Home / Financial Firm (Unknown - Insurer) / Determination 359028
Determination 359028
Quality of insurer-arranged repairs, driveway and patio damage, and claims management
Summary
The applicants said repairs to their water-damaged home were defective and the FSP's contractors damaged the driveway and patio. AFCA rejected the driveway and patio damage claims, but ordered three certificates, a $500 payment, $1,500 non-financial loss compensation and reimbursement of an expert report.
The applicants did not establish that the FSP's contractors caused the driveway or patio damage, but the delay and substandard original repairs warranted compensation.
Issues
- Repairs or contractors primary · not upheld
“I am not satisfied, on the balance of probabilities, the claimed damage to the driveway was caused by the FSP's builder.”
- Delay secondary · upheld
“the failure to provide the certificates for over four months would further prolong the anxiety caused by the claim.”
- Third-party or outsourcing failure secondary · not upheld
“neither P nor the inspector were able to positively assert the claimed aggregate damage was caused by an act or omission of the FSP's builders.”
Subjects and remedies
home or building damagepay compensationpay non financial lossprovide documents
Text of the determination
Determination
Case No: 359028 Determination Page 1 of 8
Case number: 359028 17 February 2016
1 Overview
1.1 Dispute
The Applicants’ home was damaged by water. The Applicants lodged a claim on 20
March 2013 under a home building and contents insurance policy (“the policy”) with
the Financial Service Provider (“FSP”).
The FSP accepted the claim and arranged repairs. The repairs required rectification.
The Applicants say there are still faults with the repairs/rectifications which the FSP
should remedy.
The FSP says it has taken every reasonable step to appropriately manage the
repairs and rectifications and address all concerns raised by the Applicants.
The Applicants also complain about the FSP’s claims management and the conduct
of its contractors.
1.2 Issues and key findings
Has the FSP has fulfilled its policy obligations?
The FSP has fulfilled its policy obligations as in order to resolve outstanding issues,
the parties agreed an independent inspection of the property would take place. The
Applicants’ engineer P conducted the independent inspection with the Applicants,
discussed the issues and reviewed extensive correspondence and concluded the
remedial work as now presented is satisfactory.
To carry the remedial work to an acceptable conclusion, P recommended three
certificates/warranties were to be obtained by the FSP. The FSP agreed to provide
the three certificates to the Applicants.
The material provided does not establish the driveway was damaged by the FSP’s
builders. Neither P nor the inspector from the Office of Fair Trading asserted the
damage was so caused.
As for the recent claim concerning the tiles and surface of the patio, P’s opinion is
insufficiently persuasive to establish on the balance of probabilities the claimed
damage to the patio was caused by the FSP’s poor repairs.
However, as the FSP’s builder admits some minor work is required, it is fair in all the
circumstances the FSP pay to the Applicants $500.
Case No: 359028 Determination Page 2 of 8
Are the Applicants entitled to compensation?
The Applicants are entitled to $1,500 compensation as there was an unusual amount
of physical inconvenience and time taken to resolve the dispute.
Due to the nature of the dispute, the Applicants genuinely required expert assistance
and it is fair in all the circumstances the FSP pay the Applicants the cost of the
January 2016 report from P.
1.3 Determination
This Determination is substantially in favour of the FSP.
If the Applicants accept this Determination, within seven days of notification of
acceptance, the FSP is to:
provide to the Applicants the three certificates/warranties referred to in P’s
report dated 23 October 2016
pay the Applicants $500 to repair the tiles and surface of the patio
pay the Applicants $1,500 compensation
reimburse the Applicants the cost of the January 2016 report from P upon proof
of the cost of the report.
Case No: 359028 Determination Page 3 of 8
2 Reasons for Determination
2.1 Has the FSP fulfilled its policy obligations?
The Applicants’ expert agreed the remedial work is now satisfactory
The Applicants made a number of complaints regarding the quality of work
undertaken by the FSP’s contractors.
In order to resolve the complaints, the parties agreed on an independent inspection
of the insured property and repairs undertaken.
