Text of the determination
Determination
General Insurance - Domestic Insurance - Home Building - Home Contents - FSP
Decision - Claim Amount - Service - Delay in Claim Handling
Determination
Case No: 388120 Determination Page 1 of 10
Case number: 388120 15 June 2015
1 Overview
1.1 Dispute
The Applicants hold a home building and contents insurance policy underwritten
by the Financial Services Provider (FSP) covering their residential address. The
property was destroyed by fire on 20 July 2014 and the Applicants lodged a claim.
The FSP accepted the claim and offered to settle the claim by way of cash
settlement in the amount of $166,272.82, which the FSP considers represents the
cost of replacing the home and all ancillary costs.
The Applicants dispute that decision and seek payment of the sum insured of
$269,000, in settlement of the claim. The Applicants also maintain a number of
ancillary items have not been included in the settlement amount.
1.2 Issues and key findings
The FSP is not obliged to pay the sum insured
The FSP is not obliged to automatically pay the sum insured to the Applicants,
because the costs to rebuild the property do not meet or exceed the sum insured
amount.
The FSP has not discharged its obligations under the policy terms
The FSP's offer of settlement does not fulfil its obligations pursuant to the terms of
the policy, because the quote it based its settlement offer on, was not valid at the
time of its final offer.
The FSP is to obtain further information regarding the septic and water tanks and
is to then assess its liability for their repair and/or replacement.
The FSP has no further liability in respect of the remainder of the items claimed
by the Applicants.
1.3 Determination
This Determination is partly in favour of the Applicants.
The FSP is to increase its offer of settlement based on the current price for the
rebuild of the Applicants‟ home. However, it is not automatically obliged to settle
the sum insured, as the costs to rebuild the home do not meet or exceed this
amount.
Case No: 388120 Determination Page 2 of 10
The FSP is to settle the Applicants the total sum of $200,759 (being the costs of
rebuilding the home), noting that the FSP have already paid an amount of
$108,275.38, directly to the Applicants and paid an amount of $52,997.44, to the
Applicants‟ bank, in payment of the mortgage.
The FSP is to pay interest on the total settlement amount of $200,759, in
accordance with the Insurance Contracts Act 1984 (the Act), from 24 November
2014 (the date of the FSP‟s final cash settlement offer), to 28 May 2015.
The FSP is also to pay $5,772 for the tree trimming and an amount for the
reinstatement of the garden bed and sleepers, on presentation of receipts for this
work. The FSP is similarly required, on proof of the Applicants incurring the
relevant cost, to reimburse the reconnection fees incurred for the Foxtel cable and
the telephone line.
The FSP is to pay temporary accommodation costs for a further three months , to
enable the Applicants time to make alternative arrangements.
The FSP is to obtain further information to assess its liability for the water tanks.
The FSP is not obliged to refund the difference in premium from the sum insured
and the amount actually remitted to the Applicants in respect of their claim.
The FSP is not liable for the other costs sought by the Applicants.
Case No: 388120 Determination Page 3 of 10
2 Reasons for Determination
2.1 Does the FSP's offer of settlement fulfil its obligations pursuant
to the terms of the policy?
The Applicants have established a prima facia claim
It is not disputed that the Applicants suffered a loss from a risk insured against or
that the FSP has accepted the claim. It is further not disputed between the parties
that the sum insured for the building at the time of the loss was $269,000.
However, a dispute has arisen between the parties as to the adequacy of the
FSP‟s offer of settlement.
As there are a number of issues in dispute in this matter, for the sake of clarity,
the Panel proposes to address each issue separately below.
Matters which are not in dispute or have resolved whilst the claim has been on
foot, such as the contents settlement, on site costs including replacement of the
septic tank, allowance for council fees and discharge of the mortgage, will not be
given further consideration in this Determination.
The FSP's policy does not provide automatic payment of the sum insured in
the event of a loss
There is no dispute between the parties that the property was completely
destroyed by the fire and is a total loss. It is on this basis that the Applicants seek
payment of the sum insured. They say they increased the sum insured each year
at the recommendation of the FSP, for just such a scenario and therefore should
be entitled to the entire amount in settlement.
There is further no dispute between the parties that the Applicants do not wish to
return to the property and seek to either rebuild elsewhere or purchase an
established dwelling. On this basis, the FSP has agreed to settle the Applicants‟
claim by way of a cash settlement, representing the costs to rebuild a dwelling
similar in size, quality and construction to that which it replaces. The house is not
required to be an exact replica.
The Panel notes the policy documents clearly state that where the insured
building is considered a total loss, the FSP will elect to rebuild or settle the claim
by way of cash payment of the amount it would cost to reinstate the building. The
FSP‟s maximum liability in this regard, is the sum insured. This forms a ceiling on
indemnity and any loss is settled up to the po licy limit (Panel‟s emphasis).
