Determination 372690

Delay in assessing construction loan application and progress payments

FirmFinancial Firm (Unknown - Credit)
Decided2016-01-11
ProductCredit · Home loan
OutcomeFor the complainant in part
Amount awarded$11,643
Non-financial loss$2,000
Amount claimed—
SourceAFCA PDF

Summary

The applicants, represented by a broker, complained that the FSP delayed assessing their construction loan and progress payments. AFCA found no power to review credit risk decisions and no unreasonable delay in progress payments, but found a 25-day unreasonable delay in June and July 2011 and ordered lost rental income, professional costs, interest and non-financial loss.

AFCA cannot review credit risk decisions, but an unreasonable delay in loan assessment that causes measurable loss is compensable.

Issues

Subjects and remedies

broker or intermediarypay compensationpay interestpay non financial loss

Related

All Financial Firm (Unknown - Credit) determinations · Find similar determinations

Text of the determination

Determination Case No: 372690 Determination Page 1 of 9 Case number: 372690 16 December 2015 1 Overview 1.1 Dispute The Applicants have appointed a representative to act on their behalf in this dispute. The Applicants intended to build two units on SH property which was purchased under a Family Trust. To do so, in October 2010 they applied for a construction loan with the Financial Services Provider (FSP), which was approved in July 2011.The loan was to be secured by SH property and B property, which the FSP already held as security for existing borrowings. The dispute is about whether the FSP delayed:  The assessment of the October 2010 and May 2011 loan applications.  Making progress payments to the builder. The Case Manager provided the parties with a Recommendation on the issues in dispute. The Recommendation was in favour of the FSP. A copy of the Recommendation is attached to this Determination. The Applicants rejected the Recommendation on the 9 September 2015. The FSP has also put forward information in relation to the issues raised by Applicants in rejecting the Recommendation. 1.2 Issues and Key findings Were the findings of the Recommendation correct? The findings contained in the Recommendation were correct and are adopted in this Determination. After the Recommendation the Applicant has raised further issues which I consider below. Did the FSP unreasonably delay the assessment of the October 2010 loan application? The FSP‟s decision about the acceptable borrower and construction me thod is a credit risk assessment that the Financial Ombudsman Service (FOS) does not have the power to review. Did the FSP unreasonably delay the assessment of the May 2011 loan application? Due to the FSP‟s delay between 10 June 2011 and 5 July 2011, the completion of the units on the SH property was delayed by the same period. Case No: 372690 Determination Page 2 of 9 Did the FSP unreasonably delay making the progress payment to the Builder? The FSP made the first progress payment within three weeks of approving the construction loan. The FSP completed the tasks required in a reasonable time. Are the Applicants entitled to any compensation? The FSP should pay to the Applicants $15,196.00 1.3 Determination This Determination is substantially in favour of the FSP. However, because the FSP unreasonably delayed processing the May 2011 loan application, the FSP should pay to the Applicants $15,196.00 in compensation within 14 days of their acceptance of the Determination. If the FSP fails to make the payment, it will be required to pay the Applicants interest at 4% pa on a simple interest basis for each day the payment is not made. Case No: 372690 Determination Page 3 of 9 2 Reasons for Determination 2.1 Were the findings in the Recommendation correct? I have decided this case on its merits, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions. I have taken into account all the material submitted by the parties, both before and after the Recommendation. I am satisfied that the documentation I have relied on has been provided to both parties. I am satisfied that the case manager‟s Recommendation contains an accurate summary of the dispute, the issues to be determined, any applicable paragraphs of the Terms of Reference and any relevant law. 2.2 Did the FSP unreasonably delay the assessment of the October 2010 loan application? The information does not show that the FSP delayed assessing the application because of the National Consumer Credit Code The Applicants ‟ representative says that the FSP delayed in responding to the Applicants May 2011 application after they had provided further information to the FSP in April 2011. This was because of changes that had resulted from the National Consumer Credit Code and a delay by the FSP in informing the Applicants that a new loan application had to be submitted. There is no information to support this claim. The decision about whether the borrower was acceptable was a credit risk decision for the FSP I agree with w hat was said by the case manager that the FSP‟s decision about what type of borrower is acceptable is a credit risk decision that FOS does not have the power to review. The FSP’s decision to seek clarification about the nature of the security was justified The Applicants ‟ representative disagrees with the way that the FSP classified the house construction and says that credit risk decisions do not determine „ whether a house is a house or a transportable home ‟ . Whether the house can be transported determines this question. The FSP should not have assumed it was a mobile home when seeing a reference in the