Swimming pool damage claim denied under water seepage exclusions

FirmFinancial Firm (Unknown - Insurer)
Decided2015-02-12
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The Applicant's concrete swimming pool popped out of the ground after heavy rain, and the FSP denied the claim under water seepage exclusions. AFCA found the excluded water infiltration was the proximate cause and that the claim process did not warrant compensation.

The insurer must establish on the balance of probabilities that an exclusion applies to the proximate cause of the damage, and it did so here.

Issues

Subjects and remedies

home or building damagenatural disasterno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination General Insurance - Domestic Insurance - Home Building - FSP Decision - Denial of Claim Determination Case No: 372308 Determination Page 1 of 6 Case number : 372308 10 February 2015 1 Overview 1.1 Dispute The Applicant lodged a claim under his home insurance policy with the Financial Services Provider (FSP), after his concrete in- ground swimming pool “popped out” of the ground following heavy rains on or around 18 February 2014. The FSP denied the claim on the grounds that the damage was caused by water seeping or running down the sides or underneath the pool and/or by hydrostatic water seepage, each of which is excluded under the policy. The Applicant disputes the FSP‟s findings as to the cause of the damage and says that the FSP should be prevented from denying the claim as it has previously confirmed that the claim would be accepted. He is also dissatisfied with the claim handling process. 1.1 Issue and key findings Is the FSP entitled to deny the Applicant’s claim? The available information establishes that the proximate cause of the damage to the Applicant‟s swimming pool was rainwater infiltrating the soils surrounding the pool during the storm, which caused the p ool to lift or „pop‟ . Damage caused in this manner is not covered under the policy. The Applicant has not suffered any loss as a result of relying on the FSP‟s earlier advice that it would accept his claim. Accordingly, the FSP is not prevented from relying on the terms of the policy to deny the claim. Is the Applicant entitled to compensation? The delays and inconvenience experienced by the Applicant during the claims process are not such as to justify the award of compensation. 1.2 Determination This Determination is in favour of the FSP. The FSP is not required to indemnify the Applicant for the damage to his pool. The Applicant is not entitled to compensation. Case No: 372308 Determination Page 2 of 6 2 Reasons for Determination 2.1 Is the FSP entitled to deny the Applicant’s claim? Policy provides cover for storm damage subject to exclusions The Applicant‟s policy provides cover for damage to his property caused by the events listed in the policy (including the insured event of storm), subject to the conditions and exclusions set out in the polic y. The policy provides that damage to swimming pools resulting from a storm is not covered where the damage is caused by water leaking down or against, or getting underneath, the sides of the swimming pool. The policy also contains a general exclusion for damage that is caused by, arises from or involves water seeping or running:  through the earth (hydrostatic water seepage); or  down the sides or underneath a swimming pool causing the pool to move, change shape, lift or leak through its hydrostatic valve. The FSP does not dispute that the damage to the Applicant‟s swimming pool occurred following the storm on or around 18 February 2014. In these circumstances, the FSP bears the onus of establishing that, on the balance of probabilities, it is entitled to rely on a policy exclusion to deny the Applicant‟s claim. In order to do so, the FSP must show that the proximate cause of the damage to the swimming pool (that is, the real, effective or dominant cause) was one of the excluded factors outlined above. Damage was caused by factors excluded under the policy Having carefully reviewed the available information, the Panel is satisfied that, on the balance of probabilities, the proximate cause of the damage to the Applicant‟s swimming pool was storm water infiltrating the soils surrounding the pool, which caused the pool to lift or „pop‟. The engineer (KM) appointed by the FSP to determine the cause of the damage concluded that the infiltration of water beside the pool during the heavy rains on or around 18 February 2014 had caused a sudden and significant rise in the water table surrounding the pool, which placed increased pressure on the bottom and sides of the pool. In her report, KM stated that the increase in pressure caused by the rise in the water table would have been sufficient to lift a pool of the same size and depth as the Applicant‟s out of the ground. The Panel notes that KM‟s findings are consistent with data f rom the Bureau of Meteorology, which shows that a nearby weather station recorded total rainfall of approximately 240 millimetres on 18 February 2014, when the Applicant lodged his claim. Case No: 372308 Determination Page 3 of 6 The Applicant‟s swimming pool repair specialist (MD) acknowledged the impact of the heavy rainfall experienced during the storm, but considered that the break in the secondary suction line at the bottom of the pool (due to age) combined with the erosion of backfill material over the life of the pool had also contributed to the pool lifting. The Panel notes that the FSP‟s engineer (KM) considered the potential impact of the broken suction line, but concluded that it would have been insufficient to cause the pool to lift. After reviewing MD‟s report, KM confirm ed her initial findings as to the proximate cause of the damage. Having regard to the volume of rain fall in the region and the timing of the damage, the Panel is satisfied that the real or effective cause of the damage was the rainwater infiltrating down the sides and underneath the pool and the hydrostatic effect of water seeping through the soil generally. As outlined above, the policy contains exclusions for damage caused by water leaking down the sides or underneath a swimming pool during a storm and damage caused by water seeping through the earth. Accordingly, the FSP is entitled to rely on these exclusions to deny the Applicant‟s claim. Applicant has not relied on FSP’s prior acceptance of claim The Applicant says that the FSP should not be entitled to deny his claim because it had previously advised him that the claim would be accepted. The FSP acknowledges that it advised the Applicant that his claim would be accepted and has apologised for any frustration and disappointment he suffered as a result of its subsequent decision to deny the claim. It appears that the FSP ultimately decided to deny the claim after seeking comments from its engineer on the report provided by the Applicant‟s pool repairer as to the cause of