The applicant complained that the FSP took too long to settle his refinance and construction loans and claimed a builder cost increase as loss. AFCA held the FSP responsible for about two weeks of delay and ordered $16.42 financial loss and $100 non-financial loss, rejecting the larger consequential loss claim.

Delay is apportioned by the errors that contributed to it, and consequential loss is refused where the applicant could have mitigated by locking in the builder's original price.

Issues

Subjects and remedies

pay compensationpay non financial loss

Related

All Financial Firm (Unknown - Credit) determinations · Find similar determinations

Text of the determination

Determination Credit - Consumer Credit - Home Loans - Instructions - Delay Determination Case No: 355603 Determination Page 1 of 8 Case number : 355603 24 April 2015 1 Overview 1.1 Dispute The Applicant and his partner applied for loans with the Financial Services Provider (FSP) in December 2013 in order to refinance loans held wit h another financial institution and to provide construction funding. A guarantee was to be provided by a third party, who was to provide additional security. Settlement of the loans was effected on 20 May 2014, without the guarantor support. This dispute is about whether the FSP took an unreasonable time to settle the loans, and if so, if the delay caused the Applicant a loss for which the FSP should compensate him. 1.2 Issues and key findings Did the FSP unreasonably cause a delay in the settlement of the loans? The FSP is responsible for two weeks of the delay in settlement of the loans. Otherwise the delay in the settlement of the loans was largely due to circumstances outside of the control of the FSP. Did the delay cause the Applicant loss for which he should be compensated? The loans refinanced existing liabilities for which the Applicant was already liable at a slightly more favourable rate. The FSP should therefore reimburse the Applicant with $16.42, being the difference in interest paid over a period of two weeks to his account held jointly with his partner. The FSP should compensate the Applicant $100.00 for the stress and inconvenience that he suffered as a result of the FSP’s contribution to the delay in settlement . 1.3 Determination This Determination is substantially in favour of the Applicant. The FSP contributed to the delay in settlement of the loans and should the Applicant accept this Determination within 30 days of its date (above) within a further 14 days of that acceptance the FSP must pay the Applicant compensation of:  $16.42 for his financial loss, and  $100 for his non-financial loss  by reducing account xxx861 by $116.42. Case No: 355603 Determination Page 2 of 8 2 Reasons for Determination 2.1 Did the FSP unreasonably cause a delay in the settlement of the loans? The assessment of an applicant’s request for funding is a commercial decision for the financial services provider to make and FOS does not have the power to consider disputes about a financial services provider’s assessment of credit risk. The FSP imposed conditions on funding construction after settlement of the loans, which the Applicant was required to comply with, which is acceptable. FOS can review whether a financial services provider unreasonably delayed providing an answer to a restructure proposal or application, or unreasonably delayed in settling a loan. When reviewing a dispute about a delay in settlement, FOS will determine whether an error has occurred, and if so, which party or parties contributed to the delay. A chronology of events in this dispute is set out in Section 3. The loans’ approval was conditional upon requirements being fulfilled The Applicant submitted an application to the FSP through a broker on 12 December 2013, which was amended on 18 December 2013. The FSP approved the loans on 21 January 2014. There is no obligation on a financial services provider to approve finance. It is standard practice for a financial services provider to request financial information from a customer, so it may conduct its credit assessment. Approval of the application was conditional on certain requirements being fulfilled, including clearance of over limit credit card debts. The information provided to FOS shows that this was still an issue the day before the loans were approved. In all the circumstances, the timeframe between submission of the application and the approval of the loans was reasonable. This is especially so given that the Christmas period intervened, which would generally account for two weeks delay in any event. The delay between 21 January 2014 and 4 April 2014 was reasonable The Applicant expressed his extreme dissatisfaction with the delays he was experiencing in settling the loans in an email to the FSP dated 5 March 2014 and complained that he had been waiting for 3 months, which was unacceptable to him. A review of the information provided to FOS shows that after the loans were approved on 21 January 2014, and some delays in progressing the application occurred due to circumstances out of the control of the FSP. For example, at least one of the security properties was tenanted and the FSP’s valuer had to fit in Case No: 355603 Determination Page 3 of 8 with tenants’ requirements before it could conduct an inspection in order to complete its valuation reports. After the security properties were valued, the loans needed to be restructured and the application re-approved as the Loan to Value Ratio (LVR) was higher than anticipated and this was not acceptable to the FSP. A change in guarantor support was also