Determination 354130
Flood exclusion applied to Queensland storm damage to strata car park
Summary
Residents claimed for damage to a strata car park from a January 2011 Queensland storm, which the FSP declined under its flood exclusion. AFCA accepted that stormwater inundation up to 150mm preceded the floodwater and ordered indemnity for that part, plus interest from the final decision date.
The insurer bears the onus to show an exclusion applies; stormwater overflow from underground drainage is not floodwater under the policy definitions, so the initial inundation is covered.
Issues
- Claim denial primary · upheld
“The FSP is to provide indemnity for any damage to the insured property caused by the inundation of the basement car park up to 150mm, which occurred prior to the arrival of floodwaters.”
- Product terms interpretation secondary · not upheld
“The policy wording is reasonably clear and unambiguous; the definition of flood is not ambiguous as alleged.”
Subjects and remedies
home or building damagenatural disasterpay claimpay interest
Text of the determination
Determination
General Insurance - Domestic Insurance - Residential Strata Title - FSP Decision -
Denial of claim
Determination
Case No: 354130 Determination Page 1 of 5
Case number : 354130 6 August 2014
1 Overview
1.1 Dispute
The Applicants are residents at the insured property and represent all the other
residents of the property covered by a Residential Strata (Corporate) Insurance
Policy (the policy) held with the Financial Services Provider (FSP).
A claim was lodged upon the policy for damage to the insured property caused
during a significant weather event experienced in Queensland (QLD) during
January 2011. The FSP has declined the claim based on its flood exclusion.
1.2 Issues and key findings
Is the policy adequately clear and unambiguous?
The policy reasonably sets out the scope and limitations of the cover offered by
the contract of insurance.
Is the loss claimed due to stormwater run-off and/or floodwater?
The available evidence establishes, on the balance of probabilities that there was
some initial stormwater inundation at the insured address prior to the arrival of
floodwater.
Is the FSP liable to pay interest upon settlement figure?
The FSP is obliged to pay interest upon the final settlement amount under the
policy in line with Section 57 of the Insurance Act 1984 (the Act), from 28 January
2014 until such payment is made.
1.3 Determination
This Determination is partially in favour of the Applicants.
The FSP is to provide indemnity for any damage to the insured property caused
by the inundation of the basement car park up to 150mm, which occurred prior to
the arrival of floodwaters.
Case No: 354130 Determination Page 2 of 5
2 Reasons for Determination
2.1 Is the policy adequately clear and unambiguous?
The policy wording is reasonably clear and unambiguous
There is no dispute the FSP fulfilled its obligations to make available all the
relevant policy documentation and wording to the policyholder in line with the Act,
prior to the loss.
The Applicants have raised concerns relating to the policy wording and especially
regarding the definition of the term “Flood”. The Applicants are of the view, by the
deliberate use of the word “ or ” within the definition, that this e stablishes a flood
occurs only when one of these circumstances occurs i.e. rainfall or snow melt or
water released deliberately by an authority.
Further, if the FSP meant for a flood to include a combination of all or any of these
occurrences, it could easily had done so within the Product Disclosure Statement
(PDS). The Applicants state, in line with concerns relating to the ambiguity of the
policy, the contract should be strictly construed against the FSP in line with the
principle of contra proferentum . This principle provides that in the instance the
terms of the contract are found to be unclear and ambiguous then such terms are
to be read against the author (FSP) and in favour of the policyholder.
The Panel has carefully considered the policy and is satisfied that it is reasonably
clear and unambiguous. The policy is a commercial insurance product and
provides indemnity for accidental loss or damage to the insured property subject
to the specifically listed exclusions. Further, the policy clearly provides that loss or
damage arising from the event “Flood” is excluded from cover.
The Panel has considered the Applicants‟ interpretation of the policy definition for
the event flood and the presence of the word “ or ” within this definition. The Panel
is not satisfied this definition is unclear and/or ambiguous as alleged or that it
confuses the scope of the definition. The Panel does not accept the position that
use of the word „or‟ could reasonably be accepted to limit the scope of the event
to only such instances where the flood occurs as a result of only one of the listed
causes and would not constitute a flood if there is more than one contributing
cause.
The policy as noted above provides cover for accidental loss or damage. The
Panel is satisfied the claimed damage is, for the purpose of the policy, considered
accidental which establishes a prima facie claim. Therefore, the burden rests with
the FSP to establish, on the balance of probabilities, an entitlement to decline
indemnity to the Applicants in line with the specified policy limitations.
Case No: 354130 Determination Page 3 of 5
2.2 Is the loss claimed due to stormwater run-off or flood?
The insured property was partially inundated by stormwater prior to the
arrival of floodwaters
The available evidence establishes that during January 2011, QLD was affected
by extreme weather conditions including major storms and associated significant
rainfall. The area of the insured property was ultimately severely flooded due to
the rise in the water levels of the Brisbane River (the River). However, the
Applicants maintain that prior to the arrival of the floodwaters the underground car
park was inundated by stormwater run-off.
