Text of the determination
Determination
General Insurance - Domestic Insurance - Home Building - FSP Decision - Denial of
claim
General Insurance - Domestic Insurance - Home Building - Service - Service quality
Determination
Case No: 357375 Determination Page 1 of 16
Case number : 357375 3 February 2015
1 Overview
1.1 Dispute
The Applicant lodged a claim for impact damage to her home that occurred on
4 April 2009 under a policy she held with the Financial Services Provider (FSP).
The repairs completed by the FSP following this were unsatisfactory.
Due to continual moisture ingress resulting predominantly from these repairs, it
was unsafe for the Applicant to remain in the property. As a result, she has been
placed in alternative accommodation whilst mould remedial action has been
undertaken at her home.
The claim remains ongoing, during which time the Applicant has remained in
alternative accommodation. Currently, the FSP has accepted liability for a portion
of the repairs sought by the Applicant.
The Applicant remains substantively dissatisfied with the claim and is seeking a
range of remedies, including:
$200,000 cash settlement for every year the claim has remained ongoing
the costs of rebuilding the home
medical expenses, and
legal costs.
This is underpinned by the negligent handling of the claim by the FSP and its
contractors.
1.2 Issues and key findings
Should the home be rebuilt?
The home should not be rebuilt as none of the expert evidence supports such a
requirement. Instead, the building claim should be resolved by way of cash
payment given the longstanding matter and issues with the concrete slab, which
the Applicant is required to address.
The cash settlement should be based on S’s scope of works as there is no
evidence refuting it accurately sets out what is required.
How should the Applicant’s contents claim be settled?
This should be settled with the assistance of the FSP’s expert, RS, as there i s
insufficient evidence discrediting their involvement to date. This is particularly
Case No: 357375 Determination Page 2 of 16
evident by their last report where the findings were supported by a mycologist and
building biologist.
RS is to review all of the items currently in storage and identify which are non-
salvageable, require further remediation or are suitable for return. This is to
ensure that items returned to the Applicant are suitable based on the current state
of affairs.
For the items that are non-salvageable or require further remediation, the FSP
should pay for the cost to dispose and replace same. With respect to the latter, it
is not fair in all the circumstances that the FSP has another opportunity to conduct
further remediation given it had ample opportunity to do so already.
Given this, the FSP is to continue to pay for storage costs until the later of the
following occurs:
the review is completed, or
six weeks have passed since the Applicant received confirmation that the
cash settlement for the building repairs is based on a builder prepared to do
the works privately for her.
Should the FSP pay an amount for non-financial loss?
The FSP should pay the maximum amount given the substantive levels of
inconvenience sustained by the Applicant as a result of the protracted claim. This
amounts to $933.25 after deducting the amount the FSP has already agreed to
pay ($2,066.75) towards this head of damage.
The amount the FSP paid towards the cost of installing an agricultural drain
should not be included in this deduction given it is a financial loss. Neither is the
Applicant able to split her claim to seek multiple awards for non-financial loss
given it has been the totality of her experience that has been considered.
Should the FSP pay an amount towards professional costs or consequential
financial loss?
The FSP is required to contribute $500 towards professional costs because:
There is an indication that the solicitors engaged by the Applicant added
some, but limited, value to this dispute .
There is, however, insufficient basis to substantiate the cost required to obtain
an independent medical report to review her health.
The FSP should pay $3,000 towards consequential financial loss given the
following:
The Applicant has likely incurred expenses greater than this during this
protracted claim.
This is the maximum amount FOS can award .
It is reasonable to conclude the amount of effort undertaken substantively
exceeded what was reasonably contemplated by the parties at the time the
contract was entered into.
Case No: 357375 Determination Page 3 of 16
1.3 Determination
I determine that this claim should be resolved in favour of the Applicant on the
following basis:
Issue Method of Resolution
Building Repairs The FSP pay a cash amount towards the building claim
based on a builder who has:
- prepared a quote pursuant to S’s scope of works, and
- is prepared to do the works privately for the Applicant.
If additional building costs are incurred by the Applicant that
were not addressed in S’s two scope of works, the FSP is to
pay for same upon production of invoices .
