Text of the determination
Determination
General Insurance - Domestic Insurance - Home Building - FSP Decision - Claim
Amount
Case number: 385350 17 August 2015
1 Overview
1.1 Dispute
In September 2009, the Applicant lodged a claim under his home insurance policy
with the Financial Services Provider (FSP) for movement damage to his home
due to the overflow of water from a stormwater downpipe.
The FSP accepted the Applicant’s claim but did not commence repairs
immediately, in order to allow time for the sub-floor area to dry out. Before repairs
could commence, the Applicant lodged a second claim for further movement
damage to the property following a storm in February 2011.
Despite protracted negotiations, the parties were unable to agree on an
appropriate cash settlement amount for both claims. After carrying out further
investigations, the FSP says that all of the claimed damage was caused by
factors which are excluded under the policy and has reduced its settlement offer
to $16,500 (being the amount quoted for the repair of the internal damage only).
The Applicant seeks cover for the cost of repairing all of the damage to the
property (including re-stumping), at an estimated cost of approximately $100,000.
1.2 Issue and key findings
Is the FSP liable for the movement damage?
The available information establishes that the Applicant’s property experienced
extensive and varied movement damage, which was caused by a number of
contributing factors.
While some of the damage was caused by the overflowing drainpipe in
September 2009 (and, to a lesser extent, the stormwater run-off in February
2011), the remainder was due to naturally occurring earth movement, which is not
covered under the policy. Further, some parts of the property which require
replacement as part of the repairs had pre-existing damage at the time the initial
event occurred.
Accordingly, it is fair in all the circumstances that the FSP be liable for some (but
not all) of the costs of repairing the movement damage to the property.
1.3 Determination
Case No: 385350 Determination Page 2 of 13
This Determination is partly in favour of the Applicant.
The FSP is to pay the Applicant the amount of $50,678 in full and final settlement
of both his claims. The FSP is to pay the Applicant an additional amount of $3,000
as reimbursement of costs incurred in obtaining reports from his engineer (LD).
Case No: 385350 Determination Page 3 of 13
2 Reasons for Determination
2.1 Is the FSP liable for the movement damage?
Policy provides cover for insured events subject to exclusions
The Applicant is required to show that, on the balance of probabilities, he has
suffered a loss caused by a risk insured against under the policy. This is known
as a prima facie claim.
If the Applicant is able to establish a prima facie claim, then the onus shifts to the
FSP to show that, on the balance of probabilities, it is entitled to rely on an
exclusion under the policy or is otherwise entitled to deny the claim.
The policy provides cover for damage to the Applicant’s property caused by the
events listed in the policy, including the insured events of “storm, rainwater or
wind”, “landslide and subsidence” and “water or liquid damage”. This c over is
provided subject to the conditions and exclusions set out in the policy.
The policy contains general exclusions for loss or damage which occurs as a
result of, or arising from:
landslide or subsidence (except to the extent covered under the insured event
of “landslide and subsidence”);
settling, shrinkage or any movement of earth; or
erosion, rust, corrosion, gradual deterioration, depreciation or wear or tear.
Applicant has established a prima facie claim
The FSP accepts that the Applicant’s property has suffered significant movement
damage which has worsened over time, such that the building now requires
complete re-stumping.
The Applicant has provided detailed reports from his civil engineer (LD) which
conclude that the damage to his property was caused by earth movement due to
the inundation of the sub-floor soils by the overflowing downpipe in September
2009 and stormwater run-off in February 2011.
The FSP’s claim records reflect that it initially accepted both of the Applicant’s
claims, based on the findings of its engineer (BH), who inspected the property on
several occasions over the two year period between October 2009 and October
2011.
It was only when the FSP appointed another engineer (MC) in late 2013 (after the
parties had been unable to agree on an appropriate settlement amount), that it
sought to deny liability for the movement damage to the property.
On this basis, the Panel is satisfied that the Applicant has established a prima
facie claim under the insured event of “water or liquid damage” (in relation to the
overflowing downpipe in September 2009) and/or the insured event of “storm,
rainwater or wind” (in relation to the storm in February 2011 ).
