Text of the determination
Determination
General Insurance - Domestic Insurance - Home Building - FSP Decision - Claim
Amount
Determination
Case No: 377296 Determination Page 1 of 8
Case number : 377296 1 April 2015
1 Overview
1.1 Dispute
The Applicant lodged a claim under her business insurance policy with the
Financial Services Provider (FSP) after the insured building was damaged by fire
in November 2013.
The FSP accepted the Applicant‟s claim and paid her a total of $490,158.03
(including progress payments) for the costs of repairing the damage to the
building and for loss of rent due to the fire.
The Applicant says the settlement amount should be increased to reflect the cost
of demolishing and rebuilding the property in its entirety. She says she was
required to demolish the building to comply with an order issued by the local
council.
1.2 Issues and key findings
Is the FSP required to increase the settlement amount?
The available information (including the engineers‟ reports) confirms that the
building did not need to be demolished as a result of the fire, but could be safely
and effectively repaired.
The demolition order was issued by the council after the Applicant (as the
property owner) failed to make submissions as to why the property should not be
demolished within the 60 day timeframe provided. The FSP‟s actions in managing
the claim did not cause or contribute to the demolition of the property and
therefore the FSP is not liable for any additional costs arising from the demolition.
1.3 Determination
This Determination is substantially in favour of the FSP.
The FSP is not required to increase the settlement amount, other than as required
to compensate the Applicant for any payments to the council for temporary
fencing in accordance with section 2.1 below.
Case No: 377296 Determination Page 2 of 8
2 Reasons for Determination
2.1 Is the FSP required to increase the settlement amount ?
FSP is liable for reinstatement costs
The Applicant‟s policy provides cover for loss or damage caused by the events
listed in the policy, including fire. The policy also provides cover for accidental
damage not caused by an insured event, subject to the exclusions and conditions
set out in the policy.
Under the terms of the policy, the FSP is required to pay the Applicant the cost of
rebuilding or repairing any damaged part of the insured building to the condition it
was in when new.
This includes additional costs (including demolition) necessarily incurred to
comply with the requirements of any applicable legislation or municipal by-laws.
The Applicant says that:
the cash settlement amount paid to her was calculated on the basis that the
building was able to be repaired and did not need to be completely
demolished;
however, this amount is no longer sufficient to compensate her for her loss, as
the building has since been demolished to comply with an order issued by the
council in June 2014.
Building did not require demolition due to fire damage
The Applicant says that the demolition of the building in June 2014 occurred as a
result of the damage caused by the fire in November 2013.
However, having carefully reviewed the available information (including the
various engineers‟ reports provided), the Panel does not agree that the damage
sustained in the fire necessitated the complete demolition of the building.
The Applicant was concerned that the repairs included in the initial scope of works
prepared by the FSP‟s builder (S) for the repair of the building would not be
adequate, as she had been advised by her builder (FG) that the property was
dangerous and needed to be completely demolished.
Accordingly, the Applicant engaged an engineer (SP) who provided a brief one
page report confirming FG‟s view that the building was unsafe for ongoing works
and needed to be demolished. SP noted that all of the external walls of the
building were in danger of collapse, as they had moved and expanded as a result
of the high temperatures experienced during the fire.
In order to address the Applicant‟s concerns, the FSP app ointed its own engineer
(MC). Based on his inspection of the property, MC concluded that there may have
been some fire-related bowing to the first floor brick wall near the front of the
building. However, he considered that overall there was very little of this type of
Case No: 377296 Determination Page 3 of 8
damage and therefore the bulk of the external brick walls could be salvaged and
targeted demolition only would be required.
The Applicant considered that MC had underestimated the extent of the fire
damage to the walls and continued to be concerned about the FSP‟s proposal to
repair the building. Accordingly, she engaged another engineer (CZ) to confirm
whether the building needed to be demolished.
CZ confirmed that there was significantly more bowing damage to the walls than
had been identified by MC and advised that these sections of the walls needed to
be replaced. However, he also concluded that the building did not require
complete demolition and could be repaired safely and effectively provided
appropriate methods were used.
This was subsequently confirmed by a fourth engineer (DW) appointed by the
FSP in May 2014. DW recommended that a considerable portion of the first floor
walls needed to be demolished, but confirmed that the ground floor walls could be
retained. It appears that the FSP accepted DW‟s findings.
Based on the above, it is apparent that three out of four of the engineers (MC, CZ
and DW) who inspected the building considered that it could be safely and
effectively repaired without requiring complete demolition. While each of these
engineers recognised that the walls were at risk of possible collapse, they
considered that this could be adequately addressed by the use of external
propping and/or lateral bracing.
