Home / Financial Firm (Unknown - Credit) / Determination 358266
Determination 358266
Alleged FSP direction to amend building contract (misleading product/service information) and legal costs claim
Summary
The borrowers claimed the FSP directed changes to their building contract that increased their obligations to the builder, seeking reimbursement of legal costs, and that it failed to assist them in financial difficulty. AFCA found the FSP was not liable for the contract changes or legal costs and had complied with its hardship obligations, so no compensation was awarded.
The complainants did not establish that the FSP directed the contract changes, and the FSP made genuine hardship assistance offers consistent with the Code of Banking Practice.
Issues
- Misleading conduct primary · not upheld
“The information does not support a finding that the FSP specifically directed where the words by owner were to be inserted in the Building Contract.”
- Financial difficulty assistance secondary · not upheld
“In these circumstances, the FSP has complied with its obligations to the Applicants as customers experiencing financial difficulty.”
Subjects and remedies
financial hardshipno remedy
Text of the determination
Determination
Credit - Consumer Credit - Construction Loans - Disclosure - Misleading
product/service information
Determination
Credit - Consumer Credit - Construction Loans - Disclosure - Misleading
product/service information
Case number : 358266 15 May 2015
1 Overview
1.1 Dispute
In May 2012, the Applicant, her husband and her son (the borrowers) applied to
the FSP for a residential loan. The Applicant claims:
at the time of applying for the loan she submitted a building contract (the
Building Contract) and building tender to the FSP, who advised her to make
changes to the Building Contract , in particular to inset the term “by owner” in
the tender accompanying the contract.
as a result of the changes made, the obligations of the borrowers under the
Building Contract increased
this led to a dispute between the borrowers and the builder lodged with the
Consumer Trader & Tenancy Tribunal (Tribunal Proceedings).
The Applicants seek reimbursement of legal costs incurred in connection with the
Proceedings.
1.2 Issues and key findings
Is the FSP liable for any changes made to the Building Contract?
The FSP is not liable for changes to the Building Contract. The FSP may have
directed that the words “by owner” were to be inserted in the building contract to
clarify the parties‟ responsibilities.
However there is not sufficient information to show, and it is unlikely that, the FSP
would have made specific directions as to which items in the Building Contract
were to be completed “by owner”. The FSP would not have been in a position to
do so and would have no interest in making such a specific direction.
Is the FSP liable for the borrowers’ legal costs?
Because the FSP is not liable for the changes made to the Building Contract, the
borrowers are not entitled to reimbursement of their legal costs.
Did the FSP comply with its obligations to the borrowers in respect of
financial difficulty?
Case No: 358266 Determination Page 2 of 7
The FSP did not fail to assist the borrowers in their financial difficulty. The FSP
was not obliged to provide further funds to the Applicants.
1.3 Determination
This Determination is in favour of the FSP. No compensation is to be awarded.
Case No: 358266 Determination Page 3 of 7
2 Reasons for Determination
2.1 Were the findings in the Recommendation correct?
I have decided this case on its merits, having regard to the relevant law, good
industry practice, codes of practice and previous FOS decisions. I have taken into
account all the material submitted by the parties, both before and after the
Recommendation. I am satisfied that the documentation I have relied on has been
provided to both parties.
I am satisfied that the case manager‟s Recommendation dated 31 December
2014 contains an accurate summary of the dispute, the issues to be determined,
any applicable paragraphs of the Terms of Reference and any relevant law.
The Recommendation found that:
The FSP was not liable for the changes to the Building Contract as there was
insufficient information to determine what was discussed between the
borrowers and the FSP.
The FSP was not liable for the borrower ‟ s legal costs against the builder for the
Tribunal proceedings.
The FSP had complied with its financial difficulty obligations.
The FSP accepted the Recommendation. The Applicants rejected the
Recommendation on the basis that:
The FSP has not produced any proof that they did not advise the Applicants to
change the Building Contract.
The FSP has not explained why it only have the original contract without the
amended tender.
The A pplicant‟s obtained no benefit from amending the tender. This supports
the view that the amendment was proposed by the FSP.