With the consent of the FSP, the independent inspection was conducted by an
engineer [P] selected by the Applicants. On 15 and 19 October 2015, P inspected the
insured property in the presence of the Applicants, discussed the issues with the
Applicants and reviewed extensive correspondence.
P concluded:
“…the remedial wo rk as now presented is satisfactory but with the following
reservations ..”
The FSP has agreed to provide three certificates
The reservations were regarding the provision of three certificates addressing the
issues of concern as discussed in P’s report dated 23 October 2016.
P concluded:
“it is recommended that to carry the remedial work to an acceptable conclusion to (the
Applicants), the certificates and warranty noted above be obtained by (the FSP) and
forwarded to (the Applicants) in the near future.”
The FSP reviewed the report and agreed to provide the three certificates.
In view of the Applicants’ expert report and the FSP’s response, once the three
certificates are provided, I am satisfied the FSP has fulfilled its obligations pursuant
to the terms of the policy.
However, two further items remain in dispute. One is claimed damage to driveway,
and the other is a recent complaint regarding the patio.
Information provided does not establish driveway damaged by FSP’s builders
The Applicants claim the FSP’s contractors damaged the driveway while undertaking
repairs. They contend stones were chipped or dislodged when dragging timber,
scaffolding etc. and when removing cement grout, which had been allowed to dry and
not cleaned off.
Photographs of the driveway have been provided to the Service. In correspondence,
there is reference to a driveway repair quote in the amount of $7,815 but the quote
has not been provided to the Service.
The FSP says the driveway is exposed aggregate comprising of loose stones. It says
its tradesmen have not performed any works to the driveway nor have they damaged
Case No: 359028 Determination Page 4 of 8
the driveway. The FSP also says the photographs clearly depict no damage to the
driveway.
An inspector from the Office of Fair Trading inspected the premises 29 April 2015.
The Inspector reported:
“I am unable to reasonably determine from a visual inspection alone that the decorat ive
exposed aggregate driveway finish has been damaged due to an act or omission by
(the FSP’s builder).”
The FSP’s internal building consultant Z commented:
“driveway was found in existing condition on my first site visit 3 April 2014, the issue
with the driveway is that when originally poured the concrete has washed out too much
sand and cement from the around the aggregates.”
Although the Applicants’ engineer P inspected the property on two occasions with the
Applicants and says he reviewed extensive correspondence, he made no conclusive
observation about the cause of the claimed damage to the driveway.
Whatever the FSP says the photographic evidence shows, both P and the inspector
from the Office of Fair Trading actually inspected the driveway. Although they do not
comment on the specific contention of Z, neither P nor the inspector were able to
positively assert the claimed aggregate damage was caused by an act or omission of
the FSP’s builders.
On the information provided, I am not satisfied, on the balance of probabilities, the
claimed damage to the driveway was caused by the FSP’s builder.
P’s opinion about the tiles insufficiently persuasive
In January 2016, the Applicants made complaints about cracked tiles on the patio,
and said, after water laid on the patio and dried, white stains appeared.
The Applicants provided photographs and a further report from their engineer, P.
The Applicants’ photographs show what looks like cracks or scratches and white
marks near the grouting.
A civil engineer from P provided a further report and photographs after inspecting the
deck on 7 January 2016 with the female Applicant.
Although it is contended when the deck is wet, and when water reaches the edge of
the slab it flows slightly over the surface of the column, P concluded this “ might be
due to poor sealing between the deck and the column”. However, P noted no visible
crack on the sealing.
As for the white residue on the face and surface of the deck, he said this “ might be
due to efflorescence’ which can “ possibly be originated from the grout under the tile”
and “water possibly penetrates to the deck from the top surface of the deck when the
deck is subject to rainfall”.
P noted two close cracks on the surface of the deck tiles about 10cm long. He
described the cr acks as “quite superficial”.
