Storm damage rebuild cash settlement amount
Summary
A storm-damaged home was uninhabitable and the parties could not agree the rebuild cost. AFCA ordered a cash settlement of $2,650,000 plus reimbursement of expert report costs of $9,460, with interest on the report amounts.
The FSP scope of works was inadequate and the claim handling contributed to the loss, so a cash settlement with a margin for error was the fairest resolution.
Issues
- Claim amount dispute primary · upheld“The FSP is required to pay the Applicant the sum of $2,650,000 to meet the substance of its obligations.”
- Poor claim handling secondary · upheld“The Panel is of the view that the FSP's management of the claim has contributed to the deterioration of the property.”
Subjects and remedies
home or building damagenatural disasterpay claimpay interest
Related
All Financial Firm (Unknown - Insurer) determinations · Find similar determinations
Text of the determination
Determination
Case No: 382580 Determination Page 1 of 4
Case number: 382580 2 7 October 2015
1 Overview
1.1 Dispute
This matter arises from the Applicant’s claim under his Home Building and Contents
Insurance Policy, held with the Financial Service Provider (FSP), following a storm
and damage to his property in March 2011.
The dispute has had a long and regrettable history and the parties have been unable
to agree upon the extent of the FSP’s obligations to resolve the dispute.
1.2 Issue and key findings
What is the extent of the FSP’s obligations ?
The FSP is required to pay the Applicant the sum of $2,650,000 to meet the
substance of its obligations.
1.3 Determination
This Determination is in favour of the Applicant.
Within 14 days of notification of acceptance by the Applicant of this Determination,
the FSP is to pay the Applicant the sum of $2,650,000 in respect of all matters (save
for the question of expert reports) arising from the storm event, the claim and dispute
between the parties.
The FSP is not required to pay interest on this amount.
The FSP is to pay the Applicant a further sum, in relation to reports obtained by the
Applicant in support of his claim.
The Applicant is to provide the FSP with proof of payme nt of these amounts. The
FSP is to pay interest, calculated in accordance with the Insurance Contracts Act
1984 (the Act), from the date the Applicant paid these amounts to the date of
settlement by the FSP.
Case No: 382580 Determination Page 2 of 4
2 Reasons for Determination
There has been a full exchange of material between the parties and each party has
had the opportunity of addressing the issues that arise from the material exchanged.
This Determination follows consideration of all of the information exchanged and is
based on what is fair in the circumstances, having regard to the relevant legal
principles, terms of the policy, good industry practise and where applicable, prior
Determinations.
As part of the dispute process, the Panel Chair attended with both parties, on two
occasions, in an effort to resolve the dispute. These meetings facilitated an exchange
of information and position, but unfortunately did not resolve the dispute.
The parties have agreed to the Service having jurisdiction to determine this dispute,
notwithstanding that the amounts concerned exceed what would normally be
provided for within the Service’s Terms of Reference.
2.1 What is the extent of the FSP’s obligations ?
There is no dispute that the property sustained storm related damage which was
covered under the policy.
It has been agreed by the parties that the insured property is now uninhabitable and
the only viable solution is the complete demolition of the property and a full rebuild.
The Panel is of the view that the FSP’s management of the claim has contributed to
the deterioration of the property and the Applicant’s loss.
The dispute now centr es around the FSP’s obligations , given the requirement to
return the Applicant to the position which he was in prior to the storm.
The Panel recognises that as a result of this dispute continuing over numerous years
and placing a significant emotional, medical, practical, time and financial strain upon
both parties, but in particular the Applica nt, the relationship between the parties is at
such a point that there need be finality to the dispute between the parties.
The Panel accepts that the relationship between the Applicant and the FSP has
deteriorated to the extent that there is little trust between the parties and little
likelihood that the property could be rebuilt by the FSP without ongoing disputes over
the detail of the rebuild. The Panel agrees that, under the circumstances, a cash
settlement, whilst not a perfect solution, is likely to produce the cleanest and most
efficient resolution to this dispute.
