Determination 375153

Defective flood repairs, asbestos contamination and delay in claim resolution

FirmFinancial Firm (Unknown - Insurer)
Decided2015-08-18
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded$262,819
Non-financial loss$3,000
Amount claimed—
SourceAFCA PDF

Summary

After flood damage, the FSP's appointed builder performed substandard repairs and asbestos remained on site, and the claim was delayed. AFCA decided substantially in the applicant's favour, ordering the agreed $255,866 rectification payment, asbestos remediation, temporary accommodation, $6,953.22 reimbursement and $3,000 non-financial loss, while refusing legal fees, health checks and a guarantee.

The FSP must ensure claims progress smoothly, and the prolonged asbestos contamination was an unacceptable delay warranting non-financial loss compensation up to the $3,000 cap.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay compensationpay non financial lossprovide documentsrepair or rectify

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination General Insurance - Domestic Insurance - Home Building - FSP Decision - Claim amount General Insurance - Domestic Insurance - Home Building - Service - Delay in claim handling Case number : 375153 11 August 2015 1 Overview 1.1 Dispute The Applicant holds a home and contents insurance policy underwritten by the Financial Services Provider (FSP), covering his residential address. The property was extensively damaged by floodwaters on 11 January 2011 and a claim lodged with the FSP. The FSP subsequently authorised builders “AN” to undertake the necessary repairs. The Applicant is dissatisfied with the quality of the repairs undertaken and the time taken to bring this matter to a resolution. 1.1 Issues and key findings Has the FSP fulfilled its obligations pursuant to the policy terms? The FSP has not met its obligations under the policy and there has been an unreasonable delay in the claims handling process. 1.2 Determination This Determination is substantially in favour of the Applicant. The FSP is to arrange the following items to be undertaken:  payment of the agreed sum of $255,866 for rectification  remediation of asbestos at the site  provision of clearance certificate once site cleared of asbestos  payment of $3,000 compensation for non financial loss  provide an allowance for four months temporary accommodation and storage of contents  reimburse the sum of $6,953.22 for earlier costs incurred (if not already done). The FSP is entitled to decline the Applicant‟s claim for:  legal fees yet to be incurred  health checks  a guaranteed indemnity for any damage which may occur during the rectification process. Case No: 375153 Determination Page 2 of 6 2 Reasons for Determination 2.1 Has the FSP fulfilled its obligations pursuant to the policy terms ? It is not disputed between the parties that the Applicant suffered a loss from a risk insured against, or that the FSP accepted the claim and arranged for the necessary repairs. It is further not disputed that the repairs undertaken by AN were not to standard and the property requires rectification. The FSP agrees that it is not appropriate that AN attempt to remedy the issues at the property. As there are a number of aspects still in dispute, for the sake of clarity, it is proposed to deal with each issue individually below. Although the parties have indicated that they are also in dispute over a number of items relating to the contents damaged in the event, neither party has provided any information regarding the contentious issues. Accordingly, only matters which relate to the building dispute will be considered in this Determination. The rectification works In an effort to resolve the issues, the FSP appointed independent building consultant “AM” to inspect the property and provide commentary on the issues raised. AM agreed that generally speaking, the works were not to standard. AM has since prepared a detailed scope of works (SOW) with regard to the rectification required, which is agreeable to both parties. The Applicant‟s preference is that the FSP settle the claim for the rectification works by way of cash settlement, so that he can appoint his preferred builder to do the works. The FSP has agreed to offer a cash settlement amount. The FSP has latterly offered the Applicant a cash settlement in respect of the rectification works required, in the amount of $255,866, based on the quotation provided by the Applicant‟s repairer, CC. The Applicant advises he is in agreement as to this amount for the rectification works. Accordingly, as this aspect has satisfactorily been resolved, no further consideration will be given to this issue. As this amount has been quoted at today‟s prices to repair the property, an award of interest is not appropriate in the circumstances. Asbestos removal There is no dispute between the parties that the property contained asbestos materials, which were disturbed as a result of the repairs required. AN have provided a clearance certificate dated 21 July 2012, from “PB” stating the property is cleared of asbestos. The Applicant maintains the property is still contaminated and has provided a laboratory report from “EL” of 22 January 2013, showing that three samples tested, yielded positive results for