Home / Financial Firm (Unknown - Insurer) / Determination 369416
Determination 369416
Fire claim cash settlement amount for repairs
Summary
The applicant disputed the FSP's $84,728.60 repair offer for a fire-damaged home and sought more for repairs, temporary accommodation, rewiring and non-financial loss. AFCA ordered an additional $47,138.30 for repairs, reimbursement of $1,857.50 for expert reports, further temporary accommodation up to the policy limit, and interest, but rejected the rewiring and non-financial loss claims.
Under the new-for-old basis of settlement the FSP's quote did not cover the full scope of repairs, while the PDS excludes upgrades to undamaged parts of the home and non-financial loss was not unusual.
Issues
- Claim amount dispute primary · upheld
“The FSP's settlement offer is not adequate because the FSP's evidence is insufficient to establish its quoted price is reasonable to restore the home.”
- Claim denial secondary · not upheld
“The Applicant is not entitled to a further payment because the additional rewiring is for areas that were not fire damaged.”
- Poor claim handling secondary · upheld
“The Panel acknowledges in some instances the FSP's claims handling was not ideal.”
Subjects and remedies
home or building damagepay claimpay compensationpay interest
Text of the determination
Determination
General Insurance - Domestic Insurance - Home Building -Fire FSP Decision - Claim
Amount
Determination
Case No: 369416 Determination Page 1 of 8
Case number: 369416 5 March 2015
1 Overview
1.1 Dispute
On 17 January 2014, the Applicant lodged a claim for fire damage to his home
building, which the Financial Services Provider (FSP) accepted.
This dispute arises because the Applicant is dissatisfied with the manner in which
the FSP has handled his claim.
The FSP says repairs can be done for $84,728.60. The Applicant is dissatisfied
with this amount in offer and seeks a higher settlement amount for the repairs as
well as additional amounts for temporary accommodation, rewiring of electrical
installations and compensation.
1.2 Issues and key findings
Is the FSP’s settlement offer adequate?
The basis of settlement in the policy applicable to the claim is new for old and to
pay the reasonable cost to restore the home. The FSP’s settlement offer is not
adequate because the FSP’s evidence is insufficient to establish its quoted price
is reasonable to restore the home and adequate to cover the agreed scope of
works prepared by the Applicant’s builder (P).
As the Applicant’s expert evidence assisted him in establishing his position, the
FSP should also contribute to the cost he incurred in obtaini ng P’s quotation and
the report from his loss assessor (C).
Is the Applicant entitled to further payments for temporary accommodation?
The Applicant is entitled to further payments for temporary accommodation
(subject to the policy’s limits) because he is entitled to this under the Product
Disclosure Statement (PDS) and the circumstances that caused further delays in
starting the repairs were warranted.
Is the Applicant entitled to a further payment for rewiring of electrical
installations?
The Applicant is not entitled to a further payment because the additional rewiring
of electrical installations the Applicant seeks is for areas that were not fire
damaged. They are specifically excluded from cover by the PDS.
Case No: 369416 Determination Page 2 of 8
Is the Applicant entitled to compensation for non-financial loss?
The Applicant is not entitled to compensation for non-financial loss because the
material is insufficient to establish there was an unusual extent of physical
inconvenience, time taken to resolve the situation or interference with the
Applicant’s expectation of enjoyment or peace of mind.
1.3 Determination
This Determination is substantially in favour of the Applicant.
The FSP is to pay the Applicant an additional amount of $47,138.30 for the
repairs related to his fire claim.
The FSP is t o reimburse the Applicant the amount of $1,857.50 for P’s
quotation and for C’s report.
The Applicant is entitled to further payments for temporary accommodation
according to the terms and conditions of the policy and subject to him giving
the FSP adequate proof of the expenses incurred.
The Applicant is not entitled to further payments regarding the rewiring of
electrical installations.
The Applicant is not entitled to compensation for non-financial loss.
The FSP has already cash settled part of this claim and is to cash settle the
balance of the claim. The FSP is to pay interest on the balance of the claim in
accordance with Section 57 of the Insurance Contracts Act 1984 from 26 May
2014, being the date of the FSP’s final decision, to the date of payment.
