Progress payments made to builder later in liquidation and to new account

FirmFinancial Firm (Unknown - Credit)
Decided2015-04-30
ProductCredit · Home loan
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicant alleged the FSP wrongly made construction progress payments, including a full frame-stage payment, to a builder that later went into liquidation and to a new bank account. AFCA found the full frame-stage payment was an FSP error but caused no loss, and dismissed the remaining complaints.

The lender owed the borrower no advisory or supervisory duty, and the builder completed the work it was overpaid for, so the FSP's error caused no loss.

Issues

Subjects and remedies

no remedy

Related

All Financial Firm (Unknown - Credit) determinations · Find similar determinations

Text of the determination

Determination Credit - Consumer Credit - Construction Loans - Transactions - Incorrect payment Determination Case No: 365129 Determination Page 1 of 8 Case number : 365129 30 April 2015 1 Overview 1.1 Dispute The Applicant has a construction loan with the Financial Services Provider (FSP). This dispute is about whether the FSP has made errors in making progress payments to the Building Company. 1.2 Issues and key findings Did the FSP have an obligation to ensure that construction was insured? The FSP did not obtain a copy of a Builder‟s Warranty Insurance certificate, and therefore breached its own policy. However, it was the Applicant‟s responsibility , as owner of the WH property, to ensure that proper insurance was in place. Did the FSP make an error by paying the full frame stage payment? The FSP should not have paid the Building Company more than the amount recommended by the valuer but the FSP‟s error has not caused the Applicant loss. This is because the Building Company subsequently completed the work (windows installation) it had already been paid to complete. Should the FSP’s progress payment’s area have been aware that the Building Company was in liquidation before it made the ‘bricks’ stage payment? The liquidator‟s enquiries were made to the FSP‟s business administration area and involved discrete enquiries that were answered by the FSP, did not relate to the construction loans with a nexus to the Building Company and would not have revealed the link between the Building Company and the Applicant‟s construction loan. The business administration area‟s reasonable searches also did not reveal the link between the Building Company and the construction loan. The FSP‟s progress payments area did not know and could not have reasonably known that the Building Company was in liquidation. Did the FSP make an error by making progress payments to the account on the Building Company’s invoice? Case No: 365129 Determination Page 2 of 8 The FSP was entitled to accept the Building Company‟s statement that the account on its invoice was its new bank account. 1.3 Determination This Determination is in favour of the FSP. The FSP is not obliged to pay compensation to the Applicant. Case No: 365129 Determination Page 3 of 8 2 Reasons for Determination 2.1 Did the FSP have an obligation to ensure that construction was properly insured? The FSP’s role was to be the lender, not an advisor or supervisor The relationship between the FSP and Applicant was a purely business one. The construction loan represented a standard business transaction. In this transaction:  The Applicant wanted to obtain funds to build a house; and  The FSP wanted to provide those funds and obtain an interest in the property (as registered mortgagee) to secure the Applicant‟s obligation to repay. The FSP‟s obligations to the Applicant were primarily owed under the loan contract. The FSP was not acting in an advisory or supervisory role in its dealings with the Applicant ‟s house construc tion on the WH property. That is, it did not owe a fiduciary duty to the Applicant, and was not obliged to protect the Applicant‟s interests. The FSP’s policy required that it obtain a copy of the insurance certificate The Applicant says that;  The Building Company did not obtain Building Warranty Insurance, and instead supplied the FSP with a falsified certificate.  The FSP should have identified that Building Warranty Insurance was not in place. Building Warranty Insurance provides protection for the home owner for losses arising from defective and incomplete work . The FSP‟s policy required the FSP to obtain a copy of th e Builder‟s Warranty Insurance c ertificate before it made the first progress payment. The FSP did not obtain a copy of the insurance certificate The FSP has provided a copy of the insurance documents that it holds, which are:  A Certificate of C urrency for Construction Risk insurance valid between March 2013 and March 2014. This provides insurance cover for the builder and is a different typ e of insurance from Builder‟s Warranty Insurance.  