paperwork to kit. In December 2010, the FSP told the Applicants that it required a fixed price building contract before it would approve the loan. The building contract for each unit stated that approximately $170,000 was required for „ fabrication of the kit ‟ . The FSP said it would not provide funds upfront for this cost and that it would not make a progress payment to the builder unless the house was fixed to the site. The Case No: 372690 Determination Page 4 of 9 building contracts in their original form were therefore not acceptable to the FSP because of the ref erence to „fabrication of the kit‟. I agree with what the case manager said in the Recommendation that the FSP‟s decision not to accept the building contract was a credit risk decision because it was concerned about the construction method, and the nature of the units it was taking as security. Even if it were the case that the units were fixed to the land and not mobile in nature, it appears that the building contract did not say this. Therefore, the FSP was entitled to raise this as an issue. Rather than declining the loan application, the FSP said that it would reconsider the matter if the Applicants provided an amended builders contract showing progressive payments for each stage and removal of the reference that a payment was required for „Fabrication of Kit‟. These were reasonable requests for the FSP to make. By February 2011, the Applicants had not supplied the amended documents and the loan application lapsed. I agree with the case manager that as at February 2011, when the original loan application lapsed, the FSP had not caused any unreasonable delay in assessing the application. 2.3 Did the FSP unreasonably delay the assessment of the May 2011 loan application? The FSP Valuer ’s enquiries raised a concern about B property As stated in the Recommendation, on the 20 May 2011, the Valuer told the FSP that the B property was only zoned as suitable for two dwellings , and that they had asked Council whether development approval for three dwellings existed (Development Approval). Council replied that this approval was not recorded for the property. The Valuer told the FSP its valuation of the property was subject to confirmation that approval existed. Because of this issue, the FSP placed its consideration of the loan application on hold until this matter was resolved. The Applicants representative says that the Development Approval issue should not have held up the loan assessment because:  The FSP already held B property as security for existing loans and had obtained prior valuations of the property, which had not raised this issue.  The FSP refused to provide contact details of its Valuer and these were eventually obtained by the Applicant when he was later independently contacted by the Valuer.  The Valuer‟s enquiries with the Council had been superficial and inadequate.  While the Recommendation says that proper enquiries of the Council by the FSP were enough to reveal the development had been approved , he does not recall this being the case. If his recollection is correct, the Applicants contacted Case No: 372690 Determination Page 5 of 9 Council on 23 May 2011 and approval documents were provided by Council to the Applicant. Regardless of who contacted the Council and resolved the Development Approval issue, given the issue had been raised, the FSP was entitled to have it resolved so that it could be satisfied the security it was intending to take over B property in relation to the new loan meet the zoning requirements. It was open to the Applicants to contact Council to obtain the required documents to establish that approval was in place, and this could have been done without any prior discussion with the Valuer. There is no information to show that the FSP told the Applicants that the investigation and resolution of issue was to be undertaken solely by the FSP. As the Applicants were providing B property as security, it was also incumbent on them to be proactive in resolving the issue, and providing to the FSP evidence from Council that it had issued approval for the construction of the three dwellings on the property. The fact the FSP already held B property as security for the existing loans and had obtained prior valuations of the property, which had not raised this issue, does not change my view given the property was being take as security for the new loan. For these reasons, the FSP acted appropriately in relation to this issue . The FSP did not delay the assessment of loan application before 9 June 2011 After reviewing the information, I agree with what the case manager has said that there is no information to show that the FSP caused an unreasonable delay in assessing the loan application before 9 June 2011. The Applicants representative by email dated 9 June 2011 provided a brief chronology of the loan assessment, and stated that it did not believe the loan assessment had been unreasonably delayed at that stage. My view is supported by FOS ‟ Banking Specialist who after reviewing relevant information has said that in her opinion t he FSP‟s loan assessment had not been unreasonably delayed at this stage. The FSP delayed the assessment of loan application from 10 June 2011 and should have reviewed the Family Trust Deed earlier I also agree with what the case manager has said that the information shows that the FSP caused an unreasonable delay in assessing the loan application between 10 June 2011 and 5 July 2011, and that the FSP should have reviewed the Family Trust Deed earlier. I adopt the case manager‟s reasons for saying this and the se are repeated in this Determination. Case