Denial of storm-related ridge beam, plaster and loss of rent claims; roof tile rectification
Text of the determination
Determination
General Insurance - Domestic Insurance - Home Building - FSP Decision - Denial of
Claim - Exclusion/Condition - Service - Service Quality
Determination
Case No: 361694 Determination Page 1 of 10
Case number : 361694 3 December 2014
1 Overview
1.1 Dispute
The Applicant lodged a claim under her landlord insurance policy with the
Financial Service Provider (FSP) following a hail storm in December 2011.
The FSP accepted the Applicant’s claim initial claim for damage, however it
denied liability for a number of other items subsequently claimed by the Applicant.
1.2 Issues and key findings
Is the FSP entitled to deny the claims?
The Applicant has not established that the storm and subsequent repairs are the
proximate cause of loss or damage relating to the ridge beam, the plaster and
cornices in the living room, lounge and kitchen, or the loss of rent.
The FSP is therefore entitled to deny these aspects of the Applicant’s claim.
The Applicant has established, on balance, that the storm and subsequent repairs
are the cause of damage to the roof tiles. This damage is therefore covered by
the policy.
Is the Applicant entitled to consequential loss or non- financial loss?
The FSP is not required to pay for loss of income while the Applicant attended a
VCAT hearing. This loss is too remote to be considered consequential loss and is
not otherwise covered by the policy.
The FSP must pay compensation for non-financial loss given the stress and
inconvenience caused by the FSP’s repair process and actions of the repairer.
1.3 Determination
This Determination is partly in favour of the Applicant.
The FSP must:
Cash s ettle the Applicant’s claim in respect of the roof tiles, in accordance with
the terms and conditions of the policy and after having obtained an updated
quote for the scope of works as set out by the Applicant’ s roofer (SK) on 12
August 2013.
Pay $500 to the Applicant for non-financial loss.
Case No: 361694 Determination Page 2 of 10
2 Reasons for Determination
I have decided this case on its merits, doing what is fair in all the circumstances
having regard to the relevant law, good industry practice, codes of practice and
previous FOS decisions. I have taken into account all the material submitted by
the parties. I am satisfied that the documentation I have relied on has been
provided to both parties.
This dispute has been expedited to a Determination. No Recommendation was
issued.
2.1 Is the Applicant entitled to deny the claims?
The Applicant must establish the damage was caused by an insured event
The onus of proof rests on the Applicant to establish, on the balance of
probabilities, she has suffered a loss caused by an insured risk. Once the
Applicant has established the loss was caused by a risk insured against under the
policy, the onus then shifts to the FSP to show, on the balance of probabilities, the
loss falls within an exclusion clause of the policy.
The Applicant claims loss or damage in respect of:
a cracked beam
damage to plaster and cornices in the living room, lounge and kitchen, and
damage to the roof tiles.
The Applicant also claims:
loss or rent
loss of income, and
non-financial loss
There were several experts engaged by the parties
The Applicant engaged the following experts to inspect and report on the damage
to her property:
Roofing expert – SK
Roofing expert – BJ
Engineer – G.
The FSP engaged the following experts to inspect and report on the damage:
Builder - S
Builder – BP
Engineer – F.
Ultimately, the FSP did not produce any report from BP, instead choosing to rely
on the opinions of F. According to the FSP, BP provided verbal advice about the
repair work he performed. I have given no evidentiary weight to any submissions
in re spect of BP’s findings, given:
there is no written report from BP, and
BP’s oral advice is not independent given he was commenting on his own
work.
Case No: 361694 Determination Page 3 of 10
The cracked beam was not caused by the storm
The FSP’s builder completed repairs to the storm damage buil ding in September
2012. No reference had been made to the dip in the roof or the cracked beam by
the Applicant or the FSP’s assessor at this time.
In January 2013, the Applicant became aware of a sunken roof beam and the
cracked ridge beam and emergency r epairs were conducted by the FSP’s builder.