Alternative
accommodation
The FSP is to pay for alternative accommodation costs until
six weeks have passed since confirmation is provided to the
Applicant that she has received a cash settlement in line
with the “Method of Resolution” for building repairs
If additional costs are i ncurred by the Applicant that were
not addressed in S’s two scope of works, the FSP is to pay
for additional accommodation costs if these works increase
the time estimated to complete the repairs .
Contents Claim The FSP is to engage RS to review all of the items in
storage and provide a report as to whether they are non -
salvageable, require further remediation or are ready to be
returned .
The FSP is to pay for the costs of disposing and replacing
items that are non - salvageable or require further
remediat ion .
The FSP is to pay for storage costs until the later of the
following occurs:
- RS completes its review, or
- six weeks have passed since the Applicant received
confirmation her building claim is based on a builder
prepared to do the works privately .
The FSP is entitled to credit any amount already paid to the
Applicant in its cash settlement towards the second and
third bullet points above .
Non-Financial Loss The FSP is to pay an additional $933.25 .
Professional Costs The FSP is required to pay the am ount of $500 .
Consequential
Financial Loss
The FSP is to pay the Applicant $3,000, being the maximum
amount that FOS can award for this head of damage .
Case No: 357375 Determination Page 4 of 16
2 Reasons for Determination
I have decided this case on its merits, having regard to the relevant law, good
industry practice, codes of practice and previous Financial Ombudsman Service
(FOS) decisions. I have taken into account all the material submitted by the
parties. There has been a full exchange of all documents relied on to make this
Determination and each party has had the opportunity to address any issues
raised by the other.
This dispute has not been the subject of a FOS Recommendation. Due to its
nature, it was appropriate to proceed directly to a Determination in line with the
Operational Guidelines to the FOS Terms of Reference.
2.1 Should the home be rebuilt?
This decision will focus on the current state of affairs
This is a long, protracted claim. Both parties have provided an extensive amount
of information. Much of this sets out the backgro und to the claim which, given the
timeframe that has lapsed, explains the amount of information.
This background is useful given it explains why the dispute has reached the stage
it has. However, given the parties are unable to resolve their dispute, the focus of
this decision will be on substantive current issues. This will enable FOS to offer
parties an outcome that may resolve this longstanding dispute.
As a result, much of the background material or incidents referred to by the
parties may not be relevant given it involves issues that were either resolved or
evolved into what is now the current state of affairs.
Therefore, for the sake of brevity and conciseness, I will only refer to the relevant
material and/or events that underpin the substantive issues.
The FSP states its liability to the Applicant is limited to $36,468
The FSP has submitted that the extent of its liability is the sum of $36,468,
comprising of the following:
Basis Amount
Internal building repairs – Based on S’s scope of works $ 19,239.08
Carpet in the lounge room $ 2,194.17
Temporary accommodation – 1 additional month $ 6,500.00
Non - financial loss $ 2,066.75
Storage costs – 1 additional month $ 990.00
Cost to return contents $ 4,862.00
Cost of disposing non - salvageable contents $ 616.00
In line with this, the FSP sent the Applicant a cash payment for the above sum.
Case No: 357375 Determination Page 5 of 16
The Applicant has disputed this and is seeking a much higher sum, as set out in
section 1.1 of this Determination.
The available evidence does not support the Applicant’s position that the
home should be rebuilt
The Applicant is seeking the total cost to rebuild the home. However, the available
evidence does not support such a remedy.
First, and of most significance, are JWS’s reports. JWS is a senior forensic
structural engineer . In all of JWS’s reports, he identified minimal evidence of
distress throughout the home.
Although the Applicant has disputed the contents of his reports, I consider they
are persuasive for the following reasons:
JWS is the most appropriately qualified to provide an opinion on this
substantive issue
the reasoning provided is logical and plausible
it is unrefuted by any other expert opinion.
Second, based on RS’s most recent report, it appears the mould remediation
activities have been largely successful. The current issue appears to be the
continuing water ingress and the cause for same.
