Determination 366689
Storm-damaged shed claim - further settlement refused after builder rebuild
Summary
The Applicants' storm-damaged shed was to be rebuilt by a builder authorised through the FSP's loss assessor, but the work was not completed and the FSP refused further settlement. AFCA ordered a cash settlement of $29,990 without interest.
The FSP authorised and supervised the builder as its agent and could not rely on a clearance certificate when it knew the works were incomplete.
Issues
- Claim denial primary · upheld“The FSP cannot simply rely on the clearance certificate to say it fulfilled its obligations where the information established the works had not been completed.”
- Third-party or outsourcing failure secondary · upheld“The FSP is responsible for the actions of W, the builder who acted under its authority and did not complete the claim works.”
Subjects and remedies
small businesspay claim
Related
All Financial Firm (Unknown - Insurer) determinations · Find similar determinations
Text of the determination
Determination
General Insurance - Small Business/Farm Insurance - Commercial Property - Service -
Service Quality
Determination
Case No: 366689 Determination Page 1 of 7
Case number: 366689 9 April 2015
1 Overview
1.1 Dispute
This dispute arises because the Applicants are dissatisfied with the refusal by the
Financial Services Provider (FSP) to provide a further settlement for their claim of
storm damage to a shed, which occurred on 11 February 2009.
In 2009, the FSP authorised and paid a builder (W) for the rebuild of the shed.
At that time, the FSP’s loss assessor (F) was satisfied with W’s progress updates
and with the receipt of the clearance certificate, allegedly signed by the female
Applicant, which confirmed the Applicants’ satisfaction with the completion of the
works.
On that basis, the FSP says it complied with its obligations and discharged its
liability under the policy. Therefore, it says it is not required to provide further
payments to the Applicants.
The Applicants disagree with this position and say the FSP never settled the claim
(save for a payment for cleaning of debris) as W never built a new shed and they
never received any cash settlement for the shed.
They want a further settlement of $29,990 for their claim.
1.2 Issue and key findings
Are the Applicants entitled to a further settlement of $29,990?
The Applicants are entitled to a further settlement of $29,990 because:
on balance, the FSP authorised W to rebuild the shed
the FSP is responsible for the actions of agents acting on its behalf
despite the female Applicant having signed a clearance certificate, the FSP
would have reasonably been aware the works were not completed.
1.3 Determination
This Determination is in favour of the Applicants.
The FSP is to cash settle the Applicants for $29,990.
Case No: 366689 Determination Page 2 of 7
2 Reasons for Determination
2.1 Are the Applicants entitled to a further payment of $29,990?
In its notice of response, the FSP says:
it authoris ed W’s quote on or around 21 September 2009
F sent an authority to W, approving its quote of $29,990 and asking W to
obtain a clearance certificate from the Applicants to confirm receipt of quoted
goods and authorise payment of W by the FSP.
The Applicants say they were not involved in the selection of the appointed
builder and F and the FSP had all the control on this decision. They also say that,
although W is under their son’s control, they have not had contact with him since
2008, meaning before the claimed loss occurred.
The available information (as per section 3.2 below) contradicts in part the
Applicants’ position. The notes from their broker (R) and F indicate the Applicants
were aware of W’s involvement and its appointment and als o assisted in obtaining
a revised quote from W.
The FSP says F allegedly sent a letter on 23 September 2009 to the Applicants
(the receipt of which they deny) advising them that:
the “contract for supply will be between [the Applicants] and [W]”
they should contact W to make the appropriate arrangements for supply
following satisfactory supply, F had asked W to submit the tax invoice and a
clearance certificate signed by the Applicants directly to F’s office.
However, the available information indicates:
F managed the claim and made a decision as to which builder was more
suitable for the FSP to authorise the payment to
the FSP was invoiced by W for progress payments made during the claims
handling process, before the certificate for the satisfactory supply of the shed
was obtained
F kept supervision of the claim, obtaining updates from W during the period of
alleged rebuild of the shed and even after the date in which the female
Applicant would have signed the clearance certificate.
I am satisfied based on the evidence available that F (as an agent of the FSP)
was in charge of supervising W’s actions and recommended the FSP make
progress payments to W during the claims handling process.