The policy contains no suggestion that the sum insured is the minimum settlement
amount, nor that this amount is automatically paid in the event of a claim. The
Applicants are only entitled to be settled the amount that fairly reflects their actual
loss, as measured by the costs of rebuilding.
Whilst the adequacy of that offer will be addressed in greater detail later in this
Determination, the Applicants would only be entitled to the sum insured if the
costs to rebuild were at or exceeded the amount of the sum insured.
Case No: 388120 Determination Page 4 of 10
In this instance, if the costs to reinstate the dwelling fall short of the sum insured,
were it the case that the FSP settled the Applicants in the amount of the sum
insured, then this would leave the Applicants in a better financial position to that
which they enjoyed prior to the fire, as they would have these surplus funds at
their disposal. This is not the intention of the policy.
On this basis, the FSP‟s liability is determined by the actual costs to rebuild the
dwelling as close as practically possible .
The FSP's cash settlement offer is insufficient to reinstate the building
The FSP obtained quotations to rebuild a similar dwelling to original from kit
homes suppliers “B” and “A”. After adding on ancillary costs not provided for by
the quotations, such as a wood heater and on site costs, the FSP offered a final
settlement in the amount of $166,272.82, based on the quotation submitted by A.
Whilst the initial, lower offer, was made to the Applicants on 6 October 2014, the
FSP‟s final settlement was put to the Applicants on 24 Novemb er 2014.
However, perusal of A‟s quotation shows it was valid for 30 days only from the
date of preparation, being 25 September 2014.
Therefore, at the time of the FSP‟s final offer, the price quoted by A had already
expired and thus was not suitable to use for the purposes of determining the
rebuild costs.
The Applicants have also provided confirmation from A, stating that the price
quoted is no longer valid as they have increased their prices, although it is not
known when the price increase was effective.
The Applicants have provided a current quotation from A for $181,555 for a
similar dwelling.
Generally speaking, the Panel accepts that once an FSP has established its
liability, it would be unfair to expect the FSP to absorb any increase in prices that
result as a delay of the insured in commencing rebuilding.
However, in this instance, the Panel is of the view that the FSP should bear the
increase in costs.
The reasons for this are threefold.
In the first instance, the FSP‟s offer of settlement was inadequate as it did not
include all items required. In the ensuing timeframe, whilst the FSP costed those
items and eventually offered settlement for these, the quote expired.
The Panel is of the view that the FSP should have ensured the currency of the
quotation from A, before making its final offer of 24 No vember 2014, to the
Applicants.
Further, the Applicants state the quote from A did not include upgraded items they
had on the original home such as double glazing, aluminium flyscreens and
similar. These items are reflected on the updated A quote. The FSP has not
challenged the inclusion of these items in the quote. Accordingly, the Panel
Case No: 388120 Determination Page 5 of 10
accepts the updated A quote accurately reflects the features of the property to
which it replaces.
Finally, once the FSP had established its minimum liability to the Applicants in
November 2014, it did not take any steps to release any settlement monies to
them. Accordingly, the Applicants were not in a financial position to either rebuild
or purchase a new dwelling regardless. On this basis, the Panel concludes the
settle ment amount is to be based on A‟s revised quotation, plus the ancillary costs
already allowed by the FSP.
This is set out as follows:
Cost to rebuild home $181,555
Wood heater $4,500
On site costs $16,500
DA costs $2,364
Water cost $840
Less emergency funds ($5,000)
Total Settlement $200,759
The Panel notes that the updated quotation from A includes components for pest
control and floor coverings, blinds and light fittings and accordingly, the Panel
considers these costs are adequately accounted for in the settlement amount.
The Panel is not persuaded by the Applicants‟ contention that a separate site
manager is required, given the house is a pre -fabricated kit home. A have their
own site manager to oversee the installation of the house. Although A‟s site
manager would not oversee the Applicants‟ trades, it is doubtful that a site
manager would be required for plumbing and electrical works. In any case, as the
Applicants do not intend to rebuild at the site, it is unlikely they would incur this
cost.
Further, notwithstanding the FSP has, as at 28 May 2015, remitted $108,275.38
as a cash payment to the Applicants, to enable them to either commence
rebuilding or make other arrangements and a further amount of $52,997.44 to the
Applicants‟ ba nk on 1 June 2015, the FSP is required to pay interest on $200,759,
pursuant to Section 57 of the Insurance Contracts Act 1984 , from 24 November
2014, being the date of its final cash settlement offer, to 28 May 2015.