This is fairly isolated and does not, of itself, form a basis to conclude that the
home needs to be rebuilt. Particularly given:
the rectification associated with the previous poor roof repairs has been
completed – this appears to have addressed the source of much of the
moisture, and
JWS has set out a proposed method of repair that would address the
continued moisture ingress.
Third, there is no builder or expert that supports such a requirement.
The expert opinions support the water ingress is due to issues not related
to the claim or the poor repairs
Water ingress to the property appears to be still occurring. The latest report by
RS, along with the supporting reports from a mycologist and building biologist,
conclude that there is a rising damp or capillary action of moisture through the
concrete slab.
JL’s report dated 17 April 2014 supports this. Although the installation of an
agricultural drain on the south-west boundary assisted in reducing the moisture
ingress, there is still evidence of a high moisture content in the property.
JWS’s latest report concluded that the high moisture content could be due to a
number of factors. All of them are associated with non-claim related issues, such
as:
ineffective or absence of vapour barrier under the concrete slab;
inadequate protection of the footing system, and
reactive clay soils at the site.
Case No: 357375 Determination Page 6 of 16
The Applicant has disputed this, noting there were no pre-existing issues prior to
the impact damage in 2009. However, the weight of expert opinions do not
support her.
In particular, JWS has provided a number of reports addressing the fact the
impact only resulted in localised distress. Therefore, it could not be the source of
the current issues with the slab or the foundation.
JWS did acknowledge this impact resulted in water ingress through the roof and,
due to the poor repairs conducted, this significantly exacerbated the issue.
However, JWS categorically stated a number of times this impact did not result in
foundation movement and the issues with the roof have now been rectified.
Therefore, given the preponderance of expert opinions, I am not satisfied the
current moisture ingress is due to the impact damage from 2009 or the poor
repairs conducted.
Due to the proposed works required to be undertaken by the Applicant and
the longstanding matter, a cash settlement is appropriate
The FSP is seeking to cash settle this dispute rather than follow through with its
election to repair. This is due to the identification of the waterproof membrane
failure in the slab which, based on a scope of works provided by S, could result in
extensive costs of approximately $50,000.
The FSP has argued that given this, the ability to continue with the repair is
frustrated due to circumstances outside of its control.
Given the proposed rectification cost required to address the moisture ingress and
the Applicant’s position in this dispute, I agree that the FSP’s deci sion to repair
the property is likely to be frustrated. Further, given the protracted nature of this
dispute and the desire of both parties to achieve finality, a cash settlement would
be an appropriate method of settlement.
To ensure the cash settlement is appropriate, the amount must be based on
a builder prepared to do the works directly for the Applicant
The amount the FSP has allowed for the building repairs is based on a scope of
works provided by S.
S provided a second scope of works but this was to predominantly address the
works required to be undertaken by the Applicant to address the moisture ingress.
There is no evidence to refute S’s first scope of works accurately describes the
works required for the claim related repairs. Although the Applicant has disputed
it, she has provided no evidence from any other builder to support her position.
The FSP is relying on BBS’s quote which was based on S’s scope of works.
However, this amount ($19,239.08) was substantively lower than the amount
quoted by S ($28,948.12).
It is also unclear whether:
Case No: 357375 Determination Page 7 of 16
BBS or S were prepared to do the works directly for the Applicant for the
amounts quoted, and
the likelihood of further adjustments being identified as the works commenced.
Any cash settlement based on S’s first s cope of works must be sufficient to
ensure the Applicant can have the works done for the amount provided. The
discrepancy of the two quotes and the above queries raise concerns about the
feasibility of this.
To reduce the possibility of this emerging, particularly in light of this longstanding
claim, it is my opinion that it is fair in all the circumstances that the building aspect
of the dispute be settled in the following manner:
1. If either BBS or S are prepared to do the works privately for the Applicant,
then the cash settlement be based on the builder with the lowest quote.
2. If neither BBS nor S are prepared to do the works privately, the FSP must
source a builder who can and base a settlement on that sum.
3. If the Applicant does engage the builder that the FSP has based its cash
settlement on and additional costs are incurred that are claim related, the FSP
is to pay these sums upon production of invoices.
