Home / Financial Firm (Unknown - Insurer) / Determination 374800
Determination 374800
Delay and poor management of vessel and trailer repair claim
Summary
The applicants' pleasure craft and trailer were damaged in transit and repairs took about 16 months, with poor workmanship and inadequate FSP oversight. AFCA ordered non-financial loss compensation, trailer labour costs and storage rental, but refused compensation equal to two years of premiums.
The FSP remained responsible for the authorised repairers and failed to complete the repairs in a reasonable time, causing unusual inconvenience and financial loss under the Terms of Reference.
Issues
- Poor claim handling primary · upheld
“The FSP is responsible for the delays, poor workmanship, and the conduct of the authorised repairers.”
- Claim amount dispute secondary · not upheld
“I am not satisfied the FSP is required to pay the Applicants the equivalent of two years' worth of premium.”
- Delay secondary · upheld
“It is apparent that the FSP failed to keep the Applicants properly informed as to the progress of repairs or to complete the repairs in a timely manner.”
- Repairs or contractors secondary · upheld
“The repairs were not satisfactorily completed and the FSP did not closely monitor the repair process with JK.”
Subjects and remedies
pay compensationpay non financial loss
Text of the determination
Determination
General Insurance - Domestic Insurance - Personal and Domestic Property- Pleasure
Craft - FSP Decision - Claim amount – Service – Delay in Claim Handling
Determination
Case No: 374800 Determination Page 1 of 7
Case number : 374800 11 May 2015
1 Overview
1.1 Dispute
This dispute follows a claim by the Applicants under a pleasure craft insurance
policy underwritten by the Financial Services Provider (FSP) for damage
sustained to their vessel and trailer whilst being transported from Groote Eyland
N.T. to Sydney.
The Applicants’ claim was lodged on or about 9 April 2013 . Whilst the FSP
accepted the claim repairs were not completed until 15 August 2014. The
Applicants seek compensation for financial and non-financial loss arising as a
result of the FSP’s overall management of the claim.
A Recommendation was issued by the Service on 3 March 2015 in favour of the
Applicants. The Applicants rejected the Recommendation as they believe the
Recommendation has not properly addressed all of the issues.
1.2 Issues and key findings
Are the Applicants entitled to compensation for non-financial loss?
The Applicants are entitled to compensation for non-financial loss as they suffered
an unusual degree or extent of physical inconvenience and time taken to resolve
the claim.
The FSP is to pay the Applicants $2,000 by way of compensation pursuant to
paragraph 9.3(b)(i) of the Service’s Terms of Ref erence (TOR).
Is the FSP liable to pay labour costs to repair the trailer?
The FSP is liable to meet the Applicants’ claim for labour costs associated with
repair of the trailer in the sum of $760 calculated at the rate of $95 per hour for
eight hours labour.
Is the FSP liable to pay compensation for financial loss?
The FSP is liable to pay compensation for financial loss associated with the cost
to rent storage for the boat for the period from January 2014 until August 2014
subject to the Applicants providing an invoice for those costs.
Case No: 374800 Determination Page 2 of 7
1.3 Determination
This Determination is in favour of the Applicants.
The FSP is to pay the Applicants the sum of $2,000 compensation for non-
financial loss pursuant to paragraph 9.3(b)(i) of the TOR and $760 being the
labour costs associated with the repair of the trailer.
The FSP is to pay the storage rental costs incurred for the period January 2014 to
August 2014 pursuant to paragraph 9.3(a) of the TOR subject to the Applicants
providing an invoice to identify the costs incurred.
Case No: 374800 Determination Page 3 of 7
2 Reasons for Determination
There has been a full exchange of material between the parties and each party
has had an opportunity of addressing the issues that arise from the material
exchanged.
In rejecting the Recommendation, the Applicants have made further submissions
with respect to the circumstances which led to the male Applicant attempting to
repair the trailer and further submissions with respect to the costs incurred in
renting storage space for the vessel.
I accept the Applicants ’ statements that the Recommendation that the Case
Manager misinterpreted the Applicants’ claim as being a claim for compensation
associated with the renting of a boat. I accept that the Applicants did not claim for
the rent of the boat but instead claimed for the costs of renting storage space for
the vessel on the reasonable belief that the vessel had been repaired and was
available.
The FSP has not made any further submissions following the rejection of the
Recommendation.