I am satisfied the conduct of F was so different to what was outlined in the letter of
23 September 2013 that it effectively varied its terms.
There is no indication the Applicants were in charge of the work assigned to W or
had any influence in the developments regarding the replacement of the shed or
the progress payments to W. This was controlled by F.
In the absence of further evidence, I am satisfied, on balance, that the FSP
authorised W to rebuild the shed and W was acting under the FSP ’s authority
during that time.
Case No: 366689 Determination Page 3 of 7
FSP is responsible for the actions of agents acting on its behalf
Based on the above information, I am satisfied W acted under FSP’s autho rity to
proceed with the rebuild of the shed.
Effectively, W acted as an agent of the FSP and the FSP was responsible to
ensure W had completed the work as authorised.
Female Applicant signed a clearance certificate acknowledging a shed was
“supplied”
The female Applicant says she does not remember seeing or signing the
clearance certificate.
She also says “I could not swear that the signature on the Clearance Certificate is
mine I do not remember ever seeing that document before it was emailed to me
by [FOS], the writing at the top is too shaky to be mine” [sic] and she does not
know if it is her signature or not.
I note:
without any relevant expert evidence, a plain look of the FOS dispute form and
the clearance certificate suggests there is at least a similarity in the
handwritings
the female Applicant does not categorically deny that it is her signature, she
simply does not recall the document or having signed it.
The Applicant does not clearly dispute having signed the clearance certificate. In
the absence of any evidence to the contrary, it is reasonable to accept the
accuracy of the clearance certificate on face value. As such, on the balance of
probabilities, I accept the female Applicant signed the clearance certificate.
I note the FSP was requested by F to make numerous progress payments to W
prior to the certificate being provided. The clearance certificate was sent prior to
the last payment.
FSP would have been reasonably aware the works were not completed
After the date of the signature on the clearance certificate, F (acting as an agent
of the FSP) sought an update from W regarding the works. On 24 February 2010,
F noted on the FSP’s system for the claim: “ Our recent discussions with the
supplier confirm the hayshed is anticipated to arrive within the next five (5) days” .
Therefore, F and the FSP were reasonably aware that despite the contents of the
clearance certificate, the shed had not been “satisfactorily supplied” at the time.
It is unclear why, despite this information, F issued a final report in which it told
the FSP the final invoice was in order and attached the clearance certificate
confirming the Applicants’ satisfaction with the works.
This is clearly at odds with what was actually happening at the time and with the
information that the FSP had to hand regarding the status of the claim works.
It is uncertain why F decided to accept the clearance certificate when it knew
works were not completed, yet it proceeded with finalising the claim.
Case No: 366689 Determination Page 4 of 7
It is reasonable to expect that F, on behalf of the FSP would have contacted the
Applicants to clarify the discrepancy between the signed clearance certificate and
W’s update.
Ultimately, the FSP was responsible for W’s a ctions. It was aware that W had not
completed the works.
I am satisfied the FSP cannot simply rely on the clearance certificate to say it
fulfilled its obligations and discharged its liability under the policy where the
information available established the works had not been completed.
W did not complete the claim related works and thus the FSP remains responsible
for its actions.
The FSP may be entitled to recover its costs from W not fulfilling its obligations
under its agreement with the FSP for the rebuild of the shed but that is not
something that is subject to this Determination.
FSP is to cash settle the Applicants
The Applicants have provided conflicting information regarding the status of the
ownership of their property and who currently manages the farming business
operating on site.
As the current status of the ownership of the property, or whether the Applicants
would be allowed to have a new shed is unclear, in order to bring the matter to a
conclusion, it is fair in all circumstances to cash settle the claim as per W’s
quotation, at $29,990.
Interest is not applicable
Considering the circumstances of this case and the fact the dispute had been
brought before the Financial Ombudsman Service approximately four years after
the construction of the shed was supposedly completed, I consider it would not be
fair to apply interest on the cash settlement amount.
Case No: 366689 Determination Page 5 of 7
3 Supporting information
3.1 FOS approach for this dispute
This dispute has not been the subject of a FOS Recommendation. Due to its
nature, FOS has considered it appropriate to proceed directly to Determination in
line with the Operational Guidelines to the FOS Terms of Reference.
