Home / Financial Firm (Unknown - Insurer) / Determination 374463

Determination 374463

Home building water-leak claim denied under earth movement exclusion and 72-hour limited cover

FirmFinancial Firm (Unknown - Insurer)
Decided2015-02-04
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

Homeowners claimed for damage from a leaking pipe that caused ground movement. The FSP refused the claim under the earth movement exclusion and the 72-hour limited cover, and AFCA agreed the claim was not covered.

The loss occurred before the supplementary cover applied, and the applicants could not show damage within 72 hours of the leak being fixed, so the earth movement exclusion applied.

Issues

Subjects and remedies

no remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination General Insurance - Domestic Insurance - Home Building - FSP Decision - Denial of Claim Determination Case No: 374463 Determination Page 1 of 5 Case number : 374463 4 February 2015 1 Overview 1.1 Dispute In September 2013, the Applicants lodged a claim with the Financial Services Provider (FSP) for damage sustained to the home building because of a leaking water pipe. The Applicants noticed the problem with the pipe and organised repairs sometime in September 2012. The FSP refused to pay the Applicants’ claim because:  the policy excludes cover for damage caused by earth movement  the Applicants failed to show the loss occurred within 72 hours of the water leaking from the pipe. 1.2 Issues and key findings Have the Applicants established a valid claim under the policy? The Applicants have shown a valid claim under the policy because the property sustained damage because of water discharging from a leaking pipe. This is an event insured under the policy. Was the FSP entitled to deny the Applicants’ claim? The FSP was entitled to refuse payment of the claim because:  the policy wording applicable to a loss before 15 September 2012, excludes cover for damage caused by earth movement, no matter how that earth movement was caused  the policy wording applicable to a loss after 15 September 2012, provides limited cover for damage to property, should the loss occur within 72 hours of water leaking from the pipe  there is no evidence to show the property sustained damage within 72 hours of the subject insured event. 1.3 Determination This Determination is in favour of the FSP. The FSP is not required to i ndemnify the Applicants for their loss. Case No: 374463 Determination Page 2 of 5 2 Reasons for Determination 2.1 Have the Applicants established a valid claim under the policy? Damage to the property was caused by a leaking pipe The Applicants are required to show, on the balance of probabilities, they have suffered a loss caused by an i nsured risk. This is called a prima facie claim. The FSP is then required to show, on the balance of probabilities, the loss falls within an exclusion clause of the policy or is otherwise not covered. The FSP appointed building consultant (S) to investigate the cause of the loss. He concluded the damage to the property was caused by:  the water released from a split water pipe ponding under the house. This was due to buildup of external ground surface  building movement was due to variation of the moisture level in the soil for an extended period of time  building movement was due to rotting of the timber stumps. This was not related to water discharging from the split pipe  water leak may have been occurring for an extended period of time. The Applicant’s exp ert engineer (B), disputed S’s findings and concluded the proximate cause of the damage to the Applicants’ property, was the water discharging from the pipe. The FSP has reimbursed the Applicants for B’s report. The FSP accepts the cause of the loss was the leaking pipe. As such, the Applicants have established a prima facie claim under the policy. 2.2 Was the FSP entitled to deny the Applicants’ claim? The onus now shifts to the FSP to establish its policy exclusions in denying liability for the claim. Loss occurred before 15 September 2012 The Applicants had initially informed the FSP’s loss assessor and S, that a water pipe had burst beneath the kitchen floors on or around 10 September 2012. The policy in force before 15 September 2012, excludes cover for a ny damage to the property caused by earth movement. However, a supplementary PDS issued with the Applicants’ policy renewal, effective 15 September 2012, provided limited cover for damage caused by earth movement after a leaking pipe. The female Applicant has since indicated her husband may have provided the incorrect date of loss, to the FSP’s experts. She is of the view the loss may have occurred at any time after 15 September 2012. Case No: 374463 Determination Page 3 of 5 This Service’s Case Manager has provided the Applicants an opportunity to provide evidence to clarify the above statements. The Applicants have confirmed they will not be providing any further information relating to:  when the loss was identified  when the issue was fixed by the plumber. As such, based on the evidence presented by the parties, on the balance of probabilities, the insured event, water leaking from the burst pipe, occurred before 15 September 2012. B concluded damage to property was caused by earth movement The Product Disclosure Statement (PDS) applicable for the loss event before 15 September 2012, excludes cover for loss or damage to property caused by earth movement, no matter how caused. B’s investigations confirmed the loss was caused by earth movement. The water discharging from the pipe had caused the soil to initially swell and thereafter shrink, as it died