Home / Financial Firm (Unknown - Credit) / Determination 365129
Determination 365129
Progress payments made to builder later in liquidation and to new account
Summary
The applicant alleged the FSP wrongly made construction progress payments, including a full frame-stage payment, to a builder that later went into liquidation and to a new bank account. AFCA found the full frame-stage payment was an FSP error but caused no loss, and dismissed the remaining complaints.
The lender owed the borrower no advisory or supervisory duty, and the builder completed the work it was overpaid for, so the FSP's error caused no loss.
Issues
- Payment error primary · upheld
“The FSP should not have made the full 'frames' stage progress payment; the FSP's error has not caused the Applicant a loss.”
- Administrative error secondary · not upheld
“It would not be reasonable to hold that the progress payments team had constructive knowledge of the builder's liquidation.”
- Misleading conduct secondary · not upheld
“The Applicant did not rely on any misleading conduct.”
- Other secondary · not upheld
“FSP breached its own policy by not obtaining a builder's warranty insurance certificate, but did not owe the Applicant an obligation to ensure that insurance was in place.”
Subjects and remedies
no remedy
Text of the determination
Determination
Credit - Consumer Credit - Construction Loans - Transactions - Incorrect payment
Determination
Case No: 365129 Determination Page 1 of 8
Case number : 365129 30 April 2015
1 Overview
1.1 Dispute
The Applicant has a construction loan with the Financial Services Provider (FSP).
This dispute is about whether the FSP has made errors in making progress
payments to the Building Company.
1.2 Issues and key findings
Did the FSP have an obligation to ensure that construction was insured?
The FSP did not obtain a copy of a Builder‟s Warranty Insurance certificate, and
therefore breached its own policy. However, it was the Applicant‟s responsibility ,
as owner of the WH property, to ensure that proper insurance was in place.
Did the FSP make an error by paying the full frame stage payment?
The FSP should not have paid the Building Company more than the amount
recommended by the valuer but the FSP‟s error has not caused the Applicant
loss. This is because the Building Company subsequently completed the work
(windows installation) it had already been paid to complete.
Should the FSP’s progress payment’s area have been aware that the
Building Company was in liquidation before it made the ‘bricks’ stage
payment?
The liquidator‟s enquiries were made to the FSP‟s business administration area
and involved discrete enquiries that were answered by the FSP, did not relate to
the construction loans with a nexus to the Building Company and would not have
revealed the link between the Building Company and the Applicant‟s construction
loan.
The business administration area‟s reasonable searches also did not reveal the
link between the Building Company and the construction loan. The FSP‟s
progress payments area did not know and could not have reasonably known that
the Building Company was in liquidation.
Did the FSP make an error by making progress payments to the account on
the Building Company’s invoice?
Case No: 365129 Determination Page 2 of 8
The FSP was entitled to accept the Building Company‟s statement that the
account on its invoice was its new bank account.
1.3 Determination
This Determination is in favour of the FSP.
The FSP is not obliged to pay compensation to the Applicant.
Case No: 365129 Determination Page 3 of 8
2 Reasons for Determination
2.1 Did the FSP have an obligation to ensure that construction was
properly insured?
The FSP’s role was to be the lender, not an advisor or supervisor
The relationship between the FSP and Applicant was a purely business one. The
construction loan represented a standard business transaction. In this transaction:
The Applicant wanted to obtain funds to build a house; and
The FSP wanted to provide those funds and obtain an interest in the property
(as registered mortgagee) to secure the Applicant‟s obligation to repay.
The FSP‟s obligations to the Applicant were primarily owed under the loan
contract. The FSP was not acting in an advisory or supervisory role in its dealings
with the Applicant ‟s house construc tion on the WH property. That is, it did not
owe a fiduciary duty to the Applicant, and was not obliged to protect the
Applicant‟s interests.
The FSP’s policy required that it obtain a copy of the insurance certificate
The Applicant says that;
The Building Company did not obtain Building Warranty Insurance, and
instead supplied the FSP with a falsified certificate.
The FSP should have identified that Building Warranty Insurance was not in
place.
Building Warranty Insurance provides protection for the home owner for losses
arising from defective and incomplete work . The FSP‟s policy required the FSP to
obtain a copy of th e Builder‟s Warranty Insurance c ertificate before it made the
first progress payment.
The FSP did not obtain a copy of the insurance certificate
The FSP has provided a copy of the insurance documents that it holds, which are:
A Certificate of C urrency for Construction Risk insurance valid between March
2013 and March 2014. This provides insurance cover for the builder and is a
different typ e of insurance from Builder‟s Warranty Insurance.
A Certificate of Eligibility for Builder‟s Warranty Insurance. This Certificate
merely means that the builder has been assessed as „eligible‟ by an approved
insurance agent , and has been granted the entitle ment to apply for job -
spec ific certificates of insurance.