The Panel acknowledges the Applicants‟ reference and reliance upon evidence
relevant to claims lodged by other neighbouring properties and/or Applicants. The
Panel accepts in some instances such evidence may be considered to be of some
limited assistance, however, each dispute is determined on its merits and on the
basis of the evidence relating to that particular claim. In this dispute sufficiently
detailed submissions and evidence have been made available by the parties and
it is on the basis of this evidence, FOS will issue its Determination.
The evidence is reasonably consistent that the insured car park was likely to have
been first inundated in the afternoon of 11 January 2011. The level of inundation
continued to rise within the insured property during 12 January 2011 and finally
began receding on or after 14 January 2011. Although the lobby of the insured
building was also inundated during the event the parties acknowledge this was,
on balance, due to floodwater and not stormwater run-off.
The parties differ with respect to the cause of the inundation of the underground
car park and resultant damage claimed, with the Applicants claiming it was
localised stormwater run-off/flash flood and the FSP claiming it was due to
floodwater from the rising level of the Brisbane River via backflow up an open
stormwater channel. The evidence relied upon by the parties includes consultants‟
reports, first hand witness statements and the account of the female Applicant
who with her husband were the only people to remain at the insured property
throughout the whole event.
The FSP notes the Applicants‟ reference to the LMT Surgical Pty Ltd v Allianz Pty
Ltd case, however, it says the policy definition for flood in its PDS varies to that of
the above case. So, in line with the policy, the FSP believes it is entitled to include
the pipe drainage network (relied upon by the Applicants) within the policy
definition for flood. The Panel has considered the definitions for “ Flood ” and
“ Water Catchment System ”, specifically included within the PDS.
Having considered these definitions the Panel is not satisfied it would be
reasonable to allow the FSP to include within its definition of „ water catchment
system ’, underground (not open) drainage pipe networks. The definition for water
catchment systems, which specifically lists a number of different water systems,
does not include a drainage pipe network/system. Considering the definition for
flood the Panel notes it makes no reference to water that overflows or escapes a
drain pipe (stormwater drain) network being considered floodwater.
Case No: 354130 Determination Page 4 of 5
The Panel therefore does not accept the FSP‟s position that damage due to water
overflowing the local stormwater drainage network prior to the arrival of
floodwaters (as defined) would also reasonably be determined to be floodwater in
line with the policy. Rather, quite the opposite, on the basis the policy provides
cover for accidental loss or damage and in the absence of the policy specifically
excluding damage caused by water entering the insured property from the local
drainage pipe network, the damage will be covered under the policy.
The available evidence includes multiple reports from consultants such as F
(assessors) and W (hydrologists), including statements from several of the
residents of the insured property. The Panel, having considered all this evidence,
is satisfied that the underground car park was initially inundated by stormwater
run-off in the early afternoon of 11 January 2011, prior to the arrival of floodwater
from the Brisbane River. Such a scenario has also been acknowledged by the
hydrologists in the report dated 17 December 2012.
W states the floor level of the car park is approximately 3.2m AHD and based on
the available evidence the water level of the Brisbane River would have been at
this height at around 2.00pm on 11 January 2011, which would encourage
backflow of water up the underground and connected stormwater network. The
initial inundation of the car park at or around this time is also consistent with the
evidence of the witnesses as well. The subsequent inundation to the maximum
level however was due to the arrival of floodwater due to the overflow of the open
stormwater channel and ultimately the Brisbane River, whic h is not covered under
the policy.
There is no clear evidence of the exact level of inundation and/or resultant
damage from this initial stormwater inundation of the car park. However, the
witnesses‟ statements do provide some idea of the increasing level of inundation
of the car park (prior to the arrival of floodwater) through the course of the day
from the drains. Having considered all the evidence and what would be
considered fair in the circumstances, the Panel determines it would be reasonable
to accept an initial inundation of the underground car park by stormwater run-off
up to the height of 150mm.
Accordingly, the FSP is obliged to provide indemnity for loss or damage arising
from stormwater run-off inundation of the insured building car park to a level of
150mm.
2.3 Is the FSP obliged to pay interest upon final settlement amount?
Section 57 of the Insurance Contracts Act 1984
Section 57 of the Act requires interest be paid when it becomes “unreasonable for
the insurer to have withheld payment”.
The F SP declined the Applicants‟ claim following its investigations into the loss
and made its decision on the basis of its investigations. Therefore, it is
appropriate that from that time interest be paid.
Case No: 354130 Determination Page 5 of 5
Accordingly, the Panel determines that the FSP is to pay interest from the day
upon which the FSP provided its final decision to the Applicants‟ claim (28
January 2014), until payment of the claim.
3 Supporting information
3.1 Relevant Policy terms
Flood
means when water that is normally contained in a Water Catchment System increases
because of rainfall or snow melt (whether in the immediate region or elsewhere) or is
deliberately released by an authority, and the water overflows onto land that it not
normally covered by water.
Water Catchment System
means
a. a river, creek, other natural watercourse or lake, whether they are in their original
state or have been modified, are named or unnamed, or normally dry that only run
during periods of rain;
b. a dam, reservoir, stormwater channel or canal.