Determination 367706

Mishandled repair scope and cash settlement after house fire

FirmFinancial Firm (Unknown - Insurer)
Decided2014-12-22
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$1,000
Amount claimed$237,745
SourceAFCA PDF

Summary

After a house fire the parties could not agree on the repair scope, and the FSP's management of the claim caused long delays. AFCA ordered an independent scope of works, cash settlement based on a builder's quote including temporary accommodation, and $1,000 for non-financial loss.

Having elected to settle by repair, the FSP was responsible for managing the repair process, and the bulk of the delays were attributable to it.

Issues

Subjects and remedies

financial hardshiphome or building damagepay claimpay non financial lossreassess claim

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination General Insurance - Domestic Insurance - Home Building - Service - Service Quality Determination Case No: 367706 Determination Page 1 of 7 Case number : 367706 1 2 December 2014 1 Overview 1.1 Dispute The Applicant lodged a claim under his home insurance policy with the Financial Services Provider (FSP) after his property suffered significant damage in a fire on 9 November 2013. The FSP accepted the Applicant’s claim and obtained a scope of works and a quotation for the repairs to the property. However, despite protracted negotiations, the parties have been unable to agree on the nature and extent of the repairs required. Each party blames the other for the delay in finalising the scope of works and commencing the repairs. 1.2 Issues and key findings Did the FSP manage the claim appropriately? The FSP failed to adequately manage the process of finalising the scope of works for the repair of the property. This contributed to the current dispute and significantly delayed the resolution of his claim. How should the claim be settled? There is insufficient information to conclusively determine the nature and extent of the repairs required. Accordingly, a suitably qualified independent consultant should be appointed to prepare a revised scope of works . Is the Applicant entitled to compensation? The bulk of the delays in resolving the claim are attributable to the actions of the FSP and its contractors. The Applicant has suffered significant stress and inconvenience as a result. 1.3 Determination This Determination is substantially in favour of the Applicant. The FSP is to cash settle the Applicant for the amount determined based on the replacement scope of works and quotation to be obtained in accordance with section 2.2 below (including an allowance for temporary accommodation). The FSP is to pay the Applicant an additional amount of $1,000 as compensation for non-financial loss. Case No: 367706 Determination Page 2 of 7 2 Reasons for Determination 2.1 Did the FSP manage the claim appropriately? Scope of works has been expanded significantly during claim process The FSP engaged a building consultant (CS) to prepare a scope of works for the necessary repairs, which was provided to the FSP on 28 November 2013. The FSP obtained quotes for the repairs based on CS’ scope of works and in early January 2014 appointed its builder (M) to carry out the repairs. M had quoted a total amount of $72, 256.80, based on CS’ scope of works. The Applicant was dissatisfied with the scope of the works on which M’s quotation was based, as he considered that it was inadequate to repair the necessary damage to his property. Over the following three to four months, the Applicant proposed a number of additional variations to the scope of works , some of which were accepted by the FSP while others were rejected. Copies of correspondence between the parties establishes that the Applicant engaged directly with the FSP’ s builder (M) on a number of occasions during this period. These discussions resulted in M amending the scope of works and issuing revised quotations on several occasions, including a quotation for $93,533 in March 2014 (itemised on a room by room basis). During this period, the FSP offered to cash settle the Applicant for the cost (to the FSP) of undertaking the repairs. However, in order to determine the cash settlement amount, M was required to provide a final quote for the repairs. Following further discussions with the Applicant, M issued a final revised quotation in May 2014. The amount of this quotation was more than double M’s original quotation and included total variations of approximately $136,000. These variations related to items such as the full-scale refitting of the bathrooms and the kitchen, the complete rewiring of the house and the replacement of the ducted air conditioning system, which had not been included in M’s earlier quotes. The Applicant considers that the FSP should settle his cla im on the basis of M’s final quotation. In support of his position, he has provided a quotation from his own builder for the repairs, at an estimated cost of $237,745. H owever, the FSP says that M’s final quotation is manifestly excessive and provides for the replacement of items which can be effectively restored. The FSP wants to undertake a further inspection of the property in order to determine an appropriate scope of works. FSP failed to adequately manage process for agreeing scope of repairs The FS P says that M’s final quotation is based on a revised scope of works which was requested by the Applicant. It considers that M has been unduly influenced by the Applicant’s numerous requests for additional variations. Having reviewed the FSP’s conduct of t he claim, the Panel considers that the FSP failed to adequately manage the process of finalising the scope of works for