Text of the determination
Determination
General Insurance - Domestic Insurance - Home Building - FSP Decision - Denial of
Claim
Determination
Case No: 381380 Determination Page 1 of 9
Case number : 381380 22 May 2015
1 Overview
1.1 Dispute
In January 2013, the Applicants lodged a claim under their home insurance policy
with the Financial Services Provider (FSP) for cracking and movement damage to
their property. The Applicants believed the damage had been caused by a leaking
pipe which had been located and repaired some ten months earlier.
The FSP accepted the Applicants’ claim and authorised repairs to the property,
including resin injections to stabilise the concrete slab. However, further damage
became apparent after the first stage of the repairs. The Applicants say the FSP
should be responsible for completing the original works and repairing the
additional damage (at an estimated cost of approximately $170,000).
The FSP has offered the Applicants a cash settlement of $45,000, to pay for the
cost of completing the original works, as well as that part of the additional damage
which it considers was caused by the resin injections. However, the FSP says it is
not liable for any additional costs.
1.2 Issues and key findings
Is the cash settlement offered by the FSP fair and reasonable?
The FSP accepted liability for the damage identified by the Applicants’ engineer
(A) as having been caused by the burst pipe and authorised its builder to
commence repairs based on A’s scope of works. In doing so, it took on the
associated risks.
Accordingly, it remains liable for the costs of completing the works set out in A’s
scope of works, including conventio nal underpinning works given the resin
injections have failed.
The FSP is also liable for repairing the bulk of the additional cracking and
movement damage which, on the balance of probabilities, has been caused by
the resin injection works.
1.3 Determination
This Determination is substantially in favour of the Applicants.
The FSP is to pay the Applicants the amount of $167,498 in full and final
settlement of their claim.
Case No: 381380 Determination Page 2 of 9
2 Reasons for Determination
2.1 Is the cash settlement offered by the FSP fair and reasonable ?
Policy provides cover for burst pipe subject to exclusions
The Applicants’ policy provides cover for loss or damage to their property caused
by the events listed in the policy (including water leaking or escaping from a pipe),
subject to the exclusions set out in the policy.
The policy contains general exclusions for loss or damage arising from:
gradual deterioration or erosion;
settling, shrinking or expansion in buildings, foundations or walls; and/or
subsidence or landslide (unless it happens immediately as a result of an
earthquake or explosion).
Claim arises from burst pipe in early 2012
After discovering water pooled at the side of their home in early 2012, the
Applicants engaged a plumber who discovered a burst water pipe behind the toilet
cistern in the downstairs bathroom.
The Applicants’ plumber confirmed that water leaking from the pipe had filled the
foundations of the home, saturating the sub-soil under the concrete slab. The
Applicants’ neighbours (who had seen water entering their courtyard) confirmed
that the pipe had been leaking for approximately two weeks.
When the Applicants initially notified the FSP of the burst pipe, they were told that
they were unable to lodge a claim under the policy, as the leak had not caused
any damage to the house.
However, the Applicants subsequently noticed cracks in the ground floor
bathroom, kitchen and bedroom, which slowly expanded to the external walls
shortly after. As the Applicants believed this damage was due to the burst pipe,
they lodged a claim under the policy in January 2013.
FSP accepted Applicants’ original claim and authorised repairs
The FSP initially denied the Applicants’ claim based on a report from its engineer
(S) which concluded that the cracking and movement damage to the property had
been caused by differential foundation movement due to naturally occurring
variations in the moisture content of the foundation soils over an extended period
of time.
The FSP’s engineer (S) acknowledged that the differential movement was most
pronounced in the bedroom and bathroom near the burst pipe. However, while S
noted that the burst pipe may have contributed to the damage, he considered that
there was no hard evidence of this and, in any event, the burst pipe was not the
sole cause of the damage.
The Applicants disputed the FSP’s denial of their claim and obtained a report from
their own engineer (A). In his report dated 22 May 2013, A concluded that the
Case No: 381380 Determination Page 3 of 9
observed damage to the property was consistent with the effects of a localised
water source (the burst pipe) on the moderately reactive clay soils.
In particular, A considered that there was significant foundation moveme nt in the
brickwork on the eastern side of the house, which was consistent with ground
heave (upwards movement) in the centre of the eastern wall (where the burst pipe
was located). A concluded that this heave had caused a significant rotation in the
foundation on the eastern side of the building.
A noted that the absence of damage to the western wall of the house (away from
the burst pipe) indicated that the concrete slab was generally functioning correctly
and was able to withstand normal soil loads.
