Determination 354432

Denial of storm-damaged home repairs for termite and pre-existing stump damage, and delay in claim handling

FirmFinancial Firm (Unknown - Insurer)
Decided2015-04-13
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$7,000
Non-financial loss$3,000
Amount claimed—
SourceAFCA PDF

Summary

The applicant's storm-damaged home took over five years to repair. AFCA upheld the FSP's refusal to cover termite damage and 30% of re-stumping, but ordered $10,000 in total: $3,000 non-financial loss, $5,000 water purchase costs, and $2,000 for consequential loss and re-stumping cost increases caused by delay.

Termite and gradual damage fall within the policy exclusions, but the FSP's poor management of the claim unreasonably delayed repairs and caused compensable loss.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay compensationpay non financial loss

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination General Insurance - Small Business/Farm Insurance - Commercial Property - FSP Decision/Service - Denial of Claim - Exclusion/Condition/Delay in Claim Handling Determination Case No: 354432 Determination Page 1 of 12 Case number : 354432 8 April 2015 1 Overview 1.1 Dispute The Applicant lodged a claim under his farm insurance policy with the Financial Services Provider (FSP) for damage to his home following a storm in March 2010. The FSP accepted the claim, other than partial liability for restumping of the property. However, for various reasons the repairs did not commence until October 2013. When the repairs commenced, the FSP’s contractors identified termite damage to the property. The FSP denied liability for the termite damage and required the Applicant to repair this damage at his expense. The Applicant says the resolution of his claim has been unreasonably delayed and therefore the FSP should pay for all the repairs. He also seeks compensation for financial and non-financial losses suffered during the claim process. 1.2 Issues and key findings Is the FSP liable for all of the repairs? The FSP is not liable for 30% of the re-stumping costs or any of the costs of repairing the termite damage. The apportionment of liability for the re-stumping costs was reasonable, given that some of the damage to the stumps is likely to have occurred prior to the storm. The FSP is entitled to rely on the policy exclusion for damage caused by termites, in circumstances where there is insufficient information to establish that the termite damage was caused by the storm and/or the burst sewer pipe. Is the Applicant entitled to any additional amount? The FSP’s conduct of the claim has contributed to the delay in repairing the Applicant’s property and caused him stress and inconvenience. The Applicant has incurred additional costs (in lieu of temporary accommodation benefits) as a result of having no access to fresh water due to the damage caused by the storm. He has also incurred additional heating and cooling costs as a result of claim delays. 1.3 Determination This Determination is partly in favour of the Applicant. The FSP is to pay the Applicant the amount of $10,000. Case No: 354432 Determination Page 2 of 12 2 Reasons for Determination 2.1 Is the FSP liable for all of the repairs? Policy provides cover for storm subject to exclusions The Applicant is required to show that, on the balance of probabilities, he has suffered a loss caused by a risk insured against under the policy. This is known as a prima facie claim. If the Applicant is able to establish a prima facie claim, then the onus shifts to the FSP to show that, on the balance of probabilities, the loss falls within an exclusion clause under the policy or that it is otherwise entitled to deny liability. The Applicant’s policy provides cover for damage to his home caused by the events listed in the policy (including storm and rainwater), subject to the conditions and exclusions set out in the policy. The policy includes general exclusions for loss or damage caused directly or indirectly by:  gradual deterioration, corrosion, wet ro t, dry rot, mould and mildew; and  insects, vermin or birds. Dispute concerns liability for re -stumping and termite damage The FSP does not dispute that the Applicant’s property sustained significant damage during the storm in March 2010 and has accepted liability for the replacement of the roof and the repair of the internal water damage caused by the storm. The repairs to the property have been delayed for over five years due to a number of factors which are discussed further in section 2.2 below (see also the chronology in section 3.2 ). During this time, the property has remained in varying states of disrepair as the repairs were initially commenced and later suspended. However, the property has now been re -stumped, the roof repairs have been completed and the FSP has authorised its builder to undertake the extensive internal repairs to the property required to fully repair the resulting damage. It appears from the quote provided that these works include all of the additional damage which has arisen as a result of the property being jacked up on blocks and left in that state for a substantial period of time while the re-stumping works were suspended. The FSP has accepted liability for the bulk of the repairs to the property and is also providing temporary accommodation for the Applicant and his wife while the repairs are completed. However, the FSP denied liability for:  30% of the costs of the re-stumping (equivalent to approximately $5,000), on the basis that some of the stumps were already in a poor condition at the time of the storm; and Case No: 354432 Determination Page 3 of 12  the entire costs of repairing the termite damage to