Determination 382671

Liability for roof rectification and predecessor insurer's substandard works

FirmFinancial Firm (Unknown - Insurer)
Decided2015-08-19
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed$41,405
SourceAFCA PDF

Summary

The Applicant asked the FSP to fund roof rectification to current building standards, relying on a 2006 claim and on works done by a predecessor insurer after a 1990 cyclone. AFCA found the FSP not liable on either basis.

The policy excludes inherent defects and non-compliance alone is not covered, and any claim about the predecessor's 1990/91 works is probably time-barred under the Limitation of Actions Act 1974 (Qld).

Issues

Subjects and remedies

home or building damagenatural disasterno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination General Insurance - Domestic Insurance - Home Building - Service - Service quality Case number : 382671 19 August 2015 1 Overview 1.1 Dispute A dispute has arisen in relation to whether the FSP is responsible for carrying out rectification works in order to bring the Applicant‟s roof up to current building standards. The Applicant says the roof was originally repaired/replaced in 1990/1 by her then insurer (CC). She says CC was then acquired by the FSP. The Applicant believes the FSP is liable for the rectification works on two grounds:  If CC did not repair the roof in line with applicable building standards in 1990/1, as the FSP acquired CC, it should be liable to rectify same.  If CC did repair the roof in line with applicable building standards in 1990/1, the FSP is responsible to undertake rectification works under the claim lodged with it (as her then current insurer) in 2006. 1.2 Issues and key findings Is the FSP liable for any substandard works undertaken by CC? The FSP is not liable for any substandard works undertaken by CC because:  it cannot be established it assumed liability for the Applicant‟s CC policy  it cannot be established works undertaken by CC were substandard  on the information provided, the Limitation of Actions Act probably applies applies to de feat the Applicant‟s claim. Is the FSP liable for roof rectification works under the 2006 claim? The FSP is not liable for roof rectification works under the 2006 claim as the policy does not provide cover for inherent defects in isolation. 1.3 Determination This Determination is in favour of the FSP. The FSP is not liable for rectifying the roof non-compliance issues and not required to take any further action. Case No: 382671 Determination Page 2 of 7 2 Reasons for Determination Timeline of events The facts applicable to this dispute span some 25 years and during which time three insurers (including the FSP) have had varying levels of involvement. In light of this, it is appropriate to first summarise what, from the available evidence, appears to have been the sequence of events to date: Year Event 1990  Cyclone Joy causes damage to the Applicant‟s property. The claim is accepted by CC and associated works include repairs to and/or replacement of the roof. 1990 - 2005  At some point between 1990 and 2005, the FSP acquired CC and in some cases, „in - for ce‟ CC policies. 2006  Cyclone Larry causes damage to the Applicant‟s property. The FSP, who was the Applicant‟s insurer at this time, accepted the claim. Associated works did not include any roof repairs. 2009  The Applicant contacted the FSP to advise the carport and patio roof had not been repaired. During subsequent investigations it was identified that the roof was not compliant with associated building standards. The Applicant was previously unaware of this. 2011  Cyclone Yasi caused further crackin g to the brickwork. The Applicant lodges a claim with her current insurer, EE. 2013  EE also confirms the roof was not compliant with current roofing standards and says it is not liable for associated rectification works. 2014  The Applicant approaches the FSP with her current claim in relation to rectification of the roof non - compliance issues. 2.1 Is the FSP liable for any substandard works undertaken by CC? It is u nclear whether FSP assumed liability for Applicant’s CC policy The Applicant submits that if CC did not repair the roof in line with applicable building standards in 1990/1, as the FSP acquired CC, it should be liable to rectify same. The FSP accepts it acquired CC following the Applicant‟s claim in 1990. It also accepts it assumed liability for s ome „in force policies‟. That said, whether it assumed liability for the Applicant‟s particular policy is unable to be established with any level of certainty. Due to the time that has since elapsed, neither party have been able to obtain any comprehensive information in relation to the Applicant‟s CC policy, and so whether any liability was assumed by the FSP in relation to same. Case No: 382671 Determination Page 3 of 7 Even if FSP did assume liability, Limitation of Actions Act means no remedies are available The FSP submits that, due to the time elapsed, any liability it may have borne from the claim with CC in 1990 falls outside the period dictated by the „Statute of Limitations Act‟. I note the relevant Act in Queensland is the „Limitation of Actions Act 1974‟ (the Act). The Act precludes the availability of any remedies for a breach of contract (whether by CC or the builder) not commenced within 6 years of the breach actually occurring ie, in 1990/1 when the roof repairs/replacement took place. Therefore, notwithstanding the fact the Applicant was unaware of any building compliance issues during the relevant period, it appears probable any remedy for the same are no longer available. Even if the Applicant was able to establish the necessary factual matrix to apply successfully to the Courts to extend the limitation period, there still must be evidence to establish a right of action Due to the time elapsed, the exact nature of the works completed in 1990/1 are unable to be established with any level of certainty. The Applicant has been able to make contact with the contractor who completed the associated works. However, the contractor (understandably) no longer has associated paperwork. The contractor could only suggest work would have been completed in line with instructions provided and in accordance with applicable building standards. Therefore, from the information currently available it does not appear the Applicant could establish a cause of action (sub-standard works) against any party. For these reasons, I am satisfied, on the material provided that on the balance of probabilities, the FSP is not liable for any substandard works undertaken by CC. 2.2 Is the FSP liable