Home / Financial Firm (Unknown - Insurer) / Determination 364450
Determination 364450
Denial of Claim - Exclusion/Condition
Summary
The Applicants claimed the FSP must replace their leaking cyclone-damaged roof and rectify repairs by its builders. AFCA found the ongoing leaks were caused by roof design and construction, which the policy excludes, but ordered replacement of undersized whirly birds and written confirmation of builders' qualifications.
The policy excludes damage resulting from faulty design or workmanship, and the evidence shows the continuing water entry was not caused by Cyclone Yasi or the FSP's repairs.
Issues
- Claim denial primary · not upheld
“The policy excludes damage that occurs as a result of faulty design or workmanship, so the FSP is not required to replace the roof.”
- Repairs or contractors secondary · upheld
“if the Applicants establish that whirly birds closer to the damaged ones are reasonably available, the FSP should install these”
Subjects and remedies
home or building damagenatural disasterprovide documentsrepair or rectify
Text of the determination
Determination
General Insurance - Domestic Insurance - Home Building - FSP Decision - Denial of
Claim - Exclusion/Condition
Determination
Case No: 364450 Determination Page 1 of 7
Case number : 364450 30 December 2014
1 Overview
1.1 Dispute
The Applicants lodged a claim with the Financial Services Provider (FSP) for
damage sustained to their property as a result of Cyclone Yasi in February 2011.
The FSP accepted the claim and organised for repairs to the property (including
the roof). The initial roof repairs were inadequate and the FSP subsequently
arranged for various builders to attend and attempt to rectify the repairs.
The Applicants remain dissatisfied with the roof repairs, as the roof is continuing
to leak. They want the FSP to replace the entire roof and rectify certain other
issues related to the repairs.
1.2 Issues and key findings
Is the FSP required to replace the Ap plicants’ roof?
The available information establishes that the ongoing water entry issues at the
Applicants’ property have not been caused by Cyclone Yasi or the repairs carried
out by the FSP’s builders , but are due to issues with the design and construction
of the roof. Damage caused in this manner is not covered under the policy.
Is the FSP liable for other issues relating to the repairs?
If the Applicants can establish that whirly birds equivalent to the damaged items
(in size and function) are reasonably available, then the FSP is required to install
these items in place of those installed by its builder. The FSP should also provide
the Applicants with written confirmation that its builders are adequately qualified.
The Applicants have not established t hat the FSP’s builders caused any
additional damage to their property.
1.3 Determination
This Determination is substantially in favour of the FSP.
The FSP should replace the whirly birds with items of an equivalent size and
function to the damaged items (provided that the Applicants can establish that
these are reasonably available) and provide the written confirmation referred to in
section 2.2 below.
Subject to the above, the FSP has no further liability to the Applicants.
Case No: 364450 Determination Page 2 of 7
2 Reasons for Determination
2.1 Is the F SP obliged to replace the Applicants’ roof?
FSP’s liability depends on cause of continuing roof issues
There is no dispute that the Applicants ’ property (including the roof) was damaged
by Cyclone Yasi. However, the FSP says that it has repaired the cyclone-related
damage and therefore it is not responsible for any ongoing issues with water entry
at the property.
The FSP is responsible for ensuring the adequacy of the repairs carried out by its
builders and for any additional damage caused by its builders in the course of
carrying out the repairs.
However, the FSP is not responsible for rectifying the continuing issues with the
roof unless the Applicants can show that, on the balance of probabilities, these
issues were caused by Cyclone Yasi or by the claim-related repairs carried out by
the FSP’s builders.
Applicants have not established FSP’s repairs are inadequate
It is clear from the claim records that the FSP’s efforts to repair the damage to the
Applicants’ property caused by Cyclone Yasi involved multiple attempts by a
number of different builders. As late as August 2013, the final builder (B)
appointed by the FSP noted that the repairs had been carried out to a less than
adequate standard.
The FSP acknowledges that the initial repairs were inadequate. However, the
FSP says that the rectification works finally completed by B in or around January
2014 were effective to fully repair the cyc lone-related damage. The FSP has
provided photographs showing the repairs undertaken by B.
