the Applicant.”
- Delay secondary · not upheld“I am not satisfied that the FSP has unnecessarily or unreasonably delayed the process of this claim.”
Subjects and remedies
home or building damageno remedy
Related
All Financial Firm (Unknown - Insurer) determinations · Find similar determinations
Text of the determination
Determination
General Insurance - Domestic Insurance - Residential Strata Title - FSP Decision - Denial of Claim
Determination
Case No: 388933 Determination Page 1 of 9
Case number : 388933 9 July 2015
1 Overview
1.1 Dispute
The Applicant is a beneficiary of a Strata Insurance Policy underwritten by the
Financial Service Provider (FSP), held in the name of the Owners Corporation (OC)
for the residences at the property.
On 8 April 2014, the Applicant lodged a claim on the policy for damage sustained to
the garage at Unit 1. The FSP declined the claim on the basis that the loss had
arisen from causes specifically excluded from cover.
The Applicant also says that the FSP did not complete their enquiries in a reasonable
timeframe, thus resulting in further loss to the Applicant.
1.2 Issues and key findings
Was the FSP entitled to deny the claim?
The FSP was entitled to deny the claim as the policy excludes coverage for the loss
suffered by the Applicant.
Is the Applicant entitled to compensation for the time taken by the FSP to deny
the claim?
The Applicant is not entitled to compensation for the time taken by the FSP to deny
the claim.
1.3 Determination
This Determination is in favour of the FSP.
The FSP is entitled to deny the Applicant’s claim and is not required to pay the
Applicant compensation for the time taken to deny the claim.
Case No: 388933 Determination Page 2 of 9
2 Reasons for Determination
This Determination has been the subject of a Recommendation issued by the Service
on 22 May 2015.
It was the Case Manager’s Recommendation that the FSP was entitled to deny the
Applicant’s claim on the basis of the policy exclusions contained within the policy
coverage.
In addition, the Case Manager recommended that the Applicant was not entitled to
loss of rent as the coverage for loss of rent only arose in the circumstances where
the loss itself was covered by the terms of the policy, which it was not in this case.
Finally, the Case Manager was of the view that the time taken by the FSP was not
unreasonable and the Applicant was not entitled to compensation in the
circumstances.
The Applicant has disputed the Recommendation and has provided further
submissions in relation to the loss.
I have carefully considered all of the material provided by both parties, before and
after this Recommendation, whilst making this Determination.
2.1 Was the FSP entitled to deny the claim?
The FSP was entitled to deny the claim
It is settled insurance law that the onus rests with the Applicant to show that the loss
claimed is covered by the terms of the policy.
It is only once the Applicant has established the loss was covered by the terms of the
policy that the onus transfers to the FSP to demonstrate the basis on which it
otherwise says it is entitled to deny the claim.
The policy is an accidental damage policy, providing cover for accidental damage
sustained to the Applicant’s buildings.
There is no suggestion that damage was anything other than unexpected and
unforeseen by the Applicant and in the circumstances I accept that the Applicant has
established that the loss is covered by the terms of the policy.
However, the policy must be read as a whole and it includes a number of exclusions
for loss which is not covered under the terms of the policy.
The FSP has provided detailed reports in support of submission that the exclusions
contained within the policy apply to entitle the FSP to deny the Applicant’s claim.
Having considered the reports presented by the FSP, I am satisfied that they are
logical and thorough and their conclusions are compelling.
The Applicant has not presented evidence to challenge the conclusions of those
reports.
Case No: 388933 Determination Page 3 of 9
The Case Manager within the Recommendation has provided an analysis of the
reports provided by the FSP, but save for including the summary of the reports within
part 3 of this Determination, I do not propose to repeat the Case Manager’s analysis
here. Save, that I agree with the Case Manager, that given the reports provided by
the FSP, the likely cause of the loss is ground movement which is specifically
excluded under the terms of the policy.
Given the evidence presented, I am satisfied that the FSP was entitled to deny the
Applicant’s claim for the damage to the building.
I also agree wi th the Case Manager’s conclusion that the FSP was entitled to deny
the Applicant’s claim for loss of rent.
The loss of rent provision detailed within the policy, only has application where the
loss to the buildings themselves are covered under the terms of the policy.
In this case, having made the Determination that the loss to the building is not
covered under the terms of the policy, it follows that the additional benefit for loss of
rent also does not apply.
2.2 Is the Applicant entitled to compensation for the time taken by the
FSP to deny the claim?
The Applicant is not entitled to compensation
The Applicant says that the FSP has not complied with the relevant timeframes when
investigating and determining to deny the claim.
As a result, the Applicant says that he has suffered financial loss because the time
taken by the FSP was unreasonable and as stated, not consistent with the relevant
timeframes.
I have carefully considered the evidence presented by the parties in this regard.
