Misleading statements about loan approval; delayed loan settlement and progress payments
Text of the determination
Determination
Case No: 372725 Determination Page 1 of 10
Case number: 372725 10 November 2015
1 Overview
1.1 Dispute
In March 2014, the Applicants applied to the FSP for loans to refinance an existing
loan they held with Bank S (Land Loan) and to build a home (Construction Loan) at
the property (Property). The Applicants say the FSP misled them to believe it had
unconditionally approved the Loans and unreasonably delayed advancing the Loans .
1.2 Issues and key findings
Did the FSP mislead the Applicants about its approval of the Loans?
The FSP misled the Applicants that it had unconditionally approved the Land and
Construction Loans when it required further identification documents.
Did the FSP unreasonably delay approving the Land Loan?
The FSP unreasonably delayed approving the Land Loan between 22 May and
21 July 2014 by failing to correct an issue with the name on the Property title.
Did the FSP unreasonably delay approving the Construction Loan?
The FSP unreasonably delayed approving the Construction Loan which meant it
delayed releasing progress payments seven and eight to the builder.
Have the Applicants suffered loss for which they should be compensated?
The Applicants‟ loss from having the builder commence work in mid-April 2014 is the
interest differential between the FSP‟s loans and the Bank S loan , being $1,083.60.
The Applicants are also entitled to compensation for the stress and inconvenience
caused by the FSP‟s delays, totalling $3,5 00. The Applicants have not established
their claims for penalty interest paid to the builder or rental costs unnecessarily
incurred because of the FSP‟s delay.
1.3 Determination
This Determination is substantially in favour of the Applicants. If the Applicants
accept this Determination within 30 days, then within the next 14 days the FSP is to
compensate the Applicants by crediting to their Loan account:
$1,083.60 (plus simple interest of 4% per annum from 28 April 2014 to the date
of payment) financial loss, and
$3,500 non- financial loss arising from the FSP‟s conduct.
Case No: 372725 Determination Page 2 of 10
2 Reasons for Determination
2.1 Did the FSP mislead the Applicants about its approval of the Loans?
The FSP misled the Applicants about its approval of the Loans
Broadly, to succeed in a claim for misleading or deceptive conduct in relation to a
financial product or service, the Applicants must be able to show that:
the FSP made a statement or engaged in conduct that was false or misleading
(misrepresentation), and
the Applicants relied on the misrepresentation to their detriment.
The remedy to misleading conduct is not to make the promise come true. Instead,
the question to be asked is how much worse off was the applicant as a result of
relying on the misrepresentation compared to the position they would have been in
had the misrepresentation not been made.
The Applicants say that the FSP misled them on 16 April 2014 to think that it had
unconditionally approved the Land and Construction Loans. Based on this, they say
that they:
signed the building contract, and
transferred $348,243.60 from Bank S to a transaction account with the FSP.
On 16 April 2014, the FSP told the Applicants via email that it had unconditionally
approved a $616,000 Land Loan and a $214,000 Construction Loan.
On 28 April 2014, the FSP noticed that the Property title stated the female Applicant‟s
maiden name whereas the Land and Construction Loan contracts stated her married
name. The FSP needed to either change her name on the contracts or provide
information required by the Land Property Information (LPI) to change her name on
the title. The FSP and the Applicants decided to change the female Applicant‟s name
on the Property title because the building contract was also in her married name.
The FSP sighted the Property title on 12 March 2014 and electronically imaged a
copy of it to its system. The FSP was therefore on notice that the Property title was in
the female Applicant‟s maiden name and should not have told the Applicants on 16
April 2014 that it had unconditionally approved the Land and Construction Loans.
The FSP‟s conduct in this regard was misleading.
The Applicants did not rely on the misrepresentations when entering into the
building contract
The Applicants say they signed the building contract after the FSP told them it had
unconditionally approved the Land and Construction Loans.
The information available shows that the female Applicant signed the building
contract on 23 September 2013, which was:
49 days before the Applicants first contacted the FSP on 11 November 2013
almost six months before the FSP started assessing the Loan applications on
4 March 2014, and
Case No: 372725 Determination Page 3 of 10
almost seven months before the FSP misled the Applicants to believe it had
unconditionally approved the Land and Construction Loans on 16 April 2014.