Case No: 385350 Determination Page 4 of 13
In these circumstances, the FSP bears the onus of establishing that, on the
balance of probabilities, it is entitled to rely on a policy exclusion to deny liability
for all or part of the Applicant’s claim s.
In order to do so, the FSP must show that the proximate cause of the movement
damage to the Applicant’s property (that is, the real, effective or dominant cause)
was one or more of the excluded factors outlined above.
The FSP says the proximate cause of the movement damage to the property was
the gradual deterioration of the timber stumps over time, as well as differential
foundation movement caused by naturally occurring changes in the moisture
content of the extremely reactive foundation soils.
Dispute primarily concerns extent of damage caused by 2009 event
As outlined above, the claimed damage relates to two separate events in
September 2009 and February 2011, both of which resulted in water running into
the sub- floor area under the Applicant’s house.
The available information suggests that the second event largely affected the
same area as the first event, and caused only limited additional damage.
The FSP’s original engineer (BH) indicated that the only additional damage which
could be attributed to the second event was localised subsidence under one of
the stumps under the dividing wall in the central area of the house.
The Applicant’s engineer (LD) also acknowledged in a conversation with the FOS
Case Manager on 28 May 2015 that he considered the bulk of the movement
damage at the property to be due to the effects of the overflowing downpipe in
2009, not the stormwater run-off in February 2011.
Parties have provided conflicting engineers’ reports
The Applicant’s property is situated on extremely reactive (class “E”) clay
foundation soils, which are known to exhibit a high degree of volumetric change
as a result of variations in moisture content.
The available information establishes that the property has experienced extensive
and ongoing movement during the years since the initial claim was lodged in late
2009.
The Panel notes that both the features of the property, and the length of time
which has passed, increase the difficulty of accurately identifying the cause of the
movement damage observed to various parts of the property.
Each of the two engineers appointed by the FSP (BH and MC), and the engineer
appointed by the Applicant (LD), have provided differing views as to the cause of
the extensive movement damage observed at the property.
The most significant variance is between the views expressed by the FSP’s
second engineer (MC) (on the basis of whose reports the FSP essentially denied
all liability) and the Applicant’s engineer (LD), who considered that all of the
movement damage at the property was due to the inundation from the downpipe
in September 2009.
Case No: 385350 Determination Page 5 of 13
Part of movement damage was caused by overflowing pipe
The Panel accepts that, as engineers, each of BH, MC and LD are appropriately
qualified to provide a view as to the cause of the movement damage at the
Applicant’s property.
However, the Panel notes that neither MC nor LD inspected the property until
more than four years after the initial event occurred.
MC and LD did have the benefit of reviewing BH’s reports and the results of the
level surveys he conducted in October 2009, April 2010 and August 2011.
However, MC and LD have each drawn differing inferences from this information,
which in part explains the conflicting conclusions they reached. Among other
things, MC and LD disagreed as to which point in the house should have been
used as the zero reference point.
In these circumstances, the Panel considers that it is appropriate to place
significant weight on the findings of BH, who inspected the damage to the
property on at least three occasions over a period of almost two years, including
after the sub-floor was affected by stormwater in February 2012.
As a locally based engineer, BH also had the benefit of familiarity with the
characteristics of the extremely reactive clay soils found in the region. Further, the
FSP accepted and relied on BH’s reports over an extended period of time, for the
purpose of assessing the Applicant’s claims.
When BH first inspected the property in 2009, he accepted that, while there was
evidence of some prior movement, significant movement of the stumps had
occurred in the previous month, particularly in the area immediately adjacent to,
and downslope from, the leaking downpipe.
BH observed heave (“upward movement”) of the foundation soils in the affected
area, but noted that, due to the nature of the soil, there was the potential for
subsidence (due to bearing failure of the soils under the stumps) over the longer
term, once the soils had dried out. He considered that it would not be possible to
determine the ultimate effects of the overflow (and therefore the extent of repairs
required) until such time as the soils had dried out.
When BH re-attended the property in October 2010, he noted that the anticipated
corrective movement in the affected area had occurred less quickly than expected
and predicted that it may take a further two or three years for the soils to dry out
completely. BH attributed this to the relatively poor sub-floor ventilation having
impeded the drying process, although he also noted that it was possible that
some of the movement in the affected area was due to natural moisture changes
in the soil, rather than solely the leaking pipe.
