Home / Financial Firm (Unknown - Credit) / Determination 361028
Determination 361028
delay
Summary
A company borrowing to buy a franchise complained that the FSP delayed approving and funding two loans, forcing its director to find alternative funds. AFCA found a 10-day processing delay and ordered a $221 interest refund, rejecting the rest of the claim.
The FSP was entitled to ensure documentation was in order, but it should have funded 10 days earlier, so it must refund interest for that period; the claimed wider losses were not established.
Issues
- Delay primary · upheld“The FSP should have been able to advance the Loans 10 days earlier than it did, and should be held accountable for that ten day delay.”
- Complaint handling failure secondary · upheld“The FSP should also have provided a further response to the Applicant's second complaint before the Applicant lodged this a dispute with FOS.”
- Misleading conduct secondary · not upheld“The FSP did not mislead the Applicant about its inability to release funds from the Loans to meet settlement.”
Subjects and remedies
small businessrefund fees or charges
Related
All Financial Firm (Unknown - Credit) determinations · Find similar determinations
Text of the determination
Determination
Case No: 361028 Determination Page 1 of 11
Case number : 361028 9 Ju ly 2015
1 Overview
1.1 Dispute
The Applicant obtained two loans (the Loans) from the FSP in March 2014 for the
purchase of a franchise business.
The Applicant says that the FSP unreasonably delayed approving and advancing
the Loans. Consequently, its director had to generate adequate alternative funds
to facilitate the purchase by:
selling personal assets including shares and an investment property,
taking out a bridging loan at high interest rate , and
using credit cards for business purchases incurring fees
The Applicant also complained that the FSP:
failed to advise it when the Loans were drawn down,
delayed setting up internet banking facility, and
failed to respond appropriately to its complaint.
1.2 Issues and key findings
Did the FSP unreasonably delay approving and funding of the Loans?
The documents do not show that the FSP caused an unreasonable delay in the
processing of the Applicant’s loan application.
The FSP was entitled to ensure that its documentation was in order before
advancing the Loans. However I am satisfied that the FSP should have been
able to advance the Loans 10 days earlier than it did, and should be held
accountable for that ten day delay (in terms of the interest corresponding to that
period of time).
The FSP transferred the loan funds to an account nominated by the Applicant on
20 March 2014. The Applicant has not suffered any additional financial loss above
and beyond the loss compensated by the 10 day interest refund awarded by this
Determination.
Did the FSP mislead the Applicant?
The FSP did not mislead the Applicant about its inability to release funds from the
Loans to meet settlement.
Case No: 361028 Determination Page 2 of 11
Did the FSP fail to notify the Applicant of the funding of the Loans?
The FSP followed industry practice and sent the notifications to the Applicant
about the advance of the Loans by mail.
Did the FSP delay providing internet banking facility to the Applicant?
There was delay in providing the online banking access to the Applicant , but the
available information does not support a finding that the delay caused the
Applicant to suffer financial loss.
Did the FSP fail to respond to the Applicant’s complaint appropriately?
The FSP responded appropriately to the Applicant’s first complaint in February
2014. The FSP’s failure to respond to the Applicant’s second complaint in May
2014 did not cause any loss to the Applicant for which it is required to pay
compensation.
1.3 Determination
This decision in substantially in favour of the FSP. Should the Applicant accept
this Determination within 30 days of its date, within a further 14 days of that
acceptance the FSP must refund interest totalling $221 to the Applicant’s loan
accounts, with that total sum being comprised the following refund components:
$126 to the loan account with a balance of approximately $70,000, and
$95 to the loan account with a balance of approximately $42,000.
The FSP is otherwise not required to compensate the Applicant in relation to the
other issues arising from this dispute.
Case No: 361028 Determination Page 3 of 11
2 Reasons for Determination
2.1 Did the FSP unreasonably delay approving and funding of the
Loans?
The Applicant committed to the purchase and settlement before the loan
approval
The Applicant entered into the contract to purchase the franchise business
(Purchase Contract) on 2 October 2013.
The Franchisor required the Applicant to provide certain information for approval,
including confirmation of available funds to complete the purchase.
The Applicant provided the documents to the Franchisor showing it had readily
available funds, before the FSP completed considering its loan application.
The FSP did not represent when it would advance the Loans
Throughout the process of dealing with the Applicant’s loan application, the FSP
did not represent when it would be in a position to release the loan funds.
The Applicant says that the FSP gave it no indication that there would be an issue
in providing the Loans to meet settlement.