The Applicants paid a $59,967.50 deposit to the builder on 3 March 2014. This was
the day before the Applicants asked the FSP to start the Loan applications and over
one month before the FSP‟s misrepresentation.
The factors outlined above show that the Applicants did not rely on the FSP‟s
misrepresentation to enter into the building contract because the building contract
had already been signed.
Further, it does not appear that the Applicants had applied for loans with other credit
providers at the same time and the FSP‟s actions caused them to decline any other
finance offers.
Accordingly, the FSP is not required to compensate the Applicants in relation to the
signing of the building contract or payment of the deposit under that contract.
The Applicants relied on the misrepresentations when instructing the builder
to commence work
The Applicants say that they relied on the FSP‟s April 2014 misrepresentations to
instruct the builder to “go ahead with the construction”. They say they “did not jump
the gun; we did not appoint and award the contract to build the house without getting
an approval from a … bank to commit ourselves”. In particular, they requested the
FSP officer who managed their application to give them the “go ahead in writing” and
he did so, making a signed note to that effect on their working papers.
I accept that the Applicants likely instructed the builder to commence work after
receiving the FSP‟s email and letters of 16 and 17 April 2014, and the FSP officer‟s
signed note.
The FSP‟s valuer noted on 2 April 2014 that the Property comprised a cleared site
with a shed and water tanks at its rear. On 1 May 2014, the builder submitted
progress payments 2, 3, 4 for the completion of work comprising the “concrete pier
stage”, “earthworks stage” and “footings and slab stage”. Although it is possible some
of this work was undertaken after 2 April 2014, and before the misrepresentations of
16 and 17 April 2014, I accept that the bulk of the work is likely to have occurred after
the FSP emailed the Applicants the “unconditional approval” on 16 April 2014, sent
them the letters of offer dated 17 April 2014 for the Land and Construction Loans,
and the FSP officer gave them the go ahead.
The Applicants have referred to work undertaken to demolish the old house on the
Property. Since the site was apparently clear when the valuer attended the Property
on 2 April 2014, the demolition work must have been undertaken some time earlier
and is therefore not something for which the FSP must compensate.
The issue of what loss was incurred by the Applicants as a result of them instructing
the builder to commence work based on the FSP‟s misrepresentation is considered
in section 2.4 below.
Case No: 372725 Determination Page 4 of 10
2.2 Did the FSP unreasonably delay approving the Land Loan?
The FSP took too long to resolve the issue with the Property title
As outlined above, the FSP sighted a copy of the Property title on 12 March 2014
and imaged a copy of it to its system. The FSP issued the Land and Construction
Loan contracts on 17 April 2014 and the Applicants returned them on 23 April 2014.
The FSP had notice that the title to the Property was in the female Applicant‟s name
as at 12 March 2014 and should have taken steps to have it corrected.
On 28 April 2014, the FSP noticed the issue with Property title and asked the female
Applicant to provide documents to satisfy the LPI‟s requirements .
According to the LPI ‟s circular dated August 2009 (r eissued in September 2009), the
female Applicant needed to provide one original or certified identification document
from “List A” and one from “List B”.
On 8 May 2014 (within 10 days of the FSP‟s request) , the female Applicant provided
the FSP a certified copy of her Australian citizenship certificate and a certified copy of
her Australian p assport. This satisfied the LPI‟s requirements. Yet the FSP kept
asking the female Applicant to provide more identification documents and to translate
certain documents into English.
Had the FSP taken steps to correct the issue with the Property title on 12 March
2014, it is likely that the female Applicant would have provided the required
documents to it by 22 March 2014 (10 days later). This was before the FSP
unconditionally approved the Land Loan. This means that the FSP should have been
in a position to book settlement to refinance the existing loan with Bank S when it
received the signed contracts from the Applicants on 23 April 2014.
The FSP was ready to book settlement to refinance the existing loan with Bank S on
16 July 2014 and settlement occurred on 21 July 2014. It took the FSP five days
complete settlement. It follows that had the FSP been ready to settle on 23 April
2014, it is likely that settlement would have occurred some five days later on 28 April
2014.
The FSP therefore unreasonably delayed settlement of the Land Loan from 28 April
2014 to 21 July 2014.
