Cash settlement of fire and stormwater damage; liability for claim-related delays
Text of the determination
Determination
General Insurance - Domestic Insurance - Home Building - FSP Decision - Claim
Amount - Service - Service Quality
Determination
Case No: 358301 Determination Page 1 of 9
Case number : 358301 6 January 2015
1 Overview
1.1 Dispute
The Applicants lodged a claim under their landlord insurance policy with the
Financial Services Provider (FSP) for damage to their investment property
following a fire in September 2011.
The FSP accepted the claim and elected to repair the property. However, the
repairs were delayed for several years, during which time the property sustained
further damage. The bulk of the repairs have now been completed and the FSP
has cash settled the Applicants for some of the remaining damage.
The Applicants are dissatisfied with the cash settlement and want the FSP to
arrange for the necessary repairs instead. They also seek cover for certain
additional damage to the property following the fire, which they say has been
caused by the manner in which the repairs were carried out.
1.2 Issues and key findings
Is the FSP liable for the disputed items of damage?
The available information establishes that the cracking and movement damage to
the front part of the property was caused by stormwater run-off entering the sub-
floor area while the repairs remained uncompleted. The FSP is liable for this and
other damage which has occurred due to the delay in completing the repairs.
How should the claim be settled?
The FSP is required to repair the outstanding damage for which it is liable.
Are the Applicants entitled to compensation?
The circumstances do not justify the payment of compensation, having regard to
the loss of rent benefits paid by the FSP over the course of the claim.
1.3 Determination
This Determination is substantially in favour of the Applicants.
The FSP is to make arrangements to repair the outstanding damage to the
property for which it is liable under this Determination, in accordance with the
process outlined in section 2.2 below (subject to the Applicants refunding the cash
settlement for internal repairs paid by the FSP).
Case No: 358301 Determination Page 2 of 9
2 Reasons for Determination
2.1 Is the FSP liable for the disputed items of damage?
FSP’s liab ility depends on cause of damage
The Applicants’ policy provides cover for loss or damage caused by the events
listed in the policy (including fire), subject to the exclusions and conditions set out
in the policy.
Accordingly, the FSP is only responsible for repairing the disputed damage if the
damage was caused by the fire in September 2011 or by the actions of the FSP in
carrying out the claim-related repairs (including any delays which occurred during
the repair process).
Parties dispute cause of additional damage to front part of house
The FSP accepts that the fire (which badly damaged the rear extension) also
caused smoke and soot damage to the front part of the house. The repair of this
damage was included in the original scope of works prepared by the FSP’s
assessor (CC) in September 2011.
The FSP subsequently accepted liability for removing graffiti throughout the
house, which had been caused by trespassers entering the property while it was
undergoing repairs. The repair of this damage (in addition to the smoke damage)
was included in the revised scope of works prepared by the FSP’s building
consultant (S) in September 2013.
However, following a further assessment of the property carried out in March
2014, the FSP advised the Applicants that its builders would be unable to carry
out the internal repairs, due to various pre -existing maintenance issues identified
in the assessor’s report. These issues included cracking damage, rot and rising
damp affecting the ceilings, walls and floors. The FSP cash settled the Applicants
for $4,465.11 for the cost of the internal repairs.
The Applicants were unhappy with the cash settlement, as they wanted the FSP
to arrange for the repairs. They also claimed that the issues identified by the FSP
were not pre-existing m aintenance issues, but had been caused by the FSP’s
delay in carrying out the repairs.
Additional damage was caused by stormwater run-off
The Panel has carefully reviewed the materials provided by the parties, including
the various contractors ’ reports and the photographs contained therein.
Having done so, the Panel is satisfied that, on the balance of probabilities, the
cracking and movement damage identified by the FSP’s assessor in March 2014
was caused by stormwater run-off entering the sub-floor area as a result of the
manner in which the repairs were carried out.
The Applicants say that, when the FSP’s builders demolished the rear extension
in 2012, they also removed the gutter at the rear of the front part of the property.
Case No: 358301 Determination Page 3 of 9
They say that this caused water from the roof and the rear yard to enter the sub -
floor of the property during periods of heavy rainfall, until the extension was finally
rebuilt in late 2014.
