Home / Financial Firm (Unknown - Insurer) / Determination 356246

Determination 356246

Cash settlement amount for fire damage to home and contents; total loss claim refused

FirmFinancial Firm (Unknown - Insurer)
Decided2014-12-18
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicants sought a total loss declaration, the full building and contents sums insured, demolition costs and compensation after a fire. AFCA found the FSP's cash settlement of about $264,522 for building repairs and about $153,000 for contents was reasonable and no further amounts were payable.

The FSP may choose its settlement method under the policy, the home was shown to be repairable so no total loss or demolition cost was payable, and the claim was managed reasonably.

Issues

Subjects and remedies

disabilityhome or building damageno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination General Insurance - Domestic Insurance - Home Building – Home Contents - FSP Decision - Claim amount Determination Case No: 356246 Determination Page 1 of 7 Case number : 356246 1 7 December 2014 1 Overview 1.1 Dispute The Applicants lodged a claim with the Financial Services Provider (FSP) for damage to their home and contents following a fire in November 2012. The FSP accepted the claim and has to date paid the Applicants cash settlements totalling approximately $265,000 for the cost of building repairs and approximately $153,000 for the cost of replacing contents items which could not be restored. The Applicants say that the property should have been assessed as a total loss and they should have been paid the full amount of the building sum insured (including the 25% safety net), together with demolition costs. The Applicants also seek payment of the full amount of the contents sum insured, as well as compensation for financial and non-financial losses incurred as a result of the manner in which the FSP has handled their claim. 1.2 Issues and key findings Is the cash settlement amount appropriate? The available information does not establish that the Applicants’ home was incapable of being repaired. Therefore, the FSP is not obliged to settle the building claim on a total loss basis. Further, the settlement amount appears adequate to fund the necessary repairs. The Panel is satisfied that the cash settlement paid for contents items (as increased in August 2014) is sufficient to compensate the Applicants for the cost of replacing contents items which were damaged in the fire and could not be restored. Did the FSP manage the claim appropriately? On the whole, the FSP acted appropriately in its management of the claim and sought to resolve the claim on a reasonable basis and without undue delay. 1.3 Determination This Determination is in favour of the FSP. The FSP has complied with its obligations under the policy and is not required to pay the Applicants any additional amounts. Case No: 356246 Determination Page 2 of 7 2 Reasons for Determination 2.1 Is the cash settlement amount appropriate? FSP may determine method of settling building claim Under the terms of the Applicants ’ policy as set out in the Product Disclosure Statement (PDS), the FSP may decide to settle a claim by:  repairing the damage or rebuilding the home on a new for old basis or  paying the Applicants the amount it would cost the FSP to repair or rebuild their home on a new for old basis. It is clear from the terms of the policy that the FSP has the discretion to decide how to settle the Applicants’ claim. Further, the policy clearly states that the FSP will not pay more than it costs to repair or rebuild the home. Available information establishes building can be repaired The Applicants advised the FSP that they did not want their home repaired but would prefer a cash settlement, so that they could demolish their existing home and build a new one. Accordingly, the FSP agreed to provide the Applicants with a cash settlement rather than carrying out the repairs itself. In these circumstances, the amount of the cash settlement payable by the FSP is the amount which is equal to the cost of repairing or r ebuilding the Applicants’ home. The FSP engaged a consulting engineer (DK) to inspect the property and prepare a scope of works for the repair of the fire damage. The FSP then obtained quotations from three builders to undertake the repairs set out in the scope of works. The successful builder (LS) quoted a total of $208,888 for the repairs. The FSP increased the proposed settlement amount by an additional $10,000, after the Applicants noted a number of items which were not included in the scope of works. After further negotiations, the FSP increased its offer by an extra $31,112 to allow for any unexpected costs that may have become apparent during the repair process, resulting in a final offer of $250,000. During the course of this dispute, the FSP agreed to further increase the building cash settlement to take into account additional works required in relation to the swimming pool (bringing the total amount paid to $264,522). The Applicants say that their home was not capable of being repaired and should have been declared a total loss. However, they have not provided any independent information to support their position (for example, a report from an appropriately qualified professional). Neither the engineer nor any of the builders engaged by the FSP indicated that the Applicants’ home was unable to be repaired or that it would be uneconomical to carry out the repairs. The final amount paid ($264,522) remains less than the building sum insured of $278,000. Case No: 356246 Determination