damage. The FSP is generally entitled to rely on the terms of the policy of insurance, which forms a contract between the Applicant and the FSP. However, where the Applicant has acted to his detriment in reliance on a misrepresentation made by the FSP, then the FSP may be prevented from relying on the terms of the policy, provided that the Applicant can show that he has relied on the misleading information to his detriment. In the present case, there is no information to suggest that the Applicant has suffered any loss (for example by commencing repairs or incurring any other costs) as a result of relying on the FSP‟s advice that it would accept his claim. In these circumstances, the FSP is not bound by its prior acceptance and is entitled to rely on the terms of the poli cy to deny the Applicant‟s claim. Case No: 372308 Determination Page 4 of 6 2.2 Is the Applicant entitled to compensation? Applicant has not suffered an unusual degree of delay or inconvenience The Applicant is dissatisfied with manner in which the FSP handled his claim. In particular, he says that the FSP unreasonably delayed making a final decision in relation to his claim and sent a number of contractors to his property before ultimately deciding to deny his claim. Under paragraph 9.3(b) of the Terms of Reference, FOS may award compensation (capped at $3,000) for non-financial loss where an applicant has suffered an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with their expectation of enjoyment or peace of mind. The Panel accepts that the claim process was somewhat protracted and that the FSP changed its position on several occasions. The FSP initially advised the Applicant on 31 March 2014 that it would deny his claim. It then advised the Applicant on 3 July 2014 that it had decided to accept his claim before issuing a final denial on 21 August 2014. However, the Panel acknowledges that, on each occasion, the FSP‟s position was based on its understanding of the expert evidence available at the time. Further, the Panel accepts that not all of the delays in the claim process are attributable to the actions of the FSP. The Panel accepts that the claims process has been frustrating and inconvenient for the Applicant. However, the Panel does not consider that the extent of inconvenience, time taken to resolve the situation or interference with the Applicant‟s peace of mind is sufficient to justify the award of compensation in the circumstances. Case No: 372308 Determination Page 5 of 6 3 Supporting information 3.1 Panel approach to this dispute This dispute has not been the subject of a FOS Recommendation. Due to the nature of the dispute, it been referred directly to a Panel for Determination, in line with the Operational Guidelines to the FOS Terms of Reference . The Panel consists of an Ombudsman and two representatives with consumer and insurance experience. The Panel has decided this case on its merits, having regard to the relevant law, good industry practice, codes of practice and previous Financial Ombudsman Service (FOS) decisions. There has been a full exchange of all material information relied on for the purposes of this Determination and each party has had the opportunity to address any issues raised by the other. The Panel has reviewed and considered all of the material provided by the parties. While the parties have raised numerous issues in their submissions, for the purposes of this Determination the Panel has restricted its commentary to those issues which it considers directly relevant to the outcome only. 3.2 Terms of policy Subject Terms Storm - exclusion What we do not cover …  loss or damage to swimming pools or underground tanks caused by water leaking down the sides, against the sides or getting underneath them . Escape of liquid - exclusion What we do not cover …  wear and tear, or loss or damage caused by the escape of liquid occurring as a result of a gradual process of leaking, splashing, dripping or overflowing over a period of time when you could reasonably be expected to be aware of this condition. General ex clusions You are not covered under any section of this policy for damage, loss, cost or legal liability that is caused by, arises from or involves : … Seepage of water water seeping or running:  through the earth (hydrostatic water seepage); …  down the side s or underneath swimming pools or spas causing them to move, change shape, lift or leak through their hydrostatic valves … 3.3 Reports Re port Key points FSP’s assessor (BB)  The pool had lifted from the ground by about 450mm and Case No: 372308 Determination Page 6 of 6 Report - 21 February 2014 there was noticeable water visible to the sides of the pool between the earth and the outside of the pool . It was l ikely that there was also water under the pool .  The Applicant‟s leak detection specialist (MD) had advised that the pool may have popped due to water entering the sides or by a broken secondary suction pipe under the pool.  The assessor was unable to determine whether the damage was caused by water entering the sides and the bottom of the pool or by another factors such as the broken pipe. FSP’s engineer ( KM) Report - 19 March 2014  The pool was construc ted with a concrete shell and was approximately 30 years old .  The p ool had signs of previous repairs to cracks and in at least one location the pool was leaking at the crack point .  The popping was primarily due to the large rain event reported by the Applicant . Any w ater surrounding the pool due to the cracks in the shell or the failing pipes was unlikely to have caused the pool to pop out of the ground .  The rain event had caused the wa ter table to ri se quickly and significantly. This had placed the necessary pressure on the underside of the pool required to lift a pool of this size and depth out of the ground. Applicant’s swimming pool repair specialist (MD) Report - 18 February 2014  The Applicant had advised that the swimming pool had lifted the previous night due to a storm which resulted in approximately 200 millimetres of rain in twelve hours.  The sheer amount of rainwater had caused the swimming pool to flex and move . The break in the secondary suction line at the bottom of the pool (due to age) combined with the back fill washing away over the life of the pool had caused the pool to lift . This was common in older pools.  The washing away of the backfill was evident from the fact th at he could place his arm down the side of the pool. FSP’s engineer (KM ) Supplementary r eport - 29 July 2014  Due to the timing of the large rainfall event , s he believed that the popping of the pool was primarily due to the rainfall and not a cracked pipe .  The infiltration of water beside th e pool during the rain event had caused the water table surrounding the pool to rise quickly and placed increased pressure on the underside and sides of the pool. The sudd en high increase in pressure had lifted the poo l out of the ground.