There has been a full exchange of the relevant material between the parties and
each party has had the opportunity to address the issues raised.
3.2 Key information on relevant materials
Record Key information
Applicants’
broker (R)
File note
7 Sep 2009
“[Female Applicant] ha s phoned and wanting the following noted on
claim file.
…
- Would prefer to use their own builder that original quote was done
by, they can revise to […] shed for around $30 000. Are sending a
copy of revised quote today.
Advised [female Applicant] that I would pass this request onto
[FSP] once quote received” [sic].
F’s first report
8 Sep 2009
“We acknowledge the quotation provided by the Insured’s
contractor, [W] …”
Applicants’
broker (R)
Email to F and
FSP
9 Sep 2009
“Insured has phoned and are wanting to replace damaged shed in
a new location in which they believe is subject to less wind
preventing simular [sic] damage recurring.
…
Insured is keen to have their own builder replace the shed.”
F SP ’s claim note
21 Sep 2009
“ Spoke with [L].
Has advised ou r office that he awaits a final quote for repairs, has
received the insured s revised quote for repairs. We should have
an answer by the end of the week” [sic].
F’s second report
23 Sep 2009
“Following discussions with the Insured and [FSP’s representativ e]
regarding settlement of this claim, we acknowledge [the FSP’s]
acceptance of the quotation from W at $29,990.00 (including GST)
on the basis that it has allowed for above standard footings. Supply
has been authorised and we await an invoice.
…
IMMEDIATE RESPONSIBILITIES
Insured: Authorise shed reinstatement”
F’s second report
11 Nov 2009
“[F] will continue with the management of the claim and keep you
informed of further developments.”
F SP ’s claim note F says: “Our recent discussions with t he shed supplier confirm the
Case No: 366689 Determination Page 6 of 7
13 Jan 2010 foundations have been completed, however they await the hayshed
to arrive at the end of January. We anticipate completion of the
hayshed in mid February 2010.”
Clearance
Certificate
(Supply)
15 Feb 2010
“ I /We [Applicants] … confirm [W] has satisfactorily suppled me /us
with 1 SHED AS PER QUOTED AND ACCEPTED BY INSURER.
…
I /We authorise my /our Insurer to pay the supplier’s Tax Invoice for
supply of the above.
Signed: [female Applicant]
Date: 15 – FEB – 10”.
F SP ’s claim note
24 Feb 2010
F says: “Our recent discussions with the supplier confirm the
hayshed is anticipated to arrive within the next five (5) days.”
F’s final report
24 Feb 2010
“We attach a tax invoice from [W] … for final repairs to the
machinery shed. This invoice is in order and we attach a copy of
the signed Clearance Certificate confirming the Insured’s
satisfaction with such works.”
F’s authority to W
20 May 2010
“2. Authority for supply must be provided by the Insured.
…
5. Following supply we ask that you please submit the following
direct to our office:
The attached clearance certificate, signed by the Insured,
confirming satisfactory receipt of the quoted goods and
authorising our Principal’s payment of your Tax Invoice
…
7. If the signed clearance or a similar receipt signed by the
Insured is not received we will first be required to contact the
Insured to confirm satisfactory supply, before we are in a
position to recommend payment of your Tax Invoice.
8. The above arrangement has been confirmed with the Insured.”
F’s loss assessor
(L)
Statutory
Declaration
7 Nov 2014
“The Insured provided me with [W’s] contact details.
…
The Insured informed me they wished to proceed with [W]
…
I subsequently contacted the Insured to advise them t hat [W] had
been approved to conduct the repair work.
..
In or around October 2009, I received progress invoices from [W]
for the construction of the shed … Prior to approving these invoices
and submitting them to [FSP] for payment, I telephoned and spoke
with the Insured to confirm that they were happy with the work
being done by [W]. If at any time during these conversations the
Insured had indicated that they were not happy with the progress, I
would not have approved payment of the invoices.”
Case No: 366689 Determination Page 7 of 7
3.3 Other relevant materials relied upon
Policy terms and conditions with effective date 1 March 2009.
Policy schedule for the period 14 August 2008 to 14 August 2009.
W’s quotation with date 12 August 2009.
W’s tax invoices and F’s payment advices
F’s claim history.
Parties’ submissions.