requested by the Applicant at that time. The new loan amounts were approved on 11 March 2014 and settlement booked for 4 April 2014, which was 24 days later. This is not an unreasonable time frame given that security documents needed to be prepared, signed and checked, and settlement with the existing financier arranged and booked. Further, the finance was not straight forward, as there were three security properties involved, one of which had an unusual title, as well as a third party guarantor. The delay between 4 April 2014 and 16 April 2014 was reasonable Settlement did not proceed on 4 April 2014 because there were insufficient funds to pay out the existing financier. On 9 April 2014, the Applicant requested an amendment to the finance request which removed the need to refinance one of the existing loa ns and therefore reduced the overall borrowings. A security property was removed as well as the guarantor support. The FSP asked the Applicant’s broker to acknowledge that the change to the finance application would further delay settlement. It also asked the broker to confirm that the funds released at the refinance stage would be 75.68% of land value, which he acknowledged on 16 April 2014. The newly structured loans were approved on 16 April 2014. The FSP is responsible for a delay of 2 weeks between 16 April 2014 and 20 May 2014 The loans settled on 20 May 2014, which was 30 days from the time of their verbal approval. It is noted that the Easter holiday period occurred during this time, as well as a public holiday, being Anzac Day, however this wo uld account for a delay of no more than a week. The views of the FOS Banking Specialist (Specialist) were sought in making this Determination. What is “reasonable” in terms of ap proval time and settlement time is dependent on such things as the FSP having all required information and all conditions of loan approval having been met. Whilst the FSP appeared to be actively progressing the matter, it appears mistakes were made in documenting the loans on more than one occasion. Although these were rectified in very short time frames, they did contribute towards a delay in settling the loans. Further, even though loan amounts were changed, and a security property was removed in April 2014, the FSP already had relevant information such as title searches, valuation reports and so forth to enable the loans to be documented promptly. The existing financier was ready to settle. Case No: 355603 Determination Page 4 of 8 The loans finally settled on 20 May 2014, after a further failed settlement on 16 May 2014 due to a missing title, a delay not attributable to the FSP. In all the circumstances, the Specialist is of the view that there was a delay of around two weeks for which the FSP should be held responsible. 2.2 Did the delay cause the Applicant loss for which he should be compensated? No loss where loans are refinanced on similar terms Where there is a refinance of an earlier loan on similar terms we do not consider that an applicant has suffered any loss as a result of the refinancing. This is because the Applicant simply transferred liability for an existing debt from one financial services provider to another. In this dispute, if the new loans had been settled earlier, the Applicant would have been paying interest at a rate of 0.05% lower than with the old financier, which over two weeks equates to: 0.05% x $856,000 / 365 x 14 = $16.42. Consequential loss FOS takes the approach that an award of interest is the usual remedy for delay by an FSP. The Applicant says he has suffered loss as the builder he wanted to engage increased his quote by $55,000, making it unaffordable. The Applicant claims to have:  Lost the opportunity to engage a builder at a lower price;  Been inconvenienced by having to source a new builder;  Had to obtain new quotes; and  Been unable to source a building contract as favourable as the one he had received a quote from on 25 th March 2014. A review of the original quote by the builder on 25 th March 2014 shows that the Applicant was able to lock in the original price for four months if he had paid a deposit by 4 April 2014. The Applicant did not accept the quote, and he did not lock in the price, even though the loans had been approved before 4 April 2014. He says he did not do so because he first needed finance to be in place. The Applicant could have mitigated his loss by locking it in the quoted price with the original builder. 2.3 Should the FSP compensate the Applicants for non-financial loss? The FSP ’s delay caused the Applicant undue stress Section 3.2 sets out information about how FOS assesses claims for non-financial loss which relates to stress, upset, inconvenience and anxiety caused by a financial services provider’s breach or error. I am satisfied that the Applicant did Case No: 355603 Determination Page 5 of 8 suffer undue stress as a result of the FSP’s two week contribution to the delay in settlement. For its contribution to the delay, the FSP should pay the Applicant non-financial loss compensation of $100. That award is consistent with similar award for non-financial loss in analogous circumstances. Case No: 355603 Determination Page 6 of 8 3 Supporting information 3.1 Chronology Date Details 12 December 2013  Loan application submitted for loans totaling $2,304,000 to the Applicant and his partner, and included a guarantee from his partner’s mother 17 December 2013  FSP requests further information from broker, including: building contract, rates notices, there is a requirement to lodge a second application as there is family equity support, need a letter from par ent, a credit card is not in application, and credit card is over limit 18 December 2013  Broker emails total loan amount is to be $2,112,000. New application submitted. 