Interest is also to be paid at the statutory rate on the amounts paid by the
Applicant for P’s quotation, C’s report and for temporary accommodation from
the date the Applicant paid the amounts until reimbursement by the FSP.
Case No: 369416 Determination Page 3 of 8
2 Reasons for Determination
2.1 Is the FSP’s cash settlement offer adequate?
P’s scope of works contains additional repairs to those quoted by FSP
The parties are in dispute as to whether the amount the FSP’s repairer (T) quoted
for the repairs of the building are sufficient to address all claim related repairs.
The FSP first relied on a scope of works (SOW) from its loss assessor (J) and
quotations from T and a second repairer (PC).
The Applicant considered J’s SOW was not sufficiently detailed to ensure the
adequate repair and replacement of all damaged structures. He then obtained a
detailed SOW and quotation from P and a report from C.
The FSP obtained further information from T (as per emails of 17 February and 13
March 2014 and a second SOW largely based on P’s SOW) and concluded T’ s
quoted price of $84,728.60 was essentially adequate for P’s SOW.
The FSP does not dispute the adequacy of P’s SOW. Its position is that T can do
repairs according to P’s SOW, for the price T quoted for J’s SOW.
The FSP asserts J’s SOW was adequate but less detailed than P’s. However, a
comparison between the two SOWs indicates there are substantial additional
repairs only quoted by P, some of which for example are:
Replacement and painting of doors.
Replacement of cupboards, bench tops, built-in robes, flooring, a vanity, toilet
shelves, additional insulation, a flue, ovens.
Removal and replacement of VJ wall and ceiling lining in kitchen 2 plus
insulation.
Treatment against soot bleed for unpainted plasterboard.
Painting of the external west wall.
Despite T’s assurances, it is unclear how the price quoted for J’s SOW can apply
to P’s SOW when the latter includes substantial additional repairs.
C’s evidence supports P’s position that additional repairs are required
C says some of these repairs (e.g., removing all timber panels throughout the
building) are required due to the extensive smoke damage which has deeply
impregnated the lining to walls with smoke and carcinogenic substances.
On this basis, C first considered a fair and reasonable cost for the reinstatement
of the building would be between $130,000 and $150,000. This is in line with P’s
quoted price ($131,866.90).
The FSP questioned C’s information. In response, C provided a detail of its
Cordell ’ s e-costing for the building, resulting in an estimate of $172,873.81.
However, the calculations in C’s letter dated 11 November 2014 include $10,000
for electrical rewiring of the whole building (the e-costing already includes repairs
Case No: 369416 Determination Page 4 of 8
to fire affected electrical installations in various rooms), which as per section 2.3
below, is excluded from the claimable cost.
After this deduction, the resulting price represents an increase of $12,873.81
above the top of C’s range in C’s first costing for repairs.
The Panel accepts C has a level of expertise in establishing SOWs and prices for
claim related repairs. C is well known in the insurance industry as an experienced
loss adjustor retained by several insurers.
FSP’s quoted price is inadequate to cover P’s scope of works
Having reviewed all the information provided, the Panel is not satisfied the FSP
has provided sufficient information to establish the basis under which T is able to
include the additional repairs under T’s initially quoted price. Therefore, the Panel
considers T’s quoted price is inadequate to address P’s SOW.
Further, t he Panel is persuaded by P’s detailed SOW and C’s report. C’s report
corroborates the price range needed to address all repairs in the building. The
Panel prefers P’s quotation because it was prepared by a qualified builder and in
line w ith P’s own SOW.
Basis of settlement is to pay the reasonable costs to restore the Home
The basis of settlement applicable to the Applicant’s claim is new for old. The
commitment given under the policy is to “pay the reasonable cost to restore your
Home to the same specifications it had when it was built or last renovated”.
The policy goes on to say this means the cost of rebuilding the home or the cost
of repairing the home whichever is the lesser.
There is no provision in the policy, under this basis of settlement, that allows the
FSP to elect whether to reinstate, repair or pay cash. This ability to elect is
available for Indemnity Cover but this is not the cover held by the Applicant.
Given all of the available evidence, the Panel is not satisfied that the FSP has
offered the Applicant an amount commensurate with the reasonable cost of
restoring the Home.