Following the storm in February 2011, the FSP engaged BH to re-attend the
property in order to determine whether any additional damage had occurred.
In his report dated 31 October 2011, BH referred to his earlier findings regarding
the heave resulting from the overflowing downpipe in September 2009, and noted
that the more recent changes in the floor levels on the western side of the house
Case No: 385350 Determination Page 6 of 13
were consistent with his previous expectations (that is, that the effects of the
overflow from the downpipe would dissipate as the soils dried out).
Given the drought had ended by the time of BH’s inspection in 2011, the resulting
climatic changes would have been likely to cause an increase (rather than a
decrease) in the moisture content of the soil.
Accordingly, the c omments in BH’s 2011 report suggest that the changes to the
western side of the property observed at that time were more consistent with the
initial movement to that part of the property having been caused by the
overflowing downpipe, rather than solely or primarily by naturally occurring earth
movement.
For the reasons outlined above, on the basis of the investigations carried out by
BH over the two year period following the initial event, the Panel is satisfied that at
least some of the movement damage at the property is properly attributable to the
overflowing downpipe in September 2009.
Some of damage was due to naturally occurring earth movement
Following his inspection in 2010 (and the results of the level surveys carried out at
the time), BH observed that, in addition to the effects of the overflowing downpipe
on the western side of the property, the footings on the eastern side had
subsided.
BH considered that the movement on the eastern side of the property was
independent of the damage to the western side, and had been caused by the soil
drying out as a result of the extended drought period.
When he re-attended the property in 2011, BH observed that some soil swelling
had occurred in the eastern section of the house (resulting in corrective
movement), following the end of the drought and a return to normal rainfall
patterns. However, BH noted that this recovery movement had not occurred
consistently around the house, as various areas were differently exposed to the
effects of normal rainfall.
BH also observed that the house would continue to be susceptible to ongoing
movement damage as a result of naturally occurring earth movement, due to the
extremely reactive clay foundation soils and the relatively shallow footings on
which it was built.
The Applicant’s engineer (LD) says that all of the movement damage at the
property is attributable to the initial overflow event in September 2009. LD says
that the nature of the soils is such that a single inundation event can cause
continuing movement over a period of six to ten years.
However, based on the available information, the Panel considers it unlikely that
all of the range of movement identified at the property is solely attributable to the
effects of the overflowing downpipe. The Panel accepts that the features of the
property made it susceptible to naturally occurring earth movement and there is
evidence that the floors had been re-levelled in the past.
Case No: 385350 Determination Page 7 of 13
Deterioration of stumps has contributed to repairs required
Each of the engineers who inspected the Applicant ’ s property observed that the
timber stumps had deteriorated over time. However, they have provided differing
views as to the nature and extent of this deterioration.
When he inspected the property in December 2013, the FSP’s engineer (MC)
reported that both the 80 year old original timber stumps in the main part of the
house and the newer red gum stumps in the extension were in poor condition and
required replacing.
MC attributed the bulk of the movement damage to the deterioration of the timber
stumps over time. He considered the deteriorated stumps were no longer able to
support the load imposed by the house. MC also commented that, had the stumps
been in good condition, they would not have subsided following changes in the
moisture content of the surrounding soils.
The Applicant’s engineer (LD) disputes MC’s finding that the majority of the
stumps were no longer able to support the weight of the house. While LD
acknowledges that some of the stumps have deteriorated, he maintains that the
stumps still have sufficient bearing capacity to support the weight of the house.
Both MC and LD have provided photographs showing a selection of the 96
original and 27 new stumps at the property. Each engineer accuses the other of
“cherry - picking” to show the stumps which best support their position. The original
engineer appointed by the FSP (BH) did not actually inspect the stumps, although
his report reflects that he suspected they were in poor condition.
Based on the photographs provided, and given the age of the stumps, the Panel
accepts that at least some of them were likely to be in poor condition. The Panel
notes that, during the course of previous settlement negotiations, the Applicant
accepted liability for the cost of replacing 20 to 25 rotted stumps.
