Home / Financial Firm (Unknown - Credit) / Determination 368567

Determination 368567

Default interest charged on commercial bill facility

FirmFinancial Firm (Unknown - Credit)
Decided2015-09-14
ProductCredit · Business lending
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The Applicant Companies disputed default interest charged on a matured commercial bill facility, an alleged promise to reverse it, and refinance timing. AFCA found the FSP was contractually entitled to the interest, ordered nothing, and excluded service quality and discrimination complaints from its jurisdiction.

The contract allowed default interest on overdue amounts, the Applicant Companies were already in default and on notice, and no contemporaneous evidence supports the alleged promise.

Issues

Subjects and remedies

small businessno remedy

Related

All Financial Firm (Unknown - Credit) determinations · Find similar determinations

Text of the determination

Determination Case No: 368567 Determination Page 1 of 5 Case number : 368567 14 September 2015 1 Overview 1.1 Dispute The Applicant Companies opened a number of facilities (the facilities), including a Commercial Bill Acceptance / Discount Facility (Bill Facility), with the FSP in February 2013. On 30 January 2014, the facilities, including the Bill Facility, expired. Default interest was charged to the Bill Facility from 31 January 2014 to 22 May 2014, when the facilities were refinanced by another financial services provider. The Applicant Companies say the FSP made the following errors in relation to the facilities in 2013 and 2014:  That it breached an obligation to the Applicant Companies by charging default interest to the Bill Facility.  That it misled the Applicant Companies that it would reverse default interest charged to the Bill Facility during a meeting on 15 April 2014.  That it incorrectly cancelled the Applicant Companies’ direct debits from the Bill Facility in January 2014.  That it provided an unreasonable and unfair amount of time for the Applicant Companies to refinance the facilities.  That it delayed settlement of the refinance of the facilities.  That it charged extra unfair fees to the facilities when they were refinanced. The Case Manager provided the parties with a Recommendation on the issues in dispute. The Recommendation was in favour of the FSP. A copy of the Recommendation is attached to this Determination. 1.2 Issues and Key findings Were the findings of the Recommendation correct? The findings contained in the Recommendation were correct and are adopted in this Determination. Further submissions provided after the Recommendation have been thoroughly considered. Did the FSP breach a duty of care by charging default interest? I agree with the analysis in the Recommendation that the FSP was contractually entitled to charge default interest in the circumstances, and that it was not unreasonable or unfair for the FSP to do so. Case No: 368567 Determination Page 2 of 5 Did the FSP promise to waive all extra fees and charges? No new information has been provided to support the claim that the FSP promised to waive extra fees and charges. 1.3 Determination This Determination is in favour of the FSP. I agree with the case manager’s reasons for the Recommendation and the recommended outcome. The FSP is not required to compensate the Applicant Companies. Case No: 368567 Determination Page 3 of 5 2 Reasons for Determination 2.1 Were the findings in the Recommendation correct? I have decided this case on its merits, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions. I have taken into account all the material submitted by the parties, both before and after the Recommendation. I am satisfied that the documentation I have relied on has been provided to both parties. I am satisfied tha t the case manager’s Recommendation contains an accurate summary of the dispute, the issues to be determined, any applicable paragraphs of the Terms of Reference and any relevant law. In response to the Recommendation, the Applicant Companies provided no objection to or new information in relation to the following issues covered by the Recommendation:  The reasonableness of the amount of time provided by the FSP to the Applicant Companies to refinance their facilities.  Whether or not the FSP delayed the settlement of the refinance of the facilities.  Whether the FSP made an error in relation to direct debits to the facilities. Because the Applicant Companies provided no new information in relation to these issues, I have not addressed them in this Determination. 2.2 Did the FSP breach a duty of care by charging default interest? In response to the Recommendation, the Applicant Companies say the FSP used the “technicalities of their legal documentation” to charge the disputed defa ult interest after the Applicant Companies advised the FSP it was not staying as a customer “under any circumstances” . The FSP was contractually entitled to charge default interest The Recommendation accurately set out the FSP’s entitlement to charge the disputed default interest to the Bill Facility. Specifically:  Page 19 of 27 of the Bill Facility Letter of Offer said that the FSP was entitled to charge default interest on overdue amounts.  