Home / Financial Firm (Unknown - Credit) / Determination 367043

Determination 367043

Financial difficulty request and enforcement on expired bridging facility

FirmFinancial Firm (Unknown - Credit)
Decided2014-12-09
ProductCredit · Home loan
OutcomeFor the complainant in part
Amount awarded$173
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The Applicants, in financial difficulty on a 12-month bridging facility that expired in December 2013, complained about the FSP's hardship handling and its fees and costs. AFCA found the hardship obligations were met, but ordered a $173.11 refund of reduced input tax credit and no pass-through of enforcement costs during the FOS dispute.

An FSP must genuinely consider hardship requests, and it cannot recover more than it is out of pocket, so input tax credits it is entitled to must be credited to the customer.

Issues

Subjects and remedies

financial hardshiprefund fees or charges

Related

All Financial Firm (Unknown - Credit) determinations · Find similar determinations

Text of the determination

Determination Credit - Consumer Credit - Home Loans - Charges - Incorrect fees/ costs Credit - Consumer Credit - Home Loans - Financial Difficulty - Decline of Financial Difficulty Request - Request to Suspend Enforcement Proceedings Determination Case No: 367043 Determination Page 1 of 6 Case number : 367043 7 November 2014 1 Overview 1.1 Dispute This dispute concerns financial difficulty the Applicants experienced in relation to a short term bridging facility with the FSP, which expired in December 2013. 1.2 Issues and key findings Did the FSP meet its financial difficulty obligations? The FSP has met its obligations to give genuine consideration to the Applicants’ requests for assistance by:  forbearing on enforcement action on multiple occasions from April 2013 onward, and  providing additional time to refinance following the expiry of the facility. Did the FSP apply fees, charges and costs correctly? The FSP should refund $173.11 for the reduced input tax credit. It cannot apply any enforcement costs incurred from when the FOS dispute was lodged until it is closed. 1.3 Determination This Determination is partially in favour of the Applicants. If the Applicants accept this Determination, the FSP must:  refund $173.11 applied for legal costs for the reduced input tax credit available to the Applicants. Whether or not the Applicants accept this Determination, the FSP should not pass on enforcement or legal costs incurred while the dispute was open with FOS. Once FOS closes its file, the FSP will be entitled to exercise its rights under the credit contract. Case No: 367043 Determination Page 2 of 6 2 Reasons for Determination 2.1 Did the FSP meet its financial difficulty obligations? An FSP has obligations to give genuine consideration It is good industry practice for an FSP to genuinely consider a customer’s request for assistance, where the customer is in financial difficulty. I also expect a customer to be willing to work with their financial services provider, and to propose a realistic repayment plan that will res ult in the repayment of the debt within a reasonable timeframe. The FSP met its financial difficulty obligations to the Applicants The FSP has genuinely considered the Applicants’ requests for assistance, and has met its obligations to try to assist the Applicants overcome their financial difficulty because:  in April 2013, the FSP offered the Applicants four months to repay the arrears which had accrued and supported their application to release superannuation  it provided the Applicants with additional time to clear arrears in August 2013  it met with the male Applicant in October 2013 and placed a hold on its enforcement action after agreeing to a payment arrangement; it confirmed that it would not be extending the loan past its expiry in December 2013  following the expiry of the facility, the FSP provided additional time for the Applicants to achieve refinance until April 2014, when it recommenced enforcement action  the FSP has made further offers while the dispute has been open with FOS to allow the Applicants additional time to achieve either refinance or sale of the security property in order to repay their indebtedness; it also offered to reduce their indebtedness. The term of the facility was 12 months. The Applicants were on notice at the commencement of the contract that, if the FSP did not renew the facility, they were required to repay the facility in full through either refinance wit h another financial institution or through sale of the security property. The Applicants have failed to achieve refinance in the ten months since the expiry of the facility, and have not demonstrated that a refinance is underway. It does not appear that refinance is an option available to the Applicants, and it would be unreasonable to provide any additional time to continue with this process. In these circumstances, and given the assistance already provided, the FSP is entitled to exercise its rights under the credit contract once FOS closes its file. 2.2 Did the FSP apply fees, charges and costs correctly? Interest, fees and charges have been applied correctly The interest rate, fees or charges which should be applied to any credit facility will be determined by the agreement between the financial services provider and its Case No: 367043 Determination Page 3 of 6 customer. According to the contract, the interest, fees and charges applicable were contained in the “financial table” as follows: Fee Amount Description Enforcement fee $2,150 Payable upon any default by you under the terms and conditions of this Offer and Loan Contract Dishonour fee $55 Payable for any dishonoured cheque, failed direct debit or any other failed payment method whereby payment is not received by us. Enforcement expenses $150 p/h Includes but is not limited to payment of any external legal costs. Default interest 15.50% p.a. Defau lt Interest shall be charged upon any amounts not paid by the due date for payment under the terms and conditions of this Offer and Loan Contract for the period that such amounts remain unpaid and commencing from the date of the default. Where the repaymen t of the amount of credit has been accelerated by reason of any ongoing default then default interest