While the remaining engineer (SP) recommended that the building be demolished
in its entirety, his report is significantly less detailed than those prepared by the
others. Further, there is nothing in SP‟s report to indicate that he considered
whether the risk of collapse could be addressed effectively through the use of
appropriate repair methods to create a safe working environment.
On this basis, the Panel is satisfied that the damage caused by the fire could be
repaired effectively without requiring the complete demolition of the building.
While the local council ultimately ordered that the building be demolished, it did so
only after it had first provided the Applicant with a 60 day period to make
representations as to why a demolition order should not be issued.
Further, the council did not have the benefit of the engineers‟ reports confirming
that the building could be safely repaired provided appropriate safety measures
were implemented.
Accordingly, the fact that the council issued a demolition order does not of itself
establish that the building needed to be demolished due to the fire.
FSP is not responsible for issue of demolition order
For the reasons outlined above, the Panel is satisfied that the building did not
need to be demolished due to the fire. However, due to the issues raised in the
Applicant‟s submissions, the Panel has also considered whether the FSP‟s
Case No: 377296 Determination Page 4 of 8
actions during the course of the claim caused or contributed to the issue of the
demolition order by the council.
The council notified the Applicant of its intention to issue an order to demolish the
property by way of a notice issued on 21 March 2014 on the basis that the
building was unsafe and may become a danger to the public in its then current
condition. The council advised the Applicant that the order would be issued unless
she could provide reasons why the building should not be demolished by 20 May
2014.
The Applicant did not make any submissions to the council during this period.
Accordingly, the council proceeded to issue the demolition order on 10 June
2014.
The Panel accepts that, during this period, the Applicant was focussed primarily
on agreeing to an appropriate scope of works with the FSP and finalising the
settlement amount. The Panel also accepts that the Applicant provided the FSP
with a copy of the notice and the subsequent demolition order, in an attempt to
expedite the resolution of her claim.
However, it was the Applicant (as the owner of the property) and not the FSP who
was required to respond to the notice issued by the council in relation to the
proposed demolition. Further, under the terms of the policy, the Applicant had an
obligation to the FSP to take reasonable steps to prevent any further loss or
damage to the property.
Prior to the expiry of the 60 day period specified by the council, the Applicant had
received a detailed and comprehensive report from her own engineer (CZ) which
confirmed that the property did not need to be completely demolished.
In these circumstances, it was the Applicant‟s responsibility to provide CZ‟s report
to the council to show that the building did not need to be demolished, and to
keep the council updated as to the status of the proposed repairs . It was her
failure to do so that ultimately led to the demolition of the building.
The Panel accepts that the first engineer appointed by the FSP (MC) significantly
underestimated the extent of the brickwork that needed to be removed and
replaced. Further, there may be steps which the FSP could have take n to assist
the Applicant in her dealings with the council.
However, the ultimate responsibility for dealing with the council remained with the
Applicant as the owner of the property. This responsibility arose independently of
any negotiations with the FSP in relation to the settlement of the claim.
The Panel considers it highly likely that, had the Applicant advised the council of
the status of her claim and provided a copy of the engineers‟ reports , she could
have prevented the issue of the demolition order on 10 June 2014. As it turned
out, the Applicant and the FSP reached in principle agreement on most of the
items included in the settlement amount very soon after the appeal period
expired.
Case No: 377296 Determination Page 5 of 8
For the reasons outlined above, the Panel is satisfied that the issue of the
demolition order occurred as a result of the Applicant‟s failure to make
submissions to the council as to why the order should not be issued, within the
applicable timeframe.
FSP did not unreasonably delay settlement of claim
The Applicant says that the issue of the notice by the council in March 2014
occurred because the FSP unreasonably delayed the settlement of her claim.
However, having reviewed the claim history, the Panel does not consider that the
FSP is primarily responsible for these delays.
It is not unusual for the process of agreeing a suitable scope of works and
finalising the settlement amount to take some months, in the context of a
substantial claim.
Further, it appears that the Applicant was, at least to some extent, responsible for
these delays. In particular, the Panel notes that the Applicant rejected an in
principle agreement previously reached between the FSP and her husband
(acting as her power of attorney), in the presence of her solicitor.
Finally, for the reasons outlined above, the Panel is satisfied that the Applicant
could have acted to prevent the eventual demolition of the property by making
representations to the council during the 60 day appeal period.
Even after the appeal period expired, it may have been possible to prevent the
issue of the demolition order on 10 June 2014. In an email dated 26 May 2014,
the Applicant indicated that she was willing to accept a settlement amount broadly
similar to that put forward by the FSP, subject to payment being received before
the demolition order was issued. However, this process was delayed due to the
Applicant having provided incorrect bank account details.
