Determination 360216

Ongoing movement damage after earlier rectification repairs, claimed as inadequate

FirmFinancial Firm (Unknown - Insurer)
Decided2014-12-17
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicants said earlier stumping and levelling repairs by the FSP's contractors were inadequate and the house kept moving. AFCA found the ongoing damage was caused by earth movement after a tree was removed, which the policy does not cover, and that the repairs met the policy standard, so the FSP has no further liability.

Insurance restores damage to the condition when new, excludes naturally occurring earth movement, and does not require improvements such as deeper footings beyond the repair scope.

Issues

Subjects and remedies

home or building damageno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination General Insurance - Domestic Insurance - Home Building - Service - Rectification Repairs - Repair Guarantee Determination Case No: 360216 Determination Page 1 of 9 Case number : 360216 15 December 2014 1 Overview 1.1 Dispute In December 2007, the Applicants lodged a claim under their home insurance policy with the Financial Services Provider (FSP) for movement damage caused by a leaking pipe. The FSP accepted the claim and arranged for the necessary repairs, which were completed in 2010 (after the sub-floor had dried out). In January 2011, the Applicants lodged a second claim for movement damage to their home caused by stormwater runoff. The FSP accepted this claim and arranged for repairs, after again allowing time for the sub-floor to dry out. These repairs were completed in mid-2013. The Applicants say that the repairs carried out by the FSP are inadequate as their home is still suffering movement damage. The FSP disputes this and says that any ongoing issues are due to naturally occurring soil movement at the property, which is excluded under the policy. 1.2 Issues and key findings Is the FSP liable for the additional movement damage? The ongoing movement damage at the Applicants’ property is due to naturally occurring earth movement, caused primarily by the removal of a large tree at the property (and not by the leaking pipe in 2007 or the stormwater run-off in 2011). Damage caused in this manner is not covered under the policy. Were the earlier repairs carried out by the FSP inadequate? By re- stumping relevant areas of the Applicants’ property to the depth of the existing foundations (in accordance with applicable building requirements), the FSP complied with its obligations under the policy to restore the property to its condition when new. The available information does not establish that the repairs were otherwise inadequate or caused the current damage. 1.3 Determination This Determination is in favour of the FSP. The FSP has complied with its obligations under the policy and has no further liability to the Applicants in respect of the movement damage at their property. Case No: 360216 Determination Page 2 of 9 2 Reasons for Determination 2.1 Is the FSP liable for the additional movement damage? FSP’s liability depends on cause of damage The FSP is only liable for the ongoing movement damage at the Applicants ’ property if this damage was caused by:  the leaking pipe which triggered the Ap plicants’ first claim in 2007 or the stormwater run-off which triggered the A pplicants’ second claim in 2011  the inadequacy of the repairs carried out by the FSP’s contractors in relation to either of the Applicants’ previous claims or  a separate insured event which has occurred after the previous repairs were carried out. The Applicants bear the onus of establishing that, on the balance of probabilities, the claimed damage was caused by one of the above events. Ongoing damage is due to naturally occurring earth movement After the Applicants notified the FSP of ongoing cracking and movement damage to their property in late 2013, the FSP engaged an engineer (F) to determine the cause of the damage. F concluded that the recent damage to the property was primarily caused by the removal of a large tree in December 2012, which had resulted in “heave” (expansion of the soil) due to the rehydration of the previously dry soil around the tree. F confirmed that neither the leaking pipe in 2007 no r the stormwater run-off in 2011 had caused the current damage. F also noted that the Applicants’ property would continue to be subject to naturally occurring earth movement due to the highly reactive clay soils at the site, which experience significant volumetric adjustments as a result of changes in moisture content. Such changes can be caused by factors including the effects of nearby trees, poor site drainage and seasonal rainfall variations. The Panel considers that, as an engineer, F is suitably qualified to determine the cause of the recent movement damage to the Applicants’ property . F’s report provides a logical and reasonable explanation as to how the movement damage occurred. In particular, the contour lines produced by the floor level surveys carried out by F provide clear support for his conclusion that the removal of the tree outside bedroom 3 was the underlying cause of most of the recent movement damage at the property. F’s comments about the susceptibility of the property to on going movement damage are consistent with the views expressed by the engineer (B) who inspected the property following the Applicants’ initial claim in 2007. B noted that the house had experienced