The FSP officer, Ms R, pointed to various parts of the tender and told the
Applicant‟s to insert “by owner”.
The amended tender does not accord with the progress payment schedule
The FSP failed to give the Applicants a copy of its booklet “Guide to Residential
Building Loan” . This would have assisted the Applicants to protect their rights.
The FSP failed to assist the Applicants when in financial difficulty. The
Applicants were told that their application was refused because they were in
dispute with the FSP.
2.2 Is the FSP liable for any changes made to the Building Contract?
The FSP did tell the Applicants that the Building contract was too vague
The central aspect of the Applicants claim is that Ms R from the FSP specifically
instructed Mrs C to make certain changes to the Building Contract because it was
Case No: 358266 Determination Page 4 of 7
“ too vague ” . In particular Ms R pointed to various sections of the tender and
indicted that the words “by owner” should be inserted.
Ms R says that she did not instruct the Applicant to make any specific changes,
but did tell the Applicant that the Building Contract, in the form that it was in,
would not be accepted by the FSP‟s credit team. Mrs C w as told that all inclusions
must be set out in the contract and itemised.
In the course of the dispute two versions of the tender have been produced, both
dated 3 March 2012. The first contains five pages of items. The first page
contains the heading “Inclusions”. There is a seventh page headed “Exclusion
from this “Quotation”.
The second version is the same as the first except that the items listed on pages
2 and 3 relating to the bathroom, kitchen, laundry, bedrooms and „internals‟ now
have the heading “by owner”. In addition the exclusions listed on page seven are
now also h eaded “by owner”.
I also note that prior to the dispute being lodged with FOS, the FSP wrote to the
Applicants stating that Ms R did advise that sections of the building contract
needed to be amended by inserting the words “by owner”. The letter also note
that these words meant that these sections of the contract are completed after
practical completion and hand over by the builder at the Applicants ‟ cost.
A review of the Building contract shows that the contract price was $440,000, with
$430,000 budgeted to “Lock up” stage and $10,000 to “practical completion”.
There has been considerable debate between the Applicants and the builder as to
the extent to which the house was to be completed. The builder in the Tribunal
proceedings maintained that the house was to be built to “lock up” stage. That
proceeding related to whether:
the contract was to build to lock up stage,
that stage had been reached,
there were building defects.
The proceedings were settled by the parties.
I accept that there was a discussion between Mrs C and Ms R as to the form of
the contract and whether it was „too vague‟. In that regard it is likely that Ms R
wanted the Applicants to precisely specify what building works were to be
completed by the owner and those to be specified by the builder. It is also likely
that Ms R said to Mrs C that the words “by owner” needed to be inserted into
relevant parts of the contract. This is consistent with the subsequent dispute
between the bui lder and the Applicants which shows that there was no agreement
on this.
The information does not support a finding that the FSP specifically
directed where the words “by owner” were to be inserted in the Building
Contract
Mrs C says that Ms R pointed to various parts of the tender and told the
Applicant ‟s to insert “by owner”. Ms R denies going through the contract and
Case No: 358266 Determination Page 5 of 7
indicating specific changes. In addition it appears that the actual insertion of the
word “by owner” in the new version of the co ntract were made by the builder at a
later time. However Mrs C says that occurred due to Ms R “instructing me to tell
the builder that in order for it to be accepted it would need to include the words
“by owner” , to which then the builder had returned to my house with the new
tender and inserted the words “by owner” .
In the circumstances where there are conflicting recollections of what was said in
the discussion it is not possible for me to determine precisely what was said.
It may be that Ms R pointed to sections in the contract stating that those sections
needed to be amended to make clear which, if any items, were to be the
responsibility of the owner. Such conduct would have been appropriate. It would
then be a matter for the Applicants in consultation with the builder to agree, if that
had not already done so, on what items were included or excluded from the
building contract. It would be most unusual for the Ms R to seek to direct which
particular items were to be included as the FSP would have no interest in doing
so, and would not be in a position to do so.
The Applicants also point to the fact that the progress payments do not accord
with the amended tender. I agree that there are discrepancies in the amended
tender, the building contract and the progress payment schedule. However that
does not assist in determining what was said between Mrs C and Ms R. The
actual changes to the contract document were made by the builder – not the FSP.