Page 3 of 7 In these circumstances, the Panel considers that the FSP acted reasonably in deciding to cash settle the Applicants for the cost of the repairs, rather than declaring the building to be a total loss. Available information does not establish building settlement is inadequate The Applicants say that the cash settlement provided by the FSP for the building repairs is insufficient to cover the works which would have been required to repair the property. They say that the FSP should be required to pay them the full sum insured, plus the additional 25% available under the safety net benefit. The FSP has confirmed that the quote provided by its builder (LS) (based on DK’s approved scope of works) includes certain items which the Applicants had previously queried, such as the complete electrical rewiring of the house. However, the Applicants say that the scope of works still omits a number of items, such as restoration of the masonry, cleaning of the septic system, replacement of bathroom mirrors and the costs of obtaining a structural engineer’s report in order to obtain council approval. However, even if the Applicants ’ position is accepted, they have not provided any independent information to show that the costs of these additional works would exceed the additional amount of $31,112 which the FSP included as a buffer for unforeseen costs when determining the cash settlement amount. The FSP has obtained quotes for the restoration of the masonry and the clea ning of the septic tank system for less than half the amount of the buffer. In these circumstances, the Panel considers that the cash settlement of $250,000 for the building claim is fair and reasonable, and complies with the FSP’s obligations under the policy. Safety net benefit is not available where repair costs are less than sum insured The Applicants had selected the optional safety net benefit available under their policy. This benefit entitles the Applicants to payment of an additional amount of up to 25% of the building sum insured, where the cost to repair or replace their home exceeds the building sum insured. In the present case, the cost of repairing t he Applicants’ home i s less than the building sum insured of $278,000. Accordingly, the Applicants are not entitled to any additional payment under the safety net benefit. Demolition costs are not payable where property can be repaired The Applicants’ policy provides that the FSP will pay the reasonable and necessary costs to demolish their home if necessary. To date, the FSP has paid total costs of $37,890 to the Applicants and its contractors for the removal of building debris and damaged contents from the property. A s the Applicants’ home was capable of being repaired, the FSP is not required to pay them an additional amount for the costs of demolishing the property. Any such costs arise from the Applicants’ preference to demolish and rebuild their property and are beyond the scope of the FSP’s obligations under the policy . Case No: 356246 Determination Page 4 of 7 Contents settlement is fair and reasonable Under the terms of the Applicants’ policy, the FSP is required to settle contents claims on a ‘new for old’ basis, regardless of the age of the contents item and with no allowance for depreciation. This means that, where damaged items cannot be repaired or restored to ‘as new’ condition, the FSP is required to replace them (or pay the Applicants the replacement cost). The FSP initially paid the Applicants a cash settlement of $67,542 in July 2013 for contents items which were damaged in the fire and could not be restored. This amount was subsequently increased by a further $20,000, which included the costs of replacing various electrical appliances and recarpeting four rooms of the house. The FSP also paid an additional $1,410 for a grandfather clock. The Applicants subsequently advised that they were not satisfied with the condition of a number of items which were returned to them by the FSP’s contractors. These included clothing items which had not been restored to an acceptable condition and furniture which had been damaged while in storage. The FSP acknowledged that some of the items returned were in an unacceptable condition and paid the Applicants a further amount of $61,923 in August 2014. However, the Applicants say that the cash settlement for contents items paid to date is insufficient and seek payment of the full contents sum insured of $228,000. Based on the available information, the Panel is satisfied that the total cash settlement of approximately $153,000 paid by the FSP in respect of the Applicants’ contents claim is fair and reasonable, and complies with the FSP’s obligations under the policy. The Panel considers that the FSP has sought to address the concerns raised by the Applicants during the course of the claim by proposing the payment of additional amounts where appropriate. Applicants are not entitled to additional payments for temporary accommodation The Applicants’ policy provides for the payment of temporary accommodation benefits capped at 52 weeks’ worth of benefits or 10% of the building sum insured (whichever is the lesser). The policy states that benefits will not be paid beyond the period it should reasonably take to complete the necessary building repairs. Following the fire in November 2012, the FSP paid the costs of temporary accommodation for the Applicants and their family until 18 November 2013 and then cash settled them for the cost of a further seventeen weeks’ rent (based on the estimated time required to complete the building repairs). The FSP has paid temporary accommodation benefits of $56,850 for a total of 67 weeks, which exceeds the Applicants’ maximum entitlement to benefits und er the policy. The Applicants say that the FSP should have arranged temporary rental accommodation and paid the bond on their rental property. However, the FSP is not obliged to do so under the terms of the policy. The FSP arranged short-term Case No: 356246 Determination Page 5 of 7 accommodation for the Applicants immediately following the fire, while they located an appropriate rental property. In the circumstances, the Panel is satisfied that the FSP has complied with its obligations under the policy in relation to temporary accommodation. 