extensive movement over its life, as a result of the effects of moisture changes on the highly reactive clay soils (while also recognising that the leaking pipe had caused additional damage) . Case No: 360216 Determination Page 3 of 9 The Applicants dispute the findings in F’s report and have suggested that the claimed damage may have been caused by a leak from the hot water service. However, the Panel is satisfied that this alternative explanation was adequately considered and discounted by F based on the location of the relevant damage and the fact that the Applicants’ water bills did not evidence a sig nificant leak. The Applicants have not provided any additional information (for example, a report by their own engineer) which contradicts F’s findings. In these circumstances, the Panel is satisfied that, on the balance of probabilities, the recent movement damage at the property was caused by naturally occurring earth movement due to changes in the moisture content of the highly reactive clay soils, in this case primarily due to the removal of a large tree at the property. Damage was not caused by an insured event For the reasons outlined above, the Panel is satisfied that the additional movement damage was not caused by the leaking pipe in 2007 or the stormwater run-off in 2011. Further, the additional damage was not caused by a separate insured event which occurred after the earlier claims. Damage caused by naturally occurring earth movement is not an insured event under the Applicants’ policy . 2.2 Were the repairs carried out by the FSP inadequate? FSP was not required to re-stump the house to a greater depth in 2010 The Applicants say that the repairs carried out by the FSP to fix the damage caused by the leaking pipe were inadequate. In particular, the Applicants say that the FSP should have ensured that its contractor (G) re-stumped the house to a greater depth than the existing stumps, in accordance with a recommendation provided by the FSP’s engineer (B) in March 2008. Under the terms of the Applicants’ policy, the FSP was required to repair the damaged part of the building to the same condition as when it was new. However, the FSP was not required to undertake any works which would constitute improvements. Only part of the re-stumping works undertaken by G in 2010 was carried out on behalf of the FSP to repair the damage caused by the leaking pipe. These works involved the re-stumping of the laundry, the kitchen, part of the lounge room and part of the verandah. The re-stumping of the remainder of the house was carried out by G on behalf of the Applicants at their own cost, on B’s recommendation. In his report dated 30 December 2008, B noted that the re-stumping works carried out by the FSP would effectively restore the house to a superior condition than that which existed prior to the water leak. However, he concluded that re- stumping of these areas was necessary to address the damage caused by the leaking pipe, as the extent of the foundation movement meant that it was not possible to simply re-level the house over the top of the existing stumps. Case No: 360216 Determination Page 4 of 9 When G re-stumped the house, he did so to a depth of 500mm, which reflected the depth of the existing footings. G obtained a building permit from the local council to carry out the re-stumping on this basis. However, in his report dated 31 March 2008, the FSP’s engineer (B) had clearly advised that the depth of the existing footings was inadequate to prevent future movement damage to the house. B noted that the then current minimum requirements for the relevant soil type required footings to be founded to a depth of 1500mm. Further, when F inspected the property in 2013, he confirmed that, had the property been re-stumped to a depth of 1500mm in 2010, the damage caused by the recent building movement would have been less. While the Panel accepts that re-stumping the house to a depth of 1500mm would have minimised future movement damage, it does not consider that the FSP was required to take these measures in order to satisfy its obligations under the policy. Based on B’s reports and the building permit obtained by G, it appears that the re - stumping of the Applicants’ house complied with applicable building requirements for existing houses in the area (even though new houses may have required deeper foundations). By re-stumping the relevant parts of the house in this manner, the FSP complied with its obligations to repair the damaged areas to the same condition as when new. The Panel accepts that, where an insurer is aware of improvements which should be undertaken to minimise the risk of future damage to an insured property, it is consistent with good i ndustry practice for the insurer to share that information with the insured. In the present case, there is limited information available about the discussions which occurred between the FSP, the Applicants, the engineer (B) and the re- stumper (G) between the time when the claim was lodged in late 2007 and completion of the re-stumping works in mid-2010. It appears that the Applicants were provided with a copy of B’s report at some stage (as they referred to this report in their later submissions to the FSP), although it is not clear when this occurred. In the circumstances, the Panel considers that the available information is not sufficient to establish that the FSP breached its obligations to the Applicants in relation to the re-stumping. By