However, given the varying condition of the stumps as shown in the photographs
and the nature of the damage observed, the Panel does not accept that the whole
of the movement damage to the property was wholly or primarily caused by the
deterioration of the stumps.
Nevertheless, in circumstances where it appears that the property now requires a
complete re-stumping, the Panel considers that it is appropriate to take into
account the pre-existing damage to the stumps, when considering the basis on
which the Applicant’s claims should be settled.
Damage has been caused by a range of factors
For the reasons outlined above, the Panel considers that the movement damage
to the property has been caused by a range of factors affecting the property
during the years since the stormwater overflow in September 2009.
Based on the available information, the Panel considers that the bulk of the
damage to the western side of the property is attributable to the 2009 event, while
accepting that this area has also been exposed to the ongoing changes in climatic
conditions over time.
Case No: 385350 Determination Page 8 of 13
However, the Panel considers that the movement observed to the remainder of
the property is primarily due to the effects of natura lly occurring earth movement.
The Panel accepts that the deterioration of the timber stumps may also have
contributed to some of the movement damage observed.
In any event, the Panel notes that, under the terms of the policy, the FSP is only
liable to repair that part of the property which suffered damage from an insured
event. For this reason also, the Panel considers it appropriate to take into account
the pre-existing condition of the stumps, when considering the appropriate
settlement amount.
FSP is liable for part of damage
As outlined above, the Applicant’s policy provides cover for damage to his
property caused by water, which on its ordinary meaning includes the overflow of
stormwater from a downpipe.
Accordingly, the Panel considers the FSP is liable for that part of the damage to
the Applicant’s property which was caused by the overflow event in 2009.
The FSP says that, even if the overflow event caused movement damage to the
property, it should not be liable for that damage as the policy only provides cover
for damage of this nature where it occurs within 72 hours of the insured event.
It is incumbent on an insurer to ensure that any exclusions or limitations on cover
are clearly outlined in the Product Disclosure Statement (PDS), which sets out the
terms of the policy.
In the present case, neither the insured event of “escape of water or liquid” nor
the insured event of “storm, rainwater or wind” (as described in the Product
Disclosure Statement) include any reference to a limitation based on the time at
which the damage occurs.
The policy contains exclusions for damage caused by earth movement, other than
as provided for under the separate insured event of “Landslide or subsidence”
(which includes the 72 hour limit referred to by the FSP).
However, in the Panel’s view, this exclusion only applies where the proximate
cause of the relevant damage is earth movement.
In the present case, the proximate cause (that is, the real, effective or dominant
cause) of the damage is the escape of stormwater from the downpipe, which is
subject to cover under a specific insured event.
On this basis, the Panel considers that FSP is not entitled to rely on the relevant
exclusion to deny liability for the Applicant’s claims.
Further, the Panel notes that the FSP initially accepted the Applicant’s claim
(based on the reports of its own engineer) and entered into good faith
negotiations over an extended period, in an attempt to agree on an appropriate
settlement amount.
The FSP did not seek to deny th e Applicant’s claim based on a policy exclusion
until several years later, after it had engaged a new engineer who had no prior
Case No: 385350 Determination Page 9 of 13
involvement with, or knowledge of, the circumstances of the claim. It is not clear
why, if a further opinion were required, the FSP did not re-engage its original
engineer (BH) who was very familiar with the claim history.
In these circumstances, the Panel considers it would also be unfair to allow the
FSP to seek to rely on the relevant exclusion.
2.2 How should the claims be settled?
FSP should contribute to costs of re-stumping
The original estimates for the repairs to the property (and the subsequent
settlement negotiations) were based on the proposed re-levelling of the house
and completion of the necessary internal repairs.
However, both parties now recognise that this approach will not be effective and,
given the extent of movement at the property, it is necessary for the entire
building to be re-stumped. This process is complicated by the need to ensure that
the re-stumping complies with current building requirements.
The Applicant has provided a recent quote for $36,350 from a local contractor
(BB) for the re-stumping, which includes the installation of adjustable stump
connectors to address the potential for ongoing movement.