A Certificate of Eligibility for Builder‟s Warranty Insurance. This Certificate merely means that the builder has been assessed as „eligible‟ by an approved insurance agent , and has been granted the entitle ment to apply for job - spec ific certificates of insurance. Based on the information available, the FSP did not obtain a certificate showing that the Building Company had obtained Building Warranty Insurance cover which specifically covered the WH property. Therefore, the FSP breached its own policy when it advanced the first progress payment. Case No: 365129 Determination Page 4 of 8 The FSP did not breach an obligation owed to the Applicant by failing to obtain an insurance certificate A construction lender has an interest in ensuring that a house is properly constructed, as the property secures the construction loan and because of this interest, a lender will take steps such as obtaining copies of insurance and building plans/permits. It will also obtain valuations and progress inspections. The lender‟s interest is to protect its own position, and it obtains these documents for its own purposes. This does not translate as creating an obligation to the borrower to verify the validity of plans, permits and insurance. In this case, the FSP was not the Applicant‟s advisor or construction supervisor. It was simply the lender providing funds to the Applicant so he could pay the Building Company. The responsibility to ensure that warranty insurance was in place before construction commenced rested with the Applicant as the owner, not the FSP as the lender. The warranty insurance was for the Applicant‟s benefit, and he was able to check directly with the Insurer whether insurance was in place. By not being diligent in obtaining proper insurance certificates, the FSP increased its risk that its loan would be inadequately secured. However, the FSP did not owe an obligation to the Applicant to ensure that Building Warranty Insurance was in place. 2.2 Did the FSP make an error by paying the frame stage? The Applicant says the FSP should not have made the frame stage payment The Applicant says that:  The FSP said it would not pay the progress payment unless the stage was complete.  The FSP proceeded to make the progress payment despite receiving an inspection report stating the stage was incomplete.  If the FSP had told the Applicant the stage was incomplete, he would not have authorised the progress payment, or made his $7,000 contribution.  He only authorised the progress payment because the FSP obtained an inspection report. He is not an expert and cannot be expected to know the stage was not complete. The Applicant authorised the stage payment in December 2013 The FSP received the Applicant‟s signed progress payment authority and the Building Company invoice on 11 December 2013. These instructed the FSP to pay the Building Company for the frames and trusses stage. On 16 December 2013, the valuer reported to the FSP that the frame had not yet been erected. The Applicant‟s signed progress payment authority included the Applicant‟s confirmation that he was satisfied with the standard and quality of work, and that construction is progressing in accordance with the plans and specifications. The Applicant says he is not a building expert. However, an owner has the option of Case No: 365129 Determination Page 5 of 8 obtaining their own independent building inspection before authorising a progress payment. In any event, a lay person can identify whether or not a frame has been erected. The Applicant‟s actions in signing the December 2013 progress payment authority indicated the Applicant had trust and confidence in the Building Company. The Applicant has not disagreed with the FSP‟s submissions to FOS noting that he had successfully used the Building Company on a prior occasion. The FSP should not have paid the full ‘frames’ stage progress payment On 28 January 2014, the FSP obtained an updated progress inspection report. This valuation stated that;  Construction was “nearing frame stage complete with only the windows to be installed”.  The valuer stated $81,005 should be paid, recommending $14,295 of the scheduled $95,300 repayment be withheld. The FSP paid the full stage payment of $95,300 to the Building Company on 29 January 2015. The FSP says that it made the full payment because:  This was the first stage, and it would obtain an inspection at practical completion before making the final payment.  It did not want to cause a delay in construction by withholding part of the payment. The FSP should not have made the full payment. By making the full payment, the FSP placed the Applicant at risk. For example, if the Building Company had gone into liquidation at that time, instead of April 2014, it would have been overpaid for work not completed. Further, the FSP had specifically informed the Applicant that it would not make a stage repayment until the stage was complete (see FSP‟s email 16 December 2013). By making the stage repayment, the FSP had arguably misled the Applicant that the frame stage was complete. The FSP’s error has not caused the Applicant a loss The January 2014 progress inspection identified that the windows had not been installed. The Applicant has confirmed that the windows were installed by April 2014. Therefore, although the Building Company was overpaid in January 2014, it subsequently completed the work it was paid for. Apart from the windows, the Applicant says that the Building Company did not complete the frames stage to an adequate standard. The Applicant has provided a copy of an inspection completed by another builder in May 2014. The third party builder stated:  One third of the roof framing had not been completed and trusses were scattered over the top floor.  