Determination 367015

Denial of Crisis Benefit claim for breast cancer diagnosed within the three-month waiting period

FirmFinancial Firm (Unknown - Insurer)
Decided2015-02-23
ProductLife Insurance · Trauma / critical illness
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The Applicant claimed a Crisis Benefit for his daughter's breast cancer, which was diagnosed within the policy's three-month waiting period. AFCA found the FSP was entitled to deny the claim and that any application delay did not change the outcome.

The policy excludes cancer diagnosed within the three-month waiting period from the policy start date, which was 11 August 2009 once the application was accepted, and no unreasonable delay by the FSP was established.

Issues

Subjects and remedies

health or medicalno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 367015 Determination Page 1 of 2 Case number : 367015 23 February 2015 1 Overview 1.1 Dispute This dispute is about the denial by the Financial Services Provider (FSP) of an Applicant’s claim for a Crisis Benefit. The claim was denied on the basis that the claimed condition arose within 90 days of the start date of the policy. A Financial Ombudsman Service (FOS) Case Manager provided the parties with a Recommendation on the issues in dispute. The Recommendation was in favour of the FSP. A copy of the Recommendation is attached to this Determination. 1.2 Issues and Key findings Were the findings, reasons and outcome of the Recommendation correct? The findings, reasons and outcome contained in the Recommendation were correct and are adopted in this Determination . I agree with the Case Manager’s findings and reasons and the recommended outcome. Further submissions provided after the Recommendation have been considered. 1.3 Determination This Determination is in favour of the FSP. The FSP was entitled to deny the claim and is not required to pay a Crisis Benefit to the Applicant. Case No: 367015 Determination Page 2 of 2 2 Reasons for Determination 2.1 Were the findings and outcome in the Recommendation correct? I have determined this dispute based on what I consider is fair in all the circumstances, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions. I have taken into account all the material submitted by the parties, both before and after the Recommendation. I am satisfied that the documentation I have relied on has been provided to both parties. I am satisfied that the case manager’s Recommendation contains an accurate summary of the dispute, the issues to be determined, any applicable paragraphs of the Terms of Reference and any relevant law. The following is added, after taking into account the submissions provided in response to the Recommendation. The impact of delay on the outcome The Applicant submitted that the FSP had contributed to a delay of 5 weeks to the application process. If I accept that submission, the FSP would have been responsible for the policy not starting by 7 July 2009 and the three month waiting period would have ended by 7 October 2009. Under the poli cy, no payment for a Crisis Benefit is made if “the condition occurred or was diagnosed, or the circumstances leading to the diagnosis became apparent” within the three month waiting period. In the Critical Illness claim form, the life insured (Ms Z) confirmed that:  the symptoms commenced on 2 August 2009  she became aware of the symptoms on 15 August 2009  she first attended her doctor on 17 August 2009, and  she was diagnosed with cancer on 29 October 2009. Had the policy start date been 5 weeks earlier, the evidence on file is that the circumstances leading to the diagnosis became apparent by 15 August 2009 and no Crisis Benefit would have been payable. Any delay by the FSP did not affect the outcome of the dispute. Recommendation Case No: 367015 Recommendation Page 1 of 7 Case number: 367015 3 December 2014 1 Overview 1.1 Dispute This Applicant holds a Life Insurance Policy (the Policy) with the Financial Services Provider (FSP), insuring his daughter Ms Z. On 29 October 2009 Ms Z was diagnosed with breast cancer. On 25 October 2012 Ms Z lodged a claim with the FSP seeking payment of the benefit. This dispute is about the FSP’s decision to deny the claim. 1.2 Issues and key findings Was the FSP entitled to deny the Applicant’s claim? Under the Policy terms and conditions a claim for cancer will be excluded if the cancer is diagnosed within the first three months of the Policy start date. The FSP was entitled to deny the claim as Ms Z’s cancer diagnosis was made within three months of the Policy start date. Did the FSP unreasonably delay the assessment process? There is no evidence that the FSP unreasonably delayed the application process. 