20 December 2013  FSP tries to contact broker by phone. Emails that the Applicant’s partner’s credit card is over limit, and needs a separate form for loan xx9188 9 January 2014  FSP tries to contact broker by phone. Partner’s credit card still over limit, needs a separate form for loan xx9188 20 January 2014  FSP leaves broker voice message. Emails broker that Applicant’s credit card now over limit, application now “very borderline and we may not be able to proceed further” 21 January 2014  Loans approved 22 January 2014  Valuation for property postponed due to identification issues . Rescheduled to 28 January 2014 23 January 2014  Delay in valuation due to property being tenanted. Agent arranging access. FSP requested documents from borrower. 29 January 2014  FSP requests a letter that credit card cancelled 11 February 2014  Advis ed broker what documents FSP required before it could proceed 11 February 2014  Valuations completed 12 February 2014  Emailed request for documents 18 February 2014  FSP advises LVR has changed. File is back with credit department 20 February 2014  FSP emails broker that new LVR is 82.21%. Please complete application amendment 24 February 2014  Borrowers loan documents sent to broker, guarantor’s documents sent to home address 24 February 2014  Broker called to say pledge amount needed to be amended 25 February 2014  Broker emails amended pledge amount 26 February 2014  FSP emails broker, left voicemail. Both credit cards over limit. Case No: 355603 Determination Page 7 of 8 Borrowers have also increased limits, please lodge online, amendment to reduce LVR. 5 March 2014  New loan amount now to total $2,080,000  App emails FSP with extreme dissatisfaction re time it has taken to settle loans, says FSP keeps asking for more docs, didn’t get request for information, has been waiting for 3 months 11 March 2014  Applicant emails that he is still waiting for documents  New application for $2,080,000, with change in guarantor support, approved 17 March 2014  FSP charge s $150 interest to credit card, then say s because it is $20 overdrawn it is holding u p process March 2014  Slight delay in documenting security because title to security property is unusual 19 March 2014  Documents sent to broker 25 March 2014  FSP contacts broker to request signed discharge authority for another bank 25 March 2014  Builder issues tender for $879,171 28 March 2014  Documents issued in incorrect names, and cross collateralized when should not have been 31 March 2014  FSP advises broker of outstanding documents for construction loan, including building contract, counci l approved plans, builders insurance 4 April 2014  Last date Applicant can lock in building contract price 4 April 2014  Settlement fails to proceed due to shortfall in funds 8 April 2014  Applicant submits revised paperwork 9 April 2014  Amendment to original finance request which eliminates refinancing of $588,000 loan. Construction finance now $650,000, total new lend $1,450,000. 10 April 2014  Note in FSP’s system that broker is to acknowledge that the change to the application will further delay settlement , and to acknowledge that funds released at settlement will be 75.68% of land value only 16 April 2014  Verbal approval for new loan 7 May 2014  Broker emails borrower to say FSP has loan amounts wrong again 7 May 2014  Documents issued to MP Branch for collection, with new loan amount of $1,450,000 12 May 2014  Builder issues tender for $934,171 14 May 2014  Executed documents received by FSP 16 May 2014  Settlement failed to proceed as existing financier could not produce title Case No: 355603 Determination Page 8 of 8 20 May 2014  Settlement effected May 2014  New builder found and contracts submitted to FSP 21 July 2014  FSP emails broker again noting outstanding requirements for construction, including building contract, council approved plans, builders insurance 22 July 2014  FSP requests more information from new builder. Waiting on builder to finalise Home Owners Warranty 10 September 2014  FSP emails broker detailing outstanding conditions for construction 12 September 2014  FSP emails broker detailing outstanding conditions for construction 22 September 2014  Construction commencement letter issues with condition that FSP requires evidence that $209,000 has been paid to the builder prior to first progress payment 3.2 FOS approach to compensation for non-financial loss Non-financial loss includes claims for stress or inconvenience caused by an error of the Financial Services Provider. The maximum amount we can award for non- financial loss is $3,000 for each claim. We will only award compensation for non-financial loss if there has been an unusual degree or extent of inconvenience. We will not award compensation for loss that an Applicant may incur as a result of pursuing a dispute or rectifying an FSP’s error. When assessing whether the circumstances are of an unusual nature we will review:  the degree or extent of physical inconvenience suffered  the general time taken to resolve the dispute  the extent to which the FSP’s actions interfered with the Applicant’s expectation of enjoyment or peace of mind. We assess any claims for non-financial loss in accordance with the FOS Terms of Reference. If we do award compensation, it is unlikely to be substantial and is subject to a $3,000 cap per claim.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.