The Applicant considers the ridge beam was damaged by either:
the storm (causing underlying damage to the roof truss and water soaking into
the insulation), or
foot traffic by the FSP’s builders.
In support of this the Applicant refers to approximately 50 cracked roof tiles that
were located above the area of the cracked beam.
The Applicant’s engineer (G) referred to the design drawings for the building and,
applying the Australian Standard relevant at the time, computed that the beam
had satisfactory strength for its load. However, G did not provide an opinion as to
the cause of the cracked beam only noting that wind gusts can vary and the
Applicant should not accept the denial of her claim. G made no comment in
respect of the roof truss or the insulation.
The FSP’s engineer (F) noted that G’s computations assumed that the relevant
beam was as per the design drawings and was therefore 75mm wide. F stated
that G had clearly not inspected the premises . Based on F’s inspection, F
estimated the beam was 45mm wide.
Based on today’s standards and assuming F17 timber, F concluded that the beam
had adequate strength to cope with the load applied by maintenance workers and
short term wind loading.
However, on converting G’s calculations using the standards applicable at the
time of construction and using G’s basis of F8 timber (but with 45mm width), F
concluded the beam was significantly undersized to cope with long term loading
(being self weight and applied dead load from roof tiles and ceiling).
While I have some queries in respect of the calculations adopted by F, it is logical
that the wider the beam, the greater the applied stress it can tolerate.
On balance, I accept F’s conclusions that the beam was undersized for its load.
This is particularly given it was significantly narrower than designed. This, rather
than the storm, was the proximate cause of the damage to the beam. As such, the
FSP is entitled to den y this aspect of the Applicant’s claim.
Damage to plaster and cornices in the living room, lounge and kitchen was
caused by natural movement and not the storm
F inspected the property and concluded the damage to the cornices and plaster
was related to differential movement due to long term drying and shri nkage of
building material and not related to the storm.
Case No: 361694 Determination Page 4 of 10
Builder S who attended the property in May 2013 also concluded this damage
was not related to the storm and considered it related to the expansion and
contraction of the structure due to temperature fluctuations.
The Applicant provided photographs taken shortly before the property was let to
the tenants that show the property was in excellent condition before the storm.
The damage is near the cracked beam and below where some of the roof tiles
were replaced, which is why the Applicant believes the damage was related to the
storm.
Further, the Applicant notes the property could not have sustained damaged due
to movement because the house is on a solid concrete slab.
Having reviewed the photographs pro vided by the Applicant, I accept that she
maintained her property in excellent condition. However, such maintenance will
not prevent natural movement that occurs even when a structure is built on a
concrete slab. That the storm was not the cause of the damage is supported by
the fact that there is no evidence of water damage in this area.
On balance, I accept the conclusions of F and S that the damage was not caused
by the storm. As such, the FSP is entitled to deny this aspect of the Applicant’s
claim.
Th e damaged roof tiles were caused by the storm and the FSP’s repairs
The Applicant’s roof experts indicate there are about 70 broken roof tiles that
require replacement and the repairs performed are not to standard. This follows
an initial 190 tiles replaced in September 2012 and a further 55 tiles being
replaced in July 2013.
No expert report regarding the tiles was provided by the FSP.
The FSP says the photographs presented by the Applicant’s roofing experts SK
and BJ do not exhibit this. It also says SK and BJ had provided conflicting findings
about the cracking to the pointing. The FSP’s assessor notes that the tiling to the
roof had been addressed on two separate occasions and at both times was
deemed to be completed.
While SK says the damage was not caused by the cracked beam, the FSP relies
on a photo from BJ to demonstrate that there is cracking in the vicinity of the
valley, suggesting it was caused as a result of the cracked beam.
The fact that the damage was not satisfactorily repaired (and hence required
another attempt) demonstrates that there were flaws in the first “deemed
completion”, that may well have occurred on the second occasion.
Given the history of repairs to the roof, on balance I accept that the required
rectification works are a consequence of inadequate repairs previously
undertaken by the FSP as a result of the storm.