The FSP’s leak detection specialist (A) who attended the property in connection
with a storm claim lodged by the Applicants in July 2014 confirmed that, due to
the absence of guttering, stormwater run-off from the roof was saturating the soil
at the rear of the property and running through to the sub-floor.
The builder (T) appointed by the FSP to determine the cause of the cracking and
movement damage concluded that it had been caused by water entering the sub-
floor. T noted that the area of the property where the rear extension had been
demolished sloped back towards the house, allowing water to flow into the sub-
floor. T witnessed this directly, as it was raining at the time of his inspection.
In his report, T stated that the cracking damage to the walls and ceilings and the
bounciness of the floors was consistent with the damage having been caused by
stormwater flowing under the sub-floor. However, he recommended that an
engineer be appointed to confirm this and to provide a scope of works for the
necessary repairs. T noted that it might be appropriate to cut inspection holes in
the sub-floor as part of such further investigations (as the floor was too low to
allow direct access to the sub-floor area.
The engineer (F) subsequently appointed by the FSP disagreed with T’s findings
and considered that the damage had occurred over a long period of time and had
been caused by one or more of the following factors:
long term differential foundation movements due to changes in the moisture
content of the highly reactive foundation soils. As a result of climatic
conditions and/or poor ventilation of the sub-floor area
the fact that the footings of the house were likely to be founded at relatively
shallow depths and
possible decay of the timber bearers and joists due to expected insufficient
clearance between the timber floor and the sub-floor soil.
The Panel recognises that, as an engineer, F is appropriately qualified to
determine the cause of the cracking or movement damage. However, the Panel
has the following concerns about the basis for her conclusions in the present
case:
F does not appear to have personally observed the sub-floor area, either
directly or by way of the investigations suggested by T
in her report, F acknowledges that she had not been provided with detailed
information about the Applicants’ claim for fire damage or the claim -related
repairs carried out at the property. In the context of the current claim, this
information would appear to be highly relevant
by the time F inspected the property in September 2014, the extension had
been largely rebuilt. Further, it appears that the weather was fine at the time of
F’s inspection and therefore she was unable to witness stormwater flowing
under the house and
while F noted that the cracking and movement damage was predominantly
located at the front of the house (away from the area where stormwater was
Case No: 358301 Determination Page 4 of 9
entering the sub-floor), she did not carry out any further investigations to
confirm whether the water was ultimately pooling at the front of the house.
In light of the above, the Panel considers that F’s report was based primarily on
general assumptions about the likely cause of cracking damage in a property
such as the Applicants, without sufficient regard to the particular events which had
affected the property since the fire in September 2011.
The Panel notes that extensive cracking and movement damage is not evident in
the photographs taken by the FSP’s contractors shortly after the fire.
Further, neither of the builders (JL and P) who were (at different times) authorised
by the FSP to carry out the repairs advised that they would be unable to complete
the repairs to the front section of the property due to pre-existing cracking and
movement issues. This suggests that the bulk of the cracking and movement
damage occurred after the fire, rather than over an extended period of time as
suggested by the FSP’s engineer (F).
The report prepared by the FSP’s assessor (MB) in March 2014 refers to the
presence of rising damp in the walls. However, this issue had not previously been
identified by the FSP’s contractors and the FSP has not provi ded any further
expert opinion in support of MB’s findings.
In these circumstances, to the extent that any dampness is present, the Panel
considers that this is most likely associated with the saturation of the soil under
the property due to the effects of stormwater run-off.
FSP is liable for additional damage caused by stormwater run-off
The stormwater run-off affecting the sub-floor area has occurred as a result of the
extended delays which occurred between the demolition of the rear extension
(and the removal of the gutters at the rear of the house) in 2012 and the
rebuilding of the extension in late 2014.
It is clear from the FSP’s claim records that these delays were in part due to the
actions of the builder initially appointed to carry out the repairs. However, they
were also attributable to the FSP’s attempts to clarify whether a permit (if
required) had been obtained for the rear extension when it was originally
constructed so that it could determine the extent of its liability for repairing or
rebuilding the extension.
The FSP ultimately accepted that it was liable for rebuilding the extension to
current standards, given that the Applicants had replacement cover under their
policy and the council was unable to confirm whether or not a permit had been
issued.