the timber floor bearers and joists discovered during the re-stumping (for which the Applicant has paid approximately $8,000). FSP is liable for 70% of re-stumping costs only The reports prepared by the FSP’s contractors confirm that the house had suffered differential movement as a result of rotting damage to the stumps. The Applicant advised that he had noticed significant movement in the six months following the storm. A report prepared by the FSP’s loss adjuster (CL) in September 2011 quotes advice from one of the FSP’s builders (VB) that the stumps under the house appeared to be original and were therefore estimated to be approximately 70 years old. VB noted that, while the outside stumps had been replaced at some stage, the inside stumps had “literally rotted away” resulting in parts of the house sinking up to 150 millimetres. Based on VB’s report, the FSP initially denied li ability for all of the re-stumping costs. However, the Applicant disputed the FSP’s decision on the basis that the damage to the stumps had been caused by excessive water pooling under the house. After the Applicant provided documents which established that the house had been re-stumped in 1993, the FSP agreed to accept liability for 70% of the re- stumping costs but denied liability for the remaining 30%. A report prepared by the FS P’s loss adjuster (CL) in November 2011 indicates that this apportionment was based on conversations with an unidentified contractor who advised that 70% of the damage to the stumps was due to excessive water under the house and the remaining 30% was due to lack of maintenance. One of the re-stumpers (DJ) appointed by the FSP to quote on the necessary repairs confirmed that the stumps had sunk due to excessive water having entered down the chimney and around the side of the house. It appears that the FSP decided to deny liability for 30% of the damage on the basis that drainage was an ongoing issue with the property which the Applicant was aware of and had failed to mitigate. The Panel notes that VB had referred to drainage issues in his earlier report. However, the Applicant says that the additional damage to the stumps (which the FSP has classified as “maintenance damage”) would not have occurred had the FSP assessed his claim more promptly. The available information confirms that significant quantities of water pooled under the house following the storm, as reflected by the extended period of time required to allow the soil to dry out before repairs could be undertaken. However, given the nature of the drainage issues with the property identified by the FSP’s re -stumper (DJ) and the builder (VB), it appears unlikely that all of the damage to the stumps occurred solely as a result of the storm in March 2010 (either immediately or during the subsequent period it took the FSP to appoint an assessor). Case No: 354432 Determination Page 4 of 12 In the Panel’s view, it is more likely that some of the damage had occurred gradually during the seventeen years since the property was last re-stumped. Damage which occurs in this manner is not subject to cover under the policy. On this basis, the Panel is satisfied that it was reasonable for the FSP to deny liability for 30% of the costs of the re-stumping. FSP is not liable for costs of repairing termite damage As outlined above, when the FSP’s re -stumper commenced work in October 2013, he discovered termite damage to the timber floor bearers and joists. As a result, the re-stumping works were suspended until the Applicant agreed to fund the repair of the termite damage. When the works recommenced, further termite damage was discovered. The policy is drafted broadly so as to exclude cover for damage caused by insects (including termites). However, in the Panel’s view, the exclusion does not operate to exclude cover for termite damage where the cause of that damage was an event which is otherwise covered under the policy. Accordingly, if the termite damage to the Applicant’s property was caused by the effects of the storm in March 2010 (and/or the burst pipe discovered in February 2013), then the FSP will be liable for that damage. The Applicant says that the termite damage occurred as a result of the excessive water which pooled under the house following the storm (and the effects of a burst pipe discovered in February 2013), exacerbated by the FSP ’s delay in carrying out the repairs. He says that:  there was no termite damage to the house prior to the storm, as shown by the fact that none of the FSP’s contractors who inspected the property identified any termite damage; and  he has engaged a pest controller to carry out a regular and ongoing termite prevention and maintenance program since 1995, and most recently in August 2013. Having carefully reviewed the available information, the Panel considers that it is not possible to determine with any certainty when the termite damage occurred. While the Panel accepts that the increased moisture at the property following the storm would have increased the risk of termite infestation, there is insufficient information to establish that any termite activity actually occurred during this period. In this regard, the Panel notes that:  while the re-stumper (D) noted the presence of excessive water, he did not identify this as the cause of the termite damage;  there is no information to suggest that any live termites or active termite nests were found in the house when the termite damage was first identified in October 2013;  the Applicant has acknowledged that termites had previously been found in trees at the property, which suggests that there was an ongoing risk of termite infestation; Case No: 354432 Determination Page 5 of 12  while the Applicant