Text of the determination
Determination
General Insurance - Domestic Insurance - Home Building - FSP Decision - Claim
Amount
Determination
Case No: 372598 Determination Page 1 of 9
Case number : 372598 20 March 2015
1 Overview
1.1 Dispute
The Applicants claimed for cracking and movement-related damage to their home
in April 2012, said to have been caused by a number of leaking pipes.
The Financial Services Provider (FSP) offered a cash settlement of $15,908 to
repair damage it considered covered by the policy. It declined repairs relating to
the home’s cellar on the basis this damage arose from :
gradual causes and deterioration
building and foundation movement.
1.2 Issues and key findings
Is FSP responsible for repairs associated with cellar damage?
The FSP is responsible for repairs associated with the cellar damage because
there is insufficient evidence to prove the damage was caused by an event which
is excluded under the policy.
What is an appropriate cash settlement?
Although denying liability in respect of the damage to the cellar, the FSP’s cash
settlement offer inadvertently included the costs associated with repair of that
damage. The FSP has confirmed that, despite this error, it is prepared to honour
its original offer of settlement.
The Panel considers the basis of the FSP’s offer is adequate provided:
the FSP also meets the likely cost escalations that have resulted from the
delay in commencing repairs; and
the FSP not only indemnifies the Applicants in respect of all of the repairs to
their building identified in the scope of works (SOW) dated February 2014 but
also indemnifies the Applicants for other work (if any) not specifically identified
within the scope of works which may be exposed by the building contractor
during performance of the work (as envisaged at 1.2 of the SOW).
Should FSP pay compensation for the way it handled the claim?
The FSP should pay compensation for the way it handled the claim because:
it took more than 2 years to decide the claim without any reasonable
explanation for the delay
Case No: 372598 Determination Page 2 of 9
the delay has unusually inconvenienced the Applicants and interfered with
their peace of mind and expectation of enjoyment of their home.
Providing the Applicants provide adequate proof of expenditure, the FSP is also to
compensate the Applicants for the professional costs of their engineer and for
exploration costs.
1.3 Determination
This Determination is in favour of the Applicants.
The FSP is required to indemnify the Applicants in respect of all of the repairs to
their building identified in the scope of works (SOW) dated February 2014
including:
the likely cost escalations that have resulted from the delay in commencing
repairs; and
any other work not specifically identified within the scope which may be
exposed by the building contractor during performance of the work (as
envisaged at 1.2 of the SOW).
If all or any part of the claim is to be cash settled, the settlement is to be based on
quotes obtained no longer that 3 months prior to the actual date of settlement
and, in any event, shall not be for an amount that is less than the offer of
settlement already made by the FSP.
The FSP is also required to pay the Applicants $1,500 pursuant to Paragraph
9.3(b)(i) of the Financial Ombudsman Service Terms of Reference.
Upon receipt of adequate proof of expenditure, the FSP is also to compensate the
Applicants for the professional costs of their engineer up to $3,000 and for
exploration costs up to $2,000.
Case No: 372598 Determination Page 3 of 9
2 Reasons for Determination
2.1 Is FSP responsible for repairs associated with cellar damage ?
FSP must prove the operation of exclusions
The policy covers the Applicants for accidental damage to their home, subject to a
number of exclusions.
There is no dispute the Applicants’ home sustained significant movement related
damage in March 2012. There is also no dispute:
such damage occurred suddenly and rapidly, and was severe
save for the damage to the cellar, the FSP accepts that the damage was
caused by a number of leaking pipes.
The FSP’s engineer (FE) prepared a SOW for repairs to the home. In a meeting in
January 2014, the Applicants’ engineer (HE) apparently agreed the SOW
adequately sets out the work required to repair the home caused by the leaking
pipes and this has not been disputed by the Applicants.
The FSP accepted liability for the claim with the exception of repairs associated
with the cellar damage (see section 3.1 of this Determination), which it contends:
was not damaged by the leaking pipes
was damaged by “ongoing environmental factors”
was excluded on the basis of exclusions relating to gradual deterioration and
earth movement.
