Home / Financial Firm (Unknown - Insurer) / Determination 386929
Determination 386929
Storm-related vehicle impact damage to home: FSP cash settlement offer on inadequate scope of works versus repairs
Summary
The applicant's home was damaged when a vehicle crashed into it. The FSP offered a cash settlement based on a quote of $44,434.72, which the applicant said omitted storage, accommodation and other costs. AFCA found the cash offer unfair and ordered the FSP to obtain a revised scope of works and arrange the repairs.
Given uncertainty about impact damage, possible sub-floor and unspecified works, and temporary accommodation and storage costs, a cash settlement on the existing scope would be unfair, so the FSP must carry out the repairs under the policy.
Subjects and remedies
home or building damagemotor vehicle collisionreassess claimrepair or rectify
Text of the determination
Determination
Case No: 386929 Determination Page 1 of 5
Case number: 386929 23 May 2016
1 Overview
1.1 Dispute
The applicant holds a Home Building and Contents Policy with the financial service
provider (FSP). On 8 September 2014, the applicant’s home was damaged when a
vehicle crashed into the property.
A dispute has arisen as to the Scope of Works required to repair the property. The
FSP have offered to cash settle the applicant’s claim. The applicant wants the FSP to
complete the repairs to the property plus meet the costs of any offsite
accommodation and storage costs.
1.2 Issues and key findings
Is the FSP s’ offer to cash settle fair in the circumstances?
The FSP is offer to cash settle the claim on the basis of its Scope of Works is not fair
in the circumstances. The offer does not provide for the repair of all damage
sustained to the property nor allow for any temporary accommodation required
and/or storage costs.
Should the FSP repair the property?
Given the damage to the property, it is fair in the circumstances that the FSP attend
to the repairs rather than cash settle the claim.
In attending to the repairs, it may be necessary for the applicant to complete some
maintenance to the property to be agreed between the parties.
1.3 Determination
This determination is partially in favour of the applicant.
The FSP is to obtain a revised Scope of Works and arrange for the repair of the
applicant’s property in accordance with the terms of the policy. Insofar as the repairs
cannot be completed until maintenance work is performed by the applicant, then the
parties should agree to a timeframe for the completion of that work.
In the event that the parties are unable to reach an agreement as to a suitable
timeframe then the parties may agree to cash settle the claim in accordance with the
terms and conditions of the policy.
Case No: 386929 Determination Page 2 of 5
2 Reasons for determination
This determination is reached after reviewing all of the information exchanged and is
based on what is fair in all the circumstances, having regard to the relevant legal
principles, terms of the policy, good industry practice including codes of practice and
prior determinations where applicable.
The dispute is essentially about whether the FSP’s offer to cash settle the applicant’s
claim is fair and reasonable in the circumstances and whether the FSP’s Scope of
Works is fair in the circumstances.
It was agreed that the applicant would obtain architectural drawings and a further
engineering report and Scope of Works. Although this was agreed to in November
2015, the applicant, despite repeated attempts, has been unable to obtain the Scope
of Works from his engineer.
2.1 Is the FSP ’ s offer to cash settle the claim fair in all the
circumstances?
The offer to cash settle the claim on the basis of the Scope of Works is not fair
in the circumstances.
The claim arose when a vehicle collided into the front of the applicant’s property on 8
September 2014.
The FSP had a repairer attend to complete the make safe repairs. The repairer
recommended that an engineer attend th e applicant’s property.
On 29 October 2014 C Pty Ltd provided a report and two quotes were requested.
The FSP authorised repairs on 3 December 2014 through PP who again requested a
Scope of Works. At that time, it was recommended that the claim be cash settled due
to pre- existing issues with the property. The FSP’s assessor recommended cash
settlement due to movement issues of the property, a defective guttering system and
soil not being graded away from the property.
The applicant obtained an independent structural engineer’s report from KBT. The
engineer considered the damage to the property was most likely due to the impact as
the hairline cracks identified in the ceiling and surrounding walls were first observed
post- accident. He recommended a site inspection and classification report be
conducted by a qualified civil engineer to determine whether the hairline cracking
was in fact due to seasonal movement as claimed by the FSP.