In these circumstances, the Panel is satisfied that the additional damage to the
front section of the property has been caused by the manner in which the FSP
managed the repair process. Accordingly, the FSP is liable for this damage.
Case No: 358301 Determination Page 5 of 9
FSP is liable for removal of graffiti from outside of property
The FSP has cash settled the Applicants for the internal repairs to the front
section of the property, including the removal of graffiti. However, it is unclear
whether the FSP also accepted liability for the costs of removing graffiti from the
outside of the property.
The Panel is satisfied that the graffiti damage to the outside of the property was
primarily due to the property being left in a clearly damaged and unoccupied state
for an extended period of time, while the FSP sought to arrange the repairs. In
these circumstances, the Panel considers that the FSP is liable for the costs of
removing graffiti from the outside of the property.
Revised scope of works sets out repairs to smoke damaged items
The Applicants say that the FSP has not replaced smoke damaged doors,
windows and lights in the front part of the house. They also say that the linoleum
should be replaced, rather than cleaned as proposed by the FSP.
The revised scope of works prep ared by the FSP’s building consultant (S) in
September 2013 set out the necessary repairs to the front part of the house
required to address the smoke damage. S’s scope of works indicates that not all
of the items referred to by the Applicants needed to be replaced and some of the
damage could be effectively addressed by cleaning and/or repainting the relevant
items.
The Panel accepts that S’s scope of works represents a reasonable assessment
of the works required to address the smoke damage. Under the terms of the
policy, the FSP is entitled to attempt to restore damaged items, rather than
replacing them in their entirety. However, to the extent that the measures
proposed are inadequate to restore the damaged items, the FSP is required to
replace them.
Damage to fire mantle occurred during repair process
The Applicants say that the fire mantle in the master bedroom was damaged by
trespassers.
The photographs included in the report prepared by the FSP’s assessor (MB) in
March 2014 confirm that the top and bottom sections of the mantle have
separated . The assessor reported that this damage was due to poor installation of
the fire mantle.
Photographs taken by one of the FSP’s builders (B) in October 2011 indicated
that the mantle was not damaged at that time. Accordingly, it appears that the
damage has occurred at some stage during the lengthy repair process.
In these circumstances, the Panel is satisfied that, on the balance of probabilities,
the damage to the mantle was either caused by the trespassers who vandalised
the property, or has occurred due to the movement in the property as a result of
water entering the sub-floor area during the repairs process. In either case, the
FSP is liable for this damage.
Case No: 358301 Determination Page 6 of 9
FSP has accepted liability for dishwasher
In their recent submissions, the Applicants say that the FSP is yet to agree on
replacing the dishwasher which was damaged by the fire.
In its Notice of Response, the FSP confirmed that it had agreed to accept the
Applicants’ claim for the damaged dishwasher. Accordingly, the FSP is liable for
the replacement of this item.
FSP is not liable for damage to front brick wall
The Applicants say that the front brick wall of the property has been damaged by
trespassers following the fire.
However, photographs of the front brick wall taken shortly after the fire indicate
that it was already cracked at that time. While the condition of the font brick wall
has worsened over the following years, this appears consistent with gradual
deterioration of the existing damage over time.
There is no independent information to establish that, on the balance of
probabilities, the additional damage to the brick wall was caused by trespassers
or by an insured event under the policy. Accordingly, the FSP is not liable for this
damage.
2.2 How should the claim be settled?
FSP is liable for additional damage related to internal repairs
As outlined above, the rebuilding of the rear extension has been largely
completed. The FSP has also cash settled the Applicants for $4,465.11 for the
cost of the internal repairs.
The Applicants say that the cash settlement is insufficient to repair all of the
internal damage and want the FSP to arrange for the necessary repairs to the
property.
The cash settlement paid by the FSP primarily related to the repair of the smoke
and soot damage and the removal of graffiti in the front part of the house. This
was the only damage to the front part of the house for which the FSP considered
it was liable.
The FSP took the view that it was entitled to cash settle the Applicants for the cost
of repairing this damage due to pre -existing issues with the property which meant
that its builders would be unable to provide a lifetime warranty of the repairs.
