Home / Financial Firm (Unknown - Insurer) / Determination 384841
Determination 384841
Claim for storm-damaged building windows denied under exclusions
Summary
The owners corporation claimed for storm-damaged building windows that the FSP denied under policy exclusions. AFCA found the damage accidental and caused by a design flaw, not an excluded cause, and ordered the claim accepted with interest.
The insurer bears the onus of proving an exclusion applies, and it could not show that gradual deterioration, known defects or defective workmanship caused the loss.
Issues
- Claim denial primary · upheld“The FSP has failed to prove that the cause of the damage is excluded under the policy.”
Subjects and remedies
home or building damagenatural disasterpay claimpay interest
Related
All Financial Firm (Unknown - Insurer) determinations · Find similar determinations
Text of the determination
Determination
General Insurance - Domestic Insurance - Residential Strata Title - FSP Decision -
Denial of claim-Exclusion/ condition
Determination
Case No: 384841 Determination Page 1 of 8
Case number : 384841 18 June 2015
1 Overview
1.1 Dispute
The Applicant, who represents the owners ‟ corporation for a strata titled
commercial building, lodged a claim for damage after glass panes fell from the
building in high winds on 5 August 2013.
The Financial Services Provider (FSP) denied the claim on the basis that the
cause of the damage is excluded from cover under the policy.
1.2 Issues and key findings
Is the FSP entitled to deny the claim?
The FSP is not entitled to deny the claim because:
The Applicant has established the claim falls within the policy.
The cause of the damage was the defective design of the fixing of the fins
which strengthen the frameless window panels.
The FSP has failed to prove that the cause of the damage is excluded under
the policy.
1.3 Determination
This Determination is in favour of the Applicant.
The FSP must:
accept the claim in accordance with the terms and conditions of the policy
pay interest in accordance with the Insurance Contracts Act on the amount
paid to the Applicant, calculated from 15 August 2014 until the date of
payment.
Case No: 384841 Determination Page 2 of 8
2 Reasons for Determination
2.1 The FOS Approach
I have determined this dispute considering what is fair in all the circumstances,
having regard to the relevant law, good industry practice, codes of practice and
previous FOS decisions. I have taken into account all the material submitted by
the parties.
I am satisfied that the documentation I have relied on has been provided to both
parties and each party has had the opportunity of addressing any issues raised.
This dispute has been expedited to a Determination. No Recommendation was
issued.
2.2 Is the FSP entitled to deny the claim?
The policy provides cover for accidental loss or damage
The policy provides cover for accidental loss or damage to the building that
occurs during the period of insurance.
Although the term accidental damage is not defined in the policy, the courts have
defined “accidental” in an insurance context as something that is “unintended and
unexpected. ”
On 5 August 2013, the area around the insured building experienced high winds
and the third floor windows of the building blew out. The Council issued an
emergency work order and the Applicant carried out those works to the sum on
$44,510.
I accept that the damage to the windows was accidental.
As the Applicant has established the claim falls within the policy, the burden shifts
to the FSP to establish it can deny the claim.
Cause of the damage was defective design of the fixing of the window fins
The report by the local council‟s structural engineer (H) was intended to determine
the actions for make-safe of the building. H noted that the glass window panels
were supported by glass fins, which are then fixed into steel brackets into the
building frame top and bottom. However, other than noting that several panes of
glass had fallen during strong winds, H‟s report contained little information which
can be relied upon with respect to establishing the cause of the damage.
The Applicant‟s building consu ltant (F) inspected the building in 2014 after the
repair/replacement of the window panes and strengthening fins had occurred.
F reported that the window breakage was believed to be as a result of poor
standard of fixing which may have been acceptable at the time (the windows were
installed) but would not be approved today. F stated that:
Case No: 384841 Determination Page 3 of 8
the glass strengthening fins appear to be poorly founded and connected to the
concrete support wall
it is likely that the fins have been installed into the rebates with a grout filler
a grout filler is b rittle and would not provide the resistance required under
adverse wind conditions.
The FSP‟s assessor (P) reviewed the report by F, and stated in its report of 9 May
2014 that the retrospective report by F does not unequivocally verify the
circumstances surrounding the claim. However with respect to the cause of the
damage, P appears to agree with F, saying that the principle factor is
inadequate/defective fixing of the window fins.
Further, P and F also appear to agree that the new fixings to the fins are better
suited to the function of holding the fins in place:
F reported that the “additional stainless steel angle fixtures together with
silicon filling that has been applied to the new installation and applied to all
other window fins is a vastly better fixing to withstand the wind loads ”
P, in its 9 May 2014 report, notes that the redesign by structural engineers
testifies to the defective nature of the windows.
On balance, I conclude that the cause of the damage was the defective fixing of
the window fins. This is a design flaw.
The FSP referred to three exclusions
The FSP has sought to rely on several exclusions:
damage caused by lack of maintenance, rust, oxidation, corrosion, Wear,
Tear, fading, gradual corrosion or gradual deterioration, concrete or brick
cancer, developing flaws, wet or dry rot, or failure to maintain the building
property in a reasonably good state o f repair
damage caused by non-rectification of a building defect, error or omission the
Applicant was aware of, or should reasonable have been aware of.
the cost of rectifying faulty or defective materials or faulty or defective
workmanship.