The Applicants have identified a number of issues with the way in which the
repairs were carried out. Among other things, they say that:
the flashing installed by the FSP’s builders have caused the ongoing water
entry issues and
the builders have used excessive amounts of silicone to repair the roof.
The Applicants say that they have had the roof inspected by two local roofing
specialists who have confirmed that the repairs carried out by the FSP were
inadequate.
However, the Applicants have not provided any independent information to
support their position (including written reports from their roofing specialists). Nor
have they provided any photographs evidencing the damage claimed to have
been caused by the FSP’s repairers.
While the FSP’s builder (B) identified excessive silicone used in previous repairs,
it is not clear from the available information who applied silicone to the roof and
when this occurred.
Case No: 364450 Determination Page 3 of 7
Prior repairs using silicone sealant are evident in photographs taken by the first
builder (S) engaged by the FSP in February 2011. S reported that the Applicants
had confirmed that they had sealed this area of the roof themselves following the
cyclone. Accordingly, it appears that not all of the silicone on the roof was applied
by the FSP’s builders.
Based on the available information, the Panel is not satisfied that the Applicants
have established that that any of the damage caused by Cyclone Yasi remains
unrepaired or that the rectification repairs carried out by the FSP are ineffective.
Ongoing water entry issues are due to design and construction of roof
The available information establishes that, on the balance of probabilities, the
ongoing water entry p roblems at the Applicants’ property are due to issues with
the design and construction of the roof.
After the Applicants lodged a second storm claim in April 2013, the FSP
appointed a builder (M) to determine the cause of water entry to the property. M
concluded that, during severe weather events, water was being blown into the
roof cavity at the junction between the main roof and the verandah roof, where
there was a change in the pitch of the roof.
The Applicants’ roofing plumber (T) had earlier identified the change in the pitch
of the roof as the cause of the water entry in his report dated 19 June 2012. This
was also confirmed by the FSP’s builder (B) in his report dated 6 August 2013.
The change in pitch from the steeper main roof to the flatter verandah roof is
clearly visible in the photographs included in the builders’ reports. These
photographs also show gaps between the roof sheets in this area which could
allow water to pool and enter the roof cavity during severe weather events.
The A pplicants’ roofing plumber (T) also noted several other problems with the
way in which the roof had been installed, including issues with the spacing and
fastening of the battens, which in his view would have contributed markedly to the
ability of the roof to remain weatherproof. T also confirmed that there had been
ongoing water entry issues at the property since well before Cyclone Yasi.
Based on the reports provided by the three builders, the Panel is satisfied that the
cause of the ongoing water entry was the design and construction of the roof,
which allowed water to enter the roof cavity.
FSP is not liable for roof replacement
For the reasons outlined above, the Panel is satisfied that the ongoing issues with
the Applicants’ roof were not caused by Cyclone Yasi or by the FSP’s previous
repairs, but were due to the design and construction of the roof.
The Applicants’ policy excludes cover for damage that occurs as a result of faulty
design or workmanship. Accordingly, the FSP is not required to replace the
Applicants’ roof.
Case No: 364450 Determination Page 4 of 7
2.2 Is the FSP liable for other issues relating to the repairs?
The FSP should match the whirly birds as reasonably as possible
Under the policy, the FSP is required to repair the property to its condition prior to
the insured event, using matching building materials as far as reasonably
possible.
The Applicants say that the two replacement whirly birds installed by the FSP are
smaller than those which were damaged in the cyclones. They say that the FSP’s
builders told them that larger whirly birds were not available, when this is not
correct.
The FSP has not responded to the Applicants’ concerns about the whirly birds.
However, the Panel notes that the available information establishes that the
repairer who initially replaced the whirly birds did not carry out other aspects of
the repairs appropriately.
In these circumstances, the Panel considers that, if the Applicants are able to
establish that whirly birds which more closely reflect the damaged ones are
reasonably available, then the FSP should be required to install these whirly birds
to the Applicants’ roof.
Available information does not establish FSP ’s repairers caused further
damage
The Applicants say that a tarpaulin placed on the roof was held down by lengths
of steel which caused the roof to rust. They also say that the FSP’s builders
damaged the roof sheets by walking on them.