P also reviewed photographs taken by the Applicants the day after he inspected the
deck. He said what was observed “ might be due to hypermobility of the deck surface”
Case No: 359028 Determination Page 5 of 8
and the joint between the tiles or the joint between the tiles and the walls “ might not
be adequately sealed.” (All words in italics are my emphasis).
He concluded the issues do not risk the structural performance of the deck.
The FSP arranged for an inspection by the builder R. R reported to the FSP that:
the white staining marks to the grout did not look like efflorescence nor was it
coming up through the grout. R said it used a particular epoxy grout for the tiling
and the tiler and water proofer both said efflorescence cannot come up through
this kind of grout. The only way it can do so is if the grout is cracked. R said the
grout was not cracked. R thought it was possible, during storms, high wind had
brought rain and salt from a nearby salt lake. R said the problem could resolved
with cleaning.
as for the white staining to the side of the balcony and column, R located a
piece of aluminum grey angle which was placed there to divert the water (R said
this was done at the Applicants’ request). He noted the joint between the bottom
of the angle and the tile had not been grouted or siliconed. He agreed a white
run-off (possibly from glue) is running down the face of the tile and column. R
offered to seal the joint. R said the female Applicant refused his offer.
R said there were no cracks to the tiles but “superfic ial marks caused by
scratching.” He says the scratches were not there at the time of completion, are
new and not caused by R.
The Applicants made further submissions regarding R’s comments. They say:
the epoxy grout was only used after the grout had to be removed because of
uneven colour. They say the tiler told them the grout is not easy to apply
correctly and if all the grout is not removed it is possible for white efflorescence
to appear. Further photographs were provided.
R advised he would arrange for the tiler to inspect and so the Applicants
expected the tiler (not R) to make repairs
in earlier heavy rain and wind, there was no issue with salt
P noted cracks (not scratches) in the tiles.
The Applicants also noted a rivet is needed to replace a loose bannister.
Fair in all the circumstances the FSP pay the Applicants $500
I have carefully considered all the material provided. The opinion of P is not
sufficiently compelling to establish on the balance of probabilities the claimed
damage to the pa tio was caused by poor repairs undertaken by the FSP’s
contractors. P noted no visible cracks in the sealing and merely contends it is
“possible” or the repairs “might” be responsible.
Both R and the Applicants make contentions about the tiler’s opinion b ut neither party
has provided direct information from the tiler.
Having considered all information, I am satisfied it is fair in all the circumstances the
FSP pay to the Applicants $500 in relation to this aspect of the claim.
I consider this payment is fair in all the circumstances as:
P’s opinion is insufficiently compelling to support the Applicants’ contentions
Case No: 359028 Determination Page 6 of 8
the first engineer from P noted none of these new issues despite 2 inspections
in October 2015
photographs do not show the grout is cracked
R accepts a joint needs sealing
i f there are cracks to the tiles, they are described by P as “superficial” and
issues arose sometime after the patio work was completed
the FSP has not refuted a rivet is needed to replace a loose bannister
the FSP has stated it will provide a warranty certificate of water proof
membrane adequacy
the relationship between the Applicants and the builder has become fraught and
a cash settlement obviates the need for ongoing contact.
2.2 Are the Applicants entitled to compensation?
Unusual time taken to resolve the claim
The Applicants complain about the FSP’s claims management and unnecessary
delays and disruption caused by the FSP’s builder’s conduct . They say because of
the time taken to complete and rectify repairs many months passed before they slept
in their own bedroom. They say their son left home because of the ructions caused
by the repairs.
Because of the claims process, the female Applicant claims stress and the male
Applicant claims lost wages and lost annual leave.
The female Applicant also makes serious allegations including theft and harassment.
However, no details of the alleged abuses or substantiation of these serious
allegations have been provided. The FSP strongly refutes the allegations of abuse
and harassment.
The FSP says it continued to accommodate the concerns of the Applicants and held
numerous on-site meetings to review the works done. They say numerous items
were revisited with the aim to address the Applicants’ concerns. The FSP says it took
every reasonable step to properly manage rectification and address all issues.