However, for the reasons outlined above, the Panel has found tha t the FSP’s
liability extends to other items of damage to the property including cracking and
movement damage to the property caused by stormwater run-off entering the sub-
floor area. These were the primary issues identified by the FSP as preventing its
builders from completing the necessary repairs.
Case No: 358301 Determination Page 7 of 9
As the Panel has found that the FSP is also liable for this damage, it is unable to
rely on these issues as a basis for cash settling the Applicants for the internal
repairs.
FSP is required to repair outstanding damage for which it is liable
Under the terms of the Applicants’ policy, the FSP may decide to settle a claim by
repairing the damage to the Applicants’ home or paying the A pplicants the cost of
repairing the damage. It is clear from the terms of the policy that it is the FSP (and
not the Applicants) who has the discretion to decide how to settle the Applicants’
claim.
However, once an insurer makes an election to settle a claim by repairing the
damaged property, it is ordinarily required to complete the repairs in accordance
with the terms of the policy. An insurer cannot subsequently elect to cash settle
the insured (in lieu of completing the repairs), unless the circumstances of the
claim are such that it is impracticable for the insurer to complete the repairs.
In the current case, the FSP initially elected to arrange for the repair of the
Applicants’ property following the fire and authorised its builder to carry out the
necessary repairs.
At various stages over the course of the claim, the FSP has sought to cash settle
the Applicants for the cost of all or part of the cost of the repairs, due to at various
times and for various reasons over the course of the claim. However, the
Applicants have consistently expressed their preference for the FSP to arrange
for the repairs.
In these circumstances, the Panel considers it appropriate that the FSP be
required to repair the outstanding damage to the property for which the Panel has
found it to be liable (as outlined above).
Accordingly, the FSP should:
appoint a building consultant to prepare a revised scope of works for the
necessary repairs to the property, incorporating all of the items of damage for
which the FSP is liable in accordance with this Determination and
arrange for the repairs set out in the revised scope of works to be completed
by an appropriately qualified builder within a reasonable timeframe.
The FSP’s obligations to repair the internal smoke damage and remove the graffiti
are subject to the Applicants refunding to the FSP the cash settlement of
$4,465.11 previously paid to them in respect of these repairs.
2.3 Are the Applicants entitled to compensation?
Applicants are not entitled to additional compensation
The Applicants seek compensation for financial and non-financial losses incurred
as a result of the manner in which the FSP has managed their claim. They say
that the repair process has been prolonged and difficult, and the FSP has
provided conflicting information in relation to their claim.
Case No: 358301 Determination Page 8 of 9
The Panel acknowledges that it has taken an unusually long time to resolve the
Applicants’ claim. Having reviewed the claim history, the Panel considers that
some of these delays were attributable to the actions of the FSP or its contractors.
However, the Panel also accepts that the Applicants’ claim had certain inherent
difficulties due to the age of the insured property (over 100 years) and the fact
that the rear extension had been built in a manner which did not comply with
current building regulations, such that it needed to be entirely demo lished and
rebuilt.
The Panel notes that the FSP has paid the Applicants loss of rent benefits for a
period of more than three years following the fire in September 2011, which
significantly exceeds their entitlement under the policy.
In light of the payment of loss of rent benefits by the FSP, the Panel considers
that the circumstances do not justify the award of additional compensation.
Case No: 358301 Determination Page 9 of 9
3 Supporting information
3.1 FOS approach to this dispute
This dispute has not been the subject of a FOS Recommendation. Due to the
nature of the dispute, it has been referred directly to a Panel for Determination, in
line with the Operational Guidelines to the FOS Terms of Reference. The Panel
consists of an Ombudsman and two representatives with consumer and insurance
experience.
The Panel has decided this case on its merits, having regard to the relevant law,
good industry practice, codes of practice and previous Financial Ombudsman
Service (FOS) decisions.
There has been a full exchange of all material information relied on for the
purposes of this Determination and each party has had the opportunity to address
any issues raised by the other.
The Panel has reviewed and considered all of the material provided by the
parties. While the parties have raised a number of issues in their submissions, for
the purposes of this Determination the Panel has restricted its commentary to
those issues which it considers directly relevant to the outcome only.