Transfer breaching settlement agreement, with refinance delay and loan balance offer complaints

FirmFinancial Firm (Unknown)
Decided2015-11-17
ProductPayment Systems · Account payment / transfer
OutcomeFor the complainant in part
Amount awarded$436
Non-financial loss$2,000
Amount claimed—
SourceAFCA PDF

Summary

A customer said the lender breached a settlement agreement by transferring a monthly repayment instead of the agreed fortnightly amount, and she also complained about refinance delay and a $6,000 loan reduction offer. AFCA found the transfer was a breach warranting $2,000 non-financial loss and fee refunds, and found the lender did not cause the delay or owe the $6,000.

A firm that breaches a settlement agreement by making an unauthorised transfer must compensate the customer for the stress and inconvenience caused, while fee refunds and waivers follow from the error.

Issues

Subjects and remedies

financial hardshipmental healthdebt waiver or reductionpay non financial lossrefund fees or charges

Related

All Financial Firm (Unknown) determinations · Find similar determinations

Text of the determination

Determination Case No: 367105 Determination Page 1 of 7 Case number: 367105 13 November 2015 1 Overview 1.1 Dispute This dispute is about whether the FSP breached an obligation to the Applicant by:  Transferring $1,705.38 from her account ending x6138 (Facility) to her loan ending x4111 (Loan) (the Transfer). The Transfer occurred after a settlement agreement had been reached between the parties regarding payments between the accounts.  Unreasonably delaying her refinance with a new financial services provider (New Provider).  Failing to reduce the Loan balance by $6,000 after it offered to do so. 1.2 Issues and key findings Did the FSP err in making the Transfer? The Transfer breached the terms of the FSP’s settlement agreement with the Applicant. It had agreed to accept fortnightly payments of $785.16 in settlement of a previous dispute. The Transfer comprised one month’s payment. The FSP should refund fees of $32 arising from the Transfer. An award of non- financial loss of $2,000 is appropriate for the stress and inconvenience the Applicant suffered as a result of the error by the FSP. Did the FSP cause the refinance to be unreasonably delayed? Based on the available information, the FSP did not cause the refinance delay. The FSP is not obliged to compensate the Applicant for any loss she says she has suffered as a result of the delay. Did the FSP err in failing to reduce the Loan by $6,000? The Applicant never a ccepted the FSP’s offer to reduce the loan balance by $6,000. However, the FSP should refund $404.18 in other fees that it charged to the Applicant. 1.3 Determination This Determination is partially in favour of the Applicant. Should the Applicant accept this Determination within 30 days of its date (above):  The Applicant should instruct the FSP to close her outstanding accounts. Case No: 367105 Determination Page 2 of 7  Within a further 14 days of the Applicant’s acceptance of the Determination, and her instruction to close her outstanding accounts held with it (whichever is the later), the FSP must: o pay $2,436.18 (being the compensation amount) to the Applicant’s nominated account, o waive any outstanding fees owing on the Applicant’s FSP credit card and transaction accounts, and o close the Applicant’ s credit card and transaction accounts. In the event the Applicant makes any further transactions on the transaction account or the credit card between the date of this Determination and the FSP closing those accounts, she will be liable for all such amounts plus all outstanding fees and charges associated with them. Should the Applicant not accept this Determination within 30 days of its date, the FSP is not required to pay any compensation to the Applicant. Case No: 367105 Determination Page 3 of 7 2 Reasons for Determination 2.1 Did the FSP err in making the Transfer? The FSP breached the settlement agreement On 18 April 2014, the parties resolved a previous FOS dispute by agreement. The terms of the agreement included:  the Applicant would make fortnightly Loan repayments of $785.16, and  those payment would be drawn from the Facility. On 3 July 2014, the FSP made the Transfer, made up of the monthly, rather than fortnightly, payment amount due under the settlement agreement. The FSP reversed the Transfer five days later, on 8 July 2014. The Transfer constituted a breach of the settlement agreement. The Transfer caused the Applicant to incur fees The Applicant says that the Transfer caused her to incur two overdrawn fees and two account servicing fees totalling $32. The FSP has already offered to refund those fees to her. The Applicant has not provided any