2.3 Did the FSP unreasonably delay approving the Construction Loan?
The FSP unreasonably delayed approving the Construction Loan
The available information indicates that the Applicants may have had sufficient funds
in April 2014 to complete the Property with a mixture of the Construction Loan, funds
redrawn from the existing loan with Bank S, a family gift and cash holdings. It was
also suggested at one point that the Applicants were to sell an existing property to
assist with financing the construction of the Property.
As it turned out, the Applicants did not have enough funds to complete the
construction of the Property. The FSP noticed that the Applicants had insufficient
funds when it received a copy of progress payment seven on 24 July 2014.
Case No: 372725 Determination Page 5 of 10
Subsequently, the FSP created a new application on 18 August 2014 and increased
the amount of the Construction Loan from $214,000 to $843,000.
Had the FSP made reasonable enquiries about the amount of funds the Applicants
required, it is likely that the FSP could have assessed and approved a new
application for a higher loan amount between 12 March 2014 (the date it sighted the
building contract) and 24 July 2014 (the date it received the request for progress
payment seven).
Had it done so, the FSP would not have been required to obtain the following, which
further delayed its approval of the Construction Loan:
new financial information from the Applicants because it had entered into a new
financial year, and
a second valuation of the Property on 9 October 2014 which returned the same
value as the valuation it obtained on 2 April 2014 (it does not appear that the
FSP charged the Applicants for this second valuation).
Based on the above factors I accept that the FSP unreasonably delayed settlement
of the Construction Loan. That delay impacted the timing of progress payments in
the manner discussed below.
The FSP delayed releasing progress payments seven and eight to the builder
The FSP ‟s delay in approving the Construction Loan meant that the FSP delayed
releasing progress payments seven and eight to the builder.
The FSP was required to complete a „progress payment report‟ before it released an y
progress payments. Allowing the FSP a period of seven days to complete a progress
payment report, it should have been in a position to release progress payment seven
to the builder on 31 July 2014 (seven days after it received the Applicants‟ payment
request on 24 July 2014).
The FSP released progress payment seven on 17 October 2014. This means the
FSP delayed releasing progress payment seven for 78 days.
The FSP received the request for progress payment eight on 8 September 2014.
Following the same reasoning as above, the FSP should have been in a position to
release progress payment eight on 15 September 2014. Instead the progress
payment was paid on 17 October 2014. The FSP therefore delayed releasing
progress payment eight for 32 days.
2.4 Have the Applicants suffered loss for which they should be
compensated?
The Applicants’ loss is the interest differential between the FSP and Bank S
The FSP delayed refinancing the Bank S loan between 28 April and 21 July 2014.
This is a period of 83 days. At settlement, the FSP transferred $626,995.18 to
Bank S and $16,000 to credit cards in male Applicant‟s name.
The Applicants have not provided a copy of the final account statement with Bank S
as requested. However, the FSP has provided a copy as at 8 October 2013 showing
Case No: 372725 Determination Page 6 of 10
that Bank S was applying an annual interest rate of 5.66%. The Reserve Bank of
Australia did not change its cash rate between October 2013 and July 2014. In the
absence of any information to the contrary, it is reasonable to assume that Bank S
also did not change its interest rate during this period. The FSP applied an annual
interest rate of 4.90% to the Land Loan.
The Applicants‟ loss is the difference between 5.66% and 4.90% (which is 0.76%) on
$626,995.18 for 83 days. This equals $1,083.60. The FSP should therefore
compensate the Applicants this amount for its delay.
The male Applicant has not provided any information to show what, if any, interest he
paid to his credit cards between 28 April and 21 July 2014. In the absence of such
information, the FSP is not required to provide additional compensation in this
regard.
It is also unclear how the Applicants met the alleged $460,000 in payments to the
builder. The Applicants say they borrowed privately and from friends to pay the
builder. Save, however, for providing a statutory declaration from Mr GA, they have
not provided supporting information about the source or cost of the funds used to pay
the builder.
The Applicants say Mr GA worked for the concreter who performed the
demolition/excavation work at the Property. On 31 August 2015, Mr GA made a
statutory declaration stating that:
he lent the male Applicant $27,000 at bank interest rates
the male Applicant was to start paying him a few hundred dollars a month once
he received money from the FSP, and
he has not received any repayment from the male Applicant and this has
interfered with his ability to study.