1.3 Recommendation This Recommendation is in favour of the FSP. The FSP was entitled to deny the claim and is not required to pay a benefit to the Applicant. Case No: 367015 Recommendation Page 2 of 7 2 Reasons for Recommendation 2.1 Was the FSP entitled to deny the claim? The Applicant was provided with interim cover during the application period The Applicant made an application for cover in favour of Ms Z and forwarded a cheque made out to the FSP on 5 May 2009. On 9 May 2009 the FSP advised the Applicant that it was offering interim cover during the application process, which was subject to the terms and conditions as set out the in Product Disclosure Statement (PDS). Further, the FSP outlined that the interim cover started from the date it received the application and payment, and was valid for 90 days or until the application was accepted. The interim cover excluded cancer The interim cover offered to the Applicant excluded cover for cancer. Section 7 of the PDS provides details of the interim cover: Crisis Cover If you applied for the [plan name] Plan, we will insure the life to be insured against the Crisis Events listed within the [plan name] Plan that do not have an * next to the named event.” Crisis events are: …  Cancer - Cancer* Therefore had Ms Z been diagnosed with cancer between 5 May 2009 and the date on which the application was accepted by the FSP, she would have not been covered for this condition. Interim cover was in place while the application process continued until 7 August 2009 The payment of the premium in May 2009 was in respect of the interim cover and as is usual practice, provided the Applicant with cover whilst the application process was taking place, but did not signify the commencement of full cover. This is emphasised in correspondence from the FSP to the Applicant on 9 May 2009 outlining that temporary cover was being offered. Case No: 367015 Recommendation Page 3 of 7 The Interim Cover Certificate clearly states that the purpose of interim cover “is to provide coverage up to maximum amounts against unforeseeable events while we assess you application ” (emphasis added). Letters to the adviser and Applicant confirmed the ongoing application process, that is, there was no indication that full cover had been put in place, or that the application had been approved and the Policy had commenced. During the application process the FSP wrote to the Applicant and his adviser requesting additional information. Letters dated 25 June 2009, 15 and 29 July 2009 stated the application was still pending underwriting approval. It is clear that during this period the application for insurance had not been accepted by t he FSP. Acceptance of the application by the FSP is necessary in establishing the Policy start date. The Policy start date was 11 August 2009 The Policy start date is defined in the PDS as: “ Section 6 General Policy Conditions Term of Policy and Plan As soon [as the FSP] receives and accepts [emphasis added] your application for insurance and the first premium is paid your Policy is then in place and starts working for you. The date on which this occurs is known as the Policy or Plan start date (whichever is applicable) and will be shown in t he Policy Schedule.” The Applicant signed and returned the final letter of offer and paid the remaining outstanding premiums on 10 August 2009. The letter and cheque were received by the FSP on 11 August 2009. On 11 August 2009 the FSP accepted the App licant’s application and it issued the Policy Schedule and Certificate. The diagnosis was made within three months of the Policy start date The FSP is not required to pay a benefit to the Applicant because Ms Z’s cancer diagnosis was made on 29 October 2009, within three months of the start date of the Policy. The PDS states that cancer is subject to a waiting period: *In the case of these events, no benefit would be paid under the Plan if the condition occurred or was diagnosed…within three months afte r:  The Plan start date;...” Case No: 367015 Recommendation Page 4 of 7 Whilst the Applicant is not covered for this particular event. It is noted that the Policy remains in force and provides substantial cover should Ms Z require it in the future. 2.2 Did the FSP unreasonably delay the assessment process? The initial application was processed without any unreasonable delay The chronology of events as presented in 3.1 below demonstrates:  the application was received by the FSP on 5 May 2009 and the application was accepted on 11 August 2009  the FSP maintained contact with the Applicant throughout the application process  requests were made by the FSP for information and medical evidence from third parties  the application process was not completed when the first letter of offer was sent because the Applicant requested further quotes in order to reduce premiums  on 25 June 2009 the FSP requested further medical information and this was not received until 1 July 2009  the FSP provided its Letter of Offer on 29 July 2009 and the Applicant posted the completed forms and payment on 10 August 2009. The Applicant has not established an unreasonable delay on the part of the FSP during the application process. Case No: 367015 Recommendation Page 5 of 7 3 Supporting information 3.1 Chronology of events Date Key points 27 and 30 April 2009 On 27 April 2009 Ms Z signed the completed FSP’s insurance application form. The Applicant signed the same form on 30 April 2009. 