Fo llowing receipt of A’s report, the FSP reversed its initial decision and accepted
the claim for damage to the eastern side of the property which A had identified as
having been caused by the burst pipe. However, the FSP denied liability for any
other damage to the home.
The FSP subsequently obtained quotations from two of the builders on its panel to
carry out the necessary repairs, in accordance with a scope of works prepared by
A in November 2013.
The FSP initially sought to cash settle the Applicants’ cl aim, due to concerns
raised by one of the builders (D) about ongoing movement issues at the property.
However, after the Applicants expressed concerns about finding a builder to
undertake the repairs, the FSP authorised its other builder (E) to carry out the
necessary works. E had confirmed that he was prepared to guarantee the works.
In his scope of works dated 28 November 2013, A noted that underpinning works
should be undertaken to stabilise the sub-soil area and stop any further
movement, before the repairs of the internal and external cracking and movement
damage could be carried out. Specifically, A indicated that:
the soil should be underpinned using resin injections, to arrest the excessive
movement in the eastern side of the building and the adjacent south-eastern
and north-eastern corners;
a settlement period of three months should be allowed following the injections
to assess the success of this method, before reviewing the underpinned walls
and slab. If the injections had successfully stabilised the sub-soil area, the
internal and external repairs could then be completed;
however, if the sub-soil area had not been stabilised following the resin
injections, it would be necessary to proceed with an alternative conventional
underpinning regime.
The FSP’s builder (E) quoted $59,124 to carry out the necessary works. The first
stage of the works, being the resin injections carried out by a specialist contractor
(U), were completed in February 2014.
However, a dispute arose after the Applicants noticed further cracking following
completion of these works, and sought to have the FSP undertake additional
repairs.
Case No: 381380 Determination Page 4 of 9
Dispute concerns extent of FSP’s liability for further repairs
Based on advice provided by their engineer (A), the Applicants believe that the
re sin injections undertaken by the FSP’s contractor (U) have not effectively
stabilised the sub-soil area and arrested the movement in the eastern side of the
house.
Accordingly, the Applicants say that the FSP should be required to fund the costs
of the conventional underpinning works which need to be undertaken to effectively
repair the property, at an estimated cost of over $120,000.
The Applicants also want the FSP to repair all of the additional cracking damage
to the property identified following the resin injection works, as well as the original
damage which the FSP had previously accepted as having been caused by the
burst pipe (at a total cost of approximately $50,000).
After being notified of the additional cracking damage to the property, the FSP
engaged a building consultant (IC) and another engineer (T) to determine the
cause of the additional damage.
Both the FSP’s building consultant (IC) and engineer (T) concluded that none of
the additional damage had been caused by the burst pipe in early 2012, and only
a small portion of this damage was due to the resin injections carried out by U in
February 2014.
Both experts noted a number of factors which they considered were contributing
to the ongoing movement at the property and queried whether all of the damage
identified as part of the original claim had been caused by the burst water pipe in
early 2012. In particular, T queried the findings of the Applicants’ engineer (A) that
the damage was the result of heave to the eastern side of the building. T noted
that A’s conclusions were inconsistent with the results of T’s level surveys in May
2014.
Based on discussions with the contractor (U) who carried out the resin injection
works, the FSP’s engineer (T) confirmed that these works were limited to the
northern end of the house and did not extend to the eastern side of the house or
the south-eastern corner. Accordingly, these works did not fully comply with A’s
scope of works.
In any event , the FSP’s building consultant (IC) concluded that the resin injection
works would have been inadequate to stabilise the site under any circumstances,
given the extent of ongoing movement. IC considered that A’s original scope of
works provided insufficient detail about the underpinning works to be undertaken
(by whichever method) and was based on inadequate investigations. In particular,
he noted that A had not undertaken level surveys or core moisture sampling.
While IC confirmed that the works undertaken to date had failed to return the
eastern side of the property to a satisfactory state, he also doubted whether the
full underpinning works proposed by the Applicants engineer (A) would be
appropriate.
Based on the findings of its building consultant (IC) and engineer (T), the FSP
considers that its liability for any further repairs is limited to:
Case No: 381380 Determination Page 5 of 9
the repair of the initial internal and external damage to the property which it
originally accepted as having been caused by the burst pipe; and
the repair of the limited additional cracking damage which it accepts has been
caused by the resin injection works in February 2014.