Firstly, I note that the various FSP experts recommended that further investigation be
undertaken to determine the precise cause of the loss.
It is accepted insurance law that the FSP is entitled to take reasonable steps to
establish whether or not the loss claimed is covered by the terms of the relevant
policy.
In this regard, the General Insurance Code of Practice details timeframes relevant to
an insurer’s investigation and acceptance or denial of a claim.
Having considered many similar disputes, I am aware that not all claims are straight
forward and are able to be completed within the timeframes detailed within the Code
of Practice.
I am satisfied that the FSP was entitled to properly investigate the circumstances of
the Applicant’s loss, before making a decision regarding whether to accept the claim
or not.
I have also given consideration to the details provided by the FSP in relation to the
steps they took between claim notification and denial of the claim.
Case No: 388933 Determination Page 4 of 9
Having considered the information provided, I am not satisfied that the FSP has
unnecessarily or unreasonably delayed the process of this claim.
The conclusion is that in the circumstances of the Applicant’s claim and loss, I am not
satisfied that it is appropriate that compensation be paid by the FSP for the time
taken by the FSP to deny the claim.
Case No: 388933 Determination Page 5 of 9
3 Supporting information
3.1 FOS approach for this dispute
A full exchange of the relevant information has taken place between the respective
parties and each party has had the opportunity of addressing any issues raised.
All of the provided material has been reviewed and considered. The parties have
raised numerous issues in their submissions to the Service. For the purpose of this
Recommendation, commentary is restricted to only those issues considered relevant
to the outcome.
3.2 Expert Evidence
Record Key points
FSP’s expert (L)
Engineer’s Report
3 Jun 2014
the inspection was conducted in the presence of the tenant
the owner had noticed movement to the garage and
engaged a plumber who detected damage to the storm
water pipes, and the owner is concerned that leaking storm
water pipes have caused the damage to the garage
the scope of this report is to provide a professional
engineering assessment of the building distress
the examination conducted was visual only
the site consists of three units of single story each,
constructed approximately 20 years ago
the tenant has occupied unit one for the last eight years
a brick garage is attached to the building
the building is a timber frame, brick veneer construction
built on a concrete slab with terracotta roof tiles
the garage has been constructed on perimeter strip
footings and an infill concrete slab, with brick walls with
engaged brick piers and lightweight roof sheeting
the subject site is relatively flat and the perimeter is
unpaved with garden beds adjacent the structure
the perimeter of the garage is unpaved along the north
side
a group of large sized trees were along the south side and
to the northeast corner of the unit, in relatively close
proximity to the structure
th e tenant provided the following information: he became
aware of the separation of the brick garage wall and
door/window frame approximately six years ago
the cracking and separation of the brickwork has gradually
worsened over time
an inlet pipe to the hot water system had been bent out of
place due to movement of the structure and paving
a crack to the party wall between units 1 and 2 was
repaired by the neighbours 2 years ago but has recurred
during moderate and consistent rain events, the driveway
Case No: 388933 Determination Page 6 of 9
outsid e the garage will flood
hairline cracks in the plaster and cornices in the lounge
room were noted
externally, there was movement and cracking to the
concrete paving to the north, with a buildup of debris
between the cracks
there is major separation and cra cking between the
masonry wall and garage door frame and stepped cracking
at the south wall
there is cracking and major rotation to the top of the
engaged brick piers to the east garage wall, as well as
separation between the window frame and masonry
a flo or level survey was conducted to the unit and a brick
course level survey to the shared unit and garage wall
a maximum floor level differential of 96mm was recorded
across unit 1
a general pattern of settlement was observed toward the
south side in the dir ection of the large trees
and footing heave was noted toward the north side
the maximum brick course level differential recorded
across the garage is 104mm
a general pattern of settlement was toward the north side
of the garage and footing heave toward the south side
geological surveys indicate the building is constructed on
quaternary age basaltic deposits, therefore it is expected
the foundation soils will consist of reactive clay
reactive clay soils experience volumetric changes with
relative changes in soil moisture conditions
an increase to soil moisture contents will cause soil to
swell resulting in heave, and a decrease in moisture
content causes the soil to shrink resulting in settlement
the Australian Standard (AS2870) states that structural
footing s founded on reactive sites under normal moisture
conditions are expected to experience a degree of
movement
wall cracking should be expected due to differential footing
movements under normal site moisture conditions but
should be limited to 1mm wide or i n rare instances 5mm
factors causing normal moisture content variation include
seasonal and climatic effects and normal garden
conditions
abnormal moisture conditions at the si t e can result in
increased incidences of damage to the building beyond
what is expected under normal conditions