The Applicants have not provided any photographs or other independent
information which confirms the damage claimed to have been caused by the
FSP’s builders. Further, while the photographs provided by the FSP show a
tarpaulin covering the roof, B’s repo rt confirms that this tarpaulin was installed by
local emergency services personnel, and not by the FSP’s repairers.
In the circumstances, the Panel does not consider that the Applicants have
established that the FSP’s builders caused further damage to the property.
FSP should confirm builders are appropriately qualified
The Applicants say that the FSP has refused to provide them with copies of trade
certificates for the various builders who carried out repairs at their property.
In circumstances where the initial repairs to the property were inadequate, the
Panel accepts that the Applicants may have valid concerns about the
qualifications of the contractors appointed by the FSP.
The FSP is responsible for appointing builders with appropriate trade
qualifications to conduct repairs. Accordingly, the Panel considers that the FSP
should provide the Applicants with written confirmation that its builders are
appropriately qualified and experienced.
Case No: 364450 Determination Page 5 of 7
Case No: 364450 Determination Page 6 of 7
3 Supporting information
3.1 FOS approach to this dispute
This dispute has not been the subject of a FOS Recommendation. Due to the
nature of the dispute, it has been referred directly to a Panel for Determination, in
line with the Operational Guidelines to the FOS Terms of Reference. The Panel
consists of an Ombudsman and two representatives with consumer and insurance
experience.
The Panel has decided this case on its merits, having regard to the relevant law,
good industry practice, codes of practice and previous FOS decisions.
There has been a full exchange of all material information relied on for the
purposes of this Determination and each party has had the opportunity to address
any issues raised by the other.
The Panel has reviewed and considered all of the material provided by the
parties. While the parties have raised a number of issues in their submissions, for
the purposes of this Determination the Panel has restricted its commentary to
those issues which it considers directly relevant to the outcome only
3.2 Reports
Report Key points
FSP ’s builder (S)
Report – February 2011
The hip capping on the front LHS corner of the roof had
been recently silicone sealed. The Applicants advised that
this was carried out after the cyclone ass that was where
the water had entered the property.
Applicants’ roof
plumbe r (T)
Report – 19 June 2012
The roof structure and material is generally sound
however the intersection of two different roof pitches on to
two sides and two ends is of concern.
Both during and after Cyclone Larry and Cyclone Yasi the
owners have experienced ongoing water entry issues.
The split pitch intersection shows marked signs of water
entry and some uplift with the worst affected area being
the south western side of the roo f.
Batten spacing on the roof is generally satisfactory
however the roof was not fitted with intermediate top or
bottom battens.
With only four fa steners per sheet per batten (instead of
five), the roof is quite vulnerable to lap pulling which
would have contributed markedly to the uplift and weather
proofing of the existing roof.
The fact that the roof was not originally fitted with
insulation allows more air flow and associated air borne
water into the ceiling space.
Case No: 364450 Determination Page 7 of 7
Report Key points
T he roof should be removed, interme diate battens
installed and the compromised battens either re - fixed or
replaced. N ew insulation should be installed with attention
to the intersection of the two roof pitches.
FSP’s builder (M)
Report – 12 April 2013
The internal water damage to the property had occurred
as a result of windblown rain entering into the roof cavity
at the junction where there is a change of roof pitch
between the main roof and veranda roof. A roof
inspection revealed no storm created openings.
D ue to the roof design at the junction between the main
roof and the lower pitched roof , water entry will be an
ongoing occurrence during extreme weather.
A pre - formed polyurethane flexible foam sealing strip
should be installed to prevent further water entry .
FSP’s builder (B)
R eport – 6 August 2013
Repair of Cyclone Yasi damage had been conducted to a
less than adequate standard by the previous repairer.
There were visible repairs to the roof and h ip end
cappings of the dwelling. These areas had previously
been repaired with sil icone.
The roof pitch to the verandah was very shallow to the
entire perimeter of the dwelling and underlapped the main
roof at the juncture . This was the source of the continuing
water entry.
To r ectify the problem , he recommend ed having a n
under/over fla shin g installed at the junction of the two roof
pitches as he believe d the water entry was due to the
effects of wind driven and pooling rain water at this point.
The local SES emergency services had tarped the roof to
prevent further water entry.