Payments to the Bill Facility were overdue because the Applicant Companies did not pay an amount equal to the face value of the Bill Facility once it matured on 30 January 2014. The Applicant Companies are correct to say that the FSP relied on contractual technicalities to charge the disputed default interest. The contract between the FSP and the Applicant Companies outlined the FSP’s right to charge default interest, and the FSP exercised that right. Case No: 368567 Determination Page 4 of 5 The FSP did not act negligently or unreasonably by relying on this entitlement I agree with the analysis in the Recommendation that in all the circumstances it was not unreasonable or negligent of the FSP to charge default interest from 31 January 2014 until the Applicant Companies ’ facilities, including the Bill Facility, were refinanced. This is because:  The Applicant Companies were in default of their obligations under the facilities for some time before default interest started being charged, but the FSP provided a reasonable amount of leeway before charging default interest.  The Applicant Companies were on notice of the fact they were in default in the months leading up to when default interest began to be charged.  The FSP at no time acted to waive its contractual entitlement to charge default interest on overdue payments to the facilities. Although the Applicant Companies say the FSP only started charging default interest when it advised the FSP it was “not staying under any circumstances”, the FSP actually began charging default interest from 31 January 2014 onwards. This was before the FSP notified the Applicant Companies that it required them to refinance their facilities (6 March 2014). It was also before the FSP was first officially contacted by a third party financial provider to confirm the refinance of the facilities was going ahead. In the circumstances, I am not satisfied that the FSP began charging default interest because the Applicant Companies informed the FSP it was not staying as a customer “under any circumstances”. The FSP began charging default interest because it was reasonably entitled to do so. 2.3 Did the FSP promise to waive all extra fees and charges? In response to the Recommendation, the Applicant says the FSP charged the “higher fees and charges” after promising “to waive all extra fees and charges”. No new information has been provided to support this claim I agree with the analysis in the Recommendation that there is insufficient information to hand to make a finding that the FSP misled the Applicant Companies about reversing default interest at a meeting on 15 April 2014. Specifically, the only contemporaneous evidence provided in relation to the meeting, and the emails sent between the parties after the meeting, contain no mention of a promised interest refund. In response to the Recommendation, the Applicant provided no new information that would change the view reached in the Recommendation with regard to this claim. Case No: 368567 Determination Page 5 of 5 3 Supporting information 3.1 Service quality and discrimination issues Replacement of customer managers relates to service quality In response to the Recommendation, the Applicant Companies say they dealt with seven separate customer managers during the time that they had accounts with the FSP. The Applicant Companies say this turnover of managers is not “the norm” and that it is further evidence of FSP negligence. In my view, the Applicant Companies’ complaint about the manager turnover rate goes to the level and quality of customer service provided by the FSP. FOS does not have the power to consider disputes about the general level o f customer service provided by the FSP. This is because the level of customer service provided by the FSP, and the FSP’s decision to appoint and remove customer managers, is influenced by the FSP’s policy on issue such as staff levels and training. FOS does not have the power to review such policies. FOS cannot consider disputes about discrimination In response to the Recommendation, the Applicant Companies reiterated a previous claim that the FSP discriminated against certain parties and that particular FSP employees directed racist or racially intolerant behaviour towards people associated with the Applicant Companies. As previously advised to the Applicant Companies, such claims are more appropriately dealt with by the Victorian Equal Opportunity and Human Rights Commission and are outside FOS’ jurisdiction. Recommendation Credit - Business Finance - Business Loans - Financial Difficulty - Decline of Financial Difficulty Request Case number : 368567 16 July 2015 1 Overview 1.1 Dispute The Applicant Companies opened a number of facilities (the facilities), including a Commercial Bill Acceptance / Discount Facility (Bill Facility), with the FSP in February 2013. On 30 January 2014, the facilities, including the Bill Facility, expired. Default interest was charged to the Bill Facility from 31 January 2014 to 22 May 2014, when the facilities were refinanced by another financial services provider. The Applicant Companies say the FSP made the following errors in relation to the facilities in 2013 and 2014:  That it breached an obligation to the Applicant Companies by charging default interest to the Bill Facility.  