The FSP is therefore not entitled to deny this aspect of the Applicant’s claim.
It is fair in all the circumstances for the FSP to cash settle this portion of t he
Applicant’s claim. This is because:
Case No: 361694 Determination Page 5 of 10
it is not clear whether some of the tile rectification works may need to be
undone if the roof ultimately requires lifting to repair the cracked beam, and
the deteriorated relationship between the Applicant and the FSP make it
suitable for cash settlement.
The FSP must cash settle the claim in accordance with the scope of works
obtained by the Applicant from SK dated 12 August 2013.
The FSP is entitled to deny the claim for loss of rent
The Applicant requests the FSP to reimburse her loss of rent for the period
between 16 April 2013 and 17 May 2013. She states she was unable to rent out
the property during this period because of safety concerns resulting from the
cracked beam. The Applicant says she only decided to rent the property after the
FSP’s assessor confirmed it was safe to do so.
The policy covers loss of rent where the rental property is rendered uninhabitable
as the result of an insured event.
In this instance:
the cracked beam, and therefore any resulting safety concerns, was not
caused by an insured event, and
in any event, the Applicant had received confirmation on 13 March 2013 that
the property was safe to occupy.
The FSP is therefore entitled to deny the claim for loss of rent.
2.2 Is the Applicant entitled to compensation for consequential loss
or non-financial loss?
The FSP is not required to compensate the Applicant for loss of income
The Applicant is of the view the FSP should reimburse her for loss of income
when she attended a three day VCAT hearing due to:
the delay in conducting the repairs which meant the tenants were
inconvenienced and unable to use the garage or lounge room of the property,
and
damage that had been caused to the tenant’s property during the repairs.
The FSP submits there is no provision in the policy for loss of income. It further
states that VCAT has adjudicated the dispute and redress has been ordered. As
such, the FSP says the matter should not be revisited by FOS.
There is provision in the TOR to award $3,000 for consequential loss. However, I
consider the loss of income claim arising from a VCAT hearing following a faulty
repair job, to be too remote from the insured event (storm) claim to be categorised
as consequential loss.
In any event, I agree with the Applicant ’ s claim that the correct time to have
sought this loss was at VCAT when all parties were before the Tribunal.
Case No: 361694 Determination Page 6 of 10
The Applicant is entitled to compensation for non-financial loss
FOS may grant compensation if it is satisfied the Applicant has suffered an
unusual degree or extent of physical inconvenience, time taken to resolve the
situation or interference with the Applicant’s expectation of enjoyment or peace of
mind has occurred.
While the Applicant she was only deprived of rental income for a maximum of one
month, she has suffered significant stress as a result of the FSP’s builder and
resulting VCAT hearing. This is evident in correspondence.
Further, review of the Applicant’s claim by the FSP’s legal representatives was
delayed due its inability to retrieve the claim file from the FSP.
Considering all of the above, I accept the Applicant has suffered in the manner
described in the TOR. It is fair in all the circumstances for the FSP to pay $500
compensation to the Applicant.
Case No: 361694 Determination Page 7 of 10
3 Supporting information
3.1 Relevant policy extracts
The policy covers listed events including “storm, rainwater, flood or wind” but
excludes water entering the building “because of a structural defect, fau lty design
or faulty workmanship.”
General exclusions also include: (page 37 of PDS)
“ Buildings and contents cover exclusions
We will not cover any loss or damage as a res ult of or caused by:
settling, shrinkage or expansion in the buildings foundations, walls or pavements
…
erosion, rust, corrosion, gradual deterioration, depreciation, wear or tear
…
a defect in an item, structural defects or faulty or poor workmanship or design ”
Building cover is provided for there is an additional benefit for loss of rent. (page
18-19 of PDS)
“ Loss of rent
Any loss of rent equal to the weekly amount as stated on your Rental Agreement or
Periodic Tenancy Agreement for up to 12 months and a maximum of $52,000 if your
buildings or sections of your buildings suffer loss or damage and are uninhabitable as a
result.