had an ongoing termite treatment program in place, the existence of termite damage indicates that this program was (at some point) insufficient to prevent termite infestation;  the FSP’s loss adjuster indicated that, while it was not possible to determine exactly when the damage had occurred, at least some of the damage appeared to have been present for a number of years, given the texture and colour of the affected timber;  the termite damage was not apparent to the naked eye and was only discovered when part of the flooring was removed in order to commence the re-stumping works. Even at this stage, it was not possible to determine the full extent of the damage, given the limited sub -floor access at the property; and  the lack of any reference to termite damage in the reports prepared by the FSP’s contractors does not of itself establish that there was no termite damage at the time of their inspections, given the difficulty in identifying the damage due to the location of the damage and the limited sub-floor access available. As outlined above, the policy excludes liability for termite damage, except where the damage is caused by an earlier event for which the FSP is liable. For the reasons outlined above, there is insufficient information available to establish that the termite damage occurred after, and as a result of, the storm in March 2010 and/or the burst pipe (rather than at any earlier time). In these circumstances, the FSP is entitled to rely on the general exclusion for damage caused by termites to deny liability for this aspect of the repairs. 2.2 Is the Applicant entitled to any additional amounts? Claim process has been unreasonably delayed Under paragraph 9.3(b) of the Terms of Reference, FOS may award compensation (capped at $3,000) for non-financial loss where an applicant has suffered an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with their expectation of enjoyment or peace of mind. The Applicant say that he and his wife have suffered considerable stress and inconvenience as a result of the extended delay by the FSP in resolving the claim and undertaking the repairs to the property. The Panel accepts that it has taken an extraordinary period of time (over five years) for the repairs to be completed. The Panel also notes that the Applicant and his wife have continued to live in the property throughout this period, despite the relatively extensive damage caused by the storm (and the worsening of that damage due to the re-stumping works being suspended part-way through). Having carefully reviewed the available information, the Panel accepts that not all of the delays experienced during the claim process are attributable to the conduct of the FSP. In particular, the Panel notes that the claim has been delayed by factors outside the FSP’s control, such as : Case No: 354432 Determination Page 6 of 12  the extended period required to allow the sub -floor area to dry out before the repairs could be conducted (which was further complicated by the burst pipe); and  the illness and insolvency of various contractors appointed by the FSP. The Panel accepts that the discovery of termite damage during the repair process (and the resulting negotiations in relation to liability and next steps) further delayed the commencement of the building repairs. Nevertheless, the Panel considers that the manner in which the FSP managed the claim has significantly contributed to the delays experienced and increased the stress suffered by the Applicant as a result of what was already a complicated claim. In this regard, the Panel notes that:  the FSP did not appoint a loss adjuster to inspect the damage to the property until sixteen months after the Applicant lodged his claim in March 2010. It appears that for some reason the claim was closed and was not re-opened again until the Applicant contacted the FSP in July 2011;  the FSP appears not to have actively managed the claim during the latter part of 2011 and the first half of 2012 (after it had accepted liability and approved the scope of works). The FSP’s internal file notes in February 2012 and July 2012 note that the claim was getting old and needed to be dealt with expeditiously; and  while an additional period of six to eight weeks was required to allow the soil to dry out after the burst pipe was discovered in February 2013, the re- stumping works did not commence until October 2013. While it appears that the re-stumper needed to obtain a permit, it is not clear why this could not have been arranged ahead of time in order to allow the works to commence on schedule, given the substantial delays which had already occurred. Further, the Panel is not satisfied that the FSP acted proactively to manage and resolve the additional issues which arose during the course of the claim. In particular, the Panel notes that:  while some of the delays were caused by issues with the FSP’s contractors, the FSP was responsible for appointing the contractors and ensuring they completed the necessary works promptly and efficiently (including replacing them in the event that the need arose);  responsibility for the management of the claim appears to have been transferred between various staff and contractors, including those in different regional centres;  it does not appear that the FSP sought to investigate whether there were any additional measures which could be taken to expedite the claim (for example, by speeding up the drying process or by allowing the termite damage to be addressed in conjunction with the re -stumping works, rather than insisting that it be repaired prior; and  the FSP has failed on a number of occasions to actively progress the claim, until followed up by the Applicant and/or the