Alternative accommodation should continue to be paid until six weeks after
the Applicant receives confirmation about the cash settlement
I acknowledge alternative accommodation has been paid until the end of January
based on a monthly rental of $6,500. This includes the one month timeframe
estimated by the builders for the claim related repairs to be conducted.
However, until confirmation is received that a cash settlement is based on a
builder who is prepared to do the works privately for the Applicant, then it is fair in
all the circumstances that alternative accommodation costs continue to be paid
until this is resolved.
The reason is that it would be inequitable for the Applicant to have to fund her
own alternative accommodation when it is not clear that she could engage a
builder with the funds made available to complete the works set out by S.
Once it is confirmed that the Applicant has received a cash payment that would
enable her to engage a builder to complete the works set out by S, then the FSP
is liable to pay for six more weeks of alternative accommodation from that date.
This is based on allowing the Applicant two weeks to engage the builder and four
weeks for the builder to complete the works.
In the event additional costs are incurred that are claim related and this also
increases the time taken to complete the repairs, then the FSP is to pay for
additional alternative accommodation to account for this extra time.
Case No: 357375 Determination Page 8 of 16
2.2 How should the Applicant’s contents claim be settled?
The substantive issue in dispute is the items RS maintains can be restored
The Applicant has raised concerns about the contents to be returned to her and
the fact she will not accept anything that was affected by the mould or is
unusable.
There are numerous lists and reports provided by the parties regarding the
contents aspect of the claim. Although minimal information has been provided
about the current status of the contents claim.
However, the following does not appear in dispute between the parties:
Anything deemed to be non-salvageable by RS ought to be reimbursed by the
FSP. Therefore, if it has not done so already, the FSP is to ensure the
Applicant is adequately compensated for the replacement of any of these
items.
All costs charged by RS to clean or remediate the contents items is payable
by the FSP – based on the available information, it appears this has always
been the case.
It appears the substantive issue is the items RS maintains can be restored. The
Applicant has reservations about this, although it is unclear the extent of items
that fall within this category.
There are insufficient reasons to discredit RS’s i nvolvement
The Applicant has suggested that an independent company be engaged to
manage this process moving forwards. This is predominantly due to her lack of
trust in RS and the fact that, in her view, remedial measures have failed in the
home.
In the abs ence of any expert or other evidence to contradict RS’s assessment, I
do not accept the Applicant’s position. RS clearly has the appropriate expertise to
assess whether items that were to be restored have successfully been done so.
Further, I do not accept there is sufficient evidence to discredit RS’s involvement
given the following:
The failure of remedial measures to the home appears to be due to continued
moisture ingress rather than RS’s involvement. This has been corroborated by
JL and JWS and not contradicted by any other expert opinion.
RS has been prepared to declare items non-salvageable when appropriate.
RS’s analysis of the potential mould hazard and moisture ingress appears to
be well considered. This is evident in its last report which was supported by a
mycologist and building biologist.
Engaging a new expert will prolong this matter substantively given they will
need to be briefed on all the relevant information.
Case No: 357375 Determination Page 9 of 16
To ensure items are appropriately categorised before being returned, RS
should review all of the items currently in storage
I am conscious, however, that there should be a process to ensure that prior to
the items being returned to the Applicant, they have been assessed as being
properly remediated or in a suitable condition at the time.
It is unclear when the last assessment was undertaken. In my opi nion, given the
potential hazard involved in returning clothing with mould and the historical fact
that numerous items were identified as non-salvageable, it is fair in all the
circumstances that RS:
review all of the items, and
provide a report about their suitability following this Determination and prior to
their return.
In the event items are identified as non-salvageable or require further
remediation, then the FSP is to pay for the cost to dispose and replace same.
The FSP should not be given further opportunities to remediate items if they
are still in an unsuitable condition
There is an argument that the FSP be given an opportunity to address those
items that require further remediation. However, I cannot accept it is fair in all the
circumstances to allow this due to the following:
the length of this claim
the desire by the parties to achieve finality, and
the fact the FSP has had substantive opportunities to ensure all remedial
activities have been completed by this time.