That it misled the Applicant Companies that it would reverse default interest charged to the Bill Facility during a meeting on 15 April 2014.  That it incorrectly cancelled the Applicant Companies’ direct debits from the Bill Facility in January 2014.  That it provided an unreasonable and unfair amount of time for the Applica nt Companies to refinance the facilities.  That it delayed settlement of the refinance of the facilities.  That it charged extra unfair fees to the facilities when they were refinanced. 1.2 Issues and key findings Did the FSP make an error or breach an obligation by charging default interest to the Bill Facility? The FSP was entitled to charge default interest to the Bill Facility because payment was overdue. Because the Applicants Companies were in default, it was not unreasonable or unfair for the FSP to charge default interest in the circumstances. Did the FSP mislead the Applicant Companies about reversing default interest? The weight of information does not support a finding that the FSP promised to reverse default interest charged to the Bill Facility at the meeting on 15 April 2014. Case No: 368567 Recommendation Page 2 of 8 Did the FSP provide a reasonable amount of time for the Applicant Companies to refinance? There is sufficient information to show that the FSP knew the refinance was already on foot when they sent a letter on 6 March 2014 requesting the facilities be refinanced. In the circumstances, the FSP’s request was not unreasonable. Did the FSP delay settlement of the refinance of the facilities? It took 14 business days for the refinance settlement to go ahead. Given the size and complexity of the refinance transaction, this was a reasonable turnaround time for settlement. Did the FSP make an error in relation to direct debits? Even if the Bill Facility direct debit had not been cancelled, default interest would still have been charg ed to the Applicant Companies’ accounts. It is unclear what loss was incurred because the direct debits were stopped. 1.3 Recommendation This Recommendation is in favour of the FSP. The FSP is not required to compensate the Applicant Companies. Case No: 368567 Recommendation Page 3 of 8 2 Reasons for Recommendation 2.1 Did the FSP make an error or breach an obligation by charging default interest to the Bill Facility? The FSP was entitled to charge default interest on overdue payments Page 19 of 27 of the Letter of Offer for the facilities, which relates specifically to the Bill Facility, says that the customer must pay “an amount equal to the face value of each bill we accept…not later than 10.00am on the day the bill falls due for payment at the completion of the term to maturity”. This sectio n goes on to say that if a customer does “not pay any amount you owe us when it is due (including any amount payable under this “Indemnity”) you must pay interest on that overdue amount at the default rate”. The payments were overdue Once the Bill Facility matured on 30 January 2014, the Applicant was required to pay an amount equal to the face value of the Bill Facility ($9,278,000) at 10.00am on 31 January 2014. The Applicant Companies did not pay that amount to the FSP. The payment therefore became overdue, and the FSP was entitled to charge default interest on the overdue amount from that date on. The FSP’s entitlement to charge default interest in this situation is also set out at Section 30.1(a) of the terms and conditions of the facilities, which sa ys the FSP is entitled to charge default interest “on any amount overdue for payment, from the time the amount is overdue for payment until it is paid”. The Applicant was already in default, so it was not unreasonable or unfair for the FSP not to extend the Bill Facility The reason that payments on the Bill Facility became overdue is because the FSP decided not to rollover the Bill Facility past 30 January 2014. Instead, the FSP allowed the Bill Facility to mature. The Applicant Companies’ position is tha t the FSP’s decision to do so was unreasonable and unfair. The available information does not support a claim that the FSP’s decision was unreasonable or unfair, because the Applicant had been in default of the facilities for some time. Section 28 of the terms