However, the FSP had not:
represented to the Applicant about its ability to meet the settlement time frame
otherwise influenced its decision to commit to a settlement date
There was a ten day in the processing of the loan application but that delay
was not unreasonable
The available information in this dispute show the following events occurred in
relation to the processing and progress of Applicant’s loan application:
Date Events
02/10/13 The Applicant entered into a contract to purchase the franchise business
24/11/13 Loan application submitted to the FSP
30/11/13 –
07/01/14
The parties discussed and resolved various issues bef ore formal
application could be submitted for approval
16/01/14 The FSP provided conditional loan approval letter to the Applicant
20/01/14 The FSP commenced preparation of security documents and arranged
property valuation
28/01/14 The Applicant reques ted rental bond guarantee
06/02/14 Security documents were available for the Applicant to sign
17/02/14 The FSP received signed security documents
Case No: 361028 Determination Page 4 of 11
21/02/14 The FSP received advice that the witnessing of the mortgage documents
did not meet titles office’ s requirements
26/02/14 The FSP provided the Applicant replacement mortgage documents for
signing
03/03/14 The FSP received signed replacement mortgage documents
11/03/14 Funding of the Loans occurred
20/03/14 The FSP acted on the Applicant’s instructi ons to transfer loan funds to
another account
As the FSP’s documents were in order from 3 March 2014, allowing for time to
complete the checking and processing, the Applicant should have had access to
the loan funds by 11 March 2014.
The FSP is required to refund the Applicant interest it charged on the Loans for 10
days.
As shown by the calculation in section 3.1, the interest refund amount is $221.
Section 3.2 sets out in more details the sequence of events relating to the
processing of the Applicant’s loan application.
The FSP was not responsible for the need of replacement mortgage
documents
The FSP had to arrange for replacement mortgage documents because the
previous mortgage documents had not been witnessed in accordance with the
titles office’s req uirements.
There was no delay in getting the replacement mortgage documents prepared for
the mortgagors to sign.
The FSP’s request for copy of insurance policy did not cause unreasonable
delay
On 24 & 26 February 2014, the FSP advised the Applicant that it still had not
received a copy of the director’s insurance policy.
The Applicant says that it had previously provided this information in a digital
storage device (USB) containing other documents to support its loan application .
As the FSP was able to acce ss the other documents in the USB, there was no
reason why it could not access the insurance policy document, unless the USB
had been misplaced.
Even if the Applicant had previously provided the FSP the insurance policy
information, the FSP’s request for t he same information was relatively easy to
comply with. This issue did not cause the Applicant extraordinary inconvenience
or unreasonably delay release of loan funds.
At the time of requesting for the insurance policy, the FSP was still waiting on the
mortgagors to sign and return the replacement mortgage documents.
Case No: 361028 Determination Page 5 of 11
2.2 Did the FSP mislead the Applicant?
The FSP’s position was sufficiently clear from the parties’ regular contacts
The Applicant says that even in the days before the scheduled settlement, the
FSP did not indicate that the loan funds would not be available to meet
settlement.
The FSP would have engaged in misleading conduct if:
it was aware the Applicant had misunderstood that it would release funds from
the Loans by the settlement date; and
it di d not do anything to correct the Applicant’s misunderstanding.
There were regular contacts between the parties since the Applicant lodged the
loan application on 24 November 2013.
The FSP’s conditional approval letter dated 16 January 2014 sets out detail s of
the Loans it was prepared to offer the Applicant. The letter also specified the loan
conditions, including:
a second mortgage over the director’s investment property
a copy of the signed Franchise Agreement
The FSP also advised the Applicant that it would commence preparation of loan
documents after its acceptance of the loan offer. The Applicant accepted the loan
offer on 17 January 2014.
The Applicant agreed to a settlement date of 4 February 2014 before the FSP’s
loan documents were available for signing.
I do not find the FSP’s conduct misleading when it had clearly advised the
Applicant the requirements to be completed before the Loans could be funded.
2.3 Did the FSP fail to notify the Applicant of the funding of the
Loans?
Any delay in notifying the Applicant did not cause it to suffer additional loss
The FSP sent letters to the Applicant to confirm the funding of the Loans on 11
March 2014. This is consistent with prevailing industry practice. The Applicant
says it did not receive the letters until 19 & 20 March 2014. It instructed the FSP
to transfer the loan funds on 20 March 2014 to another account.
I have found that the Applicant should have been able to access the loan funds by
11 March 2014 and required the FSP to refund interest for the 10 day delay in
approving the loan. I am satisfied that the delay in notification did not cause the
Applicant to suffer additional loss above and beyond what it has been
compensated for in this Determination.
Case No: 361028 Determination Page 6 of 11
2.4 Did the FSP delay providing internet banking facility to the
Applicant?
The Applicant did not suffer loss resulting from any delay
On 17 March 2014, the FSP advised the Applicant that online banking had not yet
been established.