Since the Applicants have been able to establish a prima facie claim under the
policy, the onus shifts to the FSP to prove the operation of the exclusions it relies
on with respect to the cellar damage.
Applicant’s engineer says broken pipes caused the damage
The Applicants relied on a report from its engineer HE. He inspected the property
and saw the earthenware pipes at the rear of the house which had obvious breaks
wetting the clay. He said the wetting was consistent with the heave of the soil
beneath the toilet and bathroom area and behind the cellar wall. He concluded an
obvious source of wetting in the region of major movement is responsible for the
movement. Despite the FSP’s contentions in its submissions, nothing in the
material provided supports the FSP’s contention that HE agreed the damage to
the cellar did not result from the leaking pipes and so fell outside the SOW.
Engineer FE’s evidence is not persuasive
The FSP relies on FE’s evidence, who:
suspects the wet patch in the north-east corner and crack in the eastern wall
of the cellar were caused by overflows from the eastern gutter (which he says
has “grossly inadequate” downpipes)
suspects water spilling from the kitchen sink may be marginally contributing to
the dampness at the cellar’s north -east corner
Case No: 372598 Determination Page 4 of 9
says surface water was possibly flowing under the verandah into the cellar,
which would cause significant dampness in the area during winter
says trees (located at the home’s northern boundary) would be extracting
moisture in summer, causing the eastern cellar wall to settle and crack
says the increase in soil moisture at the relevant area did not cause the soil to
heave because the trees were extracting moisture at a faster rate.
Insufficient evidence rain or trees were dominant causes of damage
The Panel accepts:
rains and trees do influence the moisture conditions of soils
buildings constructed on reactive clay can be expected to move (and sustain
movement-related damage) following seasonal changes in soil moisture
conditions
trees can draw moisture from soil, which can then cause soil settlement and
movement related damage to a building.
However, stating obvious natural occurrences falls short of providing the level of
proof required to establish the operation of a policy exclusion.
The critical question is whether such rains and trees were significantly influencing
the moisture condition of the soils around the home, such that it could be
concluded:
they were proximate causes of the damage to the cellar
the exclusions relied on the FSP can be applied in respect of such damage.
These matters are to be established with evidence.
FE’s evidence does not persuasively establish climatic conditions or the influence
of trees were dominant causes of the cellar damage. No geotechnical reports
have been provided in respect of the Applicants’ property.
No testing has been conducted to demo nstrate the actual, rather than theoretical,
influence of trees on or adjacent to the Applicants’ property. The Applicants’
engineer indicated that could be proven whether or not the roots were causing the
damage if a trench was excavated. This was not done.
In the absence of such evidence, and in view of the opinion of HE, the Panel is:
not persuaded the FSP has established the operation of the exclusions it
relies on to deny the repairs associated with the cellar
satisfied the Applicants are entitled to indemnity for such repairs.
2.2 What is an appropriate cash settlement?
Current cash offer may not be sufficient to cover repairs
The FSP’s $15,908 offer was derived from builder CC’s 30 April 2014 repair
estimate, which purports to cover all repairs identified in FE’s SOW. That is to say,
it also includes the repairs associated with the cellar damage which the FSP had
denied.
Case No: 372598 Determination Page 5 of 9
Although the FSP has agreed to maintain the offer, the Panel is concerned the
offer may not be sufficient to cover the repairs.
The repair estimate clearly warned it was only an estimate. As nearly a year has
passed since the estimate, there could be price variations in materials. Further,
the estimate envisages additional work could be required. The estimate says this
will be charged for separately.
Critically, FE’s SOW acknowledges the possibility of additional work (see section
1.2 of the SOW).
There is no dispute the Applicants’ home sustained damage which requires
complex repairs. The Panel also accepts that it is not always easy to acc urately
determine the cost of complex repairs at the outset, so the possibility of cost
variations arising in this instance is reasonably likely.
Considering these matters, the Panel does not consider the offer fair if it is
intended to be a full and final discharge of the FSP’s policy obligation. The FSP
should also meet possible claim related cost escalations, if they arise.