No: 372690 Determination Page 6 of 9 2.4 Did the FSP unreasonably delay making progress payments to the Builder? The FSP needed to be satisfied about other matters before it released the first progress payment As stated in the Recommendation, the FSP approved and issued the loan documents on 5 July 2011 and these were returned by the Applicants on 8 July 2011. The first progress payment was released on the 27 July 2011. The Applicant's representative says that the payment request and invoices (Documents) were included in the envelope with the contract documents when he first hand delivered them to the F SP‟s document CBD area on 8 July 2011 . The FSP accepts that this is the case, but adds that on the 14 July 2011 further information was requested. As stated in the Recommendation, it was necessary for the following to occur before the FSP was in a position to release the first progress payment:  The FSP requested Council approved building plans for the SH property and the correct builders warranty insurance certificate; and  The FSP ordered a progress inspection report in relation to the work already completed on the SH property (Information). It appears that the Information was received between 15 and 27 July 2011. I agree with the view of the Banking Specialist that this Information was required by the FSP, and until it was received, the FSP was entitled to not make the first progress payment to the builder. Given the above, I am not satisfied that the FSP unreasonably delayed making the first progress payment to the builder because it was necessary for the FSP to obtain the Information before it made the payment. 2.5 Did the FSP cause the Applicants to suffer any loss? The FSP caused the Applicants a loss of net rental income Due to the FSP‟s delay between 10 June and 5 July 2011, the completion of the units on the SH property was likely to have been delayed by that same period. The SH area was experiencing an economic boom at the time , and the units attracted tenants immediately at high prices. The Applicants have provided the rental schedule for the 2011/2012 financial year, which shows:  The SH units were available for rent for 38 weeks in that financial year.  Gross rental income was $150,968.  Water charges were $5,496. Gross rental income was $8,666.67 per month for each unit, which equals $7,122 for each unit for 25 days. This is $14,244 of lost gross rental income. Case No: 372690 Determination Page 7 of 9 Interest on the fully drawn loan of $1,090,522 at 6.81% pa for 25 calendar days is $5,086. The Applicants would have also had approximately $515 of extra water charges. Based on these figures, the Applicants‟ lost net rental income for 25 days was $8,643. The FSP should therefore pay to the Applicants $8,643, plus interest of $1,553 (total $10,196). I consider it fair and appropriate to calculate interest from 1 July 2011 to December 2015 at 4% pa (calculated on a simple interest basis). The FSP should compensate the Applicants $3000 for professional costs The Applicants‟ representative has raised certain questions regarding the $3000 compensation limit stated in FOS‟ Terms of Reference (TOR) that can be awarded towards legal or other professional costs incurred by an applicant in pursuing a dispute with FOS. Under paragraph 9.4 of FOS‟ TOR, FOS may ask a financial services provider to contribute to the legal or other professional costs incurred by an applicant in pursuing a FOS dispute to a maximum of $3000 (unless there are exceptional circumstances to say that the provider should contribute more). FOS determines, based on the available information, whether a financial services provider should contribute to such costs, and whether there are exceptional circumstances to justify an award greater than $3000. In deciding whether exceptional circumstances exist, we consider what is fair in the circumstances and take into account such matters as:  The complexity of the dispute.  Whether the d ispute raised legal issues on which, despite FOS‟ involvement, the applicant reasonably needed advice.  Whether the d ispute involved complex financial data on which, despite FOS‟ involvement, the applicant reasonably needed finance advice.  Whether the applicant genuinely required expert assistance. The representative says:  He is employed as a broker and also provides accounting services, and that it was necessary to involve the accounting practice to resolve the „valuation issue‟ .  The Applicants incurred professional accounting costs of $21,077. On the available information, there are no exceptional circumstances that justify the Applicants being awarded more that $3000 towards their cost of pursuing the dispute. Case No: 372690 Determination Page 8 of 9 FOS’ assessment of costs claimed Costs incurred FOS’ assessment $6300 was incurred in dealing with the „valuation delay and concern‟ . The Applicants say that the ir accountant‟s involvement was necessary because of their understanding of the development. For the reasons referred to earlier, the FSP was entitled to seek resolution of the D evelopment A pproval issue before the loan application could be progressed any further an d any costs the Applicants have incur red in relation to this should be borne by the Applicants. $3500 was inc urred for providing the chronology and the supply of any documents to FOS that would have been incurred by the Applicants if they had been dealing directly with FOS. While I see no significant reason why a large part of this t h i s information could not ha ve been provided by the Applicants - to the extent the Applicants required a ssistance , the $3000 awarded provides sufficient