Case No: 367706 Determination Page 3 of 7 the necessary repairs. It appears that the FSP effectively left this to the Applicant and the builder (M) to resolve, rather than remaining actively involved in the process. Once the FSP had elected to settle the claim by repairing the property, it was incumbent on it to manage the repair process efficiently and effectively. This necessarily included liaising with its appointed contractors on an ongoing basis, so that any issues could be resolved promptly and fairly. The Panel finds it concerning that the FSP refused to accept the views of its preferred contractor (M), who had been appointed to undertake the repairs and to whom the FSP had effectively delegated the responsibility of reviewing any variations to the scope of works. By the time M provided his final quotation, the parties had been engaged in detailed negotiations about the scope of works for a number of months. The Panel considers that, had the FSP been more actively involved in the process, it would have been aware of the additional variations sought by the Applicant and could have discussed these in detail with M at the relevant time. This would have assisted i n accurately identifying the extent of the repairs required and would have minimised the likelihood that M would propose significant additional variations of which the FSP was apparently unaware. It may also have allowed the FSP to seek the views of third parties (for example, the building consultant (CS) who had initially prepared the scope of works). FSP’s contractor forged Applicant’s signature During the early stages of the claim process, the FSP engaged a restoration specialist (FR) to identify which areas of the building could be restored and which required replacement. FR appointed a sub-contractor (RC) to undertake a test clean at the property, to determine which areas could be cleaned effectively. RC provided FR with a brief report setting out his findings, together with a document apparently signed by the Applicant, confirming that he was satisfied with the results of the test clean. However, the Applicant subsequently discovered that RC had forged his signature on this document. The FSP has a cknowledged this and has apologised to the Applicant for RC’s actions. However, the Applicant considers that the FSP did not investigate the matter until several months after he raised the issue and has refused to provide him with detailed information about how the fraud occurred. It appears that once the Applicant became aware that his signature had been forged, he lost faith in the ability of the FSP and its contractors to effectively manage the repair process. In particular, he refused to accept the FSP’ s advice that parts of the property could be effectively cleaned, based on the results of the inspections and test clean undertaken by FR and RC. FSP was responsible for bulk of claim delays The FSP says that the delays in settling the claim are largely d ue to the Applicant’s refusal to allow the FSP’s contractors to access his property. The FSP says that it has been prejudiced by the Applicant’s actions because areas of the Case No: 367706 Determination Page 4 of 7 property which were previously assessed as capable of being restored have now deteriorated to such an extent that restoration may no longer be possible. However, having carefully reviewed the claim history, the Panel is satisfied that the FSP and its contractors had reasonable opportunities to access the property in the period between the Applicant lodging his claim and the FSP’s builder ( M) providing his final quote. The FSP and its contractors undertook several inspections and assessments of the building during this period. To the extent that the Applicant denied the FSP’s contractors access to the building, the Panel is satisfied that this occurred largely after the relationship between the parties had already broken down. At this stage, the Applicant considered that the FSP’s requests to carry out further inspections and conduct further tests were unnecessary, given the investigations whic h had been undertaken to date. The Panel accepts that some of the delays in finalising the claim were due to the number of additional issues raised by the Applicant in relation to the scope of works. However, the Panel considers that the Applicant’s actions in this regard were to some extent driven by his lack of faith in the FSP’s ability to manage the process, as a result of the unfortunate incident involving the forgery of his signature. The Applicant’s resulting mistrust of the FSP caused him to focus on each and every detail of the scope of work to ensure that nothing was overlooked. Accordingly, while the Panel accepts that the Applicant may have been responsible for some of the delays in finalising the claim, the Panel considers that the bulk of the delays were due to the actions of the FSP and its contractors. The Panel considers it unreasonable that the FSP was unable to reach a final view on the nature and extent of the damage to t he Applicant’s property by May 2014 (six months after the fire occurred), despite having had the benefit of several assessments by its preferred contractors. 