chrysotile asbestos. These samples were taken from the front door, the south eastern corner of the house and the rear of the storage room. The Applicant says that asbestos materials are continuing to come to the surface of the topsoils and the topsoil requires removal and sanitisation. Case No: 375153 Determination Page 3 of 6 Review of PB‟s report shows that their scope and inspection was limited to the external ground surface on the southern side of the residence. Further, this was limited to a visual inspection. A ccordingly, PB‟s certification does not suggest the entire property was either sanitised or cleared of asbestos or that any investigation more involved than a visual inspection was conducted. On this basis, the certification is inadequate, particularly in light of the information supplied by the Applicant. The FSP does not appear to have taken any action in relation to the information from EL. The repairs commenced in July 2011 and as at January 2013, a full 18 months later, the property was still contaminated by asbestos fragments. As at the time of writing this Determination, more than another two years have passed. This is a completely unacceptable delay by the FSP in ensuring the site was safe for habitation and free from contaminants. Whilst I agree t he FSP‟s policy does not respond to soil as part of „the building‟ as defined by the policy, in my view this is not sufficient justification for the FSP‟s inaction and failure to ensure the site as a whole was fit for habitation. The Applicant and his family had returned to reside at the site in December 2012. Accordingly, the FSP is to, as a matter of urgency, appoint the necessary contractors to ensure the property is cleared of asbestos. This includes the removal of soil, if necessary, to ensure the site is free from asbestos as far as is practically possible. An updated clearance certificate is to be provided at the completion of this process. The costs for health checks The Applicant seeks cover for the costs of an ongoing annual health check to determine if the family have suffered any ill consequences from asbestos exposure. The policy does not provide coverage for the cost of health checks and given the evidence presented, I am not satisfied that the FSP should be required to meet this cost. However, this does not preclude FOS from considering whether an award of compensation for either financial or non-financial loss is justified in this matter. The FOS Terms of Reference allow for compensation in some circumstances The Terms of Reference (the Terms) provide that FOS may decide an FSP should compensate an Applicant for:  financial loss (which may be direct or consequential loss); or  non-financial loss. For each of these forms of loss, there is a $3,000 per claim cap on compensation. Factors FOS considers when deciding on compensation for loss include:  what it considers fair in all the circumstances  if it is satisfied that loss is caused by an FSP‟s conduct  if the losses can be substantiated  whether the Applicant was partly responsible for a loss Case No: 375153 Determination Page 4 of 6 Compensation for losses which have arisen as a result of the actions taken by the FSP in the course of handling the claims (rather than as a result of the underlying incident itself), are within the power of FOS to consider. FOS is able to award an Applicant compensation for non-financial loss where the Applicant has experienced an unusual degree or extent of physical inconvenience, time taken to resolve the dispute or interference with his or her expectation of enjoyment or peace of mind. FOS expects an Applicant to be moderately both robust and bear the usual degree of inconvenience experienced in the course of an insurance claim. However, in this instance, it is clear that despite over four years having passed from the event, the property is still not restored to its pre-loss condition. Whilst many of the items requiring rectification are cosmetic only, there were a number of more serious issues with the property, not the least, the asbestos contamination. Whilst I am mindful of the large volume of claims that arose from this weather event and the ensuing difficulties faced by insurers, in my view, this does not absolve the FSP from ensuring claims progressed smoothly and issues were promptly resolved. In the circumstances, I consider that it is appropriate that the FSP compensate the Applicants for the non-financial loss they suffered arising both from the asbestos contamination and the time taken to restore the property to its pre-loss condition. Therefore, it is appropriate that the maximum entitlement of $3,000 be awarded. Temporary accommodation and contents storage The Applicant is seeking a commitment from the FSP to cover temporary accommodation and content storage expenses, whilst the rectification works are underway. Although the policy terms limits temporary accommodation coverage to a maximum period of 12 months, this is where the temporary accommodation is as a result of an insured event. In this instance, the requirement for accommodation and storage arises as a result of the FSP‟s obligation to remedy the repairs undertaken. Accordingly, the timeframe as set out in the policy is not relevant. The quotations from PD and ZC do not include