Determination 367706
Mishandled repair scope and cash settlement after house fire
Summary
After a house fire the parties could not agree on the repair scope, and the FSP's management of the claim caused long delays. AFCA ordered an independent scope of works, cash settlement based on a builder's quote including temporary accommodation, and $1,000 for non-financial loss.
Having elected to settle by repair, the FSP was responsible for managing the repair process, and the bulk of the delays were attributable to it.
Issues
- Claim amount dispute primary · unclear
“the Panel is not satisfied that there is sufficient information available to determine the nature and extent of the necessary repairs to the property.”
- Poor claim handling secondary · upheld
“the FSP failed to adequately manage the process of finalising the scope of works for the necessary repairs.”
- Delay secondary · upheld
“the bulk of the delays were due to the actions of the FSP and its contractors.”
- Third-party or outsourcing failure secondary · upheld
“RC had forged his signature on this document. The FSP has acknowledged this and has apologised.”
Subjects and remedies
financial hardshiphome or building damagepay claimpay non financial lossreassess claim
Text of the determination
Determination
General Insurance - Domestic Insurance - Home Building - Service - Service Quality
Determination
Case No: 367706 Determination Page 1 of 7
Case number : 367706 1 2 December 2014
1 Overview
1.1 Dispute
The Applicant lodged a claim under his home insurance policy with the Financial
Services Provider (FSP) after his property suffered significant damage in a fire on
9 November 2013.
The FSP accepted the Applicant’s claim and obtained a scope of works and a
quotation for the repairs to the property. However, despite protracted negotiations,
the parties have been unable to agree on the nature and extent of the repairs
required. Each party blames the other for the delay in finalising the scope of
works and commencing the repairs.
1.2 Issues and key findings
Did the FSP manage the claim appropriately?
The FSP failed to adequately manage the process of finalising the scope of works
for the repair of the property. This contributed to the current dispute and
significantly delayed the resolution of his claim.
How should the claim be settled?
There is insufficient information to conclusively determine the nature and extent of
the repairs required. Accordingly, a suitably qualified independent consultant
should be appointed to prepare a revised scope of works .
Is the Applicant entitled to compensation?
The bulk of the delays in resolving the claim are attributable to the actions of the
FSP and its contractors. The Applicant has suffered significant stress and
inconvenience as a result.
1.3 Determination
This Determination is substantially in favour of the Applicant.
The FSP is to cash settle the Applicant for the amount determined based on the
replacement scope of works and quotation to be obtained in accordance with
section 2.2 below (including an allowance for temporary accommodation). The
FSP is to pay the Applicant an additional amount of $1,000 as compensation for
non-financial loss.
Case No: 367706 Determination Page 2 of 7
2 Reasons for Determination
2.1 Did the FSP manage the claim appropriately?
Scope of works has been expanded significantly during claim process
The FSP engaged a building consultant (CS) to prepare a scope of works for the
necessary repairs, which was provided to the FSP on 28 November 2013. The
FSP obtained quotes for the repairs based on CS’ scope of works and in early
January 2014 appointed its builder (M) to carry out the repairs. M had quoted a
total amount of $72, 256.80, based on CS’ scope of works.
The Applicant was dissatisfied with the scope of the works on which M’s quotation
was based, as he considered that it was inadequate to repair the necessary
damage to his property. Over the following three to four months, the Applicant
proposed a number of additional variations to the scope of works , some of which
were accepted by the FSP while others were rejected.
Copies of correspondence between the parties establishes that the Applicant
engaged directly with the FSP’ s builder (M) on a number of occasions during this
period. These discussions resulted in M amending the scope of works and issuing
revised quotations on several occasions, including a quotation for $93,533 in
March 2014 (itemised on a room by room basis).
During this period, the FSP offered to cash settle the Applicant for the cost (to the
FSP) of undertaking the repairs. However, in order to determine the cash
settlement amount, M was required to provide a final quote for the repairs.
Following further discussions with the Applicant, M issued a final revised
quotation in May 2014. The amount of this quotation was more than double M’s
original quotation and included total variations of approximately $136,000. These
variations related to items such as the full-scale refitting of the bathrooms and the
kitchen, the complete rewiring of the house and the replacement of the ducted air
conditioning system, which had not been included in M’s earlier quotes.
The Applicant considers that the FSP should settle his cla im on the basis of M’s
final quotation. In support of his position, he has provided a quotation from his
own builder for the repairs, at an estimated cost of $237,745.
H owever, the FSP says that M’s final quotation is manifestly excessive and
provides for the replacement of items which can be effectively restored. The FSP
wants to undertake a further inspection of the property in order to determine an
appropriate scope of works.