In these circumstances, the Panel does not consider that any delays by the FSP
in managing the Applicant‟s claim have caused or materially contributed to the
ultimate demolition of the property.
Costs arising from demolition are not within scope of cover for accidental
damage
The Applicant says that the additional costs incurred as a result of the demolition
order should be covered as “accidental damage”.
As outlined above, the Applicant‟s policy provides cover for accidental loss or
damage arising other than as a result of one of the specific insured events listed
in the policy.
T he courts have held that, in the context of a contract of insurance, “accidental
damage” means damage which is unexpected and unintended.
As noted above, the demolition of the Applicant‟s property occurred after she had
been provided with notice of the proposed demolition and allowed a period of 60
days within which to respond. In these circumstances, and in light of the
Case No: 377296 Determination Page 6 of 8
Applicant‟s failure to take any action, the Panel considers that the eventual
demolition of the property cannot be characterised as “unexpected”.
Accordingly, any costs arising from the demolition are not subject to cover under
the accidental damage cover provided under the policy.
Cash settlement amount for building repairs is appropriate
For the reasons outlined above, the FSP was entitled to determine its liability for
the Applicant‟s claim on the basis that the building was capable of being repaired,
and was not liable to pay for any additional costs arising as a result of the
demolition.
The settlement amount paid by the FSP was determined on this basis, and in
accordance with an updated scope of works and quotation obtained by the FSP.
In correspondence with the FSP, the Applicant accepted most of the underlying
amounts for demolition, repairs and related costs which formed the basis of the
settlement figure.
However, the Applicant disputed the following two items:
council fees for temporary fencing, for which the FSP offered an amount of
$1,671 and the Applicant claimed a higher amount of $3,562.98; and
a contingency allowance equal to 3% of the amount quoted for building
repairs.
Both the Applicant and the FSP have referred to their estimate of the cost of
temporary fencing as supported by relevant documents. However, neither has
provided copies of these documents.
To the extent that the Applicant is able to provide documents substantiating that
she reasonably incurred council fees for temporary barricades exceeding $1,671
prior to the demolition of the property, the FSP will be liable for the additional
amount, subject to the terms and conditions of the policy.
The Applicant has not provided any independent information to confirm the need
for a contingency allowance of 3% to be added to the quotation for the repair of
the building. Accordingly, the FSP is not liable for this amount.
For the reasons outlined above, the Panel is satisfied that the FSP did not
unreasonably delay the settlement of the claim between November 2013 and May
2014. Accordingly, the FSP is not required to pay interest on the settlement
amount in respect of this period.
Case No: 377296 Determination Page 7 of 8
3 Supporting information
3.1 FOS approach to this dispute
This dispute has not been the subject of a FOS Recommendation. Due to the
nature of the dispute, it has been referred directly to a Panel for Determination, in
line with the Operational Guidelines to the FOS Terms of Reference. The Panel
consists of an Ombudsman and two representatives with consumer and insurance
experience.
The Panel has decided this case on its merits, having regard to the relevant law,
good industry practice, codes of practice and previous Financial Ombudsman
Service (FOS) decisions.
There has been a full exchange of all material information relied on for the
purposes of this Determination and each party has had the opportunity to address
any issues raised by the other.
The Panel has reviewed and considered all of the material provided by the
parties. While the parties have raised numerous issues in their submissions, for
the purposes of this Determination the Panel has restricted its commentary to
those issues which it considers directly relevant to the outcome only.
The Applicant has been assisted by her husband during the course of this
dispute. For the purposes of this Determination, any submissions made by the
Applicant‟s husband have been treated as having been made by the Applicant
herself.
3.2 Claim for loss of rent
In the course of her submissions, the Applicant has disputed the basis on which
the FSP calculated payments for loss of rent, which were included in the
settlement amount.
The Applicant‟s claim for loss of rent was made under the section of her policy
which provides cover for business interruption.
Under FOS‟s Terms of Reference (as at the time the Applicant lodged her
dispute), FOS does not have jurisdiction to consider claims for business
interruption or loss of profits.
Accordingly, the Panel is unable to consider this aspect of the Applicant‟s dispute .
Case No: 377296 Determination Page 8 of 8
3.3 Terms of policy
Subject Terms
Settlement of claims Reinstatement or replacement value
We will pay the cost of rebuilding, replacing or repairing any
damaged part of Your Business Property to the same condition as
when they were new …
Defined events
cover
We cover You for loss or damage at the Business Premises
caused by the following defined events … fire, lightning or
explosion …
Accidental damage
cover
We will cover You for accidental loss or damage to Your Business
Property at the Business Premises other than any excl usions
detailed in this section …
Exclusions
We will not pay for claims under „Accidental damage cover‟ for:
loss or damage caused by any defined events cover in this
section …