Tree trimming expenses and site manager fees
The Applicants are seeking the sum of $5,772, in respect of tree trimming costs,
plus the costs of $2,178, for site management costs to oversee the tree removal,
plumber, Telstra connection and electrician amongst other things. The Applicants
say that in order to transport a kit home to the site, trees along the driveway and
road require trimming to accommodate the truck onsite. The Applicants accept the
supplier will have a site manager to oversee the installation of the home, however,
the builder d oes not include the onsite costs and trades, which are the Applicants‟
responsibility.
Case No: 388120 Determination Page 6 of 10
The FSP has agreed to cover the expense of the tree trimming. The Panel
considers this is fair in the circumstances. However, the FSP has declined to
cover the costs for the site manager.
The Panel appreciates it is the Applicants‟ preference to hire a site manager to
oversee the tasks that they do not feel comfortable doing themselves. However, in
the Panel‟s view, the FSP has no liability under the policy terms to provi de such
items. Further, the Panel notes that the Applicants are at liberty to utilise some of
the funds from the on-site allowance for this purpose if they wish to proceed. The
Panel considers no further funds are payable to the Applicants in this regard.
Foxtel and telephone re-connection
The Applicants seek cover for the re -connection of their Foxtel cable and the
replacement of the set-top box, which was destroyed in the fire. They also seek
the costs to reinstate a telephone line to the property. The FSP considers the
costs to re- establish the connections are accounted for in the allowance for „onsite
costs‟.
The FSP has not addressed the issue of the replacement of the set-top box.
However, in the Panel‟s view, such an item would be considered a contents item.
As the contents sum insured has previously been exhausted, any losses over and
above this would be borne by the Applicants.
The Panel accepts that pursuant to the policy terms, the FSP is required to
reinstate „services‟ to the home. The policy defines services as: „services (whether
underground or not) that are Your property or which You are liable to repair or
replace or pay the cost of their repair or replacement‟. The Panel considers,
subject to the Applicants providing satisfactory proof of paying for the cost of „their
repair or replacement‟ that the FSP is required to reimburse the Applicants the
costs entailed in restoring both the Foxtel cable and the telephone connection;
such a reimbursement would be in addition to the FSP‟s general allowance for
„onsite costs‟.
Water tank replacement
The Applicants maintain the three water tanks at the property require
replacement. The Applicants acknowledge the tanks are not physically damaged.
However, they say the water was contaminated and the sludge that has formed in
the bottom of the tanks has compromised the tanks‟ future ability to hold and store
potable water.
The Panel notes the FSP has previously agreed to cover the costs to replace the
water in the tanks. The FSP maintains that it has sought advice on the matter and
the tanks only require flushing and cleaning to enable them to safely hold potable
water.
Notwithstanding the FSP has not provided sufficient evidence in supporting its
position, the Panel is also not persuaded that the Applicants have satisfactorily
demonstrated the tanks require replacement. In fact, the evidence supplied by the
Applicants relating to water tanks that have been in bushfire affected areas,
Case No: 388120 Determination Page 7 of 10
seems to suggest that tanks can be satisfactorily cleaned and de -contaminated.
Whilst it would appear the water cannot, this aspect is not in dispute as the FSP
has already agreed to cover this.
On this basis, the Panel determines the FSP is to engage the services of a
hygienist or similar to clean and flush the tanks. In the event that process is
insufficient to restore the tanks to a sanitary working position, the FSP is then
required to assess its liability under the policy terms, for replacement of the tanks.
Costs for veranda and bush fire rating
The Panel has previously accepted that A‟s updated quotation is the appropriate
basis for determining the settlement amount for the property rebuild. The Panel
notes that the costs for a 1.8mtr veranda is included in A‟s updated quote, as well
as an allowance for $3,500, for bushfire rating the property.
Accordingly, the Panel considers no further payment is owed to the Applicants in
this regard.
Repair of garden and driveway
The Applicants seek the cost of remedying the garden bed/grassed area and
driveway, which were damaged by the fire truck attendance. The Applicants
estimate this to be in the vicinity of $3,100 to repair.
The Panel notes that the policy only covers „the home‟ as defined by the policy. In
this instance, the policy provides that whilst „the home‟ is defined to include some
items of an external nature, others are specifically excluded from the definition.
In this instance, the FSP‟s policy specifically excludes earth or gravel pathways or
driveways or other unpaved surfaces or trees, shrubs and any other plant life
including grass or lawns, or soil, sand, gravel, bark or mulch as being included in
the insured risk of „the home‟.
However, the Applicants state the garden bed including sleepers were not
damaged by the fire and did not require removal. Regardless, it was removed by
the FSP‟s contractors during the debris removal.