2.2 Did the FSP manage the claim appropriately? FSP is entitled to manage the claim in accordance with the policy The Applicants say the FSP has breached the Disability Discrimination Act because it did not take into consideration their son’s disability when d etermining how to manage the claim. The Applicants also say the FSP breached its duty of care and failed to show empathy by not declaring their property to be a total loss. The Applicants have not provided any information which suggests that the FSP managed their claim on less favourable terms and conditions or in an unfair manner, due to their son’s disability. The Panel accepts that, due to the potential impact on their son, the Applicants wanted the property to be declared a total loss and would have preferred that the FSP did not attempt to restore their contents items. However, the available information suggests that the FSP managed the Applicants ’ claim (including determining the appropriate settlement method) in the same way as it would any other similar claim. Further, the Panel does not consider that the effect of the FSP’s actions was to unreasonably exclude or disadvantage the Applicants or their son. Applicants are not entitled to compensation for time taken to progress their claim The female Applicant says she had to give up work in order to effectively manage the claim, when this should have been the FSP’s responsibility. She says that the FSP unreasonably required her to provide evidence of loss and to source quotes in order to determine the replacement value of contents items. Under the terms of the Applicants’ policy , they are required to provide proof of ownership and value to enable the FSP to assess their claim. The policy notes that this is particularly important for electrical items and furnishings, as well as values listed on the policy. The Panel notes that the process of finalising a major claim necessarily involves considerable time and effort from the insured as well as the insurer. This cannot be recovered under the policy, which specifically excludes cover for loss of income and/or time taken to prove the loss or assist the FSP in assessing the claim. Having carefully reviewed the extensive claim records, the Panel is satisfied that the FSP did not act unreasonably in requiring the Applicants to provide information to assist it in determining the appropriate basis on which to settle their claim. The Panel notes that the FSP has been willing to increase the settlement Case No: 356246 Determination Page 6 of 7 amount on multiple occasions, based on the additional information provided by the Applicants. Accordingly, the Applicants are not entitled to compensation for any losses incurred as a result of the time taken to progress their claim. FSP managed the Applicants’ claim reasonably The Panel acknowledges that the FSP’s management of the claim may have been complicated by numerous personnel changes and there may have been times when the FSP failed to promptly return the Applicants’ calls. However, the Panel is satisfied that the FSP’s overall management o f the claim was reasonable in the circumstances. In the Panel’s experience, large and complex claims typically take some time to fully resolve and are inherently stressful for the insured. In the present case, the Panel considers that the FSP sought to resolve the Applicants’ claim on a reasonable basis and without undue delay, including by making payments which exceeded its assessed liability under the policy. Although delays were experienced from time to time during the claim process, the available information does not establish that the FSP’s actions caused any lengthy or protracted delays. In these circumstances, the Panel does not consider that an award of compensation is appropriate. Case No: 356246 Determination Page 7 of 7 3 Supporting information 3.1 FOS approach to this dispute This dispute has not been the subject of a FOS Recommendation. Due to the nature of the dispute, it has been referred directly to a Panel for Determination, in line with the Operational Guidelines to the FOS Terms of Reference. The Panel consists of an Ombudsman and two representatives with consumer and insurance experience. The Panel has decided this case on its merits, having regard to the relevant law, good industry practice, codes of practice and previous Financial Ombudsman Service (FOS) decisions. There has been a full exchange of all material information relied on for the purposes of this Determination and each party has had the opportunity to address any issues raised by the other. The Panel has reviewed and considered all of the material provided by the parties. While the parties have raised a number of issues in their submissions, for the purposes of this Determination the Panel has restricted its commentary to those issues which it considers directly relevant to the outcome only.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.