compensation for these costs. The remaining costs relate to dealing with the FOS dispute. The Applicants representative says given the complex nature of the issues and given the „interesting‟ response from the FSP, the Applicants were required to be represented. It was largely not necessary for the Applicants to be represented by accountants to deal with the issues raised by the dispute , as the issues were not of such a complex nature that required their involvement. For example, accounting services were not needed to present expert information to respond to an argument raised by the FSP . The FSP should pay to the Applicants $3000 towards their professional costs. The FSP should compensate the Applicants $2000 for stress and anxiety The Applicants representative says that the $1000 non-financial loss compensation awarded by the case manager is inadequate given that Applicants suffered a high level of stress because:  The builder threatened to take legal action to recover funds for the completed building work.  They worried that the FSP might not approve a continuation of other existing lending if the FSP continued to incorrectly consider the security for the property as unsatisfactory because of the Development Approval issue. Their concern increased over time as it was proving more difficult to convince the FSP that the Valuer had been incorrect with their initial enquiries about the Development Approval.  The stress extended to the Applicants personal relationship and long-standing relationship with the representative ‟s office . Case No: 372690 Determination Page 9 of 9 The FSP says that while there were some delays that were caused by it, the Applicants should receive no compensation because the circumstances of the dispute did not lead to unreasonable or excessive inconvenience to the Applicants. While it is understandable that the Applicants would have experienced stress because of the FSPs delay in approving the loan between 10 to June and 5 July 2011, for the reasons discussed above, I do not accept that the FSP was not entitled to seek information to show that B property met the planning requirements (this was necessary so that the FSP could be satisfied the security for the new and existing loan was not affected by the planning issue). Given the circumstances of this dispute, including the fact that the Applicants contributed to the situation they found themselves by starting construction work before to they had received unconditional loan approval from the FSP, the FSP should pay $1000 to each Applicant (a total of $2000) as non-financial loss arising from the FSP ‟s delay in assessing the loan application between 10 June and 5 July 2011. 2.6 Other Matters Time given to Applicant to respond to Recommendation was appropriate The Applicants‟ representative has requested information as to why the Applicant s were required by FOS to provide a response rejecting the Recommendation within 7 days. The case manager sent a letter to the Applicants dated 26 August 2015, requesting detailed reasons within 7 days as to why they rejected the Recommendation. The letter also stated that FOS will only agree to an extension of time to provide a response or further submission in exceptional circumstances, the decision maker will issue a final decision on the information available, and that any further submissions received before the final decision was issued would be considered by the decision maker. FOS determines under its TOR, what timeframes parties are required to provide a response. The timeframe given to the Applicants to provide their response was per FOS‟ normal time frames. As such, I consider that FOS acted as per its normal process in informing the Applicants that they were expected to provide reasons for their rejection of the Recommendation within 7 days. Applicants ’ request to have a meeting with FOS The A pplicants‟ representative has requested that a FOS representative meet at their office in Western Australia to discuss the dispute, and to clarify many of the points raised so that FOS understands what has occurred between the parties. I have considered the request for a meeting and formed the view that based on the available information I have an understanding of the circumstances of the dispute and as such, a meeting was not considered necessary. Recommendation Credit - Business Finance - Business Loa ns - Instructions - Delay 3 Overview 3.1 Dispute The Applicants purchased the SH property as a Family Trust asset. The Applicants intended to construct two units on the SH property, and applied for a construction loan in October 2010. The FSP approved the construction loan in July 2011. The Applicants say that the FSP unreasonably delayed its assessment of the construction loan application, and delayed making progress payments to the Builder. 3.2 Issues and key findings Did the FSP unreasonably delay its assessment of the October 2010 application? The FSP‟s decision about the acceptable borrower and construction method is a credit risk assessment that FOS does not have the power to review. Did the FSP unreasonably delay its assessment of the May 2011 application? It was reasonable for the FSP to seek confirmation that the dwellings on the B property were approved by the local Council. However, the information it was then provided indicated that it was likely that the dwellings were approved. The FSP had previously taken the B property as acceptable security, and should have taken more active steps sooner to satisfy itself that the dwellings were approved. Did the FSP unreasonably delay making progress payments to the Builder? The FSP made the first progress payment within three weeks of approving the construction loan. The FSP completed the tasks required in a reasonable time. What loss did the FSP cause to the Applicants? The Applicants suffered a loss of net rental income, increased professional costs and stress and inconvenience. 