2.1 Are the Applicants entitled to compensation for non-financial loss
pursuant to paragraph 9.3(b)(i) of the TOR?
The Applicants are entitled to compensation for non-financial loss
Under paragraph 9.3(b)(i) of the TOR, FOS can award up to $3,000
compensation for non-financial loss where there has been an unusual degree or
extent of physical inconvenience, time taken to resolve a claim or interference
with an Applicant’s expectations of enjoyment or peace of mind.
There is no dispute that a period of 16 months elapsed between the lodgement o f
the Applicants’ claim and the completion of repairs to the vessel.
Acceptance of Claim
It would appear from the information exchanged that whilst the FSP had the
damage assessed by its assessor on 12 April 2013 four days after the claim was
lodged, the FSP did not notify the Applicants that the claim was accepted or that it
would meet the cost of the repairs until September 2013.
It is apparent from the Applicants’ time line of events and not disputed by the FSP
that the Applicants had requested confirma tion in writing that the claim was
covered as early as 21 April 2013.
Trailer Repairs
In the Notice of Response, the FSP noted that it was originally agreed that the
insured would repair the trailer and afterwards the boat will be removed to a
repairer in order that an estimate could be obtained.
Case No: 374800 Determination Page 4 of 7
I note from the assessor’s report of 12 April 2013 that he referred to the ve ssel
being located in a rural area and that waiting for a repairer to attend to the
damaged trailer could take some time. There is no indication of any effort made
by the assessor or the FSP to arrange a repairer.
The vessel was in a rural area, Woollamia which is only 21.5kms from Nowra. I
am not satisfied based on the information exchanged that any reasonable effort
was made by the FSP to arrange for the repairs to the trailer.
I am satisfied based on the information exchanged that the male Applicant agreed
to attempt the repair to expedite the matter so that the boat could be assessed.
Again, the Applicants maintain and it is not disputed that in April/May 2013 the
male Applicant requested assistance from the FSP for the repair of the trailer
because of his injuries.
In an email dated 29 August 2014 the assessor does not refer to any relevant
timeframes but it is clear he was aware that the male Applicant had suffered an
injury and had requested assistance.
The FSP’s explanation for the failure to complete the repairs to the trailer is in my
view unsatisfactory. I do not accept that any reasonable effort was made by the
FSP to attend to the trailer repairs as required under the terms of the policy.
Vessel Repairs
It was not until September 2013 that the FSP obtained a quotation for the repairs
to the vessel or that the repairs were authorised originally with JK in October
2013.
It is not in dispute that JK failed to adequately complete the repairs and that whilst
the vessel was with JK further damage was sustained. Further, it is not in dispute
that the FSP removed the vessel from JK and had the repairs completed by AM.
Those repairs were completed on 15 August 2014.
The FSP argued that it could not identify how the underwriter had been
responsible for the delay in repairs. I do not agree.
It is clear that the FSP were aware of their liability to repair the vessel from April
2013. It is apparent from the information exchanged that the FSP failed to
adequately assess the vessel at that time. The FSP arranged for the original
repairer. Whilst the vessel was with that repairer it remained the responsibility of
the FSP to ensure the repairs were completed satisfactorily. The repairs were not
satisfactorily completed. Based on the information exchanged, it would appear
that the FSP did not closely monitor the repair process with JK.
In my view, the FSP is responsible for the delays, poor workmanship, and the
conduct of the authorised repairers. The delays were not due to difficulty in
obtaining parts or the nature of the work to be performed but were due to the poor
repairs and the authorised repairers.
Case No: 374800 Determination Page 5 of 7
Compensation
I accept the vessel has now been repaired. It may be argued that the vessel is in
better condition than it was pre-damage. Given this, in my view it is not
appropriate that the Applicants be awarded the maximum amount of
compensation for non-financial loss. It is appropriate that the Applicants be
entitled to a substantial award of compensation for non-financial loss however in
view of the delays and stress placed on the Applicants.
In view of this, it is my determination that the FSP pay the Applicants $2,000 by
way of compensation in line with paragraph 9.3(b)(i) of the TOR.
2.2 Is the FSP liable for the male Applicant’s labour costs associated
with the repair of the trailer?
The male Applicant is entitled to be paid for his labour costs associated with the
repair of the trailer.
I accept that the male Applicant only agreed to attempt to repair the trailer on the
understanding that the FSP had difficulty in identifying a person or persons to
repair the trailer.