will be applied to the total loan balance which includes the amount of credit and any accrued but unpaid interest and fees. Additional fees and charges applied to the facility are summarised in Table 1, contained in Section 3 of this Determination. I am satisfied that the FSP correctly applied dishonour fees. This is because it appears to have attempted to direct debit the Applicants’ nominated account to draw payments in the periods outlined above, without success. The FSP applied interest at the higher rate in June 2013, July 2013, October 2013, November 2013 and December 2013. This was because the Applicants had not remedied the default referred to in the notices issued, as outlined in Table 2, Section 3. While the Applicants have indicated they have not received all notices issued by the FSP, I am satisfied that these were issued to the correct address to their last known address. The term of the facility expired on 7 December 2013 and the balance became due and payable; interest has been applied at the higher rate since this time. I am satisfied the FSP is entitled to apply interest at this rate in line with the credit contract. The legal and enforcement expenses are reasonable FOS will consider legal and enforcement costs insofar as to whether the costs were reasonably and properly incurred and accounted to the customer. This includes consideration of discounts or rebates to whic h the financial services provider was entitled and the impact of the GST component of such costs on a financial services provider’s claim for reimbursement. Case No: 367043 Determination Page 4 of 6 I have reviewed the solicitors’ invoices and I am satisfied the FSP was entitled to pass on the legal costs associated with enforcing its rights under the credit contract. I am also satisfied that the work was conducted on a reasonable basis, for instance, preparing affidavits of service or related court documents. Whether the Applicants received a copy of a default notice (which is claimed by the Applicants) does not mean that the costs that were not reasonably and properly incurred. The FSP has provided two invoices issued by it to the Applicants for enforcement expenses. The first invoice was issued on 1 September 2013 for an amount of $2,150 and the second on 1 July 2014 for $2,475. Both invoices were issued with reference to clause 7.3 of the FSP’s terms and conditions, which states: If a default occurs, in addition to any default interest accrued, you must pay us: a) an enforcement fee in the amount specified in the financial table; and b) the enforcement expenses we reasonably incur in collecting payment or exercising our rights under this agreement and as set out in the financial table. The financial table, contained in the credit contract, states that a flat fee of $2,150 will be applied upon any default under the terms and conditions, and enforcement expenses will be charged at $150 per hour. While the invoices do not itemise the specific work undertaken by the FSP, I am satisfied, based on the available information, that the FSP would have spent a considerable period of time in exercising its rights in the period for which the invoices cover. The FSP must apply the Reduced Tax Input Credit for legal costs It is the view of this office that a financial services provider is not entitled to recover any more than that which it is, or should reasonably be, out of pocket. Therefore, if the financial services provider is entitled to a credit from a third party, that credit should be accounted for in the financial service provider’s claim for reimbursement from its customer. It is on this basis that FOS will take into account any entitlement the financial services provider would have to claim a Reduced Input Tax Credit (RITC) as allowed under the GST legislation on the costs incurred and passed on to its customer. This is because an entitlement to claim the RITC rests with the financial services provider as the entity which received the services eligible for a RITC; if the costs are passed on in total to the customer, the customer is not able to make a claim to the Australian Taxation Office as the customer did not contract for the services supplied. A financial services provider’s practice in accounting to t he ATO for any RITC to which it is entitled is a matter for the provider. However, even if a financial services provider elects not to claim an RITC to which it is entitled, this office expects the financial services provider acting reasonably and prudently to account to its customer for any RITC entitlement. Case No: 367043 Determination Page 5 of 6 As such, if the Applicants accept this Determination the FSP should refund the RITC component of GST for each of the invoiced solicitors’ costs. GST was applied to the following costs, which would require a refund of $173.11: Invoice date Total charge GST component RITC 30 April 2013 $480.70 $43.70 $32.77 6 August 2013 $412.50 $37.50 $28.13 2 June 2014 $1,076.90 $97.90 $73.43 30 June 2014 $3,305.70 $51.70 $38.78 The parties to a FOS dispute must bear the reasonable costs of their legal representation, if they so choose to be represented. As such, the FSP will not be entitled to pass on any legal costs incurred from 4 July 2014, when the Applicants lodged their FOS dispute, until this dispute is closed. Case No: 367043 Determination Page 6 of 6 3 Supporting information Table 1: Additional fees and charges Month Description Feb 2013  2x dishonour fees: $110  Penalty/default interest: $21.28 Mar 2013  Dishonour fee: $55  Penalty /default interest: $20.90 Apr 2013  Dishonour fee: $55  Penalty interest: $41.32 May 2013  Dishonour fee: $55  Penalty/default interest: $60.45  Legal fees: $480.70 Sept 2013  Dishonour fee: $55  Penalty/default interest: $21.44 Oct 2013  Dishonour: $55 Nov 2013  Late payment: $55 Table 2: Notices Date Notice type Arrears amount Pay by Whether paid 9 Apr 13 Default notice $9,770.49 16 Apr 13 No 30 May 13 Letter $20,595.63 17 Jun 13 No 8 Aug 13 Default notice $4,249.75 16 Aug 13 No 5 Sep 13 Letter $5,015.42 7 days No 25 Sep 13 Default notice $4,749.30 2 Oct 13 No 8 Oct 13 Default notice $12,021.05 15 Oct 13 No 22 Oct 13 Default notice $12,021.05 29 Oct 13 No 12 Nov 13 Notice to pay $16,215.19 19 Nov 13 No

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.