In a supplementary report, KBT indicated the poor site drainage may not have
affected the footing performance as there was no sign of cracks to the external
brickwork elsewhere in the property.
The FSP obtained a further engineer’s report based on a visual inspection of the
property. The report from FMG dated 17 July 2015 identifies that the vehicle impact
caused damage to the front elevation of the house but otherwise the remainder of the
defects and damage was non-structural and was not unexpected on highly reactive
soil.
Case No: 386929 Determination Page 3 of 5
The Scope of Works accompanying the report from FMG is quite detailed and include
the need as part of any repair for the repairer to arrange:
inspection of the sub floor
engagement of a fully qualified structural engineer to assess issues during
repairs
potential additional works.
The report does not refer to the repairs required to the fence, roof or replacement
letterbox.
The FSPs offer based on the quotation obtained from JL of $44,434.72 to repair the
property does not take into account the possibility of unidentified building and works
not specified in the Scope being exposed, possible sub-floor damage, the need to
engage a fully qualified structural engineer or damage to the letterbox, roof or fence.
In addition, the FSP has failed to take into account the likely storage cost or
temporary accommodation costs.
The applicant in an email dated 11 June 2015 provided an estimate of the following
costs:
Storage Estimate 3 months $1,479
$1,608
Transport Cost of removalist to transport
property from applicant’s premises to
storage accommodation during
repairs
$6,000
Accommodation
costs
Estimate two to three months @$289
per night
$26,010
The FSP has provided no response to these estimates. The applicant has assessed
the accommodation costs based on a nightly rate at an apartment. It is likely that the
FSP would be able to organise accommodation at a cheaper rate from this.
The potential for additional works being required with additional associated costs is
high. The risk associated with the repairs would be transferred to the applicant which
is not consistent with the intention of the parties when entering the insurance
contract. The applicant would be exposed to the possibility of additional works being
required, temporary accommodation and storage costs as well as the engineering
costs, Further the applicant would have to bear the cost of replacing the fencing and
letterbox as well as the roof repairs.
To allow the FSP to cash settle on the basis of the quotations in the circumstances
would, in my view, be unfair.
2.2 Should the FSP repair the property?
Whilst the terms of the policy allow for the FSP to cash settle the claim, I am not
satisfied given the nature of the damage to the applicant’s property that it would be
fair to cash settle the claim.
In my view, given the uncertainty as to the damage sustained to the property from
impact, it is only fair that the FSP attend to the actual repairs.
Case No: 386929 Determination Page 4 of 5
I accept the comments made by the assessor and engineers that there may be pre-
existing issues with the property. This should be clarified by obtaining a further report
from FMG.
By agreeing to repair the property, the FSP will be able to account for any
unidentified building or works not specified in the Scope, will be able to account for
any sub-floor damage due to the impact and ensure that the repairs are conducted to
an appropriate standard. The FSP will be able to arrange for suitable temporary
accommodation and storage if required and complete the repairs to the fence and
letterbox.
Insofar as repairs to the roof are concerned, I accept that there are issues with the
guttering which the applicant should attend to as part of the repair process. The FSP
should not be required to repair the property until such time as the guttering is
repaired. It may be tha t the applicant can agree with the FSP’s repairer to meet the
costs associated with replacing the guttering as part of the repair process.
Only if the applicant is not prepared to replace the guttering, do I believe it would be
fair that the FSP be entitled to cash settle the claim.
In the event that the FSP is to cash settle the claim on this basis, then the FSP must
obtain a revised Scope of Work taking into account the issues raised in section 2.1 of
this determination and make suitable allowance for those items as well as the
removal and storage of items during the repair process as well as temporary
accommodation.
Case No: 386929 Determination Page 5 of 5
3 Supporting information
3.1 Relevant documentation
Applicant’s submissions.
FSP’s submissions.
Report from C Pty Ltd dated 29/10/2014.
Report from IL.
Applicant report KBT 23/4/2015.
Supplementary report KBT.
Additional costings supplied by applicant 11 June 2015.
JL quote - $4,434.72.
GE engineering report – 17 July 2015.