The Applicant received online banking access on 3 April 2014 and informed the
FSP that the loan accounts had not been properly linked.
As the FSP had transferred the loan funds on 20 March 2014 to the account
nominated by the Applicant, any delay in establishing online banking facility did
not prevent the Applicant access to the loan funds.
2.5 Did the FSP fail to respond to the Applicant’s complaint
appropriately?
The FSP should have been more responsive to the Applicant’s second
complaint
The FSP had provided a detailed response to the Applicant’s first complaint on 28
February 2014. However the FSP should also have provided a further response to
the Applicant’s second complaint before the Applicant lodg ed this a dispute with
FOS.
The FSP’s subsequent responses to th is dispute show that it has not moved from
the position expressed in its 28 February 2014 response. Consequently, on
balance I am satisfied that the Applicant did not suffer a loss as a result of the
FSP’s failure to respond, as given the FSP’s later disclosed position, a ny earlier
would not have prevented the need for the Applicant to lodge this dispute.
Case No: 361028 Determination Page 7 of 11
3 Supporting information
3.1 Interest refund calculation
Loan amount Interest rate Number of days Interest refund
$70,000 6.57% per annum 10 $126
$42,000 8.25% per annum 10 $ 95
$221
3.2 Sequence of events
The following table represent a summary of the events based on available
documents and the parties’ respective position.
Date Document/Event Details
02/10/13 Purchase
Contract The Applicant entered into a contract to buy the
franchise. Settlement was due within 47 days.
24 /11/13 Loan application The FSP received the Applicant's loan application and
supporting documents.
30/11/13
to
30/12/13
Email
correspondence
Regular contacts between the parties concerning:
The FSP's requirements for supporting financial
reports from the vendor
Other documents to assist its consideration of the
loan application
The shortfall in its assessment to support the
finance required
The Applicant advised the FSP that settlement was not
due until Feb 2014 and would need to know the
outcome of the ir finance application by 12 Feb 2014
when the Applicant was due to commence training
provided by the Franchisor.
The Applicant also raised its concerns that time was
running short for it to secure funds for settlement if the
FSP would not approve its loa n application.
03/01/14
to
07/01/14
Telephone
contacts
The FSP discussed a number of issues with the
Applicant relating to its loan application and sought
clarification regarding the director's credit reference
report.
10/01/14 Email
correspondence
The A pplicant provided its solicitor and the FSP each
other's email address for future reference. The
Applicant also advised both parties that settlement was
Case No: 361028 Determination Page 8 of 11
likely to occur on 05/02/14 or 12/02/14 .
16/01/14 Conditional Letter
of Offer The FSP issued condition al loan approval letter to the
Applicant. The FSP also advised the Applicant that it
would commence preparation of loan and security
documents upon their acceptance of its loan offer.
17/01/14 Acceptance of
loan offer The Applicant accepted the FSP’s loan offer
20/01/14
to
21/01/14
The FSP c ommence d document preparation and
arranged for property valuation
28/01/14 The FSP received the signed Subsequent Mortgage
Form from the Applicant and forwarded it to the 1st
mortgagee for consent.
The FSP also pro vided the Applicant an application for
a rental bond guarantee which was in addition to the
Loans it approved.
29/01/14 Email
correspondence The Applicant advised the FSP that settlement would
be due on 5 February 2014 and the rental bond
guarantee applic ation was being returned by express
post.
30/01/14 FSP's account manager (Account Manager) submitted
rental bond guarantee application for approval.
Email
correspondence The Applicant provided a copy of business insurance
policy that the FSP requeste d.
31/01/14 Email
correspondence
The Applicant advised the FSP of details of cheques
required at settlement.
Phone call to the
FSP
The Applicant was unable to contact the Account
Manager by telephone.
03/02/14 Phone call to the
FSP
The Applicant spoke to the Account Manager by
telephone regarding settlement.
Email
correspondence
The Applicant advised the FSP of details of cheques
required at settlement.
Text message The Applicant sent a follow up text message to the
Account Manager.
Email
correspo ndence
The FSP advised the Applicant of the outstanding
issues required to be resolved before it could release
funds from the Loans.
Email
correspondence
The Applicant addressed the FSP’s outstanding
requirements.
Account Manager followed up rental bond guarantee
approval.
The FSP asked & received statement of the director's
home loan account with 1st mortgagee.
Case No: 361028 Determination Page 9 of 11
04/02/14 Phone calls The Applicant was unable to contact the Account
Manager by telephone.
Email
correspondence
The FSP received confirmatio n from the Applicant's
accountant that its financial accounts were in order.
The FSP advised the Applicant that loan documents
should be ready for signing on 05/02/14.