Wall framing was incomplete, with some wall not nailed off and out of plumb. Case No: 365129 Determination Page 6 of 8 The FSP had told the Applicant that it would inspect a property in relation to stage completion, but not the quality or standard of work. This was disclosed in the following documents:  The progress payment authority forms  The „ welcome letter ‟ dated 16 May 2013 states that the inspections are for the FSP‟s own pu rposes. Progress inspections relate to stage completion, not the quality of work. A construction lender generally obtains progress inspections for its own purposes. The valuer/inspector usually performs a surface inspection and advises whether the work completed is consistent with the progress payment request. The valuer performs the inspection on the lender‟s behalf, and the progress inspection is not a substitute for the borrower‟s own building inspections. The January 2014 progress inspection report mentioned only the window installation, and did not mention any other matters being incomplete. The FSP was entitled to rely on this report. The Applicant did not rely on any misleading conduct The Applicant says that if he had been told that the stage was not complete, he would not have authorised the progress payment, or made his $7,000 contribution. However, this is not consistent with the Applicant‟s actions throughout the construction, which showed confidence in the Building Company. It is more likely than not that, if the FSP had told the Applicant the stage was not complete, the Applicant would have authorised a payment to cover work actually complete. The Building Company could then have included the remainder in the next progress payment („brick‟ stage) that it was paid in April 2014. 2.3 Should the FSP’s progress payment’s area have been aware that the Building Company was in liquidation before it made the ‘bricks’ stage payment ? The Building Company was put into liquidation in April 2014 The Building Company had been placed into liquidation in early April 2014. On 8 April 2014, the liquidator wrote to the FSP. The liquidator asked whether the Building Company had accounts or mortgages with the FSP, or had periodic payments made for its benefit. The FSP responded on 10 April 2014, and informed the liquidator that the Building Company held no accounts with the FSP. On 11 April 2014, the Applicant provided a progress payment authority for the „bricks‟ stage to the FSP‟s progress payments a rea. The FSP made the progress payment on 15 April 2014. The FSP says that if its progress payments team had been aware the Building Company was in liquidation, it would not have made the progress payment. Case No: 365129 Determination Page 7 of 8 The FSP’s progress payments area could not have known of the liquidation The FSP received the liquidator‟s correspondence at an email address managed by the FSP‟s business support s ervices team. The FSP‟s response to the liquidator advised that it had searched “its records by name”. The Applicant says that:  The FSP had the Building Company‟s name on file, as the FSP had received an account nomination form, and had made a progress payment.  Theref ore, the FSP should have identified the Building Company‟s involvement in the Applicant‟s construction loan. The FSP searched its account records in response to the liquidator‟s specific requests for information. These requests mostly related to whether the Building Company was a customer of the FSP. The Applicant has noted that one of the liquidator‟s requests was for details of “periodic payments made for the benefit of the [Building] Company”. Periodic payments are automatic payments made at regular intervals. A periodic payment is separate from a progress payment under a construction loan. None of the liquidator‟s requests related to whether the Building Company was receiving progress payments from a construction loan account. The FSP says that it does not have a consolidated list of builders used by its customers. The searches performed by the business support services team did not identify the Building Company as a customer. As a result, the FSP‟s progress payments team was not informed that the Building Company had gone into liquidation. It would not be reasonable to hold that the progress payments team had constructive knowledge of the liquidation. The FSP did not act unreasonably by making the progress payment on 15 April 2014. 2.4 Did the FSP make an error by making progress payments to the account on the Building Company’s invoice? The Applicant says the FSP should not have made payments to the new account In May 2013, the Building Company provided the FSP with a document containing its account details. This document contained details of an account ending #0764. T he Building Company‟s invoices for the „frames‟ and „bricks‟ stage ask the payer to note the Building Company‟s “new bank details”, being an account ending #1006. The Applicant says that:  The “new” account ending #1006 was actually a personal account in the name of the director of the Building Company.  The direction to pay to account #1006 conflicted with the initial instruction in the May 2013 document.  The FSP should not have accepted an inst ruction to pay to the „new‟ account without verifying the account holder. Case No: 365129 Determination Page 8 of 8  The FSP also had another standard document entitled „Progress payment builder account details nomination‟ ( the account nomination form ). This stated that the Building Company should advise the FSP in writing if it altered its preferred payment method. The FSP was entitled to accept the Building Company’s updated instructions The FSP was entitled to make progress payments to the „new‟ account because:  It was reasonable for the FS P to accept that the Building Company‟s own invoice provided correct details of its bank account.  The „new‟ account was not held with the FSP. The FSP could not have known the identity of the account holder, and it was not obliged to obtain verification.  The first progress payment was made in January 2014. This was eight months after the FSP had received the May 2013 instructions. It was not suspicious that there had been a change to the Building Company‟s banking arrangements over that time.  The account nomination form asked the Building Company to advise of a change in payment method . The payment methods available were electronic payment or cheque. The Building Company was not changing its payment method, just the account details for electronic payment.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.