…
When:
loss or damage to you buildings occurs as a result of an event as listed in this
Policy …”
3.2 Summary of expert reports
Re port Key points
FSP’s builder (S)
17/04/13
“Summary
…
I am of the opinion that the hairline cracking to the cornice joints in the
Living room, Lounge room and Kitchen are as a result of general
movement to the structure through everyday wear and tear. I am of the
opinion that these cracks are not the result of one storm event but
rather caused by a number of temperature fluctuations resulting in
expansion and contraction.
Therefore I consider this to be a maintenance issue.
Given that there has been no impact damage to the roof at this location
or other associated damage t o the roof area around this point, I am of
the opinion that the break has not been from any storm event.
Case No: 361694 Determination Page 8 of 10
Re port Key points
The only evidence of repair over this section of roof is the re - bedded
capping tiles to the ridge line. I observed that all of the capping tiles to
the roof are have been re - bedded. This Insured was also not aware of
any damage to the affected area however was confident t hat the break
did not exist prior to the storm event .
I am unable to determine the cause of the break to the ridge beam.
This may have been able to be confirmed by the Tenant to the property
or the repairers to the roof after the storm event.” (sic)
FSP’s engineer (F)
05/06/13
“ Conclusi ons
It is [F]’s opinion that: -
The failure of the ridge beam in the lounge/sitting room has been
caused by the long term overstressing of the ridge beam, which is
undersized and therefore had inadequat e capacity to sustain the applied
long term loading from the roof (i.e. the weight of the supported timber
framing, roof tiles, ceiling, etc.)
The storm event of 25 December 2011 has not caused, nor cont ribut ed
to the failure of the subject ridge beam.
The owner should engage a Structural Engineer to advise on an
appropriate repair/replacement of the failed ridge beam.
The other building distress identified by the owner is long term
cosmetic damage only and is not attr ibutable to the storm event.”
Applicant’s roofer
(SK)
12/08/13
“On Monday 12 August, 2013, I ins pected the roof at the above
address:
Upon inspection, I found tha t the roof has only been re - pointed when
the occupier has advised me that it was suppo s e to have been both re -
bedded and point ed. Also there was a dip in the roof w here the
insurance w orkers have done w o rk . However, there are no sig n s of any
cracks in the po inting, and i f the dip in the roof happened after they
fixed the pointing, there would be obvious cracks.
I a lso found 70 cracked roof tiles that ha ve not been replaced. There
are also chipped tiles that have been silicone all over the roof, as you
can see in the ph o tos attached. ” (sic)
Quote to repair is $3,960 .
Applicants roofer
(BJ)
undated
“On inspection there were evident of broken tiles that have been l eft in
roof from previous tradesman (70 + see attached photos).
A number of those tiles had bee n left under top ridge and hips (will
need to b e re - bedded and re pointed) .
Broken tile s will need to be replaced.
The valley had not been repaired to standard (please refer to attached
photo) and will need to b e re - bedded and re - point ed. ” (sic)
Applicant’s
engineer (G)
19/09/13
“ 1. Roof beam design
I have been advised that the dwellin g is 26 ye a rs old: I attach a copy
of the section of the floor plan showing the ridge beam. It indicates
that the ridge bea m is 27 5x75 F 8 hardwood timber spanning 3 300mm
between the face of supports with a load width of 4400mm . This is
com pletely c on tradic tory to the estimated size adopted by [F].
In addition, the relevant standard us ed for the design of the timber
beam must be the one relevant in 1987 i .e. AS1720 - 1975, SAA
Timber Engineering Code . The design for the beam is car ried out
using the working stress method . I checked the design of the beam
and determined that the 250x75 F8 timber beam is sa tisfact o ry; - fb=
8.18 MPa, Fb =8.60 MPa.
I also point out that council approved the design of the building and a
certificate of occupancy has been issued. As such the building is
suitable for occupation and able to be insured.