Accordingly, the FSP is to pay an additional $47,138.30 for the repair of the
Home.
FSP is to contribute to the Applicant’s cost for P’s SOW and C’s r eport
Under its Terms of Reference (TOR), the Financial Ombudsman Service (FOS)
may require an FSP to contribute to an Applicant’s professional costs incurred in
the course of the dispute up to a maximum of $3,000.
The Panel is satisfied the Applicant need ed P’s SOW and C’s report (including the
e-costing detail in a subsequent letter) in order to establish that the FSP’s quoted
price was inadequate to address all the claim related issues.
This is sufficient grounds for the Panel to consider the FSP should reimburse the
Applicant for the costs incurred in obtaining P’s SOW and C’s report .
The Applicant has provided invoices from P and C, which amount to $1,857.50.
The FSP is to reimburse this cost to the Applicant.
Case No: 369416 Determination Page 5 of 8
2.2 Is the Applicant entitled to further payments for temporary
accommodation?
PDS provides additional benefit for temporary accommodation
The PDS says temporary accommodation is paid on top of the total Sum Insured
and is paid for “…. expenses which you actually incur from the time of the
damage, while your Home is being rebuilt or repaired”. The FSP notes the PDS
allows for “reasonable accommodation expenses”.
It is not in dispute the Applicant is entitled to the additional cover for “temporary
accommodation” and the FSP has paid this up until 20 July 2014. The Applicant
says the FSP has made no further payments since. The Applicant has provided
invoices that show he has paid $490 per week for temporary accommodation until
19 November 2014.
The FSP does not dispute that the amount of $490 per week for temporary
accommodation is unreasonable.
Payment of the benefit should be maintained “while the Home is being
repaired” because delays were warranted
The FSP says:
had the Applicant allowed T to proceed with repairs, he would not have
required temporary accommodation past 5 April 2014
due to the ongoing dispute, it offered temporary accommodation until 20 July
2014
what it has paid was reasonable as it has tried to resolve the matter in an
appropriate time frame
the Applicant has not cooperated or assisted it in settling the claim.
The benefit of temporary accommodation is paid when the insured permanently
resides in the home and the home cannot be lived in because of an insured event.
Neither of these conditions are in dispute.
The policy goes on to say that the FSP will pay:
reasonable additional accommodation expenses
which are actually incurred from the time of damage
while the home is being rebuilt or repaired.
The benefit is paid in addition to the total sum insured. The FSP is not obliged to
pay more than an additional 10% of the sum insured. The sum insured in the
relevant policy period was $387,200. Thus the maximum amount payable for this
benefit is $38,720.
Whilst the Panel accepts that had the Applicant allowed T to proceed with the
repairs he would not have required temporary accommodation past 5 April 2014,
it does not accept that the Applicant has not cooperated or assisted the FSP in
settling the claim. Rather it is the Panel’s view that the delays incurred due to the
Applicant’s disagreement with T’s proposed repairs were warranted as set out
earlier in this Determination.
Case No: 369416 Determination Page 6 of 8
In all the circumstances, the Panel is of the view that it is fair in all the
circumstances that temporary accommodation is covered from the time of
damage and while the home building is repaired.
In submissions to the Service, the Applicant accepts repairs will take 12 weeks.
What is not known is how long it will take before the Applicant is in a position to
commence repairs.
The Panel accepts that the Applicant may not necessarily be able to commence
the repairs immediately as a builder may not be able to commence work
immediately.
Having said that, the Panel also considers it is not fair in all circumstances to
extend this benefit indefinitely, if further delays in obtaining an outcome for the
claim are unjustified or unreasonable.
On that basis, the Panel is satisfied it is fair in all the circumstances that the FSP
pay temporary accommodation expenses to date and until the home building is
repaired. This is subject to what is fair (no unwarranted delays by the Applicant
after the FSP settles the claim) and that the benefit is not to exceed 10% of the
sum insured which the Panel calculates is $38,720.
2.3 Is the Applicant entitled to a further payment for rewiring of
electrical installations?
PDS excludes incidental expenses for parts of the home which do not have
damage covered by the policy
The Applicant wants the FSP to pay for the upgrade of electrical wiring to comply
with current regulations. He contends these are additional costs not previously
allowed for.