Gradual deterioration and poor maintenance exclusion does not apply
With respect to the first of the above exclusions relating to gradual deterioration
and poor maintenance:
The 22 August 2013 report by P indicates that the general maintenance of the
property was poor or neglected, and points to unmonitored roof drainage,
general debris, aged graffiti and avian occupation of the roof. However the
report does not provide any evidence to show that any such lack of
maintenance caused or contributed to the damage.
The 22 August 2013 report by P also notes “crude, reactive attempts at
remedying the deteriorated natur e of the glazing fixings within the frames”.
However, the report does not provide any evidence proving the glazing fixings
were deteriorated, or how any such deterioration caused or contributed to the
damage.
Case No: 384841 Determination Page 4 of 8
Accordingly, I do not accept that the FSP proven that this exclusion applies.
Failure to rectify a building defect exclusion does not apply
With respect to the second of the above exclusions relating to the failure to rectify
building defects known to the Applicant:
The 22 August 2013 report by P noted the reference by structural engineer H
to previous problems which have resulted in the replacement of glass panels.
P stated in its 9 May 2014 report that the “comprehensive evidence of
previous problems with the glazing and pre -existing knowledge of same is
unequivocal” .
However:
the report by F states that there was likely to have been no indication of the
possible failure of the window installation prior to it occurring
the Applicant has stated that damage to a panel of glass on the first floor was
due to vandalism, and that previous reports available (by B, on 2007 and by
SP, in 2010) only refer to issues with the coating of the glass.
I therefore do not accept that the Applicant was aware of (or should reasonably
been aware of) the design flaw in respect of the fixing of the window fins.
Accordingly, I do not accept that the FSP has proven that this exclusion applies.
Faulty or defective workmanship exclusion does not apply
In order for the FSP to show that this exclusion applies, it would need to show that
the materials used in the fixings were faulty or defective, or that the workmanship
used to install the fixing was faulty or defective.
I have concluded that the design of the window fixings was flawed. There is no
evidence before me to establish that the use of a grout filler as opposed to
silicone constituted defective workmanship or materials (as opposed to design).
Even if the use of grout was not part of the design, there is no evidence to
demonstrate that this was contrary to building standards at the time. Rather, F
has stated the standard of fixing may have been acceptable at the time.
As the FSP has not established that any of the policy exclusions apply, it is
therefore not entitled to deny the claim.
Case No: 384841 Determination Page 5 of 8
3 Supporting information
3.1 Policy provisions
Policy 1 – Insured Property
Policy 1 is a „broad form‟ accidental loss and damage ins urance contract in terms of the
Insuranc e Contracts Act 1984.
What we insure
We insure You up to the Sum Insured shown for Policy 1 on the Schedule, against
ACCIDENTAL LOSS or DAMAGE to Your Ins ured Property which occurs during the Period
of Insurance.
…
Exclusions – what we do not insure
1 We will not pay for loss or damage
…
c caused by lack of maintenance, rust, oxidation, corrosion, Wear, Tear, fading, gradual
corrosion or gradual deterioration, concrete or brick cancer, developing flaws, wet or
dry rot, or failure to maintain You Insured Property in a reasonably good state o f repair.
d caused by non-rectification of an Insured Property defect, error or omission You were
aware of, or should reas onable have been aware of .
…
2 We will not pay for:
…
b the cost of rectifying faulty or defective materials or faulty or defective workmanship;
3.2 Reports referenced
Record Key points
Applicant’s building
consult ant (B)
General Condition
Report
7 Feb ruary 2007
Inspection to report on general condition of building
Building is in fair condition for its age with general deterioration
throughout and lack of adequate maintenance – work required
in various areas including to windows
Windows are frameless set into concrete structure –
deterioration is evident to glass coating, which appears
distorted on the outer face.
No evidence or reports of window leakage
Windows are in reasonable weather - tight condition, but
deterioration of the glass coating is detracting from the overall
appearance of building and effectiveness of coating to prevent
solar radiation
It appears coating has been damaged during window cleaning
and general wear and tear
Applicant’s quantity
surv eyor (SP)
Building upgrade
estimate
Coating to existing windows has been damaged due to
leaching of salt from concrete render. It appears this render
has not been sealed
Other options are available but likely to be cheaper to replace
windows
Case No: 384841 Determination Page 6 of 8
25 March 2010 Cost to remove existing glazing, including grinding out existing
grout and caulking - $23,500
Cost of new commercial section aluminum framed fixed
windows (double glazed) - $258,500
Council Emergency
Stop Order
6 Aug u s t 2013
External glass panels to the t op 3 rd level have shattered and
there are other loose and fractured panels that may collapse
without warning and cause serious injury.
There are numerous structural glass fin backings supporting
the external glass panel vertical joins on the first three l evels
that contain inadequate fixings that may cause further pane l s
to collapse.