information substantiating any additional financial loss she says she suffered as a result of the Transfer, such as late payment fees she incurred between 3 and 8 July 2014. Her claim in this regard has therefore not been established. An award for non-financial loss is appropriate A customer who enters into an agreement with their FSP to resolve an existing dispute would expect that the FSP would abide by its obligations under that agreement. If the FSP does not do so, a customer may be left without access to their own funds. That situation was exacerbated in the Applicant’s circumstances, as:  The FSP had conducted numerous similar transfers on the Applicant’s account previously. Those transfers had formed the basis of her previous dispute. The Applicant viewed the Transfer as the latest in a series of FSP errors.  As a result of the Transfer, she did not have access to $458.91 that she otherwise would have had.  She had minimal other funds available between 3 and 8 July 2014. She had not yet refinanced with the New Provider, had approximately $200 available on her FSP Credit Card - and had exceeded her credit limit with a third financial services provider at the time of the Transfer.  She says she was unable to pay for costs such as food and bills, and the lack of funds affected her mental health in making her feel like she could not provide for herself or her family. In this respect I note that the first purchase the Applicant made after the payment reversal was at a supermarket. Case No: 367105 Determination Page 4 of 7 In the circumstances of this case, an award of $2,000 is appropriate to compensate the Applicant for the unreasonable and undue stress and inconvenience she suffered as a result of the Transfer. I note this is at the higher end of the amount of compensation that FOS will award for non-financial loss as I am satisfied that the Applicant, given her circumstances – was extremely stressed as a result of the consequences of FSP’s error. 2.2 Did the FSP cause the refinance to be unreasonably delayed? Industry practice guides the FSP When a customer approaches a financial services provider to refinance their existing debt, the new financial services provider will contact the existing provider to organise the refinance. If the refinanced debt is secured by property, the new financial services provider will need to register a mortgage over that property. It is normal industry practice for that property settlement to occur in the state where the property title is registered. The FSP did not cause the delay The Applicant expected to refinance her FSP debt with the New Provider on 1 August 2014. The refinance did not occur until one week later, on 8 August 2014, due to a miscommunication between the FSP and New Provider. The New Provider believed settlement would occur in Victoria, whereas the FSP believed it would occur in Western Australia. As a result, the FSP had to send a certificate of title from Western Australia to Victoria before settlement could occur. On balance, the FSP did not delay the refinance. The FSP’s records show that it was prepared to settle on 7 July 2014. In addition, it was not unreasonable for the FSP to send the Victorian title to Western Australia for settlement. One of the two titles was registered in We stern Australia, and both the Applicant and the New Provider’s head office are based in that state. Further, the New Provider has already compensated the Applicant for the delay. The Applicant’s New Provider statements show that the New Provider drew down the new loans and started charging interest on 31 July 2014. However, on 8 August 2014, the New Provider applied “Interest Adjustment” credits of $211.05 and $464.90 to the Applicants new x064 and x065 loan accounts respectively. Those amounts are almost exactly what the Applicant should have expected to pay in interest for the 8 days to 8 August 2014. In these circumstances, it appears that the Applicant did not “double pay” interest to both the FSP and New Provider, and has not suffered a financial loss as a result of the settlement delay. 