any reference as to an estimated time for repairs. The quotation from CC estimates four months. As this is unchallenged, I accept the rectification repairs will take four months to complete. Whilst the building policy has no allowance for storage of contents, it is likely that as a result of the remediation of the repairs and need for temporary accommodation, the cost of storage of contents will also be incurred. On this basis, the FSP is to cover the costs for temporary accommodation and reasonable contents storage costs for four months, whilst the rectification is undertaken. Case No: 375153 Determination Page 5 of 6 As neither side has presented any estimate as to what amount would be considered reasonable for these costs, this is to still to be assessed. In the event that a further dispute arises between the parties regarding a settlement amount, either party is at liberty to seek the assistance of this Service in resolving such a dispute. The outstanding costs The Applicant says a sum of $6,953.22, is still owed to him in respect of the original claim. This consists of fees for the initial temporary accommodation, rental of a storage pod for their contents and plumber‟s fees to unblock the drains. The FSP advised it intended to review those costs and communicate its decision regarding its liability for same to the Applicant. However, the FSP has not advised this Service as to what that decision was. Accordingly, if it has not already done so, the FSP is to reimburse the Applicant for these costs. Other matters The Applicant seeks legal costs, which are yet to be incurred, for his solicitor to review any building contract for the rectification works. The Applicant also seeks indemnity for any legal fees which may be incurred should AN take legal action as a result of their termination from the repairs. The FSP denies it has any liability for such costs. Its position is that these are expenses the Applicant has not incurred. Further, even had the Applicant incurred these expenses there is no section of the policy which would respond to them. I agree with the FSP‟s position. Whilst this Service may, pursuant to Section 9.4 of the Terms, consider an FSP liable for the Applicant‟s professional costs, this is generally only where such costs have been actually incurred. FOS would also need to be satisfied that such costs, if awarded, were pertinent to the outcome of the dispute. In the current situation, I am not persuaded that it is necessary for the Applicant to obtain legal advice before signing any contract for rectification works. Similarly, I see no indication AN intend to take legal action for their termination of the contract. On this basis, an award of these costs is not appropriate. The Applicant also seeks a guarantee of indemnity in case of future damage caused to either his property or contents, as a result of the rectification works. The FSP says that any damage caused to the property during the rectifications, would be assessed at that time. Such an approach by the FSP is reasonable and it is not required to provide a guarantee of indemnity upfront. Case No: 375153 Determination Page 6 of 6 3 Supporting information 3.1 FOS approach to this dispute As advised to the parties, FOS has considered it appropriate to expedite this dispute in accordance with the Operational Guidelines to the FOS Terms of Reference, due to the nature of the dispute. Accordingly, this dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination. There has been a full exchange of all material information relied on for the purposes of this Determination and each party has had the opportunity to address any issues raised by the other. All of the material provided by the parties has been reviewed and considered for the purposes of this Determination. This dispute has been decided on its merits, having regard to the relevant law, good industry practice, codes of practice and previous Financial Ombudsman Service (FOS) decisions. While the parties have raised numerous issues in their submissions, for the purposes of this Determination, commentary has been restricted to only those issues considered directly relevant to the outcome. 3.2 Relevant FOS Terms of Reference 9.3 Other compensation a) Subject to paragraph 9.3 c) and paragraph 9.7, FOS may decide that the Financial Services Provider compensate the Applicant for consequential financial loss or damage up to a maximum amount of $3,000 per claim made in the Dispute. b) Subject to paragraph 9.3 c) and paragraph 9.7, FOS may decide that the Financial Services Provider compensate the Applicant for non -financial loss but only where: (i) an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with the Applicant‟s expectation of enjoyment or peace of mind has occurred; ... The maximum amount of compensation for non-financial loss will be $3,000 per claim made in the Dispute. 9.4 Applicant’ s costs in pursuing the matter FOS may decide that the Financial Services Provider contribute to the legal or other professional costs or travel costs incurred by the Applicant in the course of the Dispute. Unless exceptional circumstances apply, FOS will not require the Financial Services Provider to contribute more than $3,000 to these costs.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.