Both J and P’s SOWs mention addressing the re pairs of electrical installations,
albeit they do not specifically say electrical wiring. C makes a note regarding
electrical installations requiring examination to ensure they meet Australian
Standards.
The PDS says there is additional cover for “ incidental expenses ” , which covers:
“the extra costs which are necessary to meet the requirements of any statutory authority in
connection with rebuilding or repairing your Home on the site… ”
The PDS also says the FSP will not pay:
“incident al expenses incurred for any part of your Home which has not suffered loss or
damage covered by this policy. (We will only pay the extra costs you incur in rebuilding the
damaged part.)”
The Applicant has provided images and a quotation from an electrician (H). This
quotation is for:
“ Additional non fire damage electrical work required to meet [Australian S tandard] ”.
The PDS clearly limits the additional costs to parts of the property affected by the
claimed loss or damage and covered by the policy. B oth J and P’s SOW contain
allowances for repairs of the fire affected electrical installations.
Case No: 369416 Determination Page 7 of 8
As the additional upgrade of electrical wiring is for a part of the “Home” which did
not suffer fire damage covered by the policy, it is excluded from cover. On this
basis, the Panel is satisfied the Applicant is not entitled to the additional costs for
the upgrade of electrical wiring.
2.4 Is the Applicant entitled to compensation for non-financial loss?
Material does not warrant an award of compensation for non-financial loss
FOS can award non-financial loss compensation where there has been an
unusual extent of physical inconvenience, time taken to resolve the situation or
interference with the Applicant’s expectation of enjoyment or peace of mind.
The Applicant says he should be entitled to compensation due to the stress and
duress caused by the FSP’s inappropriate mishandling of the claim.
The information provided, in particular, the Applicant’s submissions and
chronology (with attached emails), indicates there were a few delays during the
internal dispute resolution (IDR) process and the claims handling process.
Albeit not for an adequate amount, the FSP, in less than a month from the date of
the loss, was prepared to settle the claim by authorising T to carry out the repairs.
The Panel acknowledges this process was delayed because the Applicant had his
concerns and thus sourced a SOW from P and a report from C.
The Applicant has also raised issues regarding his health, the way one of the
FSP’s representatives expressed himself about P and the FSP imposing a
deadline for accepting T ’s repairs or a cash settlement.
No doubt, these issues caused concern to the Applicant. The Panel
ac knowledges in some instances the FSP’s claims handling was not ideal.
However, the Panel considers the issues raised were isolated and overall did not
go beyond the inconvenience normally associated with an insurance claim.
The prolonged period of claims handling was caused as the parties disagreed on
the claim outcome caused. Although it is likely this interfered with the Applicant’s
expectation of enjoyment or peace of mind, the Panel is not satisfied that it is fair
in all the circumstances to award compensation for non-financial loss for this
reason.
Case No: 369416 Determination Page 8 of 8
3 Supporting information
3.1 FOS approach for this dispute
This dispute has not been the subject of a FOS Recommendation. Due to the
nature of the dispute, it has been referred directly to a Panel for Determination, in
line with the Operational Guidelines to the FOS Terms of Reference.
A Panel has made this decision. The Panel consists of an Ombudsman and two
representatives with consumer and insurance experience.
The Panel has decided this case on its merits, having regard to the relevant law,
good industry practice, codes of practice and previous FOS decisions.
There has been a full exchange of all material information relied on for the
purposes of this Determination and each party has had the opportunity to address
any issues raised by the other.
The Panel has reviewed and considered all of the material provided by the
parties. While the parties have raised a number of issues in their submissions, for
the purposes of this Determination, the Panel has restricted its commentary to
those issues that it considers directly relevant to the outcome only.
3.2 Relevant information relied upon
Product Disclosure Statement with effective date 27 November 2007.
J’s trade quote request dated 28 January 2014.
T’s undated quotation.
T’s scope of works dated 28 January 2014.
J’s emails of 17 February and 13 March 2014.
P’s quotat ion dated 3 March 2014.
C’s report dated 11 July 2014.
H’s quotation of 19 October 2014.
C’s invoice, undated.
P’s invoice dated 14 March 2014.
C’s letter of 11 November 2014.
The parties’ submissions.