3.3 Recommendation This Recommendation is substantially in favour of the FSP. However, the FSP did cause a 25 day delay, and should compensate the Applicants for the loss caused. The FSP should pay the Applicants $12,643. Case No: 372690 Recommendation Page 2 of 8 4 Reasons for Recommendation 4.1 Did the FSP unreasonably delay its assessment of the October 2010 application? FOS cannot consider a dispute about the FSP’s credit risk decisions FOS does not have the power to consider a dispute about a financial services provider ‟s assessment of the credit risk posed by a borrower or the security to be required for a loan. However, FOS can consider a dispute about whether a financial services provider has unreasonably delayed its loan assessment, or unreasonably delayed providing the funds for an approved loan. The Applicants says that the FSP unreasonably delayed its assessment of the October 2010 loan application The Applicants say that the FSP initially caused unreasonable delay because:  It declined the original loan application because it was concerned about the involvement of the Family Trust.  Once the Family Trust issue was resolved, the FSP declined the loan application because it incorrectly believed the „kit‟ home was a transp ortable home. In considering this matter, I have reviewed the parties‟ responses, the FSP‟s credit assessment notes and decision comments. The FSP’s decision about an acceptable borrower is a credit risk decision The FSP says it was initially unwilling to approve a construction loan because its policies prevented construction lending where a trust was involved. In this case, the Family Trust was the beneficial owner of the SH property. The FSP says that its policy was later relaxed, and by 30 November 2010 it had deemed the loan application “conditionally eligible”. The FSP‟s decision about what type of borrower is acceptable for each loan type is a credit risk decision that FOS does not have the power to review. The Applicants might argue the FSP misapplied its own policy, or delayed in considering whether to make an exception to their policy. However, even if this was shown, the Trust issue did not affect the final timing of the eventual loan approval. This is because the October 2010 application lapsed be cause of the FSP‟s concerns with the building contract and construction method. The FSP’s decision not to accept the building contract was a credit risk decision In December 2010, the FSP told the Applicants that it required a fixed price building contract before it would approve the construction loan. The building contract for each unit stated that approximately $170,000 was required for “fabrication of the kit”. The Case No: 372690 Recommendation Page 3 of 8 FSP said it would not provide funds upfront for this cost, and that it would not make a progress payment to the Builder unless the house was fixed to the site. The building contracts in their original form were not acceptable to the FSP. The Applicants disagree with the way that the FSP classified the house construction. However, the FSP‟s decision about whether it was comfortable with the construction method and building contract was a credit risk decision relating to the security that FOS does not have the power to review. Rather than declining the loan application, the FSP said that it would reconsider the matter if the Applicants provided an amended construction payment schedule. By February 2011, the Applicants had not supplied the FSP with such a schedule, and the loan application lapsed. As of the time (February 2011) when the original application lapsed, the FSP had not caused unreasonable delays. 4.2 Did the FSP unreasonably delay its assessment of the May 2011 application? A new loan application was lodged in May 2011 The Applicants lodged a new loan application in May 2011, and the FSP provided conditional approval. One of the conditions of approval was that the FSP was satisfied with the valuation of the security properties, which included the A pplicants‟ B property. The Applicants had constructed three units on the B property in 2006, but the B property remained on a single title (i.e. it had not been sub-divided). The Valuer’s initial enquiries raised a concern about the B property On 20 May 2011, the Valuer reported to the FSP that the B property was only zoned as suitable for two dwellings. The Valuer had asked the local Council whether the Applicants had development approval for three dwellings. The Council had replied that there was no development approval listed for the B property. The Valuer told the FSP its valuation of the B property was subject to confirmation of development approval. The FSP placed its consideration of the construction loan application on hold until this matter was clarified. The Applicants say that the development approval issue should not have held up the loan assessment. This is because:  The FSP already held the B property as security for existing loans, and had obtained prior valuations of the property. These previous valuations had not raised any concerns, and the FSP had accepted the valuations.  