To simply prolong the claim further to enable the FSP to reduce its costs is not, in
my opinion, an appropriate outcome in the context of the particular circumstances
of this case.
The FSP may be required to pay for additional storage costs following RS’s
review
Until all of the items have been catalogued and reviewed, it is fair in all the
circumstances that the FSP pay the cost of storage.
Once the review is completed, the FSP is to pay for additional storage costs. This
is conditional on six weeks not having passed since the FSP confirmed that a
cash settlement for the building repairs was based on a builder prepared to do the
works privately for the Applicant.
Once this six week period has lapsed or the review is completed, whichever is
later, the FSP is able to cease paying for storage costs.
Case No: 357375 Determination Page 10 of 16
2.3 Should the FSP pay an amount for non-financial loss?
Due to the substantive levels of inconvenience sustained, the Applicant
would normally be entitled to the maximum amount
Under paragraph 9.3(b)(i) of FOS’s Terms of Reference, I can award up to $3,000
per claim for non-financial loss if the Applicant has suffered an unusual degree or
extent of:
physical inconvenience
time taken to resolve the situation, or
interference with the Applicant’s expectation of enjoyment or peace of mind.
Due to the largely protracted nature of the claim, the poor initial repairs conducted
by the FSP and the fact she has been in alternative accommodation for years, it is
clear the Applicant has satisfied these thresholds.
It is also clear that due to the substantive levels of inconvenience sustained, the
Applicant would normally be entitled to the maximum amount.
The amount the FSP has contributed to non-financial loss is $2,066.75
The FSP has submitted that it provided a number of benefits that are technically
beyond the terms of the policy and should be accounted for under this head of
damage. These are:
installation of an agricultural drain – $3,033.69, and
the sum of $2,066.75 that it classed as non-financial loss in its latest
settlement sum.
I do not consider the installation of an agricultural drain should be considered. The
reason is that the cost to install an agricultural drain is, by its apparent nature, a
financial loss.
Therefore, the only amount that appears to have been provided to the Applicant
that can be associated with non-financial loss is $2,066.75.
Given that I accept the Applicant should be entitled to the maximum amount, I
direct the FSP to pay an additional $933.25. This would bring the total amount
paid to the Applicant at $3,000, being the maximum available under the Terms of
Reference.
I cannot partition her claims as it was the totality of her experience that led
to the maximum amount, not a discrete portion of it
In her submissions, the Applicant has attempted to state there are multiple claims
she wants FOS to consider. This includes claims against the builder that
conducted the poor repairs initially as well as JL, RS and the FSP.
I do not accept her claim can be partitioned in such a manner. The reasons are
twofold:
All of her exper iences are associated with the FSP’s failure to properly
discharge its obligations under the policy when repairing the damage initially.
Case No: 357375 Determination Page 11 of 16
The contractors the Applicant identified were clear ly the FSP’s agent during
this.
In awarding the maximum amount for non-financial loss, I considered the
totality of her experience.
Therefore, I do not accept she is entitled to more than the amount already
awarded based on the limitations of the Terms of Reference. This includes her
seeking $200,000 for every year her claim has remained ongoing.
The Applicant should receive an apology but I will not compel the FSP to do
this given it would substantively undermine its value
The Applicant has sought an apology for her claims experience. Given her
experience, this would be appropriate.
However, to compel a party to apologise for their conduct would, in my view,
undermine its value and purpose.
Accordingly, I would suggest the FSP consider doing so given it is clear that the
Applicant’s experience fell far below what a custom er should have expected in
these circumstances.
2.4 Should the FSP pay an amount towards professional costs or
consequential financial loss?
As there is an indication that solicitors added limited value to the dispute, I
will award $500 in this regard
The Applicant seeks reimbursement of the following professional costs:
legal costs; and
the cost to obtain an independent medical report to assess the impact she
sustained as a result of this claim – particularly the potential health hazard in
her home.
Under paragraph 9.4 of the Terms of Reference, FOS can award legal or other
professional costs incurred by the Applicant during the course of the dispute.
