Concrete driveway and fuel line damage claim declined as settlement or gradual deterioration
Text of the determination
Determination
General Insurance - Small Business/Farm Insurance - Commercial Property - FSP
Decision - Denial of Claim - Exclusion/Condition
Determination
Case No: 366458 Determination Page 1 of 10
Case number : 366458 27 January 2015
1 Overview
1.1 Dispute
The Applicant ‟s company (insured), claimed for the cost of repairing damage to its
property (a petrol station), submitting that the damage was caused by loads
imposed on the property‟s concrete driveway by a heavy vehicle.
The Financial Service Provider (FSP) declined the claim on the basis the damage
was caused by subsidence, settlement and long term gradual deterioration, which
were excluded events.
1.2 Issue and key findings
Can FSP refuse the claim?
The FSP can refuse the claim because the available evidence is more consistent
with a view that the damage to insured‟s property was caused by settlement,
which is an excluded event.
1.3 Determination
This Determination is in favour of the FSP.
The FSP is not required to indemnify the insured for the damage to its property.
Case No: 366458 Determination Page 2 of 10
2 Reasons for Determination
2.1 Can FSP refuse the claim?
FSP has to prove an exclusion to decline the claim
The policy provides coverage for accidental damage occurring at the property,
during the period of insurance. There is no dispute:
a number of underground fuel lines at the property failed pressure tests on 8
August 2012 and were apparently leaking
their repair necessitated the removal and replacement of a section of the
property‟s concrete driveway.
There is no evidence the insured expected or intended the damage to its property.
This means the insured would be entitled to indemnity for the damage unless the
FSP proves the claim is not covered or is otherwise excluded.
Engineer “CG” suggest damage cause by load imposed by heavy vehicle
The insured believes the fuel lines were damaged by loading imposed by a heavy
vehicle at corners of the concrete driveway, which meet a gatic cover. It relies on
engineer “CG”, who essentially explained the sequence of events as follows:
a heavy vehicle likely cracked the corners of the concrete driveway sometime
between 30 July and 12 August 2012
stormwater naturally drains towards the gatic cover area as it was located at
the low section of the driveway (relative to the rest of the property)
stormwater had seeped under the concrete slab and undermined the sub-
base through the cracks
this led to settlement of the service pit, causing further failure of the concrete
slab and likely damaged the fuel lines as well.
CG initially believed that the damage was caused by settlement, explaining that:
there was substantial moisture beneath the concrete slab
this undermined and caused the sub grade to fail, possibly creating a void
under the slab
continued traffic loads over the area caused the concrete to fracture and fail,
possibly damaging the fuel lines as well.
CG says his initial opinion should be discounted because:
he inspected the area after it was excavated and discovered that the ground
water table was at least 3.0m below the finished surface level
the crack in the concrete was “clean” and as such, did not appear consistent
with a crack arising from “fatigue failure”.
Other engineers say damage caused by settlement
The FSP maintains there is no evidence the fuel lines were damaged by loads
imposed by a heavy vehicle. It relies on other expert evidence which say the
damage was caused by long term settlement of the fill material above the
underground tanks.
Case No: 366458 Determination Page 3 of 10
This line of evidence explains the sequence of events as follows:
rainwater had seeped under the concrete slab through unsealed joints in the
concrete driveway
rainwater softened and undermined the sub-base material
repeated vehicle loads then caused further settlement and the development of
the cracks in the concrete.
Settlement or earth movement damage is excluded unless an exception
applies
The policy essentially excludes damage caused by any form of settlement or
earth movement, unless such settlement or earth movement was a direct
consequence of:
an earthquake
a subterranean fire
a volcanic eruption
water escaping from a water main owned by a water supply authority.
Although there are conflicting explanations as to how the damage to fuel lines and
concrete driveway could have occurred, it is common ground:
there is settlement of the concrete driveway
the settlement was due to excessive moisture in the sub-base and sub-soil
area
the settlement was part of the chain of events that led to or caused the
damage claimed.
There is no dispute the excessive moisture in the area was essentially stormwater
that had seeped into the sub-base and sub-soil areas. It is accordingly plain the
circumstances causing the settlement does not fall within any of the exceptions to
the relevant exclusion. This is the case whether one accepts that:
stormwater had seeped under the slab through unsealed joints or the cracks
the cracks were caused by loads imposed by a heavy vehicle.