The FSP was given the opportunity to make enquiries into the Applicants‟
allegations, however, did not do so. Accordingly, the Applicants‟ statements are
unchallenged. The Applicants have only provided a quotation for the garden bed
and (re-seeding the lawn, which is not covered). Therefore, this composite
quotation cannot be used to calculate the costs owing to the Applicants.
On this basis, the FSP is to reimburse the Applicants for the missing sleepers and
garden bed upon presentation of receipts for this work being carried out.
Medical expenses incurred
The Applicants are also seeking the costs of psychological treatment for their
children, both of whom were severely traumatised by the fire event.
Case No: 388120 Determination Page 8 of 10
The FSP has declined to cover these on the basis that the policy does not provide
cover for any medical expenses. Further, the policy specifically excludes any
consequential loss from cover.
The Panel has carefully considered the FSP‟s policy and accepts that it excludes
liability for consequential losses following an incident covered by the policy.
Accordingly, the Applicants are not entitled to compensation for any losses which
occurred as a result of the incident which gave rise to the claim.
The Panel is not satisfied that the policy terms prevent an award of compensation
for losses which have arisen as a result of the actions taken by the FSP in the
course of handling the claims (rather than as a result of the underlying incident
itself).
However, in this instance, the Panel considers that the trauma experienced by the
Applicants‟ children is largely as a result of the event itself and the repercussions
such as moving into temporary accommodation, as opposed to any delay or
misconduct on the part of the FSP.
The Panel notes that barring a delay in responding to an email from the
Applicants‟ sister on 27 October 2014, the FSP has been, in the main, proactive
and timely in its management of the claim, notwithstanding that at the time of the
FSP‟s settlement offer in November 2014, the FSP had yet to release funds to the
Applicants to enable them to purchase another home. Whilst a dispute has arisen
between the parties over settlement, this is not necessarily indicative of poor
claims handling on the part of the FSP.
On this basis, the Panel accepts the FSP has no liability for the medical costs
incurred by the Applicants.
Temporary accommodation benefit
The FSP‟s policy provides that it will cover up to 20% of the sum insured or
$20,000, whichever is the lesser, for the reasonable costs of temporary
accommodation incurred if the property is uninhabitable.
There is no dispute that the FSP are currently covering these costs.
The Panel considers that once the FSP has complied with this Determination, it is
reasonable for the FSP to continue payment for these expenses for a further three
months in order to allow the Applicants time to make other arrangements.
Premium refund
The Applicants are seeking a refund of the difference in premium they have paid
between the sum insured and the actual amount they receive in settlement. The
Applicants calculate they have been over insured by about $20,000pa, for the last
9 years.
Generally, an insured is responsible for reviewing the terms and conditions on
which insurance cover is offered and confirming that it is appropriate for their
needs. In the case of a home insurance policy, the adequacy of the building sum
Case No: 388120 Determination Page 9 of 10
insured is one of the matters which should be considered by an insured in
deciding whether to accept the cover offered.
The decision as to the amount for which to insure a property is ultimately one to
be made by the insured, after consideration of matters including the costs of
rebuilding the property and the premium they are willing to pay for the relevant
cover.
The Panel notes that the Applicants had the option of decreasing their sum
insured at any time during the policy period.
Accordingly, the Panel considers the FSP is entitled to retain the premiums paid
in respect of the contractually agreed amount between the parties, particularly as
the Applicants have accessed a benefit under the terms of the policy.
Case No: 388120 Determination Page 10 of 10
3 Supporting information
3.1 FOS approach to this dispute
This dispute has not been the subject of a FOS Recommendation. Due to the
nature of the dispute, it has been referred directly to a Panel for Determination, in
line with the Operational Guidelines to the FOS Terms of Reference. The Panel
consists of an Ombudsman and two representatives with consumer and insurance
experience.
The Panel has decided this case on its merits, having regard to the relevant law,
good industry practice, codes of practice and previous FOS decisions.
There has been a full exchange of all material information relied on for the
purposes of this Determination and each party has had the opportunity to address
any issues raised by the other.
The Panel has reviewed and considered all of the material provided by the
parties. While the parties have raised a number of issues in their submissions, for
the purposes of this Determination the Panel has restricted its commentary to
those issues which it considers directly relevant to the outcome only.
3.2 Relevant Legislation
Words with special meanings
Home includes the following:
...
c. services (whether underground or not) that are Your property or which You
are liable to repair or replace or pay the cost of their repair or replacement;
d. landscaping, paved pathways and paved driveways, retaining walls, fixed
artificial grass, fences and gates entirely or partly on the Site;
…
Home does not include:
…
b. earth or gravel pathways or driveways or other unpaved surfaces;
…
h. trees, shrubs and any other plant life including grass or lawns, or soil, sand,
gravel, bark or mulch.