Determination 382580

Storm damage rebuild cash settlement amount

FirmFinancial Firm (Unknown - Insurer)
Decided2015-11-27
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded$2,659,460
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

A storm-damaged home was uninhabitable and the parties could not agree the rebuild cost. AFCA ordered a cash settlement of $2,650,000 plus reimbursement of expert report costs of $9,460, with interest on the report amounts.

The FSP scope of works was inadequate and the claim handling contributed to the loss, so a cash settlement with a margin for error was the fairest resolution.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay interest

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 382580 Determination Page 1 of 4 Case number: 382580 2 7 October 2015 1 Overview 1.1 Dispute This matter arises from the Applicant’s claim under his Home Building and Contents Insurance Policy, held with the Financial Service Provider (FSP), following a storm and damage to his property in March 2011. The dispute has had a long and regrettable history and the parties have been unable to agree upon the extent of the FSP’s obligations to resolve the dispute. 1.2 Issue and key findings What is the extent of the FSP’s obligations ? The FSP is required to pay the Applicant the sum of $2,650,000 to meet the substance of its obligations. 1.3 Determination This Determination is in favour of the Applicant. Within 14 days of notification of acceptance by the Applicant of this Determination, the FSP is to pay the Applicant the sum of $2,650,000 in respect of all matters (save for the question of expert reports) arising from the storm event, the claim and dispute between the parties. The FSP is not required to pay interest on this amount. The FSP is to pay the Applicant a further sum, in relation to reports obtained by the Applicant in support of his claim. The Applicant is to provide the FSP with proof of payme nt of these amounts. The FSP is to pay interest, calculated in accordance with the Insurance Contracts Act 1984 (the Act), from the date the Applicant paid these amounts to the date of settlement by the FSP. Case No: 382580 Determination Page 2 of 4 2 Reasons for Determination There has been a full exchange of material between the parties and each party has had the opportunity of addressing the issues that arise from the material exchanged. This Determination follows consideration of all of the information exchanged and is based on what is fair in the circumstances, having regard to the relevant legal principles, terms of the policy, good industry practise and where applicable, prior Determinations. As part of the dispute process, the Panel Chair attended with both parties, on two occasions, in an effort to resolve the dispute. These meetings facilitated an exchange of information and position, but unfortunately did not resolve the dispute. The parties have agreed to the Service having jurisdiction to determine this dispute, notwithstanding that the amounts concerned exceed what would normally be provided for within the Service’s Terms of Reference. 2.1 What is the extent of the FSP’s obligations ? There is no dispute that the property sustained storm related damage which was covered under the policy. It has been agreed by the parties that the insured property is now uninhabitable and the only viable solution is the complete demolition of the property and a full rebuild. The Panel is of the view that the FSP’s management of the claim has contributed to the deterioration of the property and the Applicant’s loss. The dispute now centr es around the FSP’s obligations , given the requirement to return the Applicant to the position which he was in prior to the storm. The Panel recognises that as a result of this dispute continuing over numerous years and placing a significant emotional, medical, practical, time and financial strain upon both parties, but in particular the Applica nt, the relationship between the parties is at such a point that there need be finality to the dispute between the parties. The Panel accepts that the relationship between the Applicant and the FSP has deteriorated to the extent that there is little trust between the parties and little likelihood that the property could be rebuilt by the FSP without ongoing disputes over the detail of the rebuild. The Panel agrees that, under the circumstances, a cash settlement, whilst not a perfect solution, is likely to produce the cleanest and most efficient resolution to this dispute. Whilst the Panel acknowledges that the Applicant still must go through the process of demolishing and rebuilding the home himself, if he chooses to do so, at least any difficult relationship between the parties will be concluded by this proposed resolution of the dispute. The parties have been unable to agree on the amount required to settle this dispute. The amount will need to be sufficient to cover all of the following aspects of the dispute:  decontamination and demolition of the existing building Case No: 382580 Determination Page 3 of 4  replacement of the building on a like for like basis including all fees and costs associated with that activity  remediation of the site including landscaping  the Applicant’s displacement costs during the demolition and rebuild  the cost of replacing contents damaged as a result of water ingress and/or contamination  the cost of storing contents off site and transporting those contents between sites  the reimbursement of professional fees incurred by the Applicant in pursuing this dispute  an allowance for price escalations throughout the period of the rebuild. Whilst it can be said that there has been a full exchange of material between the parties, the Panel is not satisfied that the material exchanged is adequate or sufficiently accurate to reach a precise assessment of the costs to demolish and rebuild the Applicant’s home. The Panel is satisfied from the material exchanged that the Scope of Works relied upon by the FSP was inadequate and on several occasions, was so demonstrated by the Applicant to be inaccurate. Further, the Panel is not satisfied that the FSP has sufficiently supported many of the estimates that are detailed within the FSP’s material, nor does the Scope of Works reflect the quality of finish in the original dwelling or represent a like for like replacement, in many instances. Consequently, the Panel is of the view that the FSP’s offer of settlement is based upon a statement of works over which there remains considerable doubt and o n a builder’s quotation which has not been obtained through the normal market tender process, of the sort one might expect on a building project of this size and complexity. On the other hand, the Panel does recognise that in respect to the question of temporary accommodation, the FSP has allowed for a period beyond the estimated building period provided for by the FSP’s builders. In addition, the Panel acknowledges that the FSP has provided for the inclusion of interest within its efforts to resolve the dispute, despite the quotations allegedly being current. The Panel acknowledges the work undertaken by the Applicant in seeking to justify his position. In relation to the material provided by the Applicant, the Panel is satisfied that at least in the areas of the costs associated with the replacement windows, the sauna and steam room, the bush fire zoning, the scaffolding, site decontamination, the joinery and the tiling, that the material presented by the Applicant is to be preferred to the material provided by the FSP. In those areas, the Applicant’s material can be relied upon and the FSP’s material excluded. That said, the Panel has also had regard to the methods by which the Applicant has sought to calculate the plumbing and electricity expenditure and the Panel does not accept the Applicant’s methods , noting that it does not allow for trade discounts or the overall builder’s quotation. Case No: 382580 Determination Page 4 of 4 The Panel accepts that the difficulty in assessing the FSP’s obligations in relation to the loss, is a result of the incomplete Scope of Works provided by the FSP, the lack of plans in relation to the proposed rebuild of the Applicant’s home and the absence of a fair competitive tender process. A fair competitive tender process would have allowed the Panel to compare apples with apples, rather than the current situation where the Panel is required to compare two very different items. The Panel has had careful regard to all of the material that has been presented and concluded that it is fair in the circumstances that the FSP resolve all aspects of the dispute, including matters relating to temporary accommodation and contents, but not for the cost of the experts’ reports, for the sum of $2,650,000. In forming this Determination, in particular given the doubts surrounding the basis upon which the FSP’s offer has been constructed, the Panel has decided that it is reasonable to allow for a margin for error in the calculation of an appropriate cash settlement. This is so, particularly given that a cash settlement transfers the risk of any underquoting, completely to the Applicant. The acceptance of this Determination by the Applicant and the payment of the above mentioned sum by the FSP, would bring to an end all matters arising from the storm event, the claim and the dispute between the parties, save and except for the question of the cost of the experts’ reports , which the Applicant has advised amount to $9,460.