and condition outlines when a customer will be in default. Section 28(b) says that a customer will be in default “...if you don’t do something you agree to do under an arrangement with us”. Under the facilities contract, the Applicant Companies agreed to provide financial information about the Applicant Companies, and associated companies, within 30 days of the end of each financial quarter (being March 31, June 30, September 30, and December 31). The information they were required to provide in relation to each company is outlined at page 6 of 27 of the letter of offer. If the Applicant Companies did not provide this financial information as agreed, they would be in default, because they would have failed to do something they agreed to do under the facilities contract. Case No: 368567 Recommendation Page 4 of 8 The Applicant was on notice of the default During the period September to December 2013, the FSP and Applicant Companies were negotiating the possibility of the FSP providing further finance to the Applicant Companies. Even though these negotiations were ongoing, the Applicant Companies were warned that their obligation to provide quarterly financial information (for September 2013, with due date 31 October 2013) was ongoing. These warnings were given as follows:  In an email dated 4 October 2013, the Applicant Companies were told that the “continuation of other Banking facilities for the group, would be conditional upon…[the FSP] being provided with usual compliance certificate and supporting financial information for [the Applicant Companies]” by the end of November.  In an email dated 20 December 2013, the Applicant Companies were told that the provision of quarterly management prepared financial statements and further detailed financial information about the Applicant Companies was overdue, having been due on 30 October 2013.  In the same email dated 20 December 2013, the Applicant Companies were told that the FSP would be “issuing breach letters due to the non provision of the quarterly financial information”.  In an email dated 6 J anuary 2014, the Applicant Companies’ advisor was reminded about the “financial information which remains outstanding, including the usual September data”. The FSP did not waive the Applicant Companies’ obligations The Applicant Companies have not claimed, and there is no evidence to show, that the FSP at any point waived the requirement for the Applicant Companies to provide quarterly financial information. The Applicant Companies have otherwise not claimed or shown that they did provide the required quarterly information for September 2013 by the 31 October 2013 due date. Instead, it appears that the FSP gave the Applicant Companies leeway to provide the required quarterly information for September 2013 (and December 2013) in light of the ongoing finance negotiations. The leeway provided was to rollover the Bill Facility for a month beyond the contracted maturity date, to 31 January 2013. Although the Applicant Companies provided financial information to the FSP on 31 January 2014, 7 February 2014, and 12 February 2014, it remained open to the FSP to make a commercial decision not to rollover or extend the facilities once they matured on 30 January 2014. Given the Applicants were in default, and had been warned about being in default, from approximately November 2013 onwards, it was not unreasonable or unfair for the FSP not to rollover or extend the facilities beyond 30 January 2014. The FSP were entitled to charge default interest earlier than they did Once the Applicant Companies breached the quarterly information provision requirements for October 2013, the FSP was entitled to begin charging default interest after notifying the Applicant Companies that they were in default, in line with section 30.1(b) of the terms and conditions. It cannot reasonably be said that Case No: 368567 Recommendation Page 5 of 8 the FSP acted unfairly by charging default interest from 31 January 2014 onwards, when they were actually entitled to charge default interest from 1 November 2013 onwards. 2.2 Did the FSP mislead the Applicant Companies about reversing default interest? The Applicant Companies say that at a meeting with FSP representative “JC” on 15 April 2014, JC said that all default interest charged to that point would be reversed. Because the default interest was not later reversed, the Applicant Companies say that JC’s claim was misleading. The FSP says that it never told the Applicant Companies that default interest would be reversed. Instead, at the 15 April 2014 meeting, the FSP says that its representatives told the Applicant Companies that the FSP would review its position regarding the “charging of default interest going forward” after certain information was provided. The only contemporaneous evidence says nothing about an interest refund In claims about misleading conduct, FOS gives extra weight to records from