While the FSP’s engineer (MC) has previously suggested that the re -stumping
could be completed for a lesser amount, the FSP has not provided an alternative
quote for the equivalent works. Based on the various quotes obtained throughout
the course of the claim, the Panel is satisfied that BB’s quote is reasonable.
Having regard to the extent of the damage, the range of likely contributing factors
and the pre-existing condition of the stumps, the Panel considers that it is fair in
all the circumstances that the FSP contribute to 50% of the cost of the repairs
(being $18,175).
The Panel does not accept that the FSP should be required to contribute to any
further re-levelling and associated works required following completion of the re-
stumping. The original quote provided by BB should allow for such minor
adjustments as are typically required following re -stumping works.
FSP should contribute to additional costs associated with re-stumping
The Applicant’s engineer (LD) says that, in order for the re-stumping works to be
effective, it is necessary for the chimney and the paved concrete veranda
surrounding the house to be removed and replaced or rebuilt. LD says this is
required so that the floor levels can be raised to the highest point.
The FSP’s engineer (MC) disagrees with LD’s analysis. He considers the chimney
and surrounding areas can be left in place and used as the datum point (ie the
highest point) for re-levelling the floor. MC considers that the concrete veranda
only requires replacing because it has deteriorated over time and due to the use
of poor construction techniques.
Case No: 385350 Determination Page 10 of 13
As noted above, there are differences between the ways in which the various
engineers have interpreted the results of the level surveys carried out at the
property, which is partly responsible for their conflicting views as to the manner in
which the re-stumping works should be carried out. The Panel notes that such
issues may have been avoided, had the FSP continued to use the same engineer
throughout the claim process.
Based on the information provided and considering the extent and range of
movement at the property, the Panel accepts that it may be necessary for
undamaged areas to be demolished in order for the re-stumping works to be
carried out effectively.
The Panel notes that several of the building contractors engaged to quote on the
works have confirmed that it will be necessary to demolish areas such as the
chimney and the concrete veranda.
In these circumstances, it is appropriate that the cash settlement include an
allowance for any such additional works.
However, the Panel considers that at least part of the damage to the concrete
veranda pre-existed the overflowing downpipe in September 2009.
When the FSP’s original engineer (BH) initially inspected the proper ty in 2009 and
2010, he did not identify any damage to this area as having been caused by water
escaping from the overflowing downpipe.
When BH returned in 2011, he noted that the cracking damage to the external
concrete paving slab appeared to be old damage and the location of the cracks
was inconsistent with this damage having been caused by the overflowing
downpipe.
Given BH’s familiarity with the property over time, the Panel considers his views
on the cause of the cracking damage to be highly persuasive.
The Panel also accepts that it is likely that (as identified by the FSP’s engineer
(MC)), the damage to the concrete veranda was caused by the corrugated iron
sheets used to retain the soil having rusted away over time, resulting in the sand
under the slab spilling into the sub-floor area, creating voids under the slab.
In light of the issues outlined above, the Panel considers that it is fair in all the
circumstances that the FSP contribute 50% of the costs of removing and
replacing the chimney and concrete veranda. Based on the quotes obtained to
date, this amounts to $10,915.
FSP should contribute to cost of internal repairs
The FSP has offered to settle the Applicant for $16,500 for the cost of internal
repairs to the building required as a result of the movement damage, based on a
quote obtained from a local builder (DN) in April 2014.
The Applicant’s engineer (LD) says the cost of repairing the internal damage has
increased due to continuing movement at the property due to the ongoing effects
of the overflowing downpipe in September 2009, and the delay in carrying out the
necessary repairs.
Case No: 385350 Determination Page 11 of 13
The Panel accepts that the effects of a one -off inundation can be far-reaching,
particularly in the context of extremely reactive foundation soils. Howe ver, for the
reasons outlined above, the Panel considers that ongoing seasonal changes in
the moisture content of the soils have also contributed to the further movement
experienced at the property.
In these circumstances, the Panel considers that the FSP’ s liability should be
determined based on the cost of the internal repairs as initially quoted by DN, plus
50% of the increase in costs (based on DN’s updated quote). On this basis , the
FSP is required to contribute $21,588 to the cost of the internal repairs.