out. B concluded this event had subsequently caused the movement and cracking at the property. Considering the above, if the leaking pipe was fixed before 15 September 2012, any damage caused to the property because of the earth movement by the leaking pipe, will not be covered under the policy. Loss did not occur within 72 hours after the insured event The female Applicant has indicated to this Service’s Case Manager that the plumber would have fixed the leak after a week or so after her husband initially identified the problem with the pipe. As explained previously, no information was presented by the Applicants to confirm the date the leaking pipe was fixed. If it is accepted the leak was fixed after 15 September 2012, it is reasonable to conclude this would have occurred by the end of September 2012. The onus now shifts to the Applicants to show the property sustained damage within 72 hours of fixing the leak, as this will be the date of the issue with the leaking pipe was resolved. The loss assessor says the occupants at the property had vacated by Easter 2013. The damage to the property was noticed during a routine house inspection, on or around 5 September 2013. The Applicants accept they did not notice any damage to the property in the 12 months after the insured event. As the Applicants are unable to show the property sustained any damage within 72 hours of fixing the leak, they will have no cover under the limited cover extended under the supplementary PDS. Case No: 374463 Determination Page 4 of 5 3 Supporting information 3.1 Product Disclosure Statement (PDS) “ What You are insured against if Your Home is not a caravan … 11 Bursting, leaking or overflowing of water, oil or other liquid from a system fixed, attached or connected to a Domestic Building. … What is not insured This policy does not insure You against: 1 loss or damage directly caused by: … • e arth movement (except earthquake) no matter how caused, including erosion, vibration, subsidence, seepage, saturation, creeping, landslip, mudslide, collapse, shrinkage, settling, expansion or heaving” 3.2 Supplementary Product Disclosure Statement applicable from 15 September 2012 “ This SPDS (RPLSPD 02 0312) makes a number of changes to your [PDS] (RPLPDS 01 0409) to update the information contained in it. … Date prepared: 20/12/2011 … Standard home policy - Earth movement exclusion This policy is amended by deleting the words on page 52 in the fifth bullet point under the heading "What is not insured" under "1 loss or damage directly caused by ” and replacing them with the following: “ • earth movement no matter how caused, including erosion, vibration, subsidence, seepage, saturation, creeping, landslip, mudslide, collaps e, shrinkage, settling, expansion or heaving, unless the loss or damage occurs as a direct result of: (a) earthquake; or (b) water overflowing, leaking or bursting from a fixed pipe or fixed system and that loss or damage occurs within 72 hours of such overflowing, leaking or bursting. In respect of (b) above We only pay up to $10,000 for any one claim." 3.3 Loss assessor’s r eport dated 23 September 2013 “ Circum stance s: We were advised that sometime around 10 September 2012 a water pipe burst beneat h the kitchen floorboards. Subsequently the Insured have located the cracks appearing in the door frames, and doors and cupboard d oors are ajar, or do not close correctly. Cause … The actual cause of loss is reportedly that the leaking pipe has caused the ground to move and has therefore allowed the homestead to drop and move out of alignment in places. We Case No: 374463 Determination Page 5 of 5 also noted the ground below the homestead was very dry wit h noticeable cracks in the ground. … Policy liability … Therefore, as the damage to the homestead is a result of earth movement caused by seepage, saturation and the damage has not occurred within the 72 hour period as defined, we do not consider the policy will respond in regard to the claim as presented by the insured.” 3.4 S’s report dated 7 November 2013 “ Observations … The Insured stated that on 10 September 2012 the sound of hissing water escaping a water pipe was heard. During an inspection of the water pipes at the rear of the residence a split in the cold water pipe below the kitchen was found. A local plumber replaced the pipe as well as the pipes of the entire hot and cold water system of the residence. … I am of the opinion that the water that had escaped from the split water pipe has ponded under the subfloor area of the building as a result of the build up of the external ground surface. Therefore I consider this to be defective building work. … I am also of the opinion that the building movement has been occurring due to the timber rot observed in the timber stumps. This is evidenced by the recently replaced treated pine stumps. The timber rot has been occurring over an extended period of time and is not related to the water escaping the split in the water pipe. … I am of the opinion that due to the restricted volume of water, escaping the split in the water pipe, required to saturate the entire subfloor area of the residence to a depth that would cause the soil to react sufficiently to induce the building movement observed indicates the water has been escaping over an extended period of time” (sic) 3.5 B’s report dated 3 February 2014 “ 4 Conclusion … It is my opinion that the movement and cracking in the residence is a direct result of water leaking from the broken pipe wetting the highly reactive clay, causing the soil to swell and then shrink as it dried out.”

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.