for roof rectification works under the 2006 claim? No evidence of roof damage in 2006 There is no dispute the FSP accepted the Ap plicant‟s claim for property damage in 2006 following Cyclone Larry. The Applicant submits that if the roof was repaired in line with the applicable building code in 1990/1, the FSP is responsible under the claim in 2006 to bring the roof back in line with the current building standards. The issue facing the Applicant in this scenario is that, whilst the policy provided cover for accidental damage, there is no evidence the roof itself was damaged as a result of cyclone Larry. Policy does not provide cover for inherent defects Whilst accepting the apparent building compliance issues were first identified as part of this 2006 claim (albeit some years later), this was discovered in relation to investigating other damage sustained at the property. Case No: 382671 Determination Page 4 of 7 On this basis, the FSP says the building compliance issues are unrelated to the claim and cannot be considered under the terms of the policy. In other words, the FSP says there is no cover allowed for under the policy in instances relating solely to non-compliance issues being identified. Indeed, the policy specifically excludes any damage resulting from such „inherent defects‟. For these reasons, I am satisfied, on the balance of probabilities, the FSP has not erred in its position on this point and so not liable for roof rectification works under the 2006 claim. Case No: 382671 Determination Page 5 of 7 3 Supporting information 3.1 FOS approach to this dispute General information As advised to the parties, FOS has considered it appropriate to expedite the dispute in accordance with the Operational Guidelines to the FOS Terms of Reference. This dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination. A full exchange of the relevant information has taken place between the respective parties and each party has had the opportunity of addressing any issues raised. I have decided this case on its merits, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions. All of the provided material has been read and considered. The parties have raised numerous issues in their submissions to the Service. For the purpose of this Determination, commentary is restricted to only those issues considered relevant to the outcome. Prima facie claim There is an onus on an insured to establish on the balance of probabilities that a claim fits the definition of an insured event. This is known as a prima facie claim. Should this onus be discharged, it is then the responsibility of the insurer to establish the application of any exclusion on which it relies to deny the claim. 3.2 Relevant extracts from expert reports Report Key points FSP’s loss adjuster (C) 18 June 2009  Cracking of the patio brick wall has resulted from lifting of the front patio roof and recommend that an engineer inspect the wall and report on the probable cause. FSP’s engineer (PD) 12 August 2009  Inspected property 16 July 2009.  Current ro of framing was found to only just comply with current Australian standards, however the fixing of the battens to the rafters is unknown and should be investigated further to ensure compliance. FSP’s building report (N) 15 September 2009  Owner indicated ro of renewed after earlier cyclone by local plumbing firm .  Where cracking occurred, revealed no beam spanning the veranda section only rafters cantilevered over the existing top plate . FSP’s engineer (PD) 27 October 2009  Support spanning beam across the veranda was not present to the dwelling; rafters were cantilevering; a number of roof hold down ties were compromised .  Cracking to the brickwork is as a result of overstressing due to uplift by the rafter members .  Current structure exceeds the overhang . Case No: 382671 Determination Page 6 of 7  St rongly advise that the home owners seek rectification work to ensure compliance with current standards .  Also recommend that the insured consider a thorough inspection by a builder to the current roof framing to check for compliance and structural integrity in accordance with Australian Standards. FSP’s loss adjuster (C) 28 October 2009  The appointed engineer (PD) confirms the roof frame does not comply with current Australian Standards. The engineer recommends a thorough inspection by a builder to check th e current roof framing for compliance and structural integrity in accordance with Australian Standards.  This issue is not related to Cyclone Larry but is more so now related to the change in building codes from the time when the home was constructed. FSP’s loss adjuster (C) 8 June 2010  The engineer who attended the premises believed the damage to the patio wall resulted from overstressing due to uplift of the rafters.  The roof frame does not comply with Australian standards and a thorough inspection by a builder is recommended to check the current framing for compliance and structural integrity.  Until such time as the roof framing is upgraded to current building code, the pressure load on the front wall will continue to cause cracking.  The FSP are not p repared to carry out any further repairs until the roof frame has been upgraded. Applicant’s plumber 28 May 2013  A copy of the report from C confirming the brick wall was damaged as a result of uplift forces on the roof rafters connected to the wall was provided.  He has not come across a similar situation where an insurer requires the insured to complete repairs to a roof structure as a result of cyclonic uplift. He has completed numerous roof replacements for [C] in which uplift was responsible for roof replacement and as part of that process, associated work to bring the associated tie downs up to the current code were completed.  Rectification quote in the amount of $41,405.01. EE’s Causation Inspection report (S) 3 October 2013  It is the builder‟s opin ion that the rectification (tie down) of the roof frame carried out during rectification works in 1990 is inadequate and unless rectified the entire roof frame is susceptible to uplift related damage. 3.3 Limitation of Actions Act 1974 (Queensland) “ 10 Actions of contract and tort and certain other actions (1) The following actions shall not be brought after the expiration of 6 years from the date on which the cause of action arose” Case No: 382671 Determination Page 7 of 7 3.4 FSP policy exclusion “ When we will not pay a claim under your policy This policy does not cover loss, liability, injury or damage: … g. Inherent defects caused directly or indirectly through inherent defects, faulty design, structural defects or poor workmanship”