The Applicant also says that the FSP is at fault as it failed to provide a copy of it
booklet “Guide to Residential Building Loan”. However the FSP is not the
Applicant‟s advisor and is under no obligation to provide guidance to the
Applicants about their negotiations with the builder. As such it is under no
obligation to provide this information.
2.3 Is the FSP liable for the borrowers’ legal costs?
The FSP has no liability for any changes to the Building Contract
Because the Applicant has not established that the FSP is liable for the changes
made to the Building Contract, the FSP ha s no liability for the borrowers‟ legal
costs.
In any event, as the Recommendation noted, the Applicant‟s claim for
reimbursement of legal costs must fail because:
a review of the pleadings indicates that the Proceedings related to issues
which included defective works, misrepresentation by the builder and the
builder removing items from the building tender. The Proceedings (and
associated costs) therefore extended to matters unrelated to the claims
against the FSP.
the Proceedings were settled on the parties entering into Terms of Settlement,
in which the borrowers and builder each agreed to dismiss the Proceedings
and to bear their own legal costs. The borrowers‟ liability for their legal costs is
therefore the result of a commercial decision by them.
Case No: 358266 Determination Page 6 of 7
The borrowers are therefore not entitled to be compensated for their legal costs.
2.4 Has the FSP complied with its obligations to the borrowers in
respect of financial difficulty?
The FSP has complied with its obligations
The FSP has obligations under the Code of Banking Practice to try to assist
customers experiencing financial difficulty.
The National Credit Code (formerly the UCCC), the Code of Banking Practice and
good industry practice place some obligation on a lender to work with a borrower
to try to help the borrower overcome their financial difficulties.
FOS takes the view that this obligation requires a lender to make a genuine
attempt to deal with a borrowe r‟s request for assistance due to financial hardship
and make reasonable efforts, in cooperation with the borrower, to reach a
commercially sensible resolution.
The Applicants in their initial dispute said that they were never offered financial
hardship assistance from the FSP until Mrs C got in contact with the hardship
team on 2 April 2014.
The following actions of both parties below show that the FSP gave genuine
consideration to the Applicant‟s request for hardship assistance, but the
borrowers were not willing to co-operate:
Date Action
21 February 2014 The Applicant contacted the FSP and it was determined that the
borrowers required financial assistance.
26 February 2014 An overdraft account was added to one of the borrower‟s accounts
in order for the arrears on the loan to be repaid when wages were
received. The FSP then offered to switch the loan account to
interest only for two years with a nil package fee.
7 March 2 014 T he FSP hardship team approved the assistance and the loan
contract was to be varied to interest only repayments at the
amount of $1,414 per month from 28 March 2014 . The letter of
variation was sent to the borrowers.
24 March 2014 The Applicant call ed the FSP to advise that her husband and her
son were not willing to sign the letter of variation. Therefore, the
offer of assistance was rejected by the FSP, due to no response.
The Applicants in their rejection of the Recommendation say that they contacted
the FSP on several occasions in 2013 and was told that as they were in dispute
with the FSP they could not obtain financial assistance until the dispute was
resolved. However, the Applicants also say that an officer of the FSP did send
Case No: 358266 Determination Page 7 of 7
documents to them but that he explained that this would be helpful for a short
period of time only. They also say that they not only needed adjustments to their
loan but further funds to pay their lawyers.
The FSP‟s telephone contact notes confirm that the Applicants d id call for
assistance in 2013. The Applicants complaint is that they were only offered short
term assistance and more particularly that they required significant additional
funds to finance proceedings against the builder. An FSP is not required to
necessarily provide long term assistance and an initial offer of short term
assistance is appropriate. In that context I note that further assistance was
subsequently offered as set out above.
The decision to provide further funds sought by the Applicants is a commercial
decision at the discretion of the FSP and cannot be reviewed by me. The FSP is
not obliged to agree to any such request.
In these circumstances, the FSP has complied with its obligations to the
Applicants as customers experiencing financial difficulty.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.