FOS Case Manager. Case No: 354432 Determination Page 7 of 12 While none of the above issues are necessarily critical in isolation, the Panel is satisfied that, when taken as a whole, they have substantially delayed the resolution of the Applicant’s claim. Further, the effects of these issues on the Applicant need to be considered in the context of the current claim, where the initial damage caused by the storm was reasonably extensive and the FSP was aware of the financial and health issues affecting the Applicant and his wife and knew that they were continuing to live in a property which was further deteriorating over time. In the circumstances, the Panel considers that an award of compensation for non- financial loss in the amount of $3,000 is appropriate. Further, the available information indicates that the delays in completing the claim-related repairs have resulted in the cost of the re-stumping increasing from approximately $12,000 to approximately $15,000, as it is now also necessary to re-stump the verandah. This has resulted in a corresponding increase in the amount which the Applicant has been required to contribute to the cost of these repairs. In light of the issues outlined above, the Panel considers that the FSP should reimburse to the Applicant the additional amount of approximately $1,000 which he has been required to contribute to the re-stumping costs, due to the delays in undertaking the necessary repairs. The Panel notes that the FSP has already agreed to fund the costs of repairing the additional internal movement damage which occurred in part because the property was left up on blocks for an extended period of time. Applicant has incurred additional costs in lieu of temporary accommodation The Applicant says that he has incurred additional costs (at a rate of approximately $150 every six to eight weeks) in purchasing water during the period he and his wife were living at the property before the repairs were completed. The Applicant has provided documentation from the water supplier confirming these purchases. The Applicant says it was necessary for him to purchase water because the storm damaged the roof guttering which supplied rainwater to the 15,000 litre water tank which was the only source of water for the home. The Applicant has provided photographs showing the damaged guttering, which the FSP’s loss adjuster (CL) has confirmed was used to capture rainwater for the water tank. While the FP has disputed that the damage to the guttering was caused by the storm, CL’s initial report prepared in August 2011 confirms that there was storm-related damage to the roofing, guttering and downpipes. In these circumstances, the Panel is satisfied that, on the balance of probabilities, the damage to the guttering was caused by the storm. However, it appears that CL may have failed to appreciate the effect of this damage on the Applicant’s ongoing water supply, at the time of his initial inspection. The Applicant’s policy provides for the payment of temporary accommodation benefits where the property becomes unfit to live in as the result of an insured Case No: 354432 Determination Page 8 of 12 event under the policy. The Panel is satisfied that the absence of a water supply as a result of damage to the guttering caused by the storm would have rendered the property unfit to live in. Accordingly, the Applicant would have been entitled to temporary accommodation benefits. By continuing to live at the property until the repairs recommenced in December 2014 and making alternative arrangements for the supply of water during this time, the Applicant has effectively mitigated the need for the FSP to provide temporary accommodation during this period. In these circumstances, the Panel considers it is appropriate that the FSP be required to reimburse the Applicant for the cost of purchasing water during the relevant period. The FSP says that the issue of reimbursement for water was not raised by the Applicant until September 2014. However, the dispute form completed by the Applicant when he lodged his dispute with FOS in March 2014 specifically refers to the need to purchase water due to spouting and roof damage to his property. For whatever reason, the FSP did not address this aspect of the dispute until six months later, when it sought to have CL attend to investigate the cause of the damage (which did not in fact occur until some four months later). The FSP also says that the Applicant would have had to purchase water in any event, due to the drought conditions experienced during the relevant period. However, the Panel does not consider that the meteorological information provided by the FSP is sufficient to establish this. For the reasons outlined above, the Panel considers that the FSP should be required to reimburse the Applicant for costs incurred in purchasing water, in lieu of providing temporary accommodation under the policy during the relevant period. Based on the available information, the Panel considers that it is fair in all the circumstances that the FSP reimburse the Applicant an amount of $5,000 for costs incurred in purchasing water. In arriving at this amount, the Panel has taken into account the passage of time since the payments were made. Accordingly, the FSP is not required to pay interest on this amount. Applicant incurred additional costs as a result of extended delays The Applicant says that he has incurred additional heating and cooling costs as a result of his house being jacked up on blocks and left in that state for an extended period of time. He says that this caused the floor to drop further and gaps to open up in the walls, leaving the house exposed to the elements. The available information confirms