FSP failed to adequately manage process for agreeing scope of repairs
The FS P says that M’s final quotation is based on a revised scope of works which
was requested by the Applicant. It considers that M has been unduly influenced
by the Applicant’s numerous requests for additional variations.
Having reviewed the FSP’s conduct of t he claim, the Panel considers that the
FSP failed to adequately manage the process of finalising the scope of works for
Case No: 367706 Determination Page 3 of 7
the necessary repairs. It appears that the FSP effectively left this to the Applicant
and the builder (M) to resolve, rather than remaining actively involved in the
process.
Once the FSP had elected to settle the claim by repairing the property, it was
incumbent on it to manage the repair process efficiently and effectively. This
necessarily included liaising with its appointed contractors on an ongoing basis,
so that any issues could be resolved promptly and fairly.
The Panel finds it concerning that the FSP refused to accept the views of its
preferred contractor (M), who had been appointed to undertake the repairs and to
whom the FSP had effectively delegated the responsibility of reviewing any
variations to the scope of works. By the time M provided his final quotation, the
parties had been engaged in detailed negotiations about the scope of works for a
number of months.
The Panel considers that, had the FSP been more actively involved in the
process, it would have been aware of the additional variations sought by the
Applicant and could have discussed these in detail with M at the relevant time.
This would have assisted i n accurately identifying the extent of the repairs
required and would have minimised the likelihood that M would propose
significant additional variations of which the FSP was apparently unaware. It may
also have allowed the FSP to seek the views of third parties (for example, the
building consultant (CS) who had initially prepared the scope of works).
FSP’s contractor forged Applicant’s signature
During the early stages of the claim process, the FSP engaged a restoration
specialist (FR) to identify which areas of the building could be restored and which
required replacement. FR appointed a sub-contractor (RC) to undertake a test
clean at the property, to determine which areas could be cleaned effectively.
RC provided FR with a brief report setting out his findings, together with a
document apparently signed by the Applicant, confirming that he was satisfied
with the results of the test clean. However, the Applicant subsequently discovered
that RC had forged his signature on this document.
The FSP has a cknowledged this and has apologised to the Applicant for RC’s
actions. However, the Applicant considers that the FSP did not investigate the
matter until several months after he raised the issue and has refused to provide
him with detailed information about how the fraud occurred.
It appears that once the Applicant became aware that his signature had been
forged, he lost faith in the ability of the FSP and its contractors to effectively
manage the repair process. In particular, he refused to accept the FSP’ s advice
that parts of the property could be effectively cleaned, based on the results of the
inspections and test clean undertaken by FR and RC.
FSP was responsible for bulk of claim delays
The FSP says that the delays in settling the claim are largely d ue to the
Applicant’s refusal to allow the FSP’s contractors to access his property. The FSP
says that it has been prejudiced by the Applicant’s actions because areas of the
Case No: 367706 Determination Page 4 of 7
property which were previously assessed as capable of being restored have now
deteriorated to such an extent that restoration may no longer be possible.
However, having carefully reviewed the claim history, the Panel is satisfied that
the FSP and its contractors had reasonable opportunities to access the property
in the period between the Applicant lodging his claim and the FSP’s builder ( M)
providing his final quote. The FSP and its contractors undertook several
inspections and assessments of the building during this period.
To the extent that the Applicant denied the FSP’s contractors access to the
building, the Panel is satisfied that this occurred largely after the relationship
between the parties had already broken down. At this stage, the Applicant
considered that the FSP’s requests to carry out further inspections and conduct
further tests were unnecessary, given the investigations whic h had been
undertaken to date.
The Panel accepts that some of the delays in finalising the claim were due to the
number of additional issues raised by the Applicant in relation to the scope of
works. However, the Panel considers that the Applicant’s actions in this regard
were to some extent driven by his lack of faith in the FSP’s ability to manage the
process, as a result of the unfortunate incident involving the forgery of his
signature. The Applicant’s resulting mistrust of the FSP caused him to focus on
each and every detail of the scope of work to ensure that nothing was overlooked.
Accordingly, while the Panel accepts that the Applicant may have been
responsible for some of the delays in finalising the claim, the Panel considers that
the bulk of the delays were due to the actions of the FSP and its contractors. The
Panel considers it unreasonable that the FSP was unable to reach a final view on
the nature and extent of the damage to t he Applicant’s property by May 2014 (six
months after the fire occurred), despite having had the benefit of several
assessments by its preferred contractors.
2.2 How should the claim be settled?
Available information is not conclusive as to extent of repairs required
As outlined above, there are considerable discrepancies between the various
quotes provided by M over the course of the claim process.