Mr GA has not provided details of the interest rate(s) charged and his statutory
declaration provides little supporting information about the Applicants‟ claimed loss.
In any event, if, as he says, Mr GA lent the male Applicant the $27,000 “at bank
intere st rates”, the Applicants are in no worse position for having borrowed from Mr
GA than they would be had they obtained the loan funds earlier from the FSP.
In the absence of information to show what (if any) additional costs the Applicants
incurred in reli ance on the FSP‟s misrepresentation that the Loans were approved,
the loss for which the FSP must compensate the Applicants is the interest differential
between the FSP and Bank S, being $1,083.60.
The information does not support the Applicants’ claim for penalty interest
paid to the builder
The Applicants say they paid $845 per day in penalty interest to the builder due to
the FSP‟s delay in releasing progress payments seven and eight. They say they paid
a total amount of $119,680 between 22 April and 30 June 2014.
The building contract makes no mention that the Applicants have to pay $845 per
day in penalty interest if they delay making a progress payment. Clause 16 of the
building contract says:
Case No: 372725 Determination Page 7 of 10
16.1 The builder may charge the owner interest at the rate stated in Item 10 of Schedule 1 from
the day on which an amount fall due to be paid to the builder up to and including the day that
amount is paid.
Item 10 of Schedule 1 says if there is no interest rate stated then the applicable rate
is the post-judgment rate applicable to judgments in the NSW Supreme Court.
Between 1 July and 31 December 2014, this annual rate was 8.5%.
Although given the opportunity to do so, the Applicant have not provided receipts or
other information to establish that they paid any penalty interest to the builder. I am
therefore unable to conclude that the Applicants paid penalty interest to the builder
under the building contract.
Accordingly, the FSP is not required to compensate the Applicants for their alleged
penalty payments under the building contract.
The information does not support the Applicants’ claim for rent
The Applicants say that the FSP should compensate them for rent of $800 per week
(plus an unspecified penalty) they have been required to continue to pay because of
delay in the progress of the build. They say that had the FSP “honoured the contract
and [made] progress payments to the builder as per the contract… the house would
have been finished and we would be living there … at the latest [by]
January/February 2015”.
The FSP‟s loan processing notes (Notes) document the Applicants‟ request for a
“construction loan to build a large investment property” . The Notes describe the
supporting security for the Loans as “investment property under construction”. When
assessing serviceability for the Loans, the FSP factored in rent (at $2,000 per week)
expected to be derived from the newly constructed house at the Property.
The contemporaneous material contained in the FSP‟s Notes suggests that the
Applicants did not intent to move into the Property but instead anticipated leasing the
Property.
Further, there are inconsistencies in the information provided as to whether the
Applicants continued to rent during the construction period. In early March 2014, the
F SP‟s Notes document that the Applicants were renting a townhouse. However in
September 2014, when assessing serviceability on their application for further funds
to complete the construction, the FSP‟s Notes show that it relied on a family
member‟s signed letter stating that “the Applicants live rent free in a home provided
by family ” .
In contrast, the Applicants say that upon signing the building contract, they leased
the premises in which they are currently living for 7 months, and then extended it for
a further 3 months. They have provided a couple of pages of what appear to be
separate tenancy agreements for the same premises; one showing a rental term from
1 July 2013 until 31 January 2014, and the other showing a rental term from 30
December 2013 until 28 December 2014.
The Applicants may have suffered loss in terms of rental income not received from
the Property. However the Applicants have provided no information to show that the
Case No: 372725 Determination Page 8 of 10
FSP‟s delay in releasing progress payments seven and eight caused a delay in the
construction by the builder and hence resulted in a loss of rental income.
On balance, I am not satisfied that the Applicants are entitled to be compensated for
rent they claimed to have paid because:
the FSP Notes show that the Applicants‟ i ntended to use the Property as an
investment property and therefore would have had to pay rent in any event
even if that were not the case, it has not been shown that rent was paid by the
Applicants, and
it has not been shown that the delay in the progress payments resulted in a
delay in the construction of the Property.