Evidence more consistent that damage was caused by settlement
In any case, the available evidence is more consistent with a view that the
damage was likely caused by long term settlement of the relevant concrete slab.
There is no dispute stormwater naturally drains towards the relevant area. There
is also no evidence that the gaps between the concrete slabs were sealed, which
meant stormwater could readily seep into the sub-base and sub-soil area.
Bureau of Meteorology records further indicate that the property received a
moderate amount of rain in the months leading to the discovery of the fuel line
failures.
There is also:
photographic evidence of “stepping” in the concrete slabs, which is an
indication of settlement and differential movement of the slabs
6 reported incidents of contaminated fuel involving fuel dispensed by the failed
fuel lines in 2012, which indicates there was moisture in the sub-soil and the
Case No: 366458 Determination Page 4 of 10
fuel lines were already failing before the claimed vehicle impact (load)
incident.
These matters support conclusions that:
the sub-base and sub-soil in the relevant area were indeed exposed to and
undermined by excessive moisture
the concrete driveway in the relevant area likely cracked and settled as a
result, as suggested by the FSP‟s engineers and CG‟s initial opinion.
It is unlikely that the damage to the property was caused by a single incident of a
heavy vehicle cracking the concrete driveway.
The property is operated as a petrol station and its concrete driveway was some
125mm thick. There is no suggestion the driveway thickness was inadequate so it
should be expected to cope with regular vehicle traffic on a daily basis, including
traffic from heavy vehicles (such as refuelling tankers or other large vehicles).
If the driveway is somehow able to crack as a result of an incident of loads being
imposed by a heavy vehicle, the reasonable inference is that it was likely due to
fatigue failure of the slab as a result of its age, which may be excluded on the
basis of wear and tear.
No evidence damage was due to inoperable submersible pump
The Applicant‟s broker has belatedly suggested there was an inoperable
submersible pump in the valve body pit, which purportedly caused or exacerbated
the presence of moisture in the relevant area.
The Panel finds no evidence in the available material to support this proposition.
Case No: 366458 Determination Page 5 of 10
3 Supporting information
3.1 Key expert evidence
Expert evidence
Record Key points
Tenant ’s fuel tank
expert ( T )
Report
8 August 2012
Fuel lines 1 - 6 for premium fuel were failing pressure test .
Nitrogen was used to see if any visible signs of leaks
would appear .
Bubbles began appearing at the gatic cover and cracks
near or around a security bollard after a few minutes .
Water was visible at all risers throughout the tank farm .
Applicant’s consultant
e ngineer ( CG )
Report
6 September 2012
Inspected site on 23 August 2012 .
Service station‟s driveway concrete paving was generally
in satisfactory condition, with minimal evidence of cracking
or damage .
Concrete paving surrounding an underground tank/pit
showed significant cracking and some areas of the
pavement were fractured .
Fractured pavement adjacent to the corner of the tank/pit,
showed significant movement and deflection under normal
pedes trian loadings .
Substantial volume of water was evident beneath the
pavement level .
Recent increase in rainfall likely increased local
groundwater levels and flows, which then appeared to
undermine and cause the pavement sub grade to
deteriorate and fail .
The sub grade failure created a potential void under the
concrete paving and traffic loads then caused the concrete
pavement to fracture and fail .
Repair would essentially entail removal and replacement of
some 6m x 6m concrete paving, repair of underground
services and fuel supply infrastructure, and reinstatement
of sub grade material .
Tenant’s repairer (M)
Report
19 September 2012
Testing showed that tanks 2 and 4, and lines 1 - 6 have
failed, so the failed equipment was immediately removed
from service to prevent contaminated fuel from being sold .
The site uses a suction system so that one line per tank is
“teed” to all pump positions onsite, which means that any
line failure would result in the entire tank being removed
from service .
Tank 3 is not in use due to unknown suction issues .
Concrete subsidence has occurred over the tank, possibly
due to water pooling and run off from other areas of the
forecourt .
Concrete subsidence may have contributed to the site‟s
current fuel system problems .
Case No: 366458 Determination Page 6 of 10
Gene ral run off on site and from the building is not directed
to stormwater, and is causing instability to the concrete
above the tank farm and possible slab failures .
The root cause of the failure of tanks 2 and 4 is unknown .
Quoted $228,280.93 (plus GST) to expose and tests tanks
and replace the whole piping system using a non -
corrodible (UPP) piping system .