There is minimal evidence of the costs she incurred and the extent of any
solicitors’ involvement in this dis pute. For instance, no submissions prepared by
solicitors have been provided to FOS.
There has been some communication with the FSP by solicitors engaged by the
Applicant. However, part of it appears to have been associated with a potential
recovery action against the vehicle driver’s insurer.
There is an indication that solicitors engaged by the Applicant added some, but
limited, value to the process.
In such a context, I accept there is a sufficient basis to award legal costs under
paragraph 9.4 in the amount of $500.
Case No: 357375 Determination Page 12 of 16
The FSP is not required to pay for an independent medical report as there is
nothing to indicate it is necessary or would support the Applicant’s position
I do not accept the FSP is required to pay for an independent medical report for
the following reasons:
First, it is not a benefit under the policy.
Second, it is not a cost she incurred.
Third, and in the alternative to the reasons above, there is minimal evidence to
substantiate the Applicant’s physical health has been adversely affected by
the moisture ingress and, if so, to what extent.
Given this, I do not accept the FSP should incur the costs of a medical report that
may ultimately not be necessary or support the Applicant’s position.
Mortgage repayments are not a loss given they are a contractual
requirement that was in place before the claim
The Applicant has sought reimbursement of her mortgage repayments during the
course of this dispute.
I cannot accept this is a loss. This was a liability she incurred prior to the claim.
Further, her obligations to repay the loan remained unchanged regardless of her
dispute.
She has argued that the loss is due to the fact it is secured to a liability rather than
an asset. I cannot accept that. The loan is secured on both the land and the
home. It is clear the land has substantive value even if the home does not.
Therefore, as a whole, it would be considered an asset.
Due to the protracted claim, the Applicant has likely incurred consequential
financial losses of up to $3,000
The Applicant has likely incurred consequential financial losses as a result of this
claim. This would include her medical expenses and other expenses associated
with this long, protracted claim.
In regards to medical expenses, she has presented a number of invoices that she
says were incurred due to incidents surrounding this long and protracted claim.
She has also provided a letter from a consultant psychiatrist, Dr SM, dated
18 June 2012 which stated the following:
“I am the treating psychiatrist for [Applicant]. She has rec ently had an admission
to The [G] Clinic from the 4 th June – 11 th June 2012. This was in context of acute
stress associated with further damage to her home.”
Although there may have been pre-existing issues at play, it is clear the stress
and inconvenience associated with this claim has exacerbated those.
In regards to expenses associated with this claim, this would include:
making her property available
contacting numerous parties, such as the FSP, experts, builders and
electricity provider, and
Case No: 357375 Determination Page 13 of 16
providing copious photographs of the damage.
To a certain extent, these costs would be associated with the normal claims
process.
In this case, however, it is reasonable to conclude that the amount of efforts
undertaken by the Applicant way exceeded that reasonably contemplated by the
parties at the time the contract was entered into. This is reflected by the
significant protracted nature and the substantive inconvenience incurred by the
Applicant.
In such a context, I accept it is plausible that the Applicant’s exp enses exceeded
the $3,000 cap FOS is able to award in these circumstances.
Therefore, I consider it is fair in all the circumstances that the Applicant receive
$3,000 for consequential financial losses incurred during the course of this claim.
Further, for similar reasons expressed above regarding the award for non-
financial loss, I do not accept there is a basis to split her claims to enable multiple
awards under this head of damage.
Case No: 357375 Determination Page 14 of 16
3 Supporting information
3.1 Expert Reports
These reports set out the current state of affairs that underpins this Determination:
Record Key points
FSP’s expert ( JWS )
Report
03 Jul 2012
The driver of the vehicle drove through the carport in the
front yard of the residence and impacted the western
section of the kitchen
The construction of the roof decking was found to be
generally in a poor condition with the following defects
found:
- Poor installation of metal roof decking
- Inadequate fall on gutters
- Eaves gutters containing debris
- Poor roof penetration detail at extractor vent
The distress is generally limited to the water ingress into
the NW section of the house
No misalignment of the external walls were identified
The observed internal distress is consistent with moisture
ingress from external areas, specifically the roof .