I do not believe the area where the trailer and vessel were located were so
remote that the repairs could not be effected or a repairer obtained.
It is apparent from the information exchanged that the male Applicant had
difficulty with the repairs and notified the FSP’s assessor of this. The FSP’s
assessor failed to respond adequately at that time resulting in the Applicant being
affectively forced to attempt the repairs.
The Applicant provided a copy of a quotation indicating that the labour costs
charged by a repairer would be $95 per hour. The Applicant has claimed 40 hours
work.
Whilst I accept the hourly rate at $95 per hour is reasonable in particular given the
FSP has not challenged this, I do not accept that the repair of the trailer would
have required 40 hours work. Some of the work conducted would be properly
classified as maintenance and necessary repairs and some due to the accidental
damage. There may also have been a delay caused by the availability of the
trailer parts.
I do not have any scope of works to indicate the likely time it would have taken to
have completed the repairs required as a result of the insured event. In the
absence of such a document and given the time since the incident, I have
determined that it would be reasonable to allow eight hours labour to complete the
repairs. Allowing $95 per hour for eight hours, I determine the reasonable amount
of the labour cost to be $760.
Is the Applicants entitled to compensation for financial loss?
The Applicants are entitled to compensation for financial loss pursuant to
paragraph 9.3(a) of the Terms of Reference.
Case No: 374800 Determination Page 6 of 7
Under paragraph 9.3(a) of the Terms of Reference, the Service may award
compensation for financial loss up to $3,000 where the loss arises as a result of
the FSP’s conduct.
I have already determined as a result of the FSP’s conduct, there was an unusual
time taken to effect the repairs to the vessel.
Based on the information exchanged, it was reasonable for the Applicant to form
a view that the vessel would have been repaired by December 2013. The FSP
has not challenged this.
It would appear based on some of the information exchanged that the original
repairer JK contacted the FSP requesting part payment for the repairs on the
basis that the Applicant required the vessel over the Christmas period. There
does not appear to be any information on the file to suggest that the FSP or its
assessor inspected the vessel at that time to check on the progress of the repairs.
Given the information provided to the Applicant at that time, it was reasonable to
arrange for the storage of the vessel.
The Applicants incurred storage rental fees for the period from January 2014 until
the boat was delivered to him on 15 August 2014. Those fees were incurred
largely as a result of the FSP’s failure to keep the Applicants properly informed as
to the progress of repairs or to complete the repairs in a timely manner.
I am satisfied the Applicants incurred a financial loss being the cost of the storage
rental for the period from January 2014 to August 2014 due to the FSP’s conduct .
Accordingly I determine that the FSP is liable to m eet the Applicants’ claim for the
cost of the storage rental during the period January 2014 to 15 August 2014
subject to the Applicant providing the FSP with a detailed invoice from the storage
facility as to the rental charge during that period.
Compensation for lost premium
The Applicants have also requested compensation being payment for the
equivalent of two years insurance premiums.
I agree with the findings in the Recommendation. Irrespective of the level of
service received from the FSP, the fact is that the Applicants’ vessel and trailer
remained insured under the policy during the entire period.
The Applicants were still covered under the policy as the vessel and trailer were
fully insured against any additional damage that might have been sustained.
In the circumstances, I am not satisfied the FSP is required to pay the Applicants
the equivalent of two years’ worth of premium.
Case No: 374800 Determination Page 7 of 7
3 Supporting information
3.1 Applicants’ submissions
Dispute form and attachments dated 8 September 2014.
Applicants’ response to FSP’s Notice of Response.
Applicants’ time line of events provided 4 November 2014.
From SC Trailers 4 November 2014.
Medical Reports and submission.
Further submission 19 November 2014.
Submission on rejection of Recommendation 18 March 2015.
FSP’s submission including Notice of Response 23 October 2014 and
attachments including 10 assessor’s reports and photographs.
Copy of policy PDF.
3.2 FOS Terms of Reference
9.3 Other compensation
a) …
b) Subject to paragraph 9.3 c) and paragraph 9.7, FOS may decide that the
Financial Services Provider compensate the Applicant for non-financial loss
but only where:
(i) an unusual degree or extent of physical inconvenience, time taken to
resolve the situation or interference with the Applicant’s expectation of
enjoyment or peace of mind has occurred; or
(ii) …
The maximum amount of compensation for non-financial loss will be $3,000
per claim made in the Dispute.