2.3 Did the FSP err in failing to reduce the Loan by $6,000 ? Law and industry practice guide the FSP For a contract to be binding at law, there must be agreement between the parties (amongst other things). This requires an offer and acceptance. An offer can be Case No: 367105 Determination Page 5 of 7 withdrawn at any time before it is accepted. If an offer is withdrawn, the offeree is not bound by the offer. The Applicant did not accept the offer On 4 August 2014, the FSP offered to reduce the Loan balance by $6,000 by email from its representative to the Applicant. A copy of the relevant correspondence between the parties appears at 3.1 below. Based on the available information, the Applicant did not accept the offer. The Applicant has acknowledged that her response to the FSP on 4 August 2014, was effectively a rejection of its offer. In her response to its offer, she said: Even if I was to accept this reason, how/why did [the FSP] take out the amount on the 4th of July when there was insufficient funds? The Applicant in effect attached a condition to her counteroffer, by suggesting that she would accept the FSP’s offer if it explained to her how and why it made the Transfer. The Applicant has made various claims about the source of the $6,000. Ultimately the account statements show that the Applicant did owe the refinanced debt. FOS will not consider any other issues relating to the previously settled dispute. The FSP should refund other charges and fees to the Applicant The Applicant believes that the FSP should refund the following fees to her:  A $60 compensation charge she says was offered in resolution of a dispute over an interest adjustment.  An annual charge and interest owing on her FSP credit card.  A $375 loan package fee (Package Fee) she incurred on 4 July 2014, as she did not receive the promised access to a dedicated customer service centre.  Account fees for a transaction account she has left open while FOS is considering the dispute. The Applicant says she has not instructed the FSP to close the transaction account due to the issues she has had with the FSP and to enable her to access evidence. The FSP has agreed to pay the $60 compensation charge to the Applicant, and to waive the outstanding balance on the credit card. In those circumstances, it is unnecessary to consider those charges any further. On the grounds of fairness, the FSP should refund a portion of the Package Fee for that part of the year that the Applicant did not receive a benefit. I have based that conclusion on the following factors:  The FSP has said it would provide a pro-rata refund of the Package Fee if a customer cancels the Package within six weeks of incurring the fee.  Although the Applicant may not have formally requested the termination of the Package, she refinanced within that six week period, and the FSP cancelled the Package within that time. Case No: 367105 Determination Page 6 of 7  The Applicant received Package benefits for the 35 days between when the Package Fee was charged on 4 July 2014 until the refinance on 8 August 2014, such as a lower interest rate on her nominated loan account. The FSP should pay a further $344.18 pro- rata refund to the Applicant’s nominated account. A financial services provider may continue to charge account fees until a customer instructs it to close the account. A custome r who does not wish to incur those fees must close their account. On the face of it, the Applicant is liable for outstanding transaction account fees and interest of $40.71 as at 29 October 2015 as she:  used the transaction account on at least two occasions after the refinance (on 15 and 29 August 2014),  has had access to the transaction account and  has not yet instructed the FSP to close this account. However as the FSP is willing to waive this amount, and in the interests of resolving the dispute and closing this account, the FSP should waive the outstanding fees and interest and close the transaction account. In the event the Applicant makes any further transactions on this account between the date of this Determination and the transaction account being closed, she will be liable for all such amounts plus all outstanding fees and charges associated with this account. Case No: 367105 Determination Page 7 of 7 3 Supporting information 3.1 Offer and response from the Applicant On 4 August 2014, the FSP’s representative emailed the following offer to the Applicant: In light of what you have experienced and to try to lower your repayments back to $785.16 - I have identified that your home loan requires a balance reduction of $6,000.00 and then a bank initiated renewal to reinstate repayments to approximately $785.16. This is also to try and ensure no problem arises in the future. Thus, I am willing to lower your home loan balance by this amount of $6,000.00. [our emphasis added] Later on 4 August 2014, the Applicant responded Even if I was to accept this reason, how/why did [the FSP] take out the amount on the 4th of July when there was insufficient funds? I don't understand how [the FSP] can change the "rules" to suit them. Please explain this. 3.2 Other issues The Applicant has asked us to consider whether the FSP adversely affected her ability to refinance with the New Provider. As the Applicant has successfully refinanced, and we have considered the Applicant’s loss from refinance delay, it is unnecessary to consider this matter any further.