The Service’s Terms of Reference enable the Service to compensate Applicant s for
non-financial loss (capped at $3,000).
Compensation for non-financial loss is limited. FOS may decide an FSP should
compensate an Applicant for such loss only where there has been an unusual
amount of physical inconvenience, time taken to resolve a situation, or interference
wit h the Applicant’s expectation of enjoyment or peace of mind.
The Service takes a conservative approach to compensation for non-financial loss.
I have carefully considered all the material provided. I acknowledge the parties
remained in dispute about many items and issues and this caused delay. I also
acknowledge the FSP attempted to ameliorate the situation by assigning one staff
member to deal with the Applicants.
Case No: 359028 Determination Page 7 of 8
Although by the time the Applicants’ engineer (P) inspected the premises in October
2015 most issues were resolved, nonetheless, by then, the claim had been ongoing
since March 2013.
Further, I note the FSP has still not provided the certificates referred to by P in his
first report even though it indicated the certificates would be provided in its letter to
the Service dated 28 October 2015.
Because of the time which has expired since the claim was made, and the fact the
original repairs were not up to standard and required rectification, which caused
delay, I consider there has been an unusual amount of physical inconvenience and
time taken to resolve the dispute which would have interfered with the Applicants’
expectation of enjoyment or peace of mind.
Furthermore, the failure to provide the certificates for over four months would further
prolong the anxiety caused by the claim.
I consider it is fair in all the circumstances the FSP pay to the Applicants $1,500
compensation for non-financial loss.
Applicants genuinely required expert assistance from P
The engineer P was engaged on two occasions.
On the first occasion, the FSP paid P’s fee for report. On the second occasion, the
Applicants was liable for P’s fee for the report
An Applicant can seek contribution (capped at $3,000) from an FSP to costs the
Applicant incurred in the course of the dispute.
I consider it is fair in the circumstances of this dispute the FSP pay the cost of the
January 2016 report from P. Due to the nature of the dispute, the Applicants
genuinely required expert assistance.
The FSP is to pay the Applicants for P’s J anuary 2016 report. The Applicants are to
provide the FSP with P’s invoice for the report or proof of payment by the Applicants
to P for the January 2016 report.
Case No: 359028 Determination Page 8 of 8
3 Supporting information
3.1 FOS Approach
As advised to the parties, FOS has considered it appropriate to expedite this dispute
in accordance with the Operational Guidelines to the FOS Terms of Reference, due
to the nature of the dispute. Accordingly, this dispute has not been the subject of a
FOS Recommendation and has proceeded directly to Determination.
There has been a full exchange of all material information relied on for the purposes
of this Determination and each party has had the opportunity to address any issues
raised by the other. All of the material provided by the parties has been reviewed and
considered for the purposes of this Determination.
This dispute has been decided on its merits, having regard to the relevant law, good
industry practice, codes of practice and previous Financial Ombudsman Service
(FOS) decisions.
While the parties have raised numerous issues in their submissions, for the purposes
of this Determination, commentary has been restricted to those issues considered
directly relevant to the outcome only.
It is an accepted principle of general insurance law that an insured bears the onus to
establish on the balance of probabilities that they have suffered a loss caused by an
event to which the policy responds. This is known as a prima facie claim. Once so
established, the onus shifts to the insurer to prove on the balance of probabilities that
an exclusion applies if it seeks to deny or limit its liability for the loss.
3.2 Relevant expert material and other material
Parties’ submissions, emails and photographs .
Correspondence between the parties.
FSP’s storm service report dated 28 February 2015.
FSP’s report, photographs and scope of works prepared by C March 2013 .
Statutory Declaration from FSP’s builder sworn 10 June 2014 .
Scope of Works provided by FSP’s builder R .
R’s contract 22 December 2014 .
Site inspection report from FSP’s engineer dated 19 January 2015 .
Fair Trading complaint inspection advice dated 29 April 2015.
Letter and report from Fair Trading Office dated 28 July 2015.
Reports from Applicants’ consulting engineer (P) dated 23 October 2015 and
January 2016.