Whilst the Panel acknowledges that the Applicant still must go through the process of
demolishing and rebuilding the home himself, if he chooses to do so, at least any
difficult relationship between the parties will be concluded by this proposed resolution
of the dispute.
The parties have been unable to agree on the amount required to settle this dispute.
The amount will need to be sufficient to cover all of the following aspects of the
dispute:
decontamination and demolition of the existing building
Case No: 382580 Determination Page 3 of 4
replacement of the building on a like for like basis including all fees and costs
associated with that activity
remediation of the site including landscaping
the Applicant’s displacement costs during the demolition and rebuild
the cost of replacing contents damaged as a result of water ingress and/or
contamination
the cost of storing contents off site and transporting those contents between
sites
the reimbursement of professional fees incurred by the Applicant in pursuing
this dispute
an allowance for price escalations throughout the period of the rebuild.
Whilst it can be said that there has been a full exchange of material between the
parties, the Panel is not satisfied that the material exchanged is adequate or
sufficiently accurate to reach a precise assessment of the costs to demolish and
rebuild the Applicant’s home.
The Panel is satisfied from the material exchanged that the Scope of Works relied
upon by the FSP was inadequate and on several occasions, was so demonstrated by
the Applicant to be inaccurate. Further, the Panel is not satisfied that the FSP has
sufficiently supported many of the estimates that are detailed within the FSP’s
material, nor does the Scope of Works reflect the quality of finish in the original
dwelling or represent a like for like replacement, in many instances.
Consequently, the Panel is of the view that the FSP’s offer of settlement is based
upon a statement of works over which there remains considerable doubt and o n a
builder’s quotation which has not been obtained through the normal market tender
process, of the sort one might expect on a building project of this size and
complexity.
On the other hand, the Panel does recognise that in respect to the question of
temporary accommodation, the FSP has allowed for a period beyond the estimated
building period provided for by the FSP’s builders.
In addition, the Panel acknowledges that the FSP has provided for the inclusion of
interest within its efforts to resolve the dispute, despite the quotations allegedly being
current.
The Panel acknowledges the work undertaken by the Applicant in seeking to justify
his position.
In relation to the material provided by the Applicant, the Panel is satisfied that at least
in the areas of the costs associated with the replacement windows, the sauna and
steam room, the bush fire zoning, the scaffolding, site decontamination, the joinery
and the tiling, that the material presented by the Applicant is to be preferred to the
material provided by the FSP. In those areas, the Applicant’s material can be relied
upon and the FSP’s material excluded.
That said, the Panel has also had regard to the methods by which the Applicant has
sought to calculate the plumbing and electricity expenditure and the Panel does not
accept the Applicant’s methods , noting that it does not allow for trade discounts or
the overall builder’s quotation.
Case No: 382580 Determination Page 4 of 4
The Panel accepts that the difficulty in assessing the FSP’s obligations in relation to
the loss, is a result of the incomplete Scope of Works provided by the FSP, the lack
of plans in relation to the proposed rebuild of the Applicant’s home and the absence
of a fair competitive tender process.
A fair competitive tender process would have allowed the Panel to compare apples
with apples, rather than the current situation where the Panel is required to compare
two very different items.
The Panel has had careful regard to all of the material that has been presented and
concluded that it is fair in the circumstances that the FSP resolve all aspects of the
dispute, including matters relating to temporary accommodation and contents, but not
for the cost of the experts’ reports, for the sum of $2,650,000.
In forming this Determination, in particular given the doubts surrounding the basis
upon which the FSP’s offer has been constructed, the Panel has decided that it is
reasonable to allow for a margin for error in the calculation of an appropriate cash
settlement. This is so, particularly given that a cash settlement transfers the risk of
any underquoting, completely to the Applicant.
The acceptance of this Determination by the Applicant and the payment of the above
mentioned sum by the FSP, would bring to an end all matters arising from the storm
event, the claim and the dispute between the parties, save and except for the
question of the cost of the experts’ reports , which the Applicant has advised amount
to $9,460.