Mould contamination/growth was observed in bedrooms.
It is likely the moisture ingress from the roof has
contributed to the mould growth
The possible causes of the water ingress is the poor
construction of the roof. This includes:
- Roof plumbing system be ing in a very poor condition
- Different types of roof sheets
- Poor roof penetration
Without carrying out destructive testing, it is often very
difficult to identify the precise location of water ingress
The distress caused by the vehicle impact is localised to
the point of impact given the lack of foundation movement
or misalignment
FSP’s expert ( JWS )
Report
23 Nov 2012
The verandah located in the NE region has not been
affected by the impact and no evidence of structural
distress was identified
The observed timber rot / decay is consistent with long
term moisture ingress via poorly installed and
inadequately waterproofed roofing materials
It is evident that paintwork had been carried out to the
already rotted / decayed timber members, which suggests
this commenced prior to the vehicle impact
The likely moisture ingress of the building in the western
elevation is due to the following:
- Inadequate surface drainage (no spoon or AGI drains
and the footing is not adequately protected)
Case No: 357375 Determination Page 15 of 16
Record Key points
- Ineffective waterproof memb rane under concrete slab
(likely due to age)
- Clay soils at the site
The overland surface stormwater may have been seeping
under the concrete slab for a long period of time
FSP’s expert (FM)
Report
11 Nov 2013
0.2mm – 1.0mm wide cracking to concrete slab
throughout the lounge and bedrooms
Distress to the house caused by the impact is localised to
NW section of the house. The remainder of the house has
not been effected.
Did not observe any structural damage as slab cracks
were limited to Category 1. This is cosmetic only
It is consistent with typical concrete shrinkage movement,
which is expected where there is insufficient control joints
/ reinforcement installed in a relatively large slab area
The cracks in the slab were present prior to the surface
clea ning work as it was covered with floor finishes
Likely cause of moisture ingress the same as previous
report
FSP expert (RS)
Report
28 Feb 2014
As the microbiologist found high moisture readings on the
concrete slab/building materials, there is still a rising
damp issue/capillary action
This is evident through the concrete slab in the laundry,
daughter’s bedroom and the master bedroom
Recommended additional investigation to identify cause
of moisture ingress
RS Project Manager will meet the builder onsit e and
discuss the bottom plates that are non - salvageable and
gave high readings when sampled
They will be treated, sealed and contained for the builder
to remove
The tacking strips in place will be removed and an
antimicrobial mist applied on the concrete slab
underneath
FSP expert (JL)
Report
17 Apr 2014
Excavation was undertaken to a depth of 300m in the
vicinity of the earlier installation of an agricultural drain
some months earlier
Plumber found the ground to be drying out as excavation
went deeper – indicative of the drainage being corrected
These factors could be increasing localised moisture
levels:
- The discharge line from the HWS was found to
terminate on the ground of the SW sideway
- Condensate line from the A/C unit terminates to the
same area
- Nei ghbouring property on the SW boundary is
approximately 300mm higher so natural soil drainage
may be contributing to higher moisture content
Case No: 357375 Determination Page 16 of 16
Record Key points
- Moisture barrier between slab and ground
FSP’s expert (FM)
Report
01 May 2014
Site drainage on the western elevation appears to have
been addressed
However, the following factors are likely to cause the
continuing high moisture levels:
- Ineffective or absence of vapour barrier under
concrete slab
- Inadequate protection of the footing system
- Reactive soils at the site
It is likely the overland surface stormwater may have
been seeping under the concrete slab over a long period
of time
Considering the age and construction, the water vapour
transmission is not uncommon
The following remedial works should be undertaken:
- The garden beds / unpaved areas located
immediately adjacent to the building footprints shall be
paved with 50mm fall over the first 1m away from the
building
- Thoroughly clean the existing slab surface utilising
appropriate diamond grinding equ ipment
- Flood coat the slab surface with epoxy based
moisture barrier products
- Apply a cement based underlay product
- Apply preferred floor finishes according to the
manufacturer’s recommendations