The Valuer‟s enquiries with the Council had been superficial and inadequate. It was reasonable for the FSP to seek confirmation of development approval The FSP was relying on the B property as providing security of over $1 million. If the dwellings on the property did not have appropriate development approvals, this would significantly affect the value of the B property. In the circumstances, it was Case No: 372690 Recommendation Page 4 of 8 reasonable for the FSP to seek confirmation of proper approvals before it continued its loan assessment. The Applicants argued that the FSP had previously accepted the B property as valid security. However, the FSP was not obliged to approve new lending secured by the B property if it discovered there was a defect with its existing security. The fact that it was reasonable for the FSP to be concerned is reflected in Mrs S‟s email to the construction company that built the dwellings on the B property. In her email dated 9 June 2011 to the builder for the B property, Mrs S expressed concern about the consequences if there had not been proper approvals granted. This suggests that the Council‟s response had left the Applicants concerned about whether all proper approvals had been obtained. As of 9 June 2011, the FSP had not unreasonably delayed its loan assessment Between 20 May and 10 June 2011, there was communication between the relevant parties about the development approval matter. One of these parties was the company that provided the Applicants with accountancy, financial advice and mortgage broking services (the Broker). The Applicants expressed frustration to the Broker about the FSP‟s unwillingness to accept that the B property had development approval. The Broker responded in an email dated 9 June 2011 and stated that:  The Broker provided a brief chronology of the loan assessment, and stated that it did not believe the loan assessment had been unreasonably delayed at that stage.  The Broker‟s office had contacted the Council directly and had also been told that the there was no development approval. The Broker noted that Mr S was the “only person [the Council] had confirmed it too”. I have asked a FOS Banking Specialist to review the available documents relating to the FSP‟s loan assessment. The Banking Specialist has had extensive experience in the banking and financial services industry and regularly provides FOS with advice about banking practice. The Banking Specialist‟s view is that the FSP‟s loan assessment had not been unreasonably delayed at this stage. Based on the available information, including the Banking Specialist‟s opinion, it has not been established that the FSP caused an unreasonable delay before 9 June 2011. The FSP received documents indicating the B property had development approval By 10 June 2011, the FSP had the following information available:  Its previous valuation of the B property from October 2009, which stated that there were three dwellings and that its “current use” was “permitted”.  A copy of a Council approved Building Licence dated 17 March 2006 and stamped building plans.  A Council rates notice referring to a multiple dwelling property. This suggests that the Council was aware of the number of dwellings and had approved these. Case No: 372690 Recommendation Page 5 of 8 The Valuer was not satisfied that the Building Licence was sufficient confirmation of proper Council approval. The Valuer noted that the Licence required compliance with any further conditions in a development approval. While this was true, the Licence did not suggest that such a development approval was yet to be approved. As outlined above, it was reasonable for the FSP to initially have concerns. However, the information provided to the FSP by this stage (10 June 2011) indicated that it was highly likely that the Counci l had granted development approval. There was not much more the Applicants could provide, short of the actual development approval. The Applicants had already asked the Council to provide a copy of this and were waiting for a response. Active involvement from the FSP was sufficient to resolve the issue Between 13 June and 28 June 2011, the following occurred:  The FSP suggested that the Broker might want to contact the Valuer directly to discuss the matter.  The Valuer told the Broker it had provided an updated report to the FSP on 21 June 2011. FOS has not received a copy of any updated report, and it is unclear what this report said. On 28 June 2011, the FSP‟s credit area involved an FSP Valuation Risk Manager. The Valuation Risk Manager contacted the Council. Within 24 hours, the Council provided the FSP a copy of the Council‟s letter dated 15 December 2005 confirming its approval of the triple dwelling. This shows that proper enquiries to the Council from the FSP were enough to reveal the development approval. The FSP should have already vetted the Trust Deed The FSP proceeded to vet the trust structure, and then unconditionally approved the construction loan on 5 July 2011. The FSP had decided not to vet the Trust Deed until the B property issue was resolved. This may have been to save time and expense if the loan application did not proceed. However, the FSP should have already vetted the Trust deed before July 2011. This is because:  The Family Trust was the beneficial owner of the SH property, and the FSP had been aware of this since October 2010. The FSP already had security over the SH property.  