The transfer of funds from Bank S to the FSP did not cause loss
The Applicants say that , based on the FSP‟s misrepresentation, they redrew
$348,243.60 from their existing loan with Bank S o n 13 May 2014 and transferred
these funds to the FSP. The Applicants have not provided a copy of the Bank S
account statement showing this transfer but there is a credit of this amount to their
transaction account with the FSP ending 6430.
The Applicants have not explained why they transferred these funds from Bank S to
the FSP. It appears that the Applicants are claiming that they had to pay interest on
these funds to Bank S while they were not earning interest with the FSP.
The Applicants withdrew $348,000 of the Bank S funds 17 days later on 30 May
2014. It would appear that the Applicants used the Bank S funds to make progress
payments to the builder prior to the FSP making its progress payments. This means
that even if the Bank S funds had not been transferred to the FSP, the Applicants
would not have earned interest on them as they were withdrawn soon afterward .
The Applicants have not been able to show that they suffered a loss by the transfer
of funds from Bank S to the FSP. Accordingly no compensation is payable.
The FSP’s delays caused the Applicants undue stress and inconvenience
The Financial Ombudsman Service (FOS) has the power to award compensation for
non-financial loss an applicant has suffered. FOS takes a conservative approach to
awards for non-financial loss. The maximum amount that can be awarded in this
dispute is $3,000 per claim.
The FSP‟s delay in approving the Land Loan caused the Applicants considerable
stress and inconvenience given that they were required to provide additional
documents to the FSP even after they had satisfied the LPI‟s requirements . The
Applicants had to contact the FSP a number of times between 17 April and 21 July
2014 to follow up on settlement. On that basis I consider it fair that the FSP
compensate each Applicant $750 ($1,500 in total) for their non-financial loss in this
regard.
The FSP has accepted that there was an “unacceptably long delay” in releasing
progress payments seven and eight to the builder. The Applicants have described
that the builder made a number of calls to them chasing payment, which is confirmed
by the builder‟s emails to them and to the FSP.
Case No: 372725 Determination Page 9 of 10
In the circumstances I consider it fair that the FSP should compensate each
Applicant $1,000 ($2,000 in total) for the stress and inconvenience they suffered in
relation to the delayed progress payments . This amount appears reasonable given
that the FSP‟s delay in releasing progress payments added to the Applicants‟ earlier
stress and inconvenience caused by the FSP‟s delay in approving the Land Loan.
The FSP responded appropriately to the Applicants’ complaint
The Applicants have complained about the FSP‟s response to their complaint.
However, the Applicants have not provided any information to support their claim as
requested.
According to the information the FSP has provided, the Applicants first raised a
complaint internally with the FSP on 20 August 2014 and lodged the FOS dispute on
26 August 2014.
The FSP has worked with the Applicants throughout the FOS dispute in trying to get
the information it needed to release progress payments seven and eight to the
builder. It has also held meetings with them in attempt to resolve the issues in this
dispute. The available information suggests the FSP responded appropriately to their
complaint.
FOS does not award punitive compensation
The Applicants complain that FOS has not punished the FSP to “teach it a lesson for
its actions causing them misery”.
FOS does not require a financial services provider to pay compensation to an
applicant in order to punish or censure the provider. An award of compensation is
made to compensate the applicant for loss. When deciding on the compensation for
loss, FOS does what it considers fair in all the circumstances
Based on the reasoning set out in this Determination, I consider it fair in this dispute
that the FSP compensate the Applicants for their:
financial loss of $1,083.60 (plus simple interest on that amount at 4% per
annum from 28 April 2014 to the date of payment), and
non-financial loss of $3,500.
Case No: 372725 Determination Page 10 of 10
3 Supporting information
3.1 FOS process
This dispute has been the subject of a Recommendation substantially in favour of the
Applicants (except in relation to the loss amount claimed), which was not accepted
by the Applicants.
I have considered all the material submitted by the parties, both before and after the
Recommendation was issued, in order to reach my decision. I am satisfied that the
material I relied upon in reaching my findings has been exchanged between the
parties.
I have had regard what is fair in all the circumstances, having regard to legal
principles, applicable industry codes or guidance as to practice, good industry
practice and previous relevant decisions of FOS or its predecessors (though I am not
bound by these).