It appears that the differences between M’s earlier and later quotes primarily turn
on the extent to which the soot and smoke damage to parts of the ground floor
(including the wall linings) can be effectively addressed by cleaning, or whether
these areas need to be stripped out and replaced in their entirety. However, the
FSP has also queried other specific items i ncluded in M’s final quotation, such as
the complete rewiring of the house and the full replacement of the ducted air
conditioning system.
Having carefully reviewed the reports provided by the FSP’s contractors, the
Panel is not satisfied that the available information clearly establishes the extent
to which the ground floor areas can be effectively restored rather than replaced.
Case No: 367706 Determination Page 5 of 7
The Panel notes that the FSP’s restoration specialist (FR) has confirmed in an
email dated 6 June 2014 that the ground floor areas of the property were
potentially restorable. However, the Panel considers that RC ’s reported findings
following the test clean in December 2013 are ambiguous with regard to the
effectiveness of the test clean of the ground floor (other than in relation to the
windows).
Further, it is not clear to what extent the delays in finalising the claim have
resulted in the condition of the property further deteriorating such that cleaning will
now no longer be effective to restore parts of the ground floor which could have
been effectively restored in December 2013.
The Panel notes that there is limited information available in relation to the other
items raised by the FSP. M’s quotation and revised scope of works does not
provide a detailed explanation as to the basis on which he has included these
items, while the FSP’s position appears to be based largely on the views
expressed by its internal assessors.
For these reasons, the Panel is not satisfied that there is sufficient information
available to determine the nature and extent of the necessary repairs to the
property.
Claim should be cash settled based on further independent assessment
In the circumstances, the Panel considers that a suitably qualified independent
consultant (who is acceptable to both parties and has not been involved in the
claim to date) should be appointed at the FSP ’s cost to undertake a detailed
assessment of the property and prepare a scope of works for the necessary
repairs.
Given the Panel’s finding that the FSP is responsible for the bulk of the delays in
finalising the claim, the scope of works should include all of the works necessary
to restore the property to its condition before the fire (regardless of whether the
relevant damage was caused by the fire or has arisen as a result of the
subsequent delays).
Once the new scope of works has been received, the FSP is to engage an
appropriately qualified builder to provide a quotation for the repairs based on the
scope of works.
Under the terms of the Applicant’s policy, the amount of any cash settlement paid
by the FSP for a claim reflects the cost to the FSP of carrying out the necessary
repairs. Accordingly, the builder’s quotation should be prepared on this basis. The
builder should also provide an estimate of the time which will be required to
complete the works.
In the interests of finalising this dispute, the Panel considers it appropriate that the
FSP be required to cash settle the Applicant for the amount of the builde r’s
quotation.
The Panel notes that the FSP has paid the Applicant the maximum temporary
accommodation benefits available under the policy. However, given the
circumstances of this dispute, the Panel considers that the cash settlement to be
Case No: 367706 Determination Page 6 of 7
paid by the FSP should be increased to include the reasonable costs of temporary
accommodation for the Applicant and his family during the estimated repair
period.
As the cash settlement amount will be determined based on current rates, the
FSP is not required to pay interest on this amount.
2.3 Is the Applicant entitled to compensation?
Applicant is entitled to compensation for non-financial loss
Under paragraph 9.3(a) of the Terms of Reference, FOS is able to award
compensation (capped at $3,000) where an applicant has experienced an
unusual degree or extent of physical inconvenience, time take n to resolve the
situation or interference with their expectation of enjoyment or peace of mind.
For the reasons outlined above, the Panel considers that the FSP’s management
of the claim process has contributed to the excessive delays in finalising the
claim. The Applicant sys that he has suffered financial hardship as a result of
having to fund rent and mortgage payments, and has been threatened with
eviction from his rental accommodation.
In the circumstances, the Panel considers that the Applicant is entitled to the
amount of $1,000 as compensation for non-financial loss.
Case No: 367706 Determination Page 7 of 7
3 Supporting information
3.1 FOS approach to this dispute
This dispute has not been the subject of a FOS Recommendation. Due to the
nature of the dispute, it has been referred directly to a Panel for Determination, in
line with the Operational Guidelines to the FOS Terms of Reference. The Panel
consists of an Ombudsman and two representatives with consumer and insurance
experience.
The Panel has decided this case on its merits, having regard to the relevant law,
good industry practice, codes of practice and previous FOS decisions.
There has been a full exchange of all material information relied on for the
purposes of this Determination and each party has had the opportunity to address
any issues raised by the other.
The Panel has reviewed and considered all of the material provided by the
parties. While the parties have raised a number of issues in their submissions, for
the purposes of this Determination the Panel has restricted its commentary to
those issues which it considers directly relevant to the outcome only.