If asked, the Applicants were willing to bear the expense of the Trust vetting in order to ensure the soonest possible loan approval. The FSP unreasonably delayed its assessment of the loan application By 10 June 2011, the FSP had significant information to support that the B property had a development approval. It is also significant that it already held security over the B property and had prior valuations. Case No: 372690 Recommendation Page 6 of 8 In the circumstances, it would have been reasonable for the FSP to take active steps earlier, such as involving the Valuation Risk Manager. The period between 10 June and 5 July 2011 represents an unreasonable delay caused by the FSP. 4.3 Did the FSP unreasonably delay making progress payments to the Builder? The FSP needed to complete several more tasks before it released the first progress payment The FSP approved the construction loan on 5 July 2011 and issued the construction loan contract documents. The Applicants returned the completed documents to the FSP on 8 July 2011, and the FSP released the first progress payment on 27 July 2011. In between those dates the following occurred:  The FSP requested council approved building plans for the SH property, the corr ect Builder‟s Warranty Insurance Certificate, progress payment authority forms and the Builder‟s invoices.  The FSP ordered a progress inspection report in relation to the work already completed on the SH property. The Applicants say that the FSP lost the progress payment authorities and invoices that they provided to the FSP on 8 July 2011, and had to request them again on 17 July 2011. However, the Applicants have not provided any information to support that the authorities and invoices were provided on 8 July 2011. The invoices provided by the FSP have fax header‟s stating 17 July 2011. The Banking Specialist‟s view is that the information required by the FSP was necessary and that the FSP completed the required tasks within a reasonable time. Based on the available information, it has not been established that the FSP delayed in releasing the progress payments. 4.4 What loss did the FSP cause to the Applicants? The FSP caused the Applicants a loss of net rental income Due to the FSP‟s delay between 10 June and 5 July 2011, the completion of the units on the SH property was delayed by that same period of time. The SH area was experiencing an economic boom at the time and the units attracted tenants immediately at high prices. The Applicants have provided the rental schedule for the 2011/12 financial year. This states that:  The SH units were available for rent for 38 weeks in that financial year  Gross rental income was $150,968  Water charges were $5,496 Gross rental income was $8,666.67 per month for each unit, which equals $7,122 for each unit for 25 days. This is $14,244 of lost gross rental income. Case No: 372690 Recommendation Page 7 of 8 Interest on the fully drawn loan of $1,090,522 at a percentage rate of 6.81% for 25 calendar days equals $5,086. The Applicants would have also had approximately $515 of extra water charges. Based on these figures, the foregone net rental income for 25 days was $8,643 . FOS can award compensation for the cost of seeking professional advice Our processes are designed so that applicants can bring disputes to FOS without needing professional assistance. So, if an applicant chooses to be represented, this will usually be at their own cost. In some limited cases, we may require a financial services provider to reimburse the reasonable fees charged by an adviser. When we assess this issue, we will take into account the complexity of the dispute and whether the dispute raised issues that reasonably required the applicant to obtain expert advice. The FOS Terms of Reference state that FOS will not require a financial services provider to contribute more than $3,000 to an applicant‟s cost of pursuing the dispute, unless exceptional circumstances apply. The FSP should compensate the Applicants for some of the Broker’s extra charges The Applicants have claimed compensation of $21,077 in relation to the costs they incurred using the professional services of the Broker. These include the costs of dealing with the loan assessment process, and the subsequent cost of pursuing the FOS dispute. The Applicants have provided the Broker‟s invoices to support their claim. It was reasonable for the Applicants to incur the following costs of using the Broker‟s services:  In June 2011, for assistance in dealing with the Council, Valuer and the FSP.  To provide a chronology and documents (includi ng correspondence, emails etc) from their file records so that the Applicants could pursue a dispute against the FSP. The FSP should compensate the Applicants $3,000 for their costs incurred in this regard. The Applicants elected to use the Broker as their representative in the FOS dispute. A substantial proportion of the costs claimed by the Applicants relate to this. The circumstances of this dispute are not so exceptional that the FSP should be required to contribute more than $3,000 to the Applicants‟ c osts. The FSP caused the Applicants stress and inconvenience The Applicants have claimed compensation for the stress and inconvenience of dealing with the FSP‟s delay. By late June 2011, the Builder was threatening to take legal action to recover funds it was owed for completed building work. Therefore, it is understandable that the Case No: 372690 Recommendation Page 8 of 8 Applicants experienced a high degree of stress due to the delay in the construction loan approval. However, the Applicants made a significant contribution to the situation in which they found themselves. The Applicants had commenced construction work prior to receiving unconditional loan approval from the FSP. Despite this, the FSP‟s delay in assessing the loan application would have caused stress and inconvenience to a reasonable applicant in the circumstances. The FSP should pay $500 to each Applicant ($1,000 in total) as compensation for their non- financial loss.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.