Applicants’ claim for up to $100,000 not substantiated
The Applicants have suggested that the cost of repairing their home is in the
vicinity of $80,000 to $100,000. This range is based on an initial estimate
provided by their builder CC. The builder has confirmed in writing that his initial
estimate was in this range in a recent email but makes no comment as to why his
initial estimate and his tender for work varied so much. No evidence has been
provided by the Applicants indicating the SOW envisaged by CC at the time that
this initial estimate or recent email was provided.
The SOW was prepared by the FSP’s engineer in conjunction with the Applicants’
engineer and the Applicants have not disputed the adequacy of that SOW. The
Applicant’s builder CC has quoted $16,158 to complete that work and the FSP’s
offer of cash settlement has been based on that quote with deduction of the $250
policy excess.
In the absence of evidence to the contrary, the Panel is left with little alternative
but to accept the cost quoted in CC’s repair tender as being sufficient to carry out
the repairs identified in the SOW at the time the tender was provided (subject to
the Panel’s earlier comments on possible cost variations).
Accordingly, the Panel considers the Applicants’ claim that settlement should be
in the range of $80,000 to $100,000 as being unproven.
2.3 Should the FSP pay compensation for the way it handled the
claim?
FOS can award compensation for non-financial loss
Pursuant to its Terms of Reference, FOS can require the FSP pay up to $3,000
as compensation for non-financial loss where:
it has unusually delayed the resolution of the Applicants’ claim
Case No: 372598 Determination Page 6 of 9
its handling of the claim caused the insured unusual inconvenience or had
unusually interfered with their peace of mind or expectation of enjoyment of
their home.
FSP took more than 2 years to decide claim
The available material evidence indicates that the FSP did not appear to make
any formal decision on the Applicants’ claim until around August 2014, more than
two years after the claim was lodged (i.e. on 5 April 2012).
FSP has not provided reasonable explanation for delay
The FSP has not provided any reasonable explanation as to why it could not
complete its investigations and decide the claim any earlier. The FSP did not
address this although the Applicants specifically raised the concern.
Whilst the claim raises complex questions of proximate cause, the Panel
considers a period of more than two years to investigate and assess the claim,
resolve differences in expert opinions, obtain repair quotes and finally decide the
claim unreasonably lengthy.
Applicants entitled to $1,500 compensation for non-financial loss
In the circumstances, the Panel is satisfied that the FSP:
has unreasonably delayed the resolution of the Applicants’ claim
has caused the Applicants unusual inconvenience and interference with their
peace of mind and expectation of enjoyment of their property.
Considering these matters as well as the fact the Applicants’ property remains
unrepaired to this date, the Panel considers it appropriate and fair in all the
circumstances that the FSP pay the Applicants $1,500 in this instance, pursuant
to paragraph 9.3(b)(i) of the FOS Terms of Reference.
Applicants entitled to the costs of the engineer HE
Paragraph 9.4 of the Terms of Reference allow the Service to decide that the FSP
contribute to professional costs incurred by Applicants in the course of a dispute.
Unless exceptional circumstances apply, the Service will not require the FSP
contribute more than $3,000 to these costs.
The Applicants have incurred the professional costs of HE in the course of this
dispute. It is clear from the material provided that HE provided an expert report,
attended a meeting with the parties and the FSP’s engineer in January 2014, and
liaised with the FSP and the FSP’s engineer subsequent to the meeting in regard
to the scope of works.
The Panel considers that HE’s input in the course of this dispute has greatly
assisted it and the Applicants. The Panel considers that it is fair in all the
circumstances that the FSP contribute to the professional costs of HE.
The Applicants are to provide the FSP with an invoice from HE evidencing his
professional costs in the dispute. Upon receipt of that invoice the FSP is to pay
HE ’s professional costs providing they do not exceed $3,000.
Case No: 372598 Determination Page 7 of 9
Applicants entitled to exploration costs
In the circumstances of this dispute, the policy provides that the FSP will pay up
to $2,000 in locating the cause of the damage, and of reinstating the property
damaged or disturbed in any of the course of work.