The FSP has advised that its builder (E) is no longer willing to undertake any
further repairs as, given the findings of the FSP’s experts, E is unable to warrant
his work.
Accordingly, the FSP has offered to cash settle the Applicants for $45,000. This
amount represents the amount of E’s original quote ( $59,124) less the amount
paid to U for the resin injection works ($19,000), plus an allowance for the repair
of the additional damage to the upstairs bedroom which the FSP accepts was
caused by the resin injections in February 2014.
FSP is bound by prior acceptance of claim
As outlined above, the FSP accepted liability for the cracking and movement
damage to the eastern side of the Applicants’ property in 2013, based on the
findings of the Applicant’s engineer that the damage had been caused by the
burst pipe. The FSP also authorised repairs to the property based on A’s scope of
works.
Following lodgement of the claim in January 2013, the FSP had ample opportunity
to engage appropriately qualified consultants to inspect the property and
determine the cause of the claimed damage. After considering the reports
prepared by the consultants appointed by each party, the FSP ultimately decided
to accept liability for the claim based on A’s report .
In circumstances where the works authorised by the FSP have been partly
completed, it is not open to the FSP to revisit its liability for the claimed damage,
based on reports provided by different consultants after the works had already
commenced.
Further, once the FSP e lected to repair the property in accordance with A’s scope
of works, it effectively assumed the financial and other risks associated with
completing those works. An insurer who elects to undertake repairs will not
generally be entitled to later elect to cash settle the claim.
The Applicants have relied on the position adopted by the FSP in accepting
liability and authorising repairs and therefore the FSP remains bound by its prior
actions.
On this basis, the Panel is satisfied that the FSP remains liable for the costs of
completing the repair of the initial damage identified by A as having been caused
by the burst pipe, in accordance with the scope of works prepared by A.
However, the Panel notes that the Applicants have indicated that they are willing
to accept a cash settlement rather than having the FSP carry out the remaining
repairs, provided that the cash settlement amount is sufficient to fund the
necessary works.
Case No: 381380 Determination Page 6 of 9
In these circumstances, and given the fact that the builder appointed by the FSP
is no longer willing to continue, the Panel considers that a cash settlement is
appropriate.
FSP is liable for costs of conventional underpinning works and repair of
original internal and external damage
As outlined above, when the FSP authorised its builder to carry out repairs in
accordance with A’s scope of works, it took on the risk s associated with
completing those works. Such risks included the risk that the initial regime of resin
injections undertaken by U may not be effective to sufficiently stabilise the eastern
side of the property.
The engineers (A and T) appointed by both parties agree that the resin injections
have not been effective, although they may disagree about the reasons why, and
the appropriate next steps.
The scope of works prepared by A and approved by the FSP in late 2013
expressly foreshadowed the potential need for conventional underpinning works
in the event that the resin injections provided unsuccessful. Accordingly, the FSP
remains liable for the costs associated with completing these works.
The Applicants’ engineer (A) says that the FSP asked him to obtain quotes from
underpinning contractors who would be willing to carry out the necessary works.
Accordingly, he obtained quotes from two builders (H and HT) for $121,252 and
$130,955 respectively. However, the FSP subsequently denied liability for these
works.
The FSP says that it has reviewed the underpinning quotes and considers that
they are excessive, as they provide for the underpinning of the entire house.
However, the Applicants’ engineer (A) has confirmed that H’s quote for $121,252
is for the underpinning works to the eastern side of the house only, as well as the
repair of the internal and external damage set out in his original scope of works
dated 28 November 2013.
On this basis, the Panel considers that the FSP should be required to cash settle
the Applicants for the amount of H’s quote ($121,252).
Given the complex nature of the works required, the Panel considers that the final
cash settlement amount should also include A’s fees for overseeing the
underpinning works (estimated to be $5,830 (including GST)).
Given the currency of the quotations provided, the FSP is not required to pay
interest on the cash settlement amount.
FSP is liable for costs of repairing bulk of additional damage
As outlined above, the Applicants identified additional cracking and movement
damage at the property following completion of the resin injection works. This
damage is detailed in a scope of works prepared by the Applicants’ engineer (A)
in July 2014. The Applicants have obtained a quotation for $50,520 from their
builder (H) for the repair of the additional damage.
Case No: 381380 Determination Page 7 of 9
The Applicants say that the additional damage has occurred solely as a result of
the resin injection works carried out by U in February 2014. They say that the
additional damage occurred on the day the injection works were undertaken and
consider that this may have been due to the fact that U did not carry out the resin
injections in accordance with the scope of works (potentially leaving the property
“unbalanced”).