Case No: 361694 Determination Page 9 of 10
Re port Key points
2. Wind
[F] has suggested that the wind load on the roof at the time of the
storm was lower than the design load for the structure.
I do not argue that the wind gust at [Location T] w as 27.8 m/sec. The
fact is that at the property in [Location G] the wind/gust was such that
a significant number of roof tiles were dislodged. Tiled roofs must be
designed and constructed to withstand similar wind loads as the
supporting structure. To sugg est that the wind load recorded at
[Location T] can be compared to what occurred at the dwelling is
ludicrous. There are oft en in ci dents where a freak storm will cause
significant damage to a building but not the adjoining building. ”
FSP’s engineer (F )
05 /12/13
“ Conclusion
4.1 New information provided in the report by [G]
demonstrates the following:
The installed ridge beam is significantly narrower than the beam width
specified in the design drawings. Hence roof ha s not been
constructed in accordance with the original design Intent.
Adjusting the results of the calculations provided by [G] to allow the
fact that the i nstalled ridge beam is substantially narrower than the
section size specified in the design, demonstrates that the applied
bending stress is 44% greater that the permissible bending stress as
determined by [G] , i.e. the subject ridge beam, as installed , is
significantly undersized.
4.2 Henc e the information provided by [G] appears to confirm the
findings of [ F ] 's Report ref: S11958 - 20 9767 , dated 5 June 2013, which
i dentified that the failed ridge beam Is "undersized and therefore had
inadequate capacity to sustain the applied long t erm loading from the
roof (i.e. the weight of the supported timber framing, roof tiles, ceiling,
etc.)".
4. 3 For the reasons stated in Section 3.2. it would not be appropriat e
for [ F ] to comment on the letters by [SK] and [BJ] . [F] suggests that the
Client engage a suitably qualified roofed builder to comment on the
letters; it i s recommended the roofer/builder undertake a detailed site
inspection of the roof prior to providing comment.
4.4 [F]’ s conclusions in relation to this investigation, as detailed in our
Engineering Investigation Report, remain unchanged. In particular, it is
[F]’s opinion that the storm event of 25 December 2011 has not
caused, nor contributed to, the failure of the subject ridge beam.”
3.3 Chronology
Date Event
25 December 2011 Hailstorm causes damage to the Applicant’s tenanted property.
3 March 2012 Ceiling of garage collapsed .
6 March 2012 Applicant made claim for damage .
September 2012 Repairs completed by FSP’s builder (BB).
190 roof tiles required work together with replacement of a new
ceiling in the garage and repair to plaster in a number of rooms.
Case No: 361694 Determination Page 10 of 10
Date Event
15 January 2013 VCAT hearing. Damage to tenants ’ contents found to have been
caused by Applicant or agent.
Tenant makes further claims for 57 days of inconvenience, loss
of use of garage and lounge.
January 2013 Applicant discovers problems to internal cornices, beam, sag i n
the roof, cement sheets, brick and split doors on the garage and
laundry . This was the Applicant’s first six month inspection of
the property and her first opportunity to see the repairs carried
out by B B .
15 December 2013 Lease agreement entered into.
13 March 2013 Email from FSP that repairs have made building safe.
1 5 April 2013 Tenants break lease and vacate. They were unhappy that it took
5 months to repair the house, that they could not use the whole
of the house during this time, with the constant disruptions and
that the repairer mishandled their goods .
18 May 2013 New tenants arranged after the FSP’s building inspector stated
the beam was made safe.
22 May 2013 VCAT hearing. Te nant’s further claim for inconvenience of
$2,003 al lowed . FSP accepted and paid for the claim.
27 June 2013 Following F’s report, the FSP denies four out of six additional
claims made by the Applicant, agr e eing only to pa y the claims in
respect of paint damage to the bathroom and sunroom and
damage to the cornice in the ensuite.
23 July 2013 Further repairs were done to make the roof watertight, with 55
tiles being replaced together with internal cosmetic works.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.