2.2 How should the claim be settled? Available information is not conclusive as to extent of repairs required As outlined above, there are considerable discrepancies between the various quotes provided by M over the course of the claim process. It appears that the differences between M’s earlier and later quotes primarily turn on the extent to which the soot and smoke damage to parts of the ground floor (including the wall linings) can be effectively addressed by cleaning, or whether these areas need to be stripped out and replaced in their entirety. However, the FSP has also queried other specific items i ncluded in M’s final quotation, such as the complete rewiring of the house and the full replacement of the ducted air conditioning system. Having carefully reviewed the reports provided by the FSP’s contractors, the Panel is not satisfied that the available information clearly establishes the extent to which the ground floor areas can be effectively restored rather than replaced. Case No: 367706 Determination Page 5 of 7 The Panel notes that the FSP’s restoration specialist (FR) has confirmed in an email dated 6 June 2014 that the ground floor areas of the property were potentially restorable. However, the Panel considers that RC ’s reported findings following the test clean in December 2013 are ambiguous with regard to the effectiveness of the test clean of the ground floor (other than in relation to the windows). Further, it is not clear to what extent the delays in finalising the claim have resulted in the condition of the property further deteriorating such that cleaning will now no longer be effective to restore parts of the ground floor which could have been effectively restored in December 2013. The Panel notes that there is limited information available in relation to the other items raised by the FSP. M’s quotation and revised scope of works does not provide a detailed explanation as to the basis on which he has included these items, while the FSP’s position appears to be based largely on the views expressed by its internal assessors. For these reasons, the Panel is not satisfied that there is sufficient information available to determine the nature and extent of the necessary repairs to the property. Claim should be cash settled based on further independent assessment In the circumstances, the Panel considers that a suitably qualified independent consultant (who is acceptable to both parties and has not been involved in the claim to date) should be appointed at the FSP ’s cost to undertake a detailed assessment of the property and prepare a scope of works for the necessary repairs. Given the Panel’s finding that the FSP is responsible for the bulk of the delays in finalising the claim, the scope of works should include all of the works necessary to restore the property to its condition before the fire (regardless of whether the relevant damage was caused by the fire or has arisen as a result of the subsequent delays). Once the new scope of works has been received, the FSP is to engage an appropriately qualified builder to provide a quotation for the repairs based on the scope of works. Under the terms of the Applicant’s policy, the amount of any cash settlement paid by the FSP for a claim reflects the cost to the FSP of carrying out the necessary repairs. Accordingly, the builder’s quotation should be prepared on this basis. The builder should also provide an estimate of the time which will be required to complete the works. In the interests of finalising this dispute, the Panel considers it appropriate that the FSP be required to cash settle the Applicant for the amount of the builde r’s quotation. The Panel notes that the FSP has paid the Applicant the maximum temporary accommodation benefits available under the policy. However, given the circumstances of this dispute, the Panel considers that the cash settlement to be Case No: 367706 Determination Page 6 of 7 paid by the FSP should be increased to include the reasonable costs of temporary accommodation for the Applicant and his family during the estimated repair period. As the cash settlement amount will be determined based on current rates, the FSP is not required to pay interest on this amount. 2.3 Is the Applicant entitled to compensation? Applicant is entitled to compensation for non-financial loss Under paragraph 9.3(a) of the Terms of Reference, FOS is able to award compensation (capped at $3,000) where an applicant has experienced an unusual degree or extent of physical inconvenience, time take n to resolve the situation or interference with their expectation of enjoyment or peace of mind. For the reasons outlined above, the Panel considers that the FSP’s management of the claim process has contributed to the excessive delays in finalising the claim. The Applicant sys that he has suffered financial hardship as a result of having to fund rent and mortgage payments, and has been threatened with eviction from his rental accommodation. In the circumstances, the Panel considers that the Applicant is entitled to the amount of $1,000 as compensation for non-financial loss. Case No: 367706 Determination Page 7 of 7 3 Supporting information 3.1 FOS approach to this dispute This dispute has not been the subject of a FOS Recommendation. Due to the nature of the dispute, it has been referred directly to a Panel for Determination, in line with the Operational Guidelines to the FOS Terms of Reference. The Panel consists of an Ombudsman and two representatives with consumer and insurance experience. The Panel has decided this case on its merits, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions. There has been a full exchange of all material information relied on for the purposes of this Determination and each party has had the opportunity to address any issues raised by the other. The Panel has reviewed and considered all of the material provided by the parties. While the parties have raised a number of issues in their submissions, for the purposes of this Determination the Panel has restricted its commentary to those issues which it considers directly relevant to the outcome only.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.