Broken glass has fallen onto the first level footpath canopy that
may blow off onto passing pedestrians.
Local council’s
structural engineer
( H )
Report
6 Aug ust 2013
Building damage - inspection carried out 6 Aug ust 2013 to
recommend Make Safe Work
Several panes of glass fallen from NW a n d SW corners
Glass panels supported by glass fins which are fixed into steel
brackets into building frame top & bottom
In area where glass p anels have fallen, a mixture of bracke ts
has been used to fix the fin s to the top of building – original
fixings were imbedded into building and new fixings have been
bolted into structure – suggests glass panels previously
replaced due to problems
Most o f damage occurred on 3 rd fl oor of the 4 floor building
Ist fl oor showed 1 glass pane has broken previously and
timber hoarding had been provided in this area – new
replacement pane was evident
1 st fl oor NW corner showed 1 fin was moving at the base and
ex cessive flexing of glass panels was occurring either side of
fin.
Several other areas of water damage and deterioration were
evidence in the building – particularly around window areas.
Recommend that one loose fin supporting glass on 1 st fl oor
NW corner be supported by temp orary props
Recommend a glazing contractor conduct audit to determine
condition of glazing to all areas of building, and building
consultant inspect water damage areas around windows
FSP’s assessor (P)
Preliminary analysis
report
22 August 2013
Glass breakage causation – “Maintenance issues associated
with the glazing servicing the upper levels of the building were
exacerbated by high winds resulting in several large elevated
glass pane to dislodge and fall onto the streetscape.”
Complex has sustained previous similar incidents of glass
breakage with pre - existing hoarding evident. Crude, reactive
attempts at remedying the deteriorated nature of the glazing
fixings within the frames were noted and observed to have
limited/negligible effect at securing glazing
During inspection, adjustor personally identified that light
pressure of a hand upon the glass was sufficient to rattle
panes in the frame – at present, panes are unstable and could
Case No: 384841 Determination Page 7 of 8
fall
General maintenance of complex appears po or, particularly
the vacant upper level offices spaces. Roof drainage appears
unmonitored with large volume of stagnant water, general
debris, aged graffiti and avian occupation observed
Proximate cause – gradual deterioration, structural defects,
movement etcetera
It would appear the damage is not the direct result of an
accident or claimable event and does not appear to comprise
an admissible claim.
Damage as claimed appears to be within the ambit of, but not
limited to, excluded perils 1c, 1d, 1g, 1m, 2b .
Applicant’s building
consultant ( F )
Report
11 April 2014
Inspection to assist owner highlight probable cause of building
defect which appeared as result of fixed window pane blowing
in and smashing in Aug ust 2013 during high wind s
Visual inspection only (no tests) on windows after
repair/replacement
All damaged windows had been replaced and all glass
strengthening fins replaced and/or repaired under
design/direction of structural engineer
Difficult to ascertain exactly what took place at the time (that
d amage occurred)
Discussion was held with structural engineer to establish his
observations at the time and his reason for the increased fixing
method used in the repair
Likely to have been no signs of any deterioration of concrete
dado style walls supporti ng windows at the time, and no
repairs since. Windows are in original condition.
Meth od of installing glass fins as a strengthening method is
not un usual – design methods can vary but single method
used for all windows in this building – no reason to expec t any
alternative method
Ground floor (internal) fins examined to assess original
installation – inserted into a 20mmx13mm rebate in concrete,
backfilled with cement mortar and some recently topped with
silicon
All fins are located at the flexible silicon butt joins between
panes
Likely no indication of possible failure of window installation
prior to it occurring. No deterioration of concrete wall
existed/exists where glass inserted. No fins are fractured or
defective at or around concrete/glass junction
F ins appear to have been poorly founded and connected to
the concrete support wall. T here is no evidence of silicon
being used to install fin s . It is likely the fins were installed with
grout filler
Grout filler is brittle and would not provide required resistance
under adverse conditions
Broken glass panels have occurred to one side of a glass
pane butt joint filled with flexible silicon
Case No: 384841 Determination Page 8 of 8
Probable that first weakness occurred at the glass fin fixing
and cracking the minimal grout filler
Flex of window at the butt end joint combined with additional
wind loads have then caused windows to blow into building,
the first window providing even greater loads to allow
subsequent windows to break and fall
Additional stainless steel angle fixtures together with silic on
filling now applied to new and existing fins is a vastly better
fixing to withstand wind loads
Summary – window breakage believed to be as a result of
poor standard of fixing which may have been acceptable at the
time but would not be approved today. Brittle grouting used is
not sufficient to provide support required. Doubtable any fault
occurring could have been foreseen until fins broke away
FSP’s assessor (P)
Report 3
9 May 2014
Retrospective report by B does not unequivocally verify
circumstance surrounding claim
Principal factor is the inadequate/defective fixing of the
windows/window fins. This was readily observable.
Redesign by structural engineer testifies to the defective
nature of windows.
Storm/tempest and high wind not a factor in failur e of windows.
Comprehensive evidence of previous problems with glazing
and pre - existing knowledge of same is unequivocal.