Based on the information available, the FSP did not obtain a certificate showing
that the Building Company had obtained Building Warranty Insurance cover which
specifically covered the WH property. Therefore, the FSP breached its own policy
when it advanced the first progress payment.
Case No: 365129 Determination Page 4 of 8
The FSP did not breach an obligation owed to the Applicant by failing to
obtain an insurance certificate
A construction lender has an interest in ensuring that a house is properly
constructed, as the property secures the construction loan and because of this
interest, a lender will take steps such as obtaining copies of insurance and
building plans/permits. It will also obtain valuations and progress inspections. The
lender‟s interest is to protect its own position, and it obtains these documents for
its own purposes. This does not translate as creating an obligation to the borrower
to verify the validity of plans, permits and insurance.
In this case, the FSP was not the Applicant‟s advisor or construction supervisor.
It was simply the lender providing funds to the Applicant so he could pay the
Building Company. The responsibility to ensure that warranty insurance was in
place before construction commenced rested with the Applicant as the owner, not
the FSP as the lender. The warranty insurance was for the Applicant‟s benefit,
and he was able to check directly with the Insurer whether insurance was in
place.
By not being diligent in obtaining proper insurance certificates, the FSP increased
its risk that its loan would be inadequately secured. However, the FSP did not
owe an obligation to the Applicant to ensure that Building Warranty Insurance was
in place.
2.2 Did the FSP make an error by paying the frame stage?
The Applicant says the FSP should not have made the frame stage payment
The Applicant says that:
The FSP said it would not pay the progress payment unless the stage was
complete.
The FSP proceeded to make the progress payment despite receiving an
inspection report stating the stage was incomplete.
If the FSP had told the Applicant the stage was incomplete, he would not have
authorised the progress payment, or made his $7,000 contribution.
He only authorised the progress payment because the FSP obtained an
inspection report. He is not an expert and cannot be expected to know the
stage was not complete.
The Applicant authorised the stage payment in December 2013
The FSP received the Applicant‟s signed progress payment authority and the
Building Company invoice on 11 December 2013. These instructed the FSP to
pay the Building Company for the frames and trusses stage. On 16 December
2013, the valuer reported to the FSP that the frame had not yet been erected.
The Applicant‟s signed progress payment authority included the Applicant‟s
confirmation that he was satisfied with the standard and quality of work, and that
construction is progressing in accordance with the plans and specifications. The
Applicant says he is not a building expert. However, an owner has the option of
Case No: 365129 Determination Page 5 of 8
obtaining their own independent building inspection before authorising a progress
payment. In any event, a lay person can identify whether or not a frame has been
erected.
The Applicant‟s actions in signing the December 2013 progress payment authority
indicated the Applicant had trust and confidence in the Building Company. The
Applicant has not disagreed with the FSP‟s submissions to FOS noting that he
had successfully used the Building Company on a prior occasion.
The FSP should not have paid the full ‘frames’ stage progress payment
On 28 January 2014, the FSP obtained an updated progress inspection report.
This valuation stated that;
Construction was “nearing frame stage complete with only the windows to be
installed”.
The valuer stated $81,005 should be paid, recommending $14,295 of the
scheduled $95,300 repayment be withheld.
The FSP paid the full stage payment of $95,300 to the Building Company on 29
January 2015. The FSP says that it made the full payment because:
This was the first stage, and it would obtain an inspection at practical
completion before making the final payment.
It did not want to cause a delay in construction by withholding part of the
payment.
The FSP should not have made the full payment. By making the full payment, the
FSP placed the Applicant at risk. For example, if the Building Company had gone
into liquidation at that time, instead of April 2014, it would have been overpaid for
work not completed.
Further, the FSP had specifically informed the Applicant that it would not make a
stage repayment until the stage was complete (see FSP‟s email 16 December
2013). By making the stage repayment, the FSP had arguably misled the
Applicant that the frame stage was complete.
The FSP’s error has not caused the Applicant a loss
The January 2014 progress inspection identified that the windows had not been
installed. The Applicant has confirmed that the windows were installed by April
2014. Therefore, although the Building Company was overpaid in January 2014, it
subsequently completed the work it was paid for.
Apart from the windows, the Applicant says that the Building Company did not
complete the frames stage to an adequate standard. The Applicant has provided
a copy of an inspection completed by another builder in May 2014. The third party
builder stated:
One third of the roof framing had not been completed and trusses were
scattered over the top floor.
Wall framing was incomplete, with some wall not nailed off and out of plumb.
Case No: 365129 Determination Page 6 of 8
The FSP had told the Applicant that it would inspect a property in relation to stage
completion, but not the quality or standard of work. This was disclosed in the
following documents:
The progress payment authority forms
The „ welcome letter ‟ dated 16 May 2013 states that the inspections are for the
FSP‟s own pu rposes. Progress inspections relate to stage completion, not the
quality of work.