Alternatively quoted $129,423.61 (plus GST) to expose
and test failed and unused tanks, run one suction line from
tanks 2, 4 and 5, install a new VR circ uit to existing fills,
replacement of concrete for line works and integrity issues
above tank farm, and retest entire system .
CG
Report
1 November 2012
Its initial assumption that the pavement failure was caused
by rising ground water table (due to recent rains) was
incorrect because excavations subsequently confirmed
that the existing ground water table level was
approximately 3m to 3.5m below finished surface level .
The corner of the concrete pavement (adjacent to the
corner of the service pit) was likel y fractured by loading
imposed by a large vehicle driving over it .
Service pit is located on a low point relative to the rest of
the site, causing stormwater to naturally flow to this area .
Stormwater has penetrated the concrete pavement sub
grade and sub grade tank through the cracks in the
concrete .
Abnormal moisture conditions has resulted in water
causing settlement of the service pit due to differential
movement in the clay soils, undermined the pavement sub
grade and increased the severity of the init ial concrete
pavement failure .
A combination of the above events likely caused the failure
in the fuel services pipelines .
CG
Report
17 December 2012
Clarified that its second report was not intended to provide
3 feasible alternatives for the cause of the pavement
damage but rather, to provide a sequence of events that
have “singularly, as a whole” caused the pavement and
fuel lines damage .
The cracking of the concrete pavement is consistent with a
single impact loading event because the fracture is clean,
which is typical of strength failure rather than any type of
fatigue failure .
Fatigue failure usually occurs over time and exhibits cracks
over a large area, which eventually leads to a general
failure of the concrete pavement as a whole .
The crack in the site‟s concrete pavement is inconsistent
with fatigue failure, so by elimination process, the damage
was likely caused by a single loading incident .
The concrete crack was at an internal corner of the
pavement, adjacent to the service pit .
Internal corner s of concrete slabs are geometrical weak
Case No: 366458 Determination Page 7 of 10
spots and are more likely to fracture under loading
conditions .
The location of the crack at a geometrical weak point
rather than general damage over the entire slab indicates it
was likely cause by a single impact event .
The single impact incident likely occurred between 30 July
and 12 August 2012 .
FSP’s corrosion
materials consultant
engineer (CMET)
Report
15 April 2013
The claimed impact crack is located in an area subject to
traffic from light vehicles and fuel trucks .
The cracks in the slab were “well worn”, with evidence of
progressive breakdown/crumbling of the edges over time,
rounding of the cracks and lumps of concrete debris in the
cracks .
There is no evidence of “residual sharp well - defined crack
edges”, which is indicative of a recent fracture .
The age of the cracks was likely to be in excess of 12
months .
Photographs taken 3 weeks after the claimed incident
shows moisture in the joints around the gatic cover .
This indicates there is significant moisture under the slab,
which would compromise the sub grade‟s bearing capacity
and explain the slab settlement and stepping across the
construction joints .
The elevated moisture levels under the slab can be caused
by:
- Poor drainage around the slab
- Insufficient dr ainage on the slab surface
- Unsealed open joints in the slab
The reported 150mm of water ponding over the
underground tanks suggests that gradual settlement in the
area has occurred over an extended period .
It is improbable that the fuel pipe ruptured as a result of a
single load impact incident .
The evidence suggests that the concrete in the area of the
fuel tank was damaged by gradual settlement as a result of
poor drainage .
This caused differential movement of the slab, and
fractures and degradation of th e concrete edges as
vehicles move across the joints .
FSP’s structural and
forensic engineer (RJA)
Report
16 April 2013
Inspected site on 12 April 2013 .
Geological survey plan suggests that the site soil class is
M (moderately reactive) but a geotechnical investigation is
required to confirm this .
CG‟s suggestion that the service pit is located on a low
point relative to the site is consistent with the photo
provided by T, which shows the valve pit gatic cover to be
under water .
Photographs supplied by assessor “C” show that the
concrete pavement construction joints were not sealed,
which would also allow water to seep under the slab .
Case No: 366458 Determination Page 8 of 10
Photographs taken on 23 August 2013 show rising
moisture was evident at the construction joints .
RJA does not agree with CG‟s suggestion that water would
not have penetrated the concrete pavement if it was not
cracked because:
- The concrete construction joints in and around the gatic
cover do not appear to be sealed
- The gatic cover is located in an area where water was
found to have ponded
M‟s report confirms that stormwater and run off from the
supermarket outlet onsite was ponding at the depressed
area above the valve pit gatic cover and underground tank
area .