The FSP advised the Applicant that it could not confirm
when it would be in a positio n to fund the Loans.
Settlement
occurred Settlement for the business purchase occurred without
funds provided by the FSP.
05/02/14 Phone call The Applicant was unable to contact the Account
Manager by telephone.
Email
correspondence
The Applicant foll owed up loan documents.
The Applicant advised the FSP that its director had to
fund the settlement by using savings, selling shares,
borrowing from family and friends.
The FSP advised the Applicant that loan documents
should be available by 06/02/14.
06/02/14 Email
correspondence
The FSP arranged with the Applicant to collect the loan
documents from its branch.
07/02/14 Email
correspondence The Applicant complained to the FSP about the
handling of the loan application and preparation of loan
document s.
12/02/14 Email
correspondence
Formal complaint logged with the FSP. The FSP
advised the Applicant that it would respond within 5
business days.
12/02/14 Agency
Agreement
The Applicant appointed a real estate agent to sell his
investment property.
17/ 02/14 Signing of loan
documents
Documents signed and returned to FSP's branch.
19/02/14 1st mortgagee's
consent
The FSP received 1st mortgagee's approval for its 2nd
mortgage.
Email
correspondence
The FSP asked the Applicant for a copy of the signed
Fra nchise Agreement and advised that:
it could not say when loan funding could occur
on funding of the Loans, it would reimburse the
funds provided by the director
The FSP's head office advised the Applicant that it
would provide a response to his complaint by 25/02/14.
Email
correspondence
The Applicant advised the FSP:
signed documents were returned to its branch on
17/02/14
the Franchise Agreement was being sent to the
Case No: 361028 Determination Page 10 of 11
Franchisor's head office for signing
the amounts of expenses incurred and its intentio n
to lodge a dispute with FOS
21/02/14 Mortgage
incorrectly
executed
The FSP received advice that its mortgage was not
acceptable & fresh mortgage documents would need to
be prepared and re - signed
24/02/14 Email
correspondence
The Applicant provided a co py of signed Franchise
Agreement to the FSP.
The FSP requested the 1st mortgagee for production of
the certificate of title.
The FSP asked the Applicant for a copy of the director's
life and disability insurance policy.
25/02/14 Email
correspondence
The FSP’s head office advised the Applicant that it
would provide its response to the complaint by
28/02/2014.
26/02/14 New mortgage
documents
required
The FSP provided the Applicant new mortgage
documents for signing. The FSP also requested a copy
of the di rector's insurance policy.
27/02/14 Email
correspondence
The Applicant asked the FSP to:
acknowledge receipt of the signed Franchise
Agreement
provide an update on release of loan funds
28/02/14 Email
correspondence
FSP responded to the Applicant's compl aint.
01/03/14 Email
correspondence
The Applicant provided details of director's insurance
policy and reiterated that the information had previously
been provided to the FSP.
03/03/14 New mortgage
signed
The Applicant returned signed loan documents to t he
FSP.
Production of title 1st mortgagee advised the FSP of production of
certificate of title.
11/03/14 Email
correspondence The Applicant followed up progress with FSP.
Loan funding The FSP credited proceeds of the Loans to the
Applicant’s business account.
17/03/14 Telephone
contact
The Applicant complained that the FSP did not keep it
informed of the loan processing progress and did not
advise it when the Loans were drawn down.
The Account Manager advised the Applicant that loan
funding occurr ed on 11/03/14.
Internet banking facility yet to be set up.
18/03/14 Email
correspondence
The Applicant returned the direct debit form to the FSP.
19/03/14 Funding letter The Applicant received advice of the funding of the 1st
loan on 11/03/14.
Case No: 361028 Determination Page 11 of 11
20/03 /14 Funding letter The Applicant received advice of the funding of the 2nd
loan on 11/03/014.
20/03/14 Email
correspondence
The Applicant followed up availability of loan funds.
Funds transfer The FSP transferred funds in the Applicant's business
accoun t to an account with another financial institution
nominated by the Applicant.
03/04/14 Email
correspondence
The Applicant followed up and received online account
access.
4/04/14 Email
correspondence
The FSP added the loan accounts to the Applicant’s
onl ine access in response to its queries.
24/04/14 Email
correspondence
The Applicant lodged a new complaint with the FSP.
28/04/14 Email
correspondence
Interim response from the FSP advising its aim to
address the Applicant's complaint within 5 working
day s.
9/05/14 Email
correspondence
The Applicant followed up FSP's response to its
complaint.
11/05/14 Dispute lodged
with FOS
12/05/14 Email
correspondence
The FSP advised it would respond to the complaint by
19/05/14.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.