the time of the alleged misrepresentation. This is because records from the time of the alleged misrepresentation are more likely to be an accurate record of what had just been said or not said. The Applicant Companies have not provided any contemporaneous evidence in relation to the 15 April 2014 meeting. The FSP has provided a typed diary note in relation to the meeting. The diary note is dated 15 April 2014. If the FSP promised to reverse default interest during the meeting, it is reasonable to expect that this would have been noted in the diary note. If such a promise was made, it would have been important for the FSP to note it so it could be actioned later. Also, given approximately $50,000 of default interest had accrued to the date of the meeting, such a promise would have been significant enough for the FSP to note for future reference. The diary note makes no mention of a promise to reverse default interest. The fact the promise is not noted in the only contemporaneous piece of evidence relevant to the meeting makes it less likely that such a promise was made by the FSP at the meeting. Emails sent after the meeting say nothing about an interest refund After the 15 April 2014 meeting, the FSP and Applicant Companies emailed each other as follows:  On 15 April 2014, the FSP sent an email to “confirm our meeting and take outs”. The FSP clarified what information the Applicant Companies needed to provide to it in order to “move to the next step”.  On 28 April 2014, the FSP followed up its request for information “so we can progress”.  On 28 April 2014, the Applicant Companies responded to say the required information was being prepared. Case No: 368567 Recommendation Page 6 of 8  On 30 April 2014, the FSP requested a timeframe for when the provision of information will be complete.  On 30 April 2014, the Applicant Companies responded to say it would provide the “latest financials by tomorrow evening”. These emails, which were sent soon after the meeting, carry weight as contemporaneous records of what was said and agreed upon during the meeting. None of the emails between the Applicant Companies and the FSP up to 30 April 2014 make mention of any promise to reverse interest charges. The purpose of these emails was to “confirm” what was said during the meeting and to ensure the parti es could “move to the next step”. You would reasonably expect the parties, and particularly the Applicant Companies, to mention in these emails the progress of any promise to reverse default interest, particularly given default interest continued to accrue in large amounts each day. The fact these emails do not mention the alleged promise makes it less likely that the promise was made. The emails do, however, make clear that the FSP required the Applicant Companies to provide further information. This is c onsistent with the FSP’s recollection that at the 15 April 2014 meeting, it told the Applicant Companies it would review interest going forward if information was required. It has not been shown that the information requested in these emails was ever provided by the Applicant Companies, and that the FSP was therefore required to review default interest going forward. It is not clear what loss was incurred in reliance on the alleged misrepresentation In FOS’s letter dated 20 March 2015, FOS asked the Applica nt Companies to clarify what loss they incurred in reliance on the alleged promise. In order for a claim of misleading conduct to succeed, an applicant needs to shows that he or she relied on the misleading conduct to their detriment. Although the Applicant Companies claim that they were misled, they have not shown what loss they suffered in reliance on the promise. For example, they have not demonstrated how the loss they are claiming in this dispute (the default interest) would not have been incurred if they were not misled by JC. If JC did not make the alleged misrepresentation, the default interest, which the FSP was otherwise entitled to charge, would still have been charged to the facilities until the facilities were refinanced. 2.3 Did the FSP provide a reasonable amount of time for the Applicant Companies to refinance? On 6 March 2014, the FSP sent a letter to the Applicant Companies requesting that the Applicant Companies:  Provide evidence that the refinance of their facilities had been approved by 31 March 2014  Fully refinance their facilities by 30 April 2014 The Applicant Companies say that the FSP letter dated 6 March 2014 was unfair and unreasonable, because it did not give them sufficient time to refinance. Case No: 368567 Recommendation Page 7 of 8 The refinance process had started already, so the timeframe was not unreasonable In their letter to FOS dated 6 June 2014, the Applicant Companies say that in February 2014, they had approached a third party financial services provider to refinance their FSP facilities. They arranged for “valu ations to