Site manager (DM) has informed that:
- There were reports contamina tion involving 7 vehicles
in the last year (ie. 2012), 1 concerning unleaded fuel
and 6 concerning the premium fuel
- He experienced ankle deep water (approximately
150mm deep) ponding above the underground tank
area
- He only saw the inside of the valve pit w hen it was
opened and it was full of water on that occasion
- The drain – that drains water from the onsite
supermarket‟s roof and discharges into a drain pit
(located on the west side of the building) – became
blocked not long after he commenced employment,
which was some 3 ½ years prior to RJA‟s 12 April 2013
site inspection
Bureau of Meteorology records for Hastings shows the
area averaged about 80mm of rain in July and August
2012 .
Total rainfall between 30 July and 12 August 2012 was
33.2mm .
The site received about 10.2mm of rain at the time of T‟s
site inspection .
Rainfall in May, June and August 2012 were 152.9mm,
122.8mm and 63.2mm respectively .
Majority of the original concrete pavement was in
reasonable condition for its age, with the following de fects:
- 25mm slab stepping at the F - F Road exit ramp
- 2.5mm wide crack on the F - F Road entry ramp
- 2.5mm wide cracks on the H Street ramp
- Significant localised concrete distress (with exposed
reinforcing) within the LPG service pipeline trench
- 3.0mm wide crac ks in the south east area of the onsite
supermarket
Concrete pavement is 125mm thick and is founded on at
least 200mm thick crushed rock sub base .
The slab settlement was localised and caused by a
combination of the following:
- Long term consolidation settl ement of the fill material
Case No: 366458 Determination Page 9 of 10
over the underground tanks
- The difference in founding level between the valve pit
and concrete pavement, which do not appear to be
supported by or connected to the concrete valve pit
- Degradation or loss of sub base and sub grade
strength as a result of stormwater seeping under the
slab over a long period of time, due to poor or
inadequate pavement and stormwater drainage design
and the lack of flexible waterproof sealants within the
joints
The slab failure would not have occurred if the pavement
and stormwater drainage was adequately designed and
constructed .
CG
Email
6 September 2013
Reinspected site on 5 October 2012 to review existing site
conditions after excavation works were completed .
The reinspection proved its initial ass umption (that rising
ground water) caused the pavement damage was
incorrect .
The initial construction of the underground tanks and
associated pipe works effectively created a confined
subsoil area deep with the clay soils .
The pipes were disposed of but th e site foreman advised
that pipes were crushed and broken around the concrete
pit .
FSP’s structural and
forensic engineer (FES)
Report
19 December 2013
FES was previously a subsidiary of RJA .
There was a meeting between representatives of the FSP,
assesso r C, RJA (now FES), the broker, CG and the
insured on 22 November 2013 .
It was discussed and agreed:
- It is unlikely that the depressed area of the concrete
slab was constructed „as is‟ because a stormwater
drainage pit would likely to have been installed a t the
low point if this was the case
- The concrete pavement over the underground tanks
and valve pit had undergone local settlement, with
water ponding occurring during significant rain events
- RJA and CG also agreed that ponded water would
seep through the cracks and defective slab sealant in
the joints, which most likely caused the sub grade to
soften
- RJA and CG also agreed this gradual process may
have accelerated after the drought (between 1997 and
late 2010), when “normal” rainfall patterns returned .
3.2 Relevant policy wordings
“ Definitions
…
Damage or Damaged means accidental physical damage , destruction or loss.
…
Case No: 366458 Determination Page 10 of 10
Cover
We will pay up to the total sum insured in accordance wit h the Basis of Settlement for
property that is damaged at the premises during the period of insurance .
…
Exclusions
…
3. We will not pay for damage caused by or arising from:
…
(i) erosion,… subsidence, settling, seepage, shrinkage or expansion of eart h, vibration
or other earth movement, unless caused by or arising from a direct c onsequence of
an earthquake, subterranean fire, volcanic eruption or wat er escaping from a water
main owned by a water supply authority.
4. We will not pay for consequential loss or any kind
5. We will not pay for damage caused directly by or arising directly from:
…
(b) gradually operating causes such as, but not limited to, wear and tear…;
…
(d) latent defect, inherent defects, faulty workmanship, faulty material, structural defects
or faulty design; ”