The FSP is not obliged to pay for repair or replacement of the leaking pipes.
The material provided indicates that the Applicants may have incurred these
expenses. If this is the case, and providing the Applicants provide adequate proof
of the exploration costs in the form of an invoice or otherwise, the FSP is to
reimburse the Applicants for exploration costs up to $2,000.
Case No: 372598 Determination Page 8 of 9
3 Supporting information
3.1 FOS Approach
This dispute has not been the subject of a FOS Recommendation. Due to the
nature of the dispute, it has been referred directly to a Panel for Determination, in
line with the Operational Guidelines to the FOS Terms of Reference.
This decision has been made by a Panel. The Panel consists of an Ombudsman
and two representatives with consumer and insurance experience.
The Panel has decided this case on its merits, having regard to the relevant law,
good industry practice, codes of practice and previous FOS decisions.
There has been a full exchange of all material information relied on for the
purposes of this Determination and each party has had the opportunity to address
any issues raised by the other.
The Panel has reviewed and considered all of the material provided by the
parties. While the parties have raised a number of issues in their submissions, for
the purposes of this Determination the Panel has restricted its commentary to
those issues which it considers directly relevant to the outcome only.
3.2 Sec tion 3.6 of engineer FE’s scope of works (declined repairs)
Cellar Infill
Due to the poor condition of the eastern wall of the cellar, it is proposed to backfill it up to
the base of the window sill in the perimeter brickwork on the northern wall. This infill shall
also be set so that it is at least 300mm below the timber bearer positioned in the roof of the
cellar. As such, all timber below this level shall be carefully removed including to the steps
where possible. Once the temporary bracing to the eastern wall has been carried out using
steel members and the Acro-props be replaced with temporary steel sections, the area shall
be backfilled using Controlled Low Slump Material (CLSM). This material shall be pumped
in through the external air vent to achieve the levels nominated above. It shall be vibrated
and the Contractor shall ensure it is fully distributed throughout the cellar and the stair area
without voids in any area, including beneath the props. Following this, the kitchen timber
flooring to the cellar access shall be nailed to the joist for permanent fixing. This cellar is
approximately 3.3m x 2.8m x 1.8m maximum depth.
3.3 Relevant policy wordings
What you are insured against
Accidental loss or damage to your home…
…
What you are not insured against
You are not insured against:
…
b. loss or damage resulting from or caused by:
…
11. wear, tear, rust, corrosion, depreciation or gradual deterioration
…
13. settling, shrinkage or expansion in buildings, foundations, walls or pavements,
Case No: 372598 Determination Page 9 of 9
16. Exploration Costs
If this policy insures the home and we pay for damage caused by liquid escaping from any
fixed basin, shower base, or other fixed apparatus, fixed tanks, or fixed pipes used to hold
or carry liquid, we will also pay up to $2,000 in locating the cause of the damage, and of
reinstating the property damaged or disturbed in any in the course of work.
We do not pay for repair or replacement of any:
water main or water pipe
gutter or down-pipe
fixed water tank, aquariums
fixed domestic apparatus including wat er beds
We will not pay for damage res ulting from the breakdown of grouting or sealer over a period
of time allowing for seeping under tiles which results in the lifting of tiles nor for damage
caused over a prolonged period of time.
3.4 Relevant FOS Terms of Reference
9.3 Other compensation
…
b) Subject to paragraph 9.3 c) and paragraph 9.7, FOS may decide the Financial
Services Provider compensate the Applicant for non-financial loss but only
where:
(i) an unusual degree or extent of physical inconvenience, time taken to
re solve the situation or interference with the Applic ant’s expectation of
enjoyment of peace of mind has occurred;…
…
The maximum amount of compensation for non-financial loss will be $3,000
per claim made in the Dispute.
9.4 Applicant’ s costs in pursuing t he matter
FOS may decide that the Financial Services Provider contribute to the legal or
other professional costs or travel costs incurred by the Applicant in the course of
the Dispute. Unless exceptional circumstances apply, FOS will not require the
Financial Servic es Provider to contribute more than $3,000 to these costs.