the large trees adjacent the building and leaks in the
stormw a ter line can result in abnormal site moisture
conditions causing footing movement and damage
for water inundation of the soils to affect the structural
footings, the inundation must be of a degree and duration
so as to ingress to sufficient depths to increase the
moisture content of the foundation clay, into which
Case No: 388933 Determination Page 7 of 9
structural footings are founded
AS2870 identifies the ‘influence zone’ within which tree
roots affect footing foundations
tree roots remove moisture from foundation soils and this
moisture loss causes the reactive clays to shrink, resulting
in differential footing settlement
the floor level survey confirms the slab of unit 1 has tilted,
being higher at th e north side and falling toward the south
due to the stiffness of the slab, minimal curvature has
occurred which is consistent with the lack of damage in the
main building
however, tilting of the structural slab has resulted in the
rotation of the joint be tween the building slab and the
garage footing, causing the damage in this area
it is the opinion of this office that the observed damage is
as a result of differential moisture content variation of the
clay foundations caused by one or more of the followi ng
contributing factors: footing settlement due to tree root
drying of the soils and footing heave due to a leaking
stormw a ter line at the site
to ascertain the extent of the damage from the respective
causes it is recommended that the leaking pipes be
rep aired and the site allowed to dry out for a period pf 12 -
18 months to allow foundation moisture to return to pre -
peak levels
at the completion of the drying period, the property can be
re - assessed to determine the extent of movement by the
leaking pipes
no repair work should be undertaken until the site has
dried properly
the damage to the garage is structural and should be
considered unstable. Make safe works should be instigated
and the east wall should be cordoned off to prevent human
traffic in or aroun d the garage
FSP’s expert (AL)
Leak detection report
6 May 2014
CCTV to storm water found system is PVC in construction
two pulled connections were located
one was at the drainage gate in front of the roller door and
the other in the front yard
no faults located in the sewer line in the section that was
accessed
as the dw elling is of slab construction n o access to waste
pipes available
considering the amount of structural damage occurring it is
recommended that further CCTV of wastes and toilet
sewer be un dertaken
toilet pan and waste traps require removal to do this
faults located in storm water to be dug out and repaired
FSP’s expert (PB)
Plumber
28 May 2015
AL completed the CCTV inspections to the storm water
drainage system
CCTV of the below ground sewer drainage system found
Case No: 388933 Determination Page 8 of 9
all inspected sewer drainage pipes in a serviceable
condition
no defects or areas of concern were sighted during
inspection
FSP’s expert (L)
Supplementary
Engineer’s Report
2 Sep 2014
AL and PB conducted CCTV tests of the storm water and
sewer lines
this revealed two pulled connections in the storm water
lines, one in front of the garage and the other in the front
yard
no leaks were detected in the mains or waste lines
pulling of the pipes refers to the connection of the PVC
con nection being pulled apart so the pipe becomes
disconnected
pulling occurs from long term ground movements that can
be contributed to by soil moisture content variations which
cause the reactive soils to swell and shrink
ground movement can also result in movement of the slab
and stru cture
as the ground, slab and structure moves, this can in turn
result in movement and pulling of the stormwater pipes
causing a disconnection
the pulling of the connections has been caused by ground
movements and subsequent mo vement of the slab due to
soil moisture content variations caused by the drying effect
of tree roots, seasonal and climatic effects and the drought
conditions in Victoria between 1997 and 2010, followed by
the return of normal rainfall patterns .
Relevant policy provisions
ADDITIONAL BENEFITS
This insurance is extended to include the Additional Benefits shown below following Damage
not excluded by this Section…
…
18. LOSS OF RENT, TEMPORARY ACCOMMODATION AND REMOVAL COSTS
We will pay the following costs where Your Unit or Common Area suffers Damage and is
unable to be occupied for its intended purposes or when reasonable access to or occupancy
of Your Unit or Common Area is prevented by Damage happening to other property within
the immediate vicinity of Your Unit or Common Area:
a. Loss of Rent
Where a Unit or Common Area is leased out, or You can provide evidence by means
of a signed agreement that it would have been leased out, We will pay an amount
equal to the actual rent lost. We will pay up until the time the Unit is re-leased.
…
EXCLUSIONS
We will not cover Your Insured Property for Damage arising form or caused by:
…
Case No: 388933 Determination Page 9 of 9
7. Erosion, collapse or any other earth movement
…
11. Landslide or subsidence. We will pay for landslide or subsidence if it occurs within 72
hours after one of the following events:
a. storm, rainwater or wind.
b. earthquake.
c. explosion.
d. liquid that escapes from a fixed pipe or something attached to a pipe, a fixed gutter, fixed
tank or drain.
…
14. Normal settling, seepage, shrinkage, expansion, creeping, heaving or vibration.
…
16. Roots from trees, plants, shrubs or grass. It the roots from trees, plants, shrubs or grass
block drains or pipes, We will pay for the resultant Damage to Insured Property caused by
the escape of water or liquids.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.