30 April 2009 The Applicant’s dated cheque stub for payment of $2,815.01 to the FSP. 5 May 2009 The FSP received the Appl icant’s application and the first premium was banked. The Application was assessed under Policy number 1344419. 9 May 2009 The FSP wrote to the Applicant stating it was offering interim cover subject to the terms and Conditions in the PDS. Further, that i nterim cover started on the date the FSP received the application and payment and was valid for 90 days or until either:  it accepted the application  the application was withdrawn  it accepted the application subject to conditions or;  it advised the Applicant in writing that the application was not accepted. 7 to 14 May 2009 The FSP asked a question regarding the financial assessment and this was referred to the Chief Underwriter. 14 May 2009 The FSP requested a Personal Medical Attend ees Report from Ms Z’s treating doctor. 23 June 2009 Personal Medical Attendees Report received. 25 June 2009 The FSP wrote to the adviser requesting Ms Z undertake a spirometry test. The letter stated the application was pending underwriting approval an d further requirements may be requested. 1 July 2009 Additional medical information was received however the spirometry results remained outstanding. 14 July 2009 The FSP referred the application to the CMO for interpretation of the results. 15 July 2009 The FSP wrote to the Applicant and adviser with a requirement request, increasing the loadings for Policy number 1344419 as follows:  Life with 50% loading  Crisis with 75% loading Case No: 367015 Recommendation Page 6 of 7  TPD with 50% loading  Total annual premium of $4581.72 The letter to the adviser stated: “ Please note that your application is pending Underwriting approval & further requirements may be requested. ” The letter to the Applicant stated: “ To finalise the documentation and establish commencement of cover, could you please sign and date the attached Letter of Offer ...” 20 July 2009 Email between the insurance broker to the adviser that made recommendations reducing the premiums. Recommended life cover of two million that will reduce if any TPD or trauma payment is made. 29 July 2009 Ms Z requested increased cover and a new quote was received. A new policy was set up under Policy number 1347543 for Crisis Protection and Total and Permanent Disablement Benefits. 29 July 2009 The FSP sent a Letter of Offer to the Applicant and to t he adviser with an increased loading of 75% for the Crisis Protection Plan on Policy number 1347543. The letter to the adviser stated: “ Please note that your application is pending Underwriting approval & further requirements may be requested. ” The letter to the Applicant stated: “ To finalise the documentation and establish commencement of cover, could you please sign and date the attached Letter of Offer ...” 29 July 2009 The FSP sent a Letter of Offer to the Applicant and to the adviser with an increased loading of 50% for the Life Protection Benefit of two million on Policy number 1344419. 7 August 2009 Interim cover expired. 7 August 2009 The Applicant’s adviser wrote to the FSP enclosing:  Letter of Offer dated 29 July 2009 in respect of the Life Benefit of two million  Letter of Offer dated 29 July 2009 in respect of the Crisis Protection Plan for $500,000  a cheque for $743.71 covering the loadings on the Policies. 10 August 2009 A handwritten note on the above letter (dated 7 August 2009) state d; “Posted to [the FSP] in a prepaid envelope on 10/8/09”. 11 August 2009 Policy Schedule and Certificate for 1347543 – Crisis Protection Plan (linked to Life Protection Plan). Recorded the premium was increased by 75% by agreement and the start Case No: 367015 Recommendation Page 7 of 7 date is 1 1 August 2009. 11 August 2009 Policy Schedule and Certificate for 1344419 – Life Protection Plan. Recorded a start date of 11 August 2009. 13 August 2009 Letter from the FSP to the Applicant confirming Policy number 1347543 was now in place. The letter requested the Applicant check the Policy Certificate and contact the FSP if any amendments were needed. 13 August 2009 Letter from the FSP to the Applicant confirmed Policy number 1344419 was in place. The letter requested the Applicant check the Policy Certificate and contact the FSP if any amendments were needed. 15 November 2012 Treating Doctor’s report confirmed Ms Z’s breast cancer was diagnosed on 29 October 2009.