A construction lender generally obtains progress inspections for its own purposes.
The valuer/inspector usually performs a surface inspection and advises whether
the work completed is consistent with the progress payment request. The valuer
performs the inspection on the lender‟s behalf, and the progress inspection is not
a substitute for the borrower‟s own building inspections.
The January 2014 progress inspection report mentioned only the window
installation, and did not mention any other matters being incomplete. The FSP
was entitled to rely on this report.
The Applicant did not rely on any misleading conduct
The Applicant says that if he had been told that the stage was not complete, he
would not have authorised the progress payment, or made his $7,000
contribution. However, this is not consistent with the Applicant‟s actions
throughout the construction, which showed confidence in the Building Company.
It is more likely than not that, if the FSP had told the Applicant the stage was not
complete, the Applicant would have authorised a payment to cover work actually
complete. The Building Company could then have included the remainder in the
next progress payment („brick‟ stage) that it was paid in April 2014.
2.3 Should the FSP’s progress payment’s area have been aware that
the Building Company was in liquidation before it made the
‘bricks’ stage payment ?
The Building Company was put into liquidation in April 2014
The Building Company had been placed into liquidation in early April 2014. On 8
April 2014, the liquidator wrote to the FSP. The liquidator asked whether the
Building Company had accounts or mortgages with the FSP, or had periodic
payments made for its benefit. The FSP responded on 10 April 2014, and
informed the liquidator that the Building Company held no accounts with the FSP.
On 11 April 2014, the Applicant provided a progress payment authority for the
„bricks‟ stage to the FSP‟s progress payments a rea. The FSP made the progress
payment on 15 April 2014. The FSP says that if its progress payments team had
been aware the Building Company was in liquidation, it would not have made the
progress payment.
Case No: 365129 Determination Page 7 of 8
The FSP’s progress payments area could not have known of the liquidation
The FSP received the liquidator‟s correspondence at an email address managed
by the FSP‟s business support s ervices team.
The FSP‟s response to the liquidator advised that it had searched “its records by
name”. The Applicant says that:
The FSP had the Building Company‟s name on file, as the FSP had received
an account nomination form, and had made a progress payment.
Theref ore, the FSP should have identified the Building Company‟s
involvement in the Applicant‟s construction loan.
The FSP searched its account records in response to the liquidator‟s specific
requests for information. These requests mostly related to whether the Building
Company was a customer of the FSP. The Applicant has noted that one of the
liquidator‟s requests was for details of “periodic payments made for the benefit of
the [Building] Company”. Periodic payments are automatic payments made at
regular intervals. A periodic payment is separate from a progress payment under
a construction loan.
None of the liquidator‟s requests related to whether the Building Company was
receiving progress payments from a construction loan account. The FSP says that
it does not have a consolidated list of builders used by its customers. The
searches performed by the business support services team did not identify the
Building Company as a customer. As a result, the FSP‟s progress payments team
was not informed that the Building Company had gone into liquidation.
It would not be reasonable to hold that the progress payments team had
constructive knowledge of the liquidation. The FSP did not act unreasonably by
making the progress payment on 15 April 2014.
2.4 Did the FSP make an error by making progress payments to the
account on the Building Company’s invoice?
The Applicant says the FSP should not have made payments to the new
account
In May 2013, the Building Company provided the FSP with a document containing
its account details. This document contained details of an account ending #0764.
T he Building Company‟s invoices for the „frames‟ and „bricks‟ stage ask the payer
to note the Building Company‟s “new bank details”, being an account ending
#1006.
The Applicant says that:
The “new” account ending #1006 was actually a personal account in the name
of the director of the Building Company.
The direction to pay to account #1006 conflicted with the initial instruction in
the May 2013 document.
The FSP should not have accepted an inst ruction to pay to the „new‟ account
without verifying the account holder.
Case No: 365129 Determination Page 8 of 8
The FSP also had another standard document entitled „Progress payment
builder account details nomination‟ ( the account nomination form ). This
stated that the Building Company should advise the FSP in writing if it altered
its preferred payment method.
The FSP was entitled to accept the Building Company’s updated
instructions
The FSP was entitled to make progress payments to the „new‟ account because:
It was reasonable for the FS P to accept that the Building Company‟s own
invoice provided correct details of its bank account.
The „new‟ account was not held with the FSP. The FSP could not have known
the identity of the account holder, and it was not obliged to obtain verification.
The first progress payment was made in January 2014. This was eight months
after the FSP had received the May 2013 instructions. It was not suspicious
that there had been a change to the Building Company‟s banking
arrangements over that time.
The account nomination form asked the Building Company to advise of a
change in payment method . The payment methods available were electronic
payment or cheque. The Building Company was not changing its payment
method, just the account details for electronic payment.