take place on [their] properties and get our loans approved by [the third party provider]”. Once the valuations were completed, the Applicant Companies say they gave the valuations to the FSP on 26 February 2014. The Applicant Companies acknowledge that the valuations were on the letterhead of the third party provider. Having received the valuations on the letterhead of the third party provider, it is reasonable to assume that by 26 February 2014 the FSP was aware that the Applicant Companies’ fac ilities were being refinanced elsewhere. Taking into account the fact the FSP already knew the refinance was on foot, it was not unreasonable for the FSP to then write to the Applicant Companies on 6 March 2014 requesting evidence of refinance approval by 31 March 2014, and for refinance to be finalised by 30 April 2014. 2.4 Did the FSP delay settlement of the refinance of the facilities? Information shows settlement took 14 business days to finalise The information provided by the FSP and the Applicant Companies indicates that the FSP was first contacted by the third party financial provider to confirm refinance was going ahead on 5 May 2014. On that date, the third party provider emailed the FSP explaining that “it had approved funding” to refinance the facilities. There is no other information to show that the FSP knew the refinance was approved prior to this date. On 8 May 2014, the third party provider advised the FSP that, at settlement, eleven securities would need to be released. The Applicant Companies say that the FSP caused delays by providing incorrect payout figures to the third party provider between 13 May 2014 and 16 May 2014. Even if there were disagreements between the FSP, the third party provider, and the Applicant Companies about the correct payout figure, settlement still proceeded on 22 May 2014. 14 business days elapsed between 5 May 2014, when the FSP was first notified that the third party provider had approved the refinance, and 22 May 2014, when settlement took place. 14 business days was a reasonable turnaround time in the circumstances The facilities totalled over $11M, and the refinance of this figure involved the release of 11 securities and the discharge of a number of separate accounts. Given the size and complexity of the transaction, 14 business days was a reasonable period of time to ensure settlement went ahead successfully. Case No: 368567 Recommendation Page 8 of 8 2.5 Did the FSP make an error in relation to direct debits? Unclear what loss incurred because direct debits were stopped Before the Bill Facility matured, interest on the Bill Facility was direct debited monthly from the Applicant Companies’ overdraft account. When the Bill Facility matured on 30 January 2014, direct debits to the overdraft account were stopped because the Bill Facility balance was moved to a Bills Matured Account. It is unclear what loss was suffered because the direct debit of interest from the overdraft account stopped. If the direct debit was not stopped, this would simply have meant that default interest (which was otherwise co rrectly charged) would have been debited to the Applicant’s overdraft account instead of the Bills Matured account. Further, email correspondence between the FSP and the Applicant Companies’ representatives from 7 February 2014 and 12 February 2014 shows that the Applicant Companies more than likely knew that the Bill Facility had matured and not been rolled over. The Applicant Companies would also have received a statement dated 31 January 2014 that the balance of the Bill Facility had matured and was attracting default interest charges. With this information to hand, the Applicant Companies had the opportunity as early as 7 February 2014 to avoid any loss they now claim to have suffered because interest was no longer debited to the overdraft account. An FSP cannot be held responsible for loss that an applicant could have reasonably avoided. 3 Supporting information 3.1 Alleged extra fees charged upon settlement Throughout the dispute, the Applicant Companies have said that they were made to pay unfair charges when the refinance of the facilities was settled on 22 May 2015. FOS wrote to the Applicant Companies on 20 March 2015 requesting that they clarify what “extra unfair charges” they said they incurred upon refinance. The Applicant Companies clarified t hat the “extra charges made under this point as per what was noted in original emails to FOS”. The original losses claimed in this dispute were in relation to default interest charged after 31 January 2014. This decision has primarily been concerned with the default interest loss claim. The Applicants have otherwise not identified what further extra unfair charges they allege were incorrectly charged upon refinance. For that reason, the issue of extra unfair charges has not been addressed in this Recommenda tion.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.