that the Applicant’s house suffered further movement damage during the period of almost two years while it was left jacked up on blocks. While the Applicant has not provided details of the additional costs incurred, the Panel is satisfied that the amount of $1,000 represents a reasonable estimate of the consequential financial loss suffered by the Applicant due to the insured event and the subsequent delays in finalising his claim. Case No: 354432 Determination Page 9 of 12 Accordingly, the FSP is required to pay the Applicant the amount of $1,000 as compensation for consequential financial loss. In arriving at this amount, the Panel has taken into account the passage of time since the relevant costs were incurred. Accordingly, the FSP is not required to pay interest on this amount. Case No: 354432 Determination Page 10 of 12 3 Supporting information 3.1 FOS approach to this dispute This dispute has not been the subject of a FOS Recommendation. Due to the nature of the dispute, it has been referred directly to a Panel for Determination, in line with the Operational Guidelines to the FOS Terms of Reference. The Panel consists of an Ombudsman and two representatives with consumer and insurance experience. The Panel has decided this case on its merits, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions. There has been a full exchange of all material information relied on for the purposes of this Determination and each party has had the opportunity to address any issues raised by the other. The Panel has reviewed and considered all of the material provided by the parties. While the parties have raised a number of issues in their submissions, for the purposes of this Determination the Panel has restricted its commentary to those issues which it considers directly relevant to the outcome only. 3.2 Chronology of key events Date Details 7 March 2010  Applicant ’s property is damaged by storm . 11 March 2010  Applicant lodges claim with FSP . July 2011  Claim is reopened after having previously been closed. September 2011  FSP accepts liability for external damage (roof etc) and internal water damage caused by the storm, but denies liability for re - stumping on the basis that damage was pre - existing.  FSP obtains quote from builder (B) to complete the internal and external building repairs. 17 October 201 1  Re - stumper (D) confirms all existing timber stumps need to be replaced with concrete stumps and the house re - levelled.  After Applicant disputes FSP’s denial of liability for re - stumping and provides further information, FSP accepts liabili ty for 70% of re - stumping costs.  Applicant and FSP accept D’ s quote of $12,000 for re - stumping .  FSP authorises builder (B) to complete internal and external repairs once re - stumping completed. August 2012  After DJ does not respond to FSP’s requests to con firm start date for re - stumping, FSP asks BL to provide a quote for the re - stumping . September/ October 2012  BL is appointed to undertake the re - stumping based on his quotation for $11,950, to be apportioned between the FSP (70%) and the Applicant (30%). Case No: 354432 Determination Page 11 of 12 Date Details  BL advises soil is still incredibly wet and requires a further 12 month drying period before re - stumping can commence . BL agrees to inspect regularly . January 2013  BL confirms soil is dry enough for re - stumping works to commence. February 2013  Applicant’s property is “jacked up” by BL to commence re - stumping.  BL discovers burst sewer pipe and confirms a further drying out period of around 6 to 8 weeks is required. May/ June 2013  BL confirms site is sufficiently dry to allow re - stumping works to commence.  CL advises builder (B) will re - attend to confirm remaining repairs. July 2013  BL applies for permits to allow re - stumping works to commence in August 2013.  Applicant asks FSP to cover 100% of re - stumping costs due to delays . August 2013  Applicant carried out termite treatment at property . Mid - October 2013  Re - stumping work commences.  BL identifies termite damage to bearers and joists . December 2013  FSP advises Applicant termite damage is not covered and offers to cash settle Applicant for the cost of repairin g the damage for which it has accepted liability.  Applicant rejects FSP’s offer and disputes FSP’s denial of liability for termite damage. 3 January 2014  FSP writes to Applicant declining claim for termite damage. 16 March 2014  Applicant lodges dispute w ith FOS. May 2014  CL prepares revised scope of works for internal building repairs. January 2015  FSP arranges temporary accommodation (caravan) at the property while the re - stumping is completed. February 2015  Re - stumper (BL) commences re - stumping works and discovers additional termite damage.  BL advises he is no longer willing to undertake the re - stumping works.  FSP engages a third re - stumper (Q) to quote on the re - stumping works. 23 February 2015  Re - stumping works and building works commence. Case No: 354432 Determination Page 12 of 12 3.3 Terms of policy Subject Terms Insured events Defined Event …  Storm or Rainwater …  Escape of Liquid as a result of bursting, leaking, discharging or overflowing of fixed domestic apparatus, tanks, or pipes Exclusions – property damage Wear and Tear We will not pay for loss, destruction, damage, or the incurring of a liability caused directly or indirectly by gradual deterioration, wear, tear, depreciation, rust, corrosion, wet rot, dry rot, mould or mildew … Insects, Vermin or Birds We will not pay for loss, destruction, damage, or the incurring of a liability caused directly or indirectly by insects, vermin, or birds.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.