engaging G to re-stump the remainder of the house, the Applicants were directly involved in this process. It is not clear that the Applicants relied on advice from the FSP in determining the nature and extent of the re-stumping works to be undertaken on their beha lf. Earlier repairs were otherwise adequate In addition to their concerns about the re-stumping, the Applicants say that the FSP’s contractors should not have advised them to remove the tree near the verandah of bedroom 3 during the course of their earlier claims, given that this has now been identified by F as having caused further building movement. Having carefully reviewed the claim history, the Panel is satisfied that at no time did the FSP’s contractors specifically recommend to the Applicants that the tree Case No: 360216 Determination Page 5 of 9 outside bedroom 3 be removed. Accordingly, the FSP is not liable for any further damage caused by the removal of this tree. The Applicants also say that they have never been satisfied with the repairs to the main bedroom and consider that the contractor who re-levelled the house in mid- 2013 (following their second claim in 2011) failed to check that the levels were correct. While the Applicants have experienced continuing issues with the floor leve ls following completion of these repairs, the report provided by F in December 2013 establishes that these issues were due to naturally occurring earth movement, exacerbated by the removal of the tree. The Applicants have not provided any independent information which supports their position that the re-levelling works were inadequate. Case No: 360216 Determination Page 6 of 9 3 Supporting information 3.1 FOS approach to this dispute This dispute has not been the subject of a FOS Recommendation. Due to the nature of the dispute, it has been referred directly to a Panel for Determination, in line with the Operational Guidelines to the FOS Terms of Reference. The Panel consists of an Ombudsman and two representatives with consumer and insurance experience. The Panel has decided this case on its merits, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions. There has been a full exchange of all material information relied on for the purposes of this Determination and each party has had the opportunity to address any issues raised by the other. The Panel has reviewed and considered all of the material provided by the parties. While the parties have raised a number of issues in their submissions, for the purposes of this Determination the Panel has restricted its commentary to those issues which it considers directly relevant to the outcome only. 3.2 Expert Reports Record Key points FSP’s engineer ( F ) R eport - 29 November 2013  The property is a single story weatherboard residence which is around 60 years old. The site had a slight fall towards the east and had poor drainage.  Geological survey maps indicated that the soils in the area were highly reactive clay soils.  There were a significant number of large trees in close proximity to all sides of the property (other than the east).  There was a 500mm diameter tree stump approximately 2 metres from the verandah of bedroom 3. The tree had been cut down in December 2012. Another large tree at the front entry had been cut down in September 2013.  The house showed cracking and movement damage in a number of areas.  The re - stumping sketches prepared by the re - stumper (G) in 2009 showed typical 100mm square red gum stumps with a founding depth of 500mm minimum. The sketches were consistent with F’s observations of the new stumps present throughout the property.  The contractor (AP) who carried out re - levelling works in 2013 advised that at that time, he installed packers up to approximately 50mm thick. AP also advised that packers up to 125mm thick were already present. AP confirmed that the floors were level fol lowing completion of his works.  F’s floor level surveys showed heave occurring in sections Case No: 360216 Determination Page 7 of 9 Record Key points of the residence. The contour lines of the level survey showed concentric circles radiating out from the verandah of bedroom 3, where the tree had been removed.  The se circles were indicative of heave, resulting from the rehydration of the previously dry soil after the tree was cut down. This process can take well over a year.  The majority of the damage to the property had occurred relatively recently and comprised bo th the reopening of previous cracks and new damage.  The damage was consistent with differential movement of the isolated stump pad footings.  The size and location of the timber packers above the original timber stumps in the bedroom 3 and laundry areas s howed that extensive movement and settlement had occurred previously in these areas, which was consistent with the presence of nearby large trees.  The differential foundation movements had been caused by deep (ie > 3 metres) variations in the moisture cont ent of the highly reactive clay soils which was expected to occur seasonally. The soils experience significant volumetric adjustments, shrinking as they dry and heaving as the moisture content increases.  Possible causes of the differential changes in the m oisture content of the clay soils included the drying effects of nearby trees, poor site drainage, seasonal changes in soil moisture content and the rehydration of the soil due to the removal of trees.  