The Applicants’ engineer (A) has confirmed that the additional cracking damage
was not evident when he attended the property in 2013. A says that the additional
damage has occurred as a result of the reversal of the ground forces induced as
part of the resin injection works. A reinspected the property in March 2015 and
confirmed that there had been no discernible change to the areas where the
additional damage occurred since his previous inspections in April and July 2014.
The FSP’s building consultant (IC) and engineer (T) dispute A’s findings that the
additional damage was caused by the resin injection works.
Both T and IC consider that the areas in which the additional damage was
observed are between 8 metres and 13 metres away from the injection sites and
are therefore too remote for the damage to have been caused by the resin
injections. However, IC notes that the injection works appear to have affected
tape placed on an external wall to monitor further damage, at a location 13 metres
away from the injection site. However, IC dismisses this as essentially
coincidental.
The FSP’s consultants ( T and IC) consider that the bulk of the additional damage
has been caused by ongoing differential foundation movement due to variations in
the moisture content of the surrounding soils. They have identified a number of
factors which they consider are likely to be contributing to this movement,
including the presence of trees on the eastern side of the property, possible
issues with the stormwater drains and downpipes and the manner in which the
building was constructed.
As outlined above, the FSP’s engineer (T) considers that the results of his level
surveys are inconsistent with the initial damage to the property having been
caused by the burst pipe. Accordingly, he says other factors must have caused or
significantly contributed to the cracking and movement damage at the property.
Having carefully considered the available information (including the various
consultants’ reports), the Panel considers that, on the balance of probabilities, the
additional cracking and movement damage was caused by the resin injection
works in February 2014.
While the FSP’s experts have identified various factors which may have
contributed to ongoing foundation movement at the property, the Panel is not
satisfied that there is sufficient independent information available to establish that
such factors were responsible for the bulk of the damage.
In particular, the Panel notes that the specific issues with the stormwater pipes
identified by the FSP’s consultants appear to be relatively minor and are unlikely
to have been the primary cause of the damage. While the FSP’s engineer (T)
Case No: 381380 Determination Page 8 of 9
referred to the potential effects of tree roots on the underground pipes,
subsequent CCTV investigations did not reveal any damage of this nature.
The Panel also notes that the weight which can be given to the findings of the
FSP’s consultants is limited by the fact that both T and IC did not inspect the
property until after the resin injection works had been completed. Accordingly,
unlike the Applicants’ engineer (A ), they were not able to directly compare the
damage before and after these works.
To the extent that the FSP has been prejudiced as a result, this has occurred as a
result of the approach it adopted in investigating the original claim.
The reports prepared by the various assessors and contractors who inspected the
property during the course of the initial claim in 2013 suggest that the cracking
and movement damage was located primarily at the eastern side of the property.
These reports refer to minimal damage to the western side.
The FSP has referred to evidence of past repairs sighted during its initial
investigations into the claim. However, it is unclear whether these repairs
occurred before the pipe burst, or during the period of almost a year between t he
date the pipe burst and the date the Applicants’ claim was lodged.
Nevertheless, the Panel accepts that it is likely that some of the additional
damage at the property has been caused by naturally occurring differential
foundation movement, which is excluded under the policy.
Based on the available information, the Panel considers that it is appropriate to
attribute 20% of the additional damage to such excluded causes.
On this basis, the Panel considers that the FSP should be required to cash settle
th e Applicants for $40,416 (being 80% of the amount quoted by the Applicants’
builder (H) for the repair of this damage).
Case No: 381380 Determination Page 9 of 9
3 Supporting information
3.1 FOS approach to this dispute
This dispute has not been the subject of a FOS Recommendation. Due to the
nature of the dispute, it has been referred directly to a Panel for Determination, in
line with the Operational Guidelines to the FOS Terms of Reference. The Panel
consists of an Ombudsman and two representatives with consumer and insurance
experience.
The Panel has decided this case on its merits, having regard to the relevant law,
good industry practice, codes of practice and previous Financial Ombudsman
Service (FOS) decisions.
There has been a full exchange of all material information relied on for the
purposes of this Determination and each party has had the opportunity to address
any issues raised by the other.
The Panel has reviewed and considered all of the material provided by the
parties. While the parties have raised numerous issues in their submissions, for
the purposes of this Determination the Panel has restricted its commentary to
those issues which it considers directly relevant to the outcome only.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.