Applicant is entitled to partial reimbursement of LD’s costs
Under paragraph 9.4 of the FOS Terms of Reference, FOS may require a
financial services provider to contribute to legal or other professional costs
incurred by an applicant in the course of their dispute.
However, unless exceptional circumstances apply, FOS will not require a financial
services provider to contribute more than $3,000 to such costs.
The Applicant incurred costs of approximately $8,000 in obtaining reports from his
engineer (LD). While the Panel has found LD’s reports to be of assistance, it has
not fully accepted LD’s findings that all of the movement damage to the
Applicant’s property was caused by the insured events .
In these circumstances, the Panel considers that it is fair and reasonable for the
FSP to reimburse the Applicant an amount of $3,000 for the costs of obtaining
LD ’s report s.
FSP is not required to pay interest
The Panel acknowledges that the Applicant’s claims have taken a n extended
period to resolve.
Some of the delays experienced during the claim process were unavoidable, due
to the need to allow the sub-floor of the property to dry out so that the damage
arising from the overflowing drainpipe could be accurately assessed.
The claim process was further complicated by the occurrence of a further event
(the stormwater run-off in February 2011) before the initial claim had been
resolved.
However, the claim history also indicates that the parties failed to act promptly to
progress the claim. In particular, there were extended delays during 2012 and
2013 while the Applicant sought to obtain his own engineer’s report. It was partly
due to these extended delays that the FSP finally appointed a second engineer
(MC) in late 2013, in an effort to expedite resolution of the claim.
In these circumstances, the Panel does not consider that the FSP should be
required to pay interest on the settlement amount.
Case No: 385350 Determination Page 12 of 13
3 Supporting information
3.1 FOS approach to this dispute
This dispute has not been the subject of a FOS Recommendation. Due to the
nature of the dispute, it has been referred directly to a Panel for Determination, in
line with the Operational Guidelines to the FOS Terms of Reference. The Panel
consists of an Ombudsman and two representatives with consumer and insurance
experience.
The Panel has decided this case on its merits, having regard to the relevant law,
good industry practice, codes of practice and previous Financial Ombudsman
Service (FOS) decisions.
There has been a full exchange of all material information relied on for the
purposes of this Determination and each party has had the opportunity to address
any issues raised by the other.
The Panel has reviewed and considered all of the material provided by the
parties. While the parties have raised numerous issues in their submissions, for
the purposes of this Determination, the Panel has restricted its commentary to
those issues that it considers directly relevant to the outcome only.
During the course of this dispute, the Applicant has been represented by his civil
engineer (LD). For the purposes of this Determination, submissions made by LD
(in his capacity as the Applicant’s representative) have been treated as havin g
been made by the Applicant himself.
3.2 Terms of policy
Subject Terms
Insured event -
storm
We will cover your buildings or contents for loss or damage as a
result of storm, rainwater or wind.
Insured event -
water or liquid
damage
We will cover your buildings or contents for loss or damage
caused by water or liquid …
Insured event -
landslide or
subsidence
We will cover your buildings or contents for loss or damage as a
result of a landslide or subsidence.
We will ONLY do this if the loss or damage o ccurs with in 72 hours
of:
an earthquake or explosion
a storm, including rainwater or wind, or
liquid escaping from a fixed pipe, fixed gutter, fixed tank or a
drain.
Exclusions to cover
- insured events
We will NOT cover any loss, damage or liability as a result of, or
arising from: …
landslide or subsidence, unless … we agree to cover the
Case No: 385350 Determination Page 13 of 13
Subject Terms
incident as described under “Landslide or Subsidence”
General exclusions We will NOT cover any loss or damage as a result of, or caused
by:
settling, shrinkage or any movement of earth;
erosion, rust, corrosion, gradual deterioration, depreciation,
wear or tear …
How we settle your
claim
If your buildings suffer loss or damage we will decide whether to:
repair
rebuild, or
pay you the cost to repair or rebuild that part of your buildings
that suffered loss or damage.
If we do, we will: …
only repair, rebuild or pay you for the part or parts of the
building that actually sustained loss or damage …
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.