In his opinion, the recent damage had been caused pri marily by cutting down the tree. The burst water pipe in 2007 and the stormwater run - off in 2011 (and the subsequent repairs) had not caused or contributed to this damage.  The 500mm deep stump footings were inadequate for the site due to the reactive clay soil and the extent of trees present. Accordingly, ongoing differential footing movements and associated damage was likely to continue. FSP’ s engineer ( F ) Supplementary report - 20 January 2014  He had reviewed the reports prepared by the engineer (B) appointed by the FSP at the time of the 2007 claim, as well as a recent report from the Applicants’ plumber (F).  F considered the classification of site drainage as either poor or fair to be largely a matter of opinion. While B had classified the drainage as fair, F considered it to be poor, given the relatively high moisture content of the soil.  In the present case, the poor site drainage had a limited impact only, as the dominant influence on the differential foundation movements was the presence (and rem oval) of trees. Trees can influence the soil content to a depth of several metres, whereas drainage has a lesser impact.  The results of the level surveys (which showed contours Case No: 360216 Determination Page 8 of 9 Record Key points radiating from the tree stump) confirmed that any leak from the hot water servi ce was not contributing to the building movement. Further, the Applicants’ water bills did not indicate a significant leak.  The building permit for the restumping issued in 2009 showed that the new stumps were to be founded at a depth of 500mm or the dept h of the original plates, whichever was greater.  The timing of the re - stumping had no effect on the house movements from 2011 onwards because the new stumps were installed to the same depth as the original stumps.  Both the original and new stumps are much shallower than the requirement for new houses in the area (as stated in B’s report). These shallow footings are subject to greater ground movement – in particular, due to changes caused by the presence and removal of large trees.  If the house had been ful ly re - stumped to a depth of 1500mm in 2008 then the recent building movement would have been similar but the damage caused would have been less. Re - stumping to this depth would have required the removal of the tongue and groove flooring. FSP’s engineer (B ) Report - 31 March 2008  The house is an old weatherboard clad residence with a conventional timber bearer and joist subfloor system, supported on a combination of newer red gum stumps and old sawn log stumps.  The land has a moderate fall from the main ro ad with the site generally having fair surface drainage.  There were several medium to large trees nearby.  The soils in this area are highly to extremely reactive clays that can be subject to significant movement following wetting or drying.  His inspection of the subfloor indicated that the house had experienced extensive movement over its life, as shown by the number and height of the packers between the stumps and the underside of floor bearers.  However there was also further movement attributable to the leaking water pipe in December 2007, which had caused movement of the stumps (although movement would also be occurring due to other factors).  The footings were significantly inferior to current minimum requirements for the soil type although they generall y represented building practices at the time of construction.  Stump footings for a new house in the area were now founded to a depth of at least 1500mm whereas the footings of the Applicants’ property were likely to be only 450mm deep at best.  Even with ca reful site maintenance, the magnitude of seasonal movements that may be expected will be significant as the footing system is inadequate for the Case No: 360216 Determination Page 9 of 9 Record Key points extremely reactive clay soils.  Repairing the additional damage caused by the leaking pipe would reconstruct the house to a similar condition but significant movement would continue to occur.  I t would be desirable to fully restump the entire house , rather than just repacking over the existing stumps. However, a full re - stumping is not required to repair the damage from the leaking pipe .  Much of the movement in the north wall of the house was attributable to the large tree nearby, not only the water leak.  The scope of works for the repair of the water leak included jacking - up and re - stumping the laundry, kitchen, part of the lounge room and the south part of the verandah and re - levelling the central part of the house over the existing stumps. However, he re commended that the cost of the repairs be applied to fund a portion of the full cost of the re - stumping. FSP’s engineer (B) Supplementary r eport – 30 December 2008  He inspected the property after a temporary re - levelling of the floor had been carried ou t.  The subfloor area was still too moist to undertake the re - stumping and should be left to dry for a further 12 months.  His views remained as expressed in his earlier report. His updated scope of works would effectively restore the house to a superior con dition than that which existed prior to the water leak, as it was not possible to simply re - level the house over the top